CN104009482B - Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode - Google Patents
Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode Download PDFInfo
- Publication number
- CN104009482B CN104009482B CN201410217426.2A CN201410217426A CN104009482B CN 104009482 B CN104009482 B CN 104009482B CN 201410217426 A CN201410217426 A CN 201410217426A CN 104009482 B CN104009482 B CN 104009482B
- Authority
- CN
- China
- Prior art keywords
- critical point
- idle
- load
- power
- loss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/30—Reactive power compensation
Abstract
The invention provides a method for dynamically setting a gateway reactive power control range under a single-line and single-variable wiring mode. The problem that the dynamic variation of power grid operation characteristics can not be adapted due to the fact that the gateway reactive power control range is fixed in automatic voltage control of a current power grid is solved. The method comprises the specific steps that first, the parameter of a regional power grid circuit, the parameter of a main transformer and the voltage data of an electricity sending end are collected; second, the minimum value of system active power loss of the main transformer under different load rates, the gateway reactive power optimal section, and the corresponding gateway power factor variation range are calculated; at last, the gateway power factor constraints of the transformer in the low load process and in the heavy load process are considered, and the gateway reactive power control ranges under different working conditions are obtained. According to the method for dynamically setting the gateway reactive power control range under the single-line and single-variable wiring mode, the gateway reactive power optimal control range can be dynamically adapted to the variation of power grid load levels, and reactive power balance, energy saving and consumption reduction of the system can be promoted.
Description
Technical field
The present invention relates to power system critical point powerless control method, particularly to critical point under a kind of monotropic mode of connection of single line
Idle span of control dynamic tuning method.
Background technology
With the continuous expansion of electrical network scale, the safety of operation of power networks, reliability and economy problems have become all the more
Prominent, and tradition carries out the method for centralized optimization not only feasibility is low after whole complex large power grid is modeled but also control effect
Poor.Comparatively speaking, the vqc control strategy based on the local electric information of transformer station, the idle in-situ balancing of pursuit, due to modeling
Less demanding, information interaction amount is few, control algolithm is simple, has obtained wide at present in the reactive power/voltage control of avc transformer substation side
General application.
However, there is an obvious problem in the method: for the interval setting of critical point reactive power be often basis with
Past operating experience and lack the guidance of theoretical foundation, do not account for that electric network element parameter is different and operation characteristic change is to no yet
The diversity of work(demand for control, this can lead to the safety of system operation (to be related to abundance, the voltage amplitude of dynamic reactive deposit
Qualification rate of value etc.), reliability (avoiding the frequent regulation of equipment) and economy (reduce and run power attenuation) tend not to
To coordination optimization.
The present invention proposes the idle span of control in critical point dynamic tuning method under a kind of monotropic mode of connection of single line, for this
The different operating condition of system provides the idle span of control in adaptable critical point, thus avoiding because of the change of network load level
The idle upper lower limit value in critical point causing sets irrational problem.This setting method is applicable not only to that single line is monotropic also can be pushed away simultaneously
Wide to other more complicated modes of connection such as: the double change of single line, two-wire three become and chain wiring and t type wiring etc., have
Stronger engineering application value.
Content of the invention
It is an object of the invention to the idle span of control in critical point solving to lead to because of the change of network load level does not conform to
The problem of reason, proposes a kind of single-phase electricity and becomes critical point idle span of control dynamic tuning method under the mode of connection, concrete technical scheme
As follows.
A kind of single-phase electricity becomes critical point idle span of control dynamic tuning method under the mode of connection, comprises the following steps:
(1) the resistance r of collection circuit, reactance x, node susceptance b, the capacity s of transformatorn, open circuit loss p0, load loss
pk, short-circuit voltage percentage value uk%, no-load current percentage value i0% and its power transmission terminal voltage ua;
(2) select in transformer load rate β=10%, 40% and the lighter state 1 of 70% 3 kind of level representation load, load
Etc. state 2 and the heavier state of load 3, circuit and transformer active under three kinds of load conditions are asked for respectively using graphing method it is lost
Minima p of sumlmin1、plmin2、plmin3;Calculate optimum network loss offset delta pl;
(3) calculate the idle q in critical point under three kinds of load conditions respectivelyhOptimization interval And corresponding critical point power factor change scope
(4) judgeWhether delayed, if meeting, β < when 40%, the idle span of control in critical point is:If being unsatisfactory for, β < when 40%, the idle span of control in critical point is:
(5) judgeWhether it is not less than 0.95, if meeting, during β >=40%, the idle span of control in critical point is:If being unsatisfactory for, the span of control that critical point during β >=40% is idle is:DescribedForWhen critical point reactive power.
