CN104863621B - Integrated device is transported in roadway support - Google Patents

Integrated device is transported in roadway support Download PDF

Info

Publication number
CN104863621B
CN104863621B CN201510161317.8A CN201510161317A CN104863621B CN 104863621 B CN104863621 B CN 104863621B CN 201510161317 A CN201510161317 A CN 201510161317A CN 104863621 B CN104863621 B CN 104863621B
Authority
CN
China
Prior art keywords
track
umbrella
pneumatic
support
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510161317.8A
Other languages
Chinese (zh)
Other versions
CN104863621A (en
Inventor
谢强珍
陈建峰
周文川
张云宁
张伟合
韦节园
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING SHUANGTAI PNEUMATIC EQUIPMENT Co Ltd
Yanzhou Coal Industry Co Ltd
Original Assignee
BEIJING SHUANGTAI PNEUMATIC EQUIPMENT Co Ltd
Yanzhou Coal Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING SHUANGTAI PNEUMATIC EQUIPMENT Co Ltd, Yanzhou Coal Industry Co Ltd filed Critical BEIJING SHUANGTAI PNEUMATIC EQUIPMENT Co Ltd
Priority to CN201510161317.8A priority Critical patent/CN104863621B/en
Publication of CN104863621A publication Critical patent/CN104863621A/en
Application granted granted Critical
Publication of CN104863621B publication Critical patent/CN104863621B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Chain Conveyers (AREA)

Abstract

The invention discloses the roadway support transport integrated device that a kind of present invention is provided, for tunnelling material transportation and work surface meet head on before visit gib, including with tunnel at the top of hard-wired track, also include the pneumatic traction devices being installed on track, also include promoting suspension device along slide by pneumatic traction devices, suspension device is slidably mounted on track by its bogey;Roadway support transport integrated device is also included by the assistant conveyance device of pneumatic traction devices drives edge slide.Using setting track in the tunnel for completing supporting, pneumatic traction devices are installed on track, the gib that spy before new pick section is carried out is reached using pneumatic promotion suspension device, the minority Manpower operating device is needed only by complete support work, entrance is withdrawn from conveniently, work efficiency is higher, it also avoid the danger that manpower is directly operated;Assistant conveyance device is installed also, weight handling is carried out along track, it is to avoid manpower lift to move improves work efficiency.

Description

Integrated device is transported in roadway support
Technical field
A kind of the present invention relates to Work machine technical field under mine, more particularly, it relates to thing for tunnelling Material transport and work surface visit the roadway support transport integrated device of gib before meeting head on.
Background technology
At present, with modernization development, energy demand is growing, and the big country as coal production, the annual coal of China The yield of charcoal is constantly being lifted, and the coal production for ending the end of the year 2008 whole nation breaches 2,400,000,000 tons, and coal production has in China Very important effect.
In existing mine operation, it is pure artificial operation in most cases that work surface visits gib operation before meeting head on, In not fully safe new pick tunnel, workman is needed to be climbed and assembled protecting wire net ladder beam.And manually installed suspension device Not only activity duration length, supporting intensity are low, seriously lack setting load, and after brill installs anchor pole, also want artificial unloading whole Supporting.There is of short duration operating risk in the operation for manually carrying out upper protecting network and terraced beam in the process, and work efficiency is relatively low.
In addition, meet head on manpower transport and very universal along the situation of ground dragging heavy in conventional tunnel, using manpower Not only personnel's occupancy is more for lift fortune weight, and physical demandss are big, and long-term operation will result in damage to staff's body.
In sum, how to efficiently solve pure artificial operation carries out the work efficiency of gib and its related work Low, labor strength is excessive and the problems such as relatively low safety, be current those skilled in the art's urgent problem.
Content of the invention
In view of this, it is an object of the invention to provide a kind of roadway support transport integrated device, the roadway support transport The structure design of integrated device can efficiently solve pure artificial operation and carry out the work efficiency of gib and its related work Low, labor strength is excessive and the problems such as relatively low safety.
In order to achieve the above object, the present invention provides following technical scheme:
Integrated device is transported in a kind of roadway support, for tunnelling material transportation and work surface meet head on before visit interim Shield, including with tunnel at the top of hard-wired track, also include the pneumatic traction devices being installed on track, pneumatic traction dress Put to roll by the wheel group of its grip track and promote its orbital motion, also include being promoted along slide by pneumatic traction devices Suspension device, suspension device is slidably mounted on track by its bogey, and bogey is connected with pneumatic traction devices, Suspension device also includes the supporting umbrella being connected with bogey one end;Roadway support transport integrated device is also included by pneumatic traction The assistant conveyance device of device drives edge slide, assistant conveyance device are included along the coaster of slide and are installed with coaster The air hoist of connection.
Preferably, in above-mentioned roadway support transport integrated device, suspension device also includes the support chassis for supporting supporting umbrella, Supporting umbrella is connected with bogey by support chassis.
Preferably, in above-mentioned roadway support transport integrated device, bogey is hung on track before and after including two groups side by side On suspension arm, away from supporting umbrella one group of suspension arm be provided with adjustment supporting umbrella position and attitude adjusting screw.
Preferably, in above-mentioned roadway support transport integrated device, away from being fixedly installed on one group of suspension arm of supporting umbrella Support cylinder, support cylinder one end are connected with suspension arm, are offseted at the top of the other end and tunnel.
Preferably, in above-mentioned roadway support transport integrated device, push-tight cylinder is additionally provided between support chassis and supporting umbrella, Push-tight cylinder one end is fixedly connected with support chassis position, and the other end is connected with supporting umbrella.
Preferably, in above-mentioned roadway support transport integrated device, supporting pack includes many bars and is hinged strutting or receiving for composition The support cylinder that tight umbrella body and driving umbrella body are strutted or tightened up, umbrella body surface is equipped with protecting wire net.
Preferably, in above-mentioned roadway support transport integrated device, umbrella body includes several bows for support being arranged side by side The bracing frame of horizontally set between ellbeam and bow beam, bow beam and support chassis are provided with the toggle that opens an umbrella, and support cylinder and support Umbrella toggle connects, and drives the toggle that opens an umbrella movable to strut or tighten up umbrella body.
Preferably, in above-mentioned roadway support transport integrated device, pneumatic traction devices are connected with complemental brake system side by side, The normally closed braking vane of brake of fitting with track is provided with complemental brake system, and normally closed braking vane is connected with the normally closed braking vane of change The brake cylinder of operating attitude.
Preferably, in above-mentioned roadway support transport integrated device, pneumatic traction devices pass through pull bar and the universal joint being hinged It is connected with bogey, coaster and complemental brake system respectively.
Preferably, in above-mentioned roadway support transport integrated device, air hoist includes pneumatic cord winder and aerobraking Device, pneumatic braking system are to open the normally closed brake unit that air valve is just opened.
The present invention provide roadway support transport integrated device, for tunnelling material transportation and work surface meet head on before Visit gib, including with tunