CN104779625B - Capacitive reactive compensation configuration method for 110kV transformer substation in saturated load region - Google Patents
Capacitive reactive compensation configuration method for 110kV transformer substation in saturated load region Download PDFInfo
- Publication number
- CN104779625B CN104779625B CN201510107783.8A CN201510107783A CN104779625B CN 104779625 B CN104779625 B CN 104779625B CN 201510107783 A CN201510107783 A CN 201510107783A CN 104779625 B CN104779625 B CN 104779625B
- Authority
- CN
- China
- Prior art keywords
- main transformer
- transformer
- capacitive reactive
- power
- formula
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/30—Reactive power compensation
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Control Of Electrical Variables (AREA)
Abstract
The invention discloses a capacitive reactive compensation configuration method for an 110kV transformer substation in a saturated load region. The method specifically comprises the following steps: (1) acquiring the main transformer number n of the 110kV transformer substation, wherein i is equal to 1-n; (2) collecting the model parameters of each main transformer, wherein the model parameters comprise rated capacity SN, no-load current percentage I0% and short-circuit voltage percentage VS%; (3) acquiring the highest active load average value Pav and the power factor average value cosphiav of each main transformer in a power supply region in each month all the year; (4) calculating the capacitive reactive compensation QCi of each main transformer and calculating the sum of QCi of n transformers as the capacitive reactive compensation of the 110kV transformer substation. The method disclosed by the invention is suitable for planning the capacitive reactive compensation of the existing 110kV transformer substation in the saturated load region, therefore, local reactive power balancing is facilitated and a lot of reactive-load compensation equipment is prevented from being idled.
Description
Technical field
The present invention relates to the reactive power compensation technology field of transformer station, more particularly to saturation loading region 110kV transformer stations
Capacitive reactive power compensation capacity collocation method.
Background technology
South China grid voltage quality and var administrative standard require that the idle configuration of power system should ensure that
Under system burden with power peak and the load valley method of operation, the reactive balance of layering and zoning.The capacitive of 110kV transformer stations without
Work(is compensated based on compensator transformer reactive loss, and suitably takes into account the reactive-load compensation of load side, and capacitive reactive power compensation configuration is pressed
10%~30% configuration of main transformer capacity.
Reactive-load compensation is configured according to the principle there is simple and convenient, workable advantage, but the principle does not have
More optimal configuration is made according to the reactive balance demand of different reactive voltage characteristic electrical networks, causes some transformer stations to compensate
Degree, and the not enough problem of some transformer station's compensation.Therefore, the present invention starts with from idle in-situ balancing angle, for different electrical networks
Power supply level research differentiation capacitive reactive power compensation.
Additionally, some capacitive reactive power compensation capacity collocation methods, are the extreme operation sides maximum according to annual load is met
The reactive requirement of formula goes configuration, this method that the utilization rate of annual capacitor equipment may be caused low.Therefore, the present invention is to take into account
Capacitive reactive power compensates the utilization power of equipment, it is contemplated that the load level in annual each month.
The content of the invention
It is an object of the invention to overcome the shortcoming and deficiency of prior art, there is provided a kind of saturation loading region 110kV becomes
Power station capacitive reactive power compensation capacity collocation method.
The purpose of the present invention is realized by following technical scheme:
A kind of saturation loading region 110kV transformer stations capacitive reactive power compensation capacity collocation method, it is characterised in that comprising with
The step of lower order:
S1. the main transformer number n of 110kV transformer stations is obtained, i=1 is made;
S2. obtain number of windings m of i-th main transformer;
S3. m is judged whether equal to 2, be then execution step S4, otherwise execution step S8;
S4. the model parameter of i-th main transformer is gathered, described model parameter includes the rated capacity of main transformer
SN, no-load current percent I0% and short-circuit voltage percent VS%;
S5. obtain average value P of i-th main transformer power supply area in the highest burden with power of annual each moonaviWith it is corresponding
The meansigma methodss of power factor
S6. calculate i-th main transformer capacitive reactive power compensation dosage QCi;
S7. i is judged whether equal to n, be then execution step S9, otherwise make i=i+1, and return to step S2;
S8. the model parameter of i-th main transformer is gathered, described model parameter includes the rated capacity of main transformer
SN, no-load current percent I0%, height-low short-circuit voltage percent VS13%, and return to step S5;
S9. n platform main transformer capacitive reactive power compensation dosages Q are calculatedCiSum, as saturation loading region 110kV transformer stations hold
Property reactive-load compensation amount, carry out capacitive reactive power compensation configuration.