Further, under different loads rate in described step (2), circuit and transformer active are lost the minima of sum
plminAnd optimum network loss offset delta plObtained according to following methods:
When power transmission terminal voltage uaWhen known, active loss sum p of circuit and transformatorlIt is represented by:
pl=△pt+△pl(1),
Formula (1) to (8) comprising variable: transformer active loss δ pt;Circuit active loss δ pl;Receiving end voltage ub;Become
Depressor reactive loss δ qt;Load apparent energy sd;Load active power pd;Reactive load power qd;Load power factor
Understand, when in system, network element parameter and burden with power give, to close by change according to formula (1) to (4)
Mouthful idle qhAmount try to achieve plWith the idle q in critical pointhThe u-shaped pattern changing and changing, the minimum point of this curve is just plMinima
plmin, this determines plminMethod be graphing method, described optimum network loss offset delta plIdle for critical point under different loads rate
Optimize the active loss p corresponding to each point in intervallWith respect to minima plminMaximal increment, can be obtained by formula (9):
δpl=α %plmin3(9),
Formula (9) comprising variable: the minima of circuit and transformer active loss sum during transformer load rate β=70%
plmin3;The artificial constant α % setting of power conservation requirement when being run according to system reload.
Further, the idle q in critical point under different loads rate in described step (3)hOptimization interval can be by with lower section
Method obtains: when in system, network element parameter and burden with power give, active loss sum p of circuit and transformatorlCan see
It is the idle q in critical pointhFunction of a single variable, and by change the idle q in critical pointhAmount can try to achieve plWith the idle q in critical pointhChange and change
U-shaped pattern, can determine p from this curvelMinima plmin, according to given optimum network loss offset delta pl, mark
plminWith δ plThe contour of sum and u-shaped pattern intersect at 2 points, and in the abscissa of two intersection points, larger and smaller corresponds to respectively
The interval upper limit value and lower limit value of critical point idle work optimization.
Further, described step (4), the implementation process of (5) are:
(1) judgeWhether delayed:
If meeting, during transformer station's underloading, the idle span of control in critical point is:
If being unsatisfactory for, during transformer station's underloading, the idle span of control in critical point is:
(2) judgeWhether not less than 0.95:
If meeting, during transformer station's non-underloading, the idle span of control in critical point is:
If being unsatisfactory for, during transformer station's non-underloading, the idle span of control in critical point is: Described
'sForWhen critical point reactive power;
Wherein, using transformer load rate β=40% as the separation of transformer station's underloading and non-underloading.
Compared with prior art, present invention has the advantage that
(1) consider the impact to the idle control in critical point for the operation of power networks characteristic variations, can be for different operating conditions
Make the idle span of control in adaptable critical point.
(2) the idle span of control dynamic tuning method in proposed critical point, not only allows for critical point work(when light transformer, heavy duty
Controlling of rate factor requires it is also possible to avoid the frequent of low-pressure side reactive power compensator while meeting system operation economy
Action.
Brief description
Fig. 1 is the idle span of control in critical point dynamic tuning method flow diagram in the monotropic mode of connection of single line.
Fig. 2 is idle work optimization interval diagram in critical point under certain load factor.
Fig. 3 is certain monotropic mode of connection schematic diagram of 110kv electrical network single line.
Specific embodiment
Below in conjunction with accompanying drawing and example to the present invention be embodied as be described further, but the enforcement of the present invention and protection
Not limited to this.
As Fig. 1, critical point idle span of control dynamic tuning method in a kind of monotropic mode of connection of single line, walk including following
Rapid:
(1) the resistance r of collection circuit, reactance x, node susceptance b, the capacity s of transformatorn, open circuit loss p0, load loss
pk, short-circuit voltage percentage value uk%, no-load current percentage value i0% and its power transmission terminal voltage ua;
(2) select in transformer load rate β=10%, 40% and the lighter state 1 of 70% 3 kind of level representation load, load
Etc. state 2 and the heavier state of load 3, circuit and transformer active under three kinds of load conditions are asked for respectively using graphing method it is lost
Minima p of sumlmin1、plmin2、plmin3;Calculate optimum network loss offset delta pl;
As shown in Fig. 2 in figure dotted line and chain-dotted line respectively indication transformer loss and line loss, solid line represent total losses
(transformator and line loss sum), because two groups of numerical value difference are larger, is represented using major-minor axis of ordinates to represent convenient.
As seen from the figure, when system parameters give, active loss sum p of circuit and transformatorlThe idle q in critical point can be regarded ashUnitary
Function, and by changing the idle q in critical pointhAmount can try to achieve total losses plWith the idle q in critical pointhThe u-shaped pattern changing and changing, its
Middle plminIt is this total losses value corresponding to curve minimum point, optimum network loss offset delta plCan be obtained by following formula:
δpl=α %plmin3
In formula, plmin3Minima for circuit during transformer load rate β=70% and transformer active loss sum;α %
It is the artificial constant setting of power conservation requirement when being run according to system reload;
(3) calculate respectively and ask for the idle q in critical point when transformer load rate β=10%, 40% and 70%hOptimization intervalAnd corresponding critical point power factor change scope
As shown in Fig. 2 according to optimum network loss offset delta p set in advancel, mark plminWith δ plThe contour of sum
Intersect at 2 points with u-shaped pattern, in the abscissa of two intersection points larger and smaller correspond to respectively critical point idle work optimization interval upper,
Lower limit.
(4) judgeWhether delayed, if meeting, β < when 40%, the idle span of control in critical point is:If being unsatisfactory for, β < when 40%, the idle span of control in critical point is:
(5) judgeWhether it is not less than 0.95, if meeting, during β >=40%, the idle span of control in critical point is:If being unsatisfactory for, the span of control that critical point during β >=40% is idle is:DescribedForWhen critical point reactive power.
Further, described step (4), the implementation process of (5) are:
(1) judgeWhether delayed.
If meeting, during transformer station's underloading, the idle span of control in critical point is:
If being unsatisfactory for, during transformer station's underloading, the idle span of control in critical point is:
(2) judgeWhether it is not less than 0.95.
If meeting, during transformer station's non-underloading, the idle span of control in critical point is:
If being unsatisfactory for, during transformer station's non-underloading, the idle span of control in critical point is: Institute
StateForWhen critical point reactive power.
Wherein, using transformer load rate β=40% as the separation of transformer station's underloading and non-underloading.
The following is an example of calculation of the inventive method, taking the monotropic mode of connection of single line in certain 110kv electrical network as a example, figure
3 topological structure showing this mode of connection.
(1) the resistance r of collection circuit, reactance x, node susceptance b, the capacity s of transformatorn, open circuit loss p0, load loss
pk, short-circuit voltage percentage value uk%, no-load current percentage value i0% and its power transmission terminal voltage ua, have:
R=0.8 ω, x=3.98 ω, b=2.91 × 10-5S, sn=50mva, p0=25kw
pk=178.4kw, uk%=16, i0%=0.01, ua=115kv
(2) select in transformer load rate β=10%, 40% and the lighter state 1 of 70% 3 kind of level representation load, load
Etc. state 2 and the heavier state of load 3, circuit and transformer active under three kinds of load conditions are asked for respectively using graphing method it is lost
Minima p of sumlmin1、plmin2、plmin3;Calculate optimum network loss offset delta pl;
β=10%:plmin1=28kw;β=40%:plmin2=73kw;β=70%:plmin3=173kw makes constant α %=
6% optimum network loss side-play amount is:
δpl=α %plmin3=173 × 6%kw ≈ 10kw
(3) calculate respectively and ask for the idle q in critical point when transformer load rate β=10%, 40% and 70%hOptimization intervalAnd corresponding critical point power factor change scope
Optimum network loss offset delta p when given systemlDuring=10kw, the idle optimization in critical point under different loads rate can be obtained
Interval and corresponding critical point power factor change scope is as shown in table 1.
The optimization that under table 1 different loads rate, critical point is idle is interval
Transformer load rate β | 10% | 40% | 70% |
Optimize interval/mvar | (- 8.5,9.0) | (- 7.5,9.5) | (- 6.5,10.5) |
Power factor is interval | (0.47,0.49) | (0.89,0.93) | (0.95,0.98) |
Note: in table, runic numerical value represents that power factor is advanced
(4) judgeWhether delayed, if meeting, β < when 40%, the idle span of control in critical point is:If being unsatisfactory for, β < when 40%, the idle span of control in critical point is:Due toIn advance, then β < when 40%, the idle span of control in critical point is: (0,9)
∩ (- 7.5,9.5)=(0,9).