Further, described step S5, takes into account annual capacitive reactive power compensation machine utilization, annual with previous year
The highest burden with power of each moon is as foundation, specific as follows:I-th main transformer previous year annual each moon is obtained first most
High burden with power PijAnd corresponding power factorSubscript j takes 1~12;Then the average of burden with power is calculated by formula (1)
Value Pavi, the meansigma methodss of power factor are calculated by formula (2)
In formula (1), PaviUnit be MW.
Further, described step S6, capacitive reactive power compensation dosage consider idle in-situ balancing, idle comprising sending under main transformer
Amount and main transformer reactive loss, it is specific as follows:Judge number of windings m of i-th main transformer, if m is 2, Q is calculated by formula (3)Ci,
If m is 3, Q is calculated by formula (4)Ci,
In formula (3) and formula (4), QCiUnit be Mvar, SNUnit be MVA.
Described saturation loading region, refers to that the annual load level in the region has reached saturation and steady statue.
The present invention compared with prior art, has the advantage that and beneficial effect:
(1) The present invention gives specifically for the capacitive reactive power compensation capacity configuration of saturation loading region 110kV transformer stations
Method, ensure electric network reactive-load in-situ balancing on the premise of, reasonably control the quantity of reactive power compensator, saved into
This, be 110kV transformer stations Correlative plans content providers just, effective reference frame.
(2) planing method provided by the present invention, depending on being the actual loading level for different power supply areas, it is to avoid
Carry out the blindness of 110kV transformer stations capacitive reactive power compensation capacity configuration.
Description of the drawings
Fig. 1 is the stream of saturation loading region 110kV transformer stations capacitive reactive power compensation capacity collocation method of the present invention
Cheng Tu;
Calculating embodiment transformer station schematic diagrams of the Fig. 2 for Fig. 1 methods describeds.
Specific embodiment
With reference to embodiment and accompanying drawing, the present invention is described in further detail, but embodiments of the present invention are not limited
In this, if having below, it is that those skilled in the art can refer to prior art realization.
Certain 110kV transformer station is made up of the transformator that bench-types No. 3 are SFZ7-40000/110, its schematic diagram such as Fig. 2 institutes
Show.
With reference to Fig. 1 planning processes, a kind of saturation loading region 110kV transformer stations capacitive reactive power compensation capacity collocation method,
Comprise the following steps:
(1) the main transformer number n of 110kV transformer stations is obtained, i=1 is made:In the present embodiment, n=3;
(2) obtain number of windings m of i-th main transformer:In the present embodiment, m is equal to 2;
(3) m being judged whether equal to 2, being the model parameter for then gathering i-th main transformer, described model parameter includes
Rated capacity S of main transformerN, no-load current percent I0% and short-circuit voltage percent VS%:In the present embodiment, the 1st~3
The model parameter of platform main transformer all, as shown in table 1;
1 110kV main transformer parameters of table
(4) obtain highest burden with power average value P of i-th main transformer power supply area in annual each moonaviWith power because
Number meansigma methodssIt is specific as follows:
A, the highest burden with power P for obtaining i-th main transformer previous year annual each moonijAnd corresponding power factorSubscript j takes 1~12;
B, by formula (1) calculate burden with power average value Pavi, power factor is calculated by formula (2)
In the present embodiment, the highest burden with power and corresponding power factor, burden with power of 3 main transformers annual each moon
Meansigma methodss and power factor meansigma methodss are as shown in table 2:
2 110kV transformer stations of table, 3 main transformer load datas
(5) calculate i-th main transformer capacitive reactive power compensation dosage QCi, capacitive reactive power compensation dosage considers idle in-situ balancing,
It is comprising idle amount and main transformer reactive loss are sent under main transformer, specific as follows:Judge number of windings m of i-th main transformer, if m is 2,
Q is calculated by formula (3) thenCiIf m is 3, calculates Q by formula (4)Ci,
In the present embodiment, the number of windings of 3 main transformers is 2, calculates the capacitive of every main transformer according to formula (3)
Reactive compensation capacity, it is as follows:
(6) n platform main transformer capacitive reactive power compensation dosages Q are calculatedCiSum, as 110kV transformer stations capacitive reactive power compensation dosage:
In the present embodiment, QC1+QC2+QC3=13+13+12=38Mvar, thus take 38Mvar as the 110kV transformer stations capacitive without
Work(compensation dosage.