(5) judgeWhether it is not less than 0.95, if meeting, the idle control model in critical point when can directly obtain β >=40%
Enclose for:If being unsatisfactory for, the span of control that critical point during β >=40% is idle is:WhereinForWhen critical point reactive power.Due toCause
The critical point idle work optimization interval of this β=70% is still (- 6.5,10.5), then during β >=40%, the idle span of control in critical point is: (-
6.5,10.5) ∩ (- 7.5,9.5)=(- 6.5,9.5).
Using transformer load rate β=40% as the separation of transformer station's underloading and non-underloading, then in the case of different loads
Critical point critical point span of control as shown in table 2.
The idle span of control in critical point under the different operating condition of table 2
Loading condition | Critical point is idle span of control/mvar | (pl-plmin)/kw |
β < 40% (underloading) | (0,9) | ≤10 |
β >=40% (non-underloading) | (- 6.5,9.5) | ≤10 |
As shown in Table 2, critical point idle span of control dynamic tuning under a kind of monotropic mode of connection of single line proposed by the present invention
Method can make the idle span of control in adaptable critical point for different operating condition in the monotropic mode of connection of single line, and
Ensure to meet the economy of system operation in this span of control, be also avoided that frequently moving of low-pressure side reactive power compensator
Reactive power releasing problem when work and transformer station's underloading.This setting method is applicable not only to that single line is monotropic also to extend to it simultaneously
His more complicated mode of connection is such as: single line is double to be become, two-wire three becomes and chain wiring and t type wiring etc., has stronger
Engineering application value.
Above-described embodiment is the present invention preferably embodiment, but embodiments of the present invention are not subject to above-described embodiment
Restriction, the modification made under other any spirit without departing from the present invention and principle, modification, replacement, combination, simplification, all
Should be equivalent substitute mode, all should be included within protection scope of the present invention.
Claims (2)
1. under a kind of monotropic mode of connection of single line critical point idle span of control dynamic tuning method it is characterised in that including following walking
Rapid:
(1) the resistance r of collection circuit, reactance x, node susceptance b, the capacity s of transformatorn, open circuit loss p0, load loss pk, short
Road voltage percentage value uk%, no-load current percentage value i0% and its power transmission terminal voltage ua;
(2) transformer load rate β=10%, 40% and the lighter state 1 of 70% 3 kind of level representation load, the medium shape of load are selected
State 2 and the heavier state of load 3, ask for circuit and transformer active under three kinds of load conditions respectively using graphing method and sum are lost
Minima plmin1、plmin2、plmin3;Calculate optimum network loss offset delta pl;Circuit and transformer active loss under different loads rate
Minima p of sumlminAnd optimum network loss offset delta pl, obtained according to following methods:
When power transmission terminal voltage uaWhen known, active loss sum p of circuit and transformatorlIt is represented by:
pl=δ pt+δpl... ... ... ... ... ... ... ... (1),
Formula (1) to (8) comprising variable: transformer active loss δ pt;Circuit active loss δ pl;Receiving end voltage ub;Transformator
Reactive loss δ qt;Load apparent energy sd;Load active power pd;Reactive load power qd;Load power factor
Understand when in system, network element parameter and burden with power give according to formula (1) to (4), can be by changing critical point no
Work(qhAmount try to achieve plWith the idle q in critical pointhThe u-shaped pattern changing and changing, the minimum point of this curve is just plMinima plmin,
This determines plminMethod be graphing method;
Described optimum network loss offset delta plActive damage corresponding to each point in idle work optimization interval in critical point under different loads rate
Consumption plWith respect to minima plminMaximal increment, can be obtained by formula (9):
δpl=α %plmin3... ... ... ... ... ... .... (9),
Formula (9) comprising variable: minima p of circuit and transformer active loss sum during transformer load rate β=70%lmin3;
According to the artificial constant α % setting of power conservation requirement during single line monotropic system heavy service;
(3) calculate the idle q in critical point under described three kinds of load conditions respectivelyhOptimization interval And corresponding critical point power factor change scope
(4) judgeWhether delayed, if meeting, β < when 40%, the idle span of control in critical point is:If being unsatisfactory for, β < when 40%, the idle span of control in critical point is:
(5) judgeλ h3Whether it is not less than 0.95, if meeting, during β >=40%, the idle span of control in critical point is:If being unsatisfactory for, the span of control that critical point during β >=40% is idle is:DescribedForλ h3Critical point reactive power when=0.95.