It can be seen that, matched somebody with somebody using a kind of saturation loading region 110kV transformer stations capacitive reactive power compensation capacity proposed by the invention
Method is put, the idle planning of transformer station can be effectively instructed, is contributed to idle in-situ balancing, and is avoided reactive-load compensation equipment a large amount of
It is idle.
Above-described embodiment is the present invention preferably embodiment, but embodiments of the present invention not by above-described embodiment
Restriction, the modification made under other any spirit and principle without departing from the present invention, modification, replacement, combination, simplification,
Equivalent substitute mode is should be, should be all included within protection scope of the present invention.
Claims (1)
1. saturation loading region 110kV transformer stations capacitive reactive power compensates collocation method, it is characterised in that comprise the steps of:
S1. the main transformer number n of 110kV transformer stations is obtained, i=1 is made;
S2. obtain number of windings m of i-th main transformer;
S3. m is judged whether equal to 2, be then execution step S4, otherwise execution step S8;
S4. the model parameter of i-th main transformer is gathered, described model parameter includes rated capacity S of main transformerN, it is unloaded
Electric current percent I0% and short-circuit voltage percent VS%;
S5. obtain average value P of i-th main transformer power supply area in the highest burden with power of annual each moonaviAnd corresponding power
The meansigma methodss cos φ of factoravi;Annual capacitive reactive power compensation machine utilization is taken into account, with the highest of previous year annual each moon
Burden with power is as foundation, specific as follows:The highest burden with power of i-th main transformer previous year annual each moon is obtained first
PijAnd corresponding power factorSubscript j takes 1~12;Then the average value P of burden with power is calculated by formula (1)avi, by formula
(2) meansigma methodss of power factor are calculated
In formula (1), PaviUnit be MW;
S6. calculate i-th main transformer capacitive reactive power compensation dosage QCi, capacitive reactive power compensation dosage considers idle in-situ balancing, comprising
Idle amount and main transformer reactive loss two parts are sent under main transformer, it is specific as follows:Judge number of windings m of i-th main transformer, if m is
2, then Q is calculated by formula (3)CiIf m is 3, calculates Q by formula (4)Ci,
In formula (3) and formula (4), QCiUnit be Mvar, SNUnit be MVA;
S7. i is judged whether equal to n, be then execution step S9, otherwise make i=i+1, and return to step S2;
S8. the model parameter of i-th main transformer is gathered, described model parameter includes rated capacity S of main transformerN, it is unloaded
Electric current percent I0%, height-low short-circuit voltage percent VS13%, and return to step S5;
S9. n platform main transformer capacitive reactive power compensation dosages Q are calculatedCiSum, as saturation loading region 110kV transformer stations capacitive without
Work(compensation dosage, carries out capacitive reactive power compensation configuration.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510107783.8A CN104779625B (en) | 2015-03-12 | 2015-03-12 | Capacitive reactive compensation configuration method for 110kV transformer substation in saturated load region |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510107783.8A CN104779625B (en) | 2015-03-12 | 2015-03-12 | Capacitive reactive compensation configuration method for 110kV transformer substation in saturated load region |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104779625A CN104779625A (en) | 2015-07-15 |
CN104779625B true CN104779625B (en) | 2017-04-19 |
Family
ID=53620934
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510107783.8A Expired - Fee Related CN104779625B (en) | 2015-03-12 | 2015-03-12 | Capacitive reactive compensation configuration method for 110kV transformer substation in saturated load region |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104779625B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107040244B (en) * | 2016-12-14 | 2020-04-03 | 中国人民解放军国防科学技术大学 | All-solid-state high-voltage microsecond pulse generator based on FRSPT and anti-resonance network |