2. critical point idle span of control dynamic tuning method under the monotropic mode of connection of single line according to claim 1, it is special
Levy and be: the idle q in critical point under described different loads ratehOptimization interval be prepared by the following: when network element in system
When part parameter and burden with power give, by active loss sum p of circuit and transformatorlRegard the idle q in critical point ashFunction of a single variable,
And by changing the idle q in critical pointhAmount try to achieve plWith the idle q in critical pointhThe u-shaped pattern changing and changing, can determine that from this curve
plMinima plmin, according to given optimum network loss offset delta pl, mark plminWith δ plThe contour of sum and u-shaped pattern
Intersect at 2 points, larger and smaller's interval upper limit value and lower limit value of corresponding critical point idle work optimization respectively in the abscissa of two intersection points.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410217426.2A CN104009482B (en) | 2014-05-21 | 2014-05-21 | Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410217426.2A CN104009482B (en) | 2014-05-21 | 2014-05-21 | Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104009482A CN104009482A (en) | 2014-08-27 |
CN104009482B true CN104009482B (en) | 2017-01-25 |
Family
ID=51370030
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410217426.2A Expired - Fee Related CN104009482B (en) | 2014-05-21 | 2014-05-21 | Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104009482B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104300552B (en) * | 2014-10-16 | 2016-09-14 | 国家电网公司 | A kind of take into account correction voltage out-of-limit with reduce active loss idle work optimization method |
CN104779624B (en) * | 2015-03-12 | 2017-03-29 | 华南理工大学 | The idle control range differentiation setting method in transformer station critical point in a kind of looped network |
CN104779625B (en) * | 2015-03-12 | 2017-04-19 | 华南理工大学 | Capacitive reactive compensation configuration method for 110kV transformer substation in saturated load region |
CN105140932A (en) * | 2015-09-24 | 2015-12-09 | 中国南方电网有限责任公司 | Terminal substation gateway reactive power control interval making method fit for wind power access |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3802677A1 (en) * | 1988-01-27 | 1989-08-03 | Licentia Gmbh | Method for improving the operating behaviour of dynamic power-factor correction installations having a limited power control capability |
CN102709918B (en) * | 2012-05-21 | 2014-09-10 | 广东省电力调度中心 | Reactive power control method of grid gateway based on automatic volume control (AVC) system |
-
2014
- 2014-05-21 CN CN201410217426.2A patent/CN104009482B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN104009482A (en) | 2014-08-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103474985B (en) | Realization method for function of adaptive load type distribution transformer | |
CN104917173B (en) | Adapt to the distribution optimization method of power distribution network Large Copacity load transfer | |
CN104009482B (en) | Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode | |
CN104009499B (en) | The unbalanced dispatching method of a kind of solution wind-electricity integration system load flow | |
CN105490281B (en) | Layering and zoning reactive voltage analysis method based on boundary condition | |
CN110299717A (en) | A kind of distributed mixed energy storage system balancing energy control strategy based on Model Predictive Control | |
CN103259267A (en) | Mold splitting type voltage control method for wind power plant cluster | |
CN103606932A (en) | Load-related automatic control method of low-voltage dynamic reactive compensation capacitor | |
CN103544656A (en) | Active power distribution network operational control method based on minimum carbon emission | |
CN104242318A (en) | Direct current near zone voltage automatic control method based on model predictive control theory | |
CN103401249B (en) | Reactive power automatic arrangement method based on available resource of reactive equipment | |
Astero et al. | Improvement of RES hosting capacity using a central energy storage system | |
CN107769218B (en) | Comprehensive coordination control strategy for reactive voltage of power distribution network | |
CN102386623A (en) | Method for reducing loss of wind farm | |
CN102593844B (en) | Method for controlling voltage reactive variables of high-voltage power grid transformer substation | |
CN109193683B (en) | Transformer substation inductive reactive power adequacy evaluation method based on line charging ratio | |
CN104917188B (en) | Powerless control method is coordinated in a kind of 220kV transformer stations packet | |
CN106712042A (en) | Power grid energy conservation and loss reduction control method considering reactive response capability of charging pile | |
CN103094910A (en) | Multilevel automatic voltage reactive power control system AVC coordination control method | |
CN108390391A (en) | A kind of alternating current-direct current paired running System Reactive Power voltage control method for coordinating and device | |
CN105071401A (en) | Multiport unified power quality conditioner (UPQC) applied to active power distribution network and method | |
CN104362652A (en) | Method and device for controlling excitation difference adjustment coefficient of generator | |
CN110137985A (en) | A kind of phase-change switch control method and relevant apparatus | |
CN104821590A (en) | Smart grid energy-saving optimized comprehensive evaluation method | |
CN106208110B (en) | Method for screening optimal configuration strategy of reactive power compensation of power distribution network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170125 |