CN109066716B (en) * | 2018-08-31 | 2021-12-07 | 深圳供电局有限公司 | 110kV transformer substation reactive compensation single-group capacity selection and grouping method |
CN112838593A (en) * | 2021-02-04 | 2021-05-25 | 扬州浩辰电力设计有限公司 | Compensation optimization calculation method for 110kV transformer substation reactive device |
CN112838596A (en) * | 2021-02-04 | 2021-05-25 | 扬州浩辰电力设计有限公司 | 110kV transformer substation reactive equipment capacity calculation method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5972621B2 (en) * | 2012-03-22 | 2016-08-17 | 株式会社東芝 | Inverter control device |
CN103107547B (en) * | 2013-01-23 | 2015-03-11 | 华南理工大学 | Reactive compensation differentiation collocation method of 10kV distribution lines |
CN103474985B (en) * | 2013-06-27 | 2015-05-27 | 国家电网公司 | Realization method for function of adaptive load type distribution transformer |
CN104009482B (en) * | 2014-05-21 | 2017-01-25 | 华南理工大学 | Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode |
-
2015
- 2015-03-12 CN CN201510107783.8A patent/CN104779625B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN104779625A (en) | 2015-07-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104779625B (en) | Capacitive reactive compensation configuration method for 110kV transformer substation in saturated load region | |
CN103701140B (en) | Improve the dynamic reactive optimization method for subsequent use of alternating current-direct current electrical network Transient Voltage Stability | |
CN103346577B (en) | Reduce wind energy turbine set AVC powerless control system and the method for wind power loss | |
CN201805234U (en) | Comprehensive voltage reactive power control system with harmonic suppression function | |
CN105703401B (en) | A kind of emergency control method for being suitable for honourable power station | |
CN103094913B (en) | Optimal configuration of 10 kV power distribution network parallel reactor and compensation method of 10 kV power distribution network parallel reactor | |
CN107863777B (en) | It is a kind of to consider powerless control method when low anti-sending end converter station high power fluctuates | |
CN102694386B (en) | Electrified railway negative sequence unbalance compensation method | |
CN111009906B (en) | Reactive compensation balancing method for full cable net rack | |
CN106451487A (en) | 220kV urban power grid reactive power compensation method | |
CN110138002A (en) | Offshore wind farm reactive configuration method, device, computer equipment and storage medium | |
CN108376986B (en) | Reactive voltage control method and device for power distribution network | |
CN104538966A (en) | Hybrid compensation system for negative-sequence current in high speed railway | |
CN103401249B (en) | Reactive power automatic arrangement method based on available resource of reactive equipment | |
CN104917188B (en) | Powerless control method is coordinated in a kind of 220kV transformer stations packet | |
CN105720589A (en) | Reactive power control method and system of convertor station | |
CN105449707A (en) | Distributed photovoltaic power generation access method | |
CN103368180B (en) | Timing sequence optimization control method for distributed power flow controller, and controller | |
CN104868481B (en) | A kind of capacitance compensation method for making the active loss of distribution network whole day minimum | |
CN104377711B (en) | A kind of dynamic reactive compensating method | |
CN102646983B (en) | Long-term reactive voltage analyzing and optimizing method in power system | |
CN105186527A (en) | 220 kV transformer station binding type reactive compensation capacity configuration method | |
Zhao et al. | Optimal Configuration of ESS and SVG for the Coordinated Improvement of Power Quality in Low Voltage Distribution Network with high Penetration PV | |
CN102983578A (en) | Medium voltage distribution network reactive power counterbonification method | |
CN113852142A (en) | Multi-voltage-level static and dynamic reactive power configuration method for multi-direct-current feed-in power grid |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170419 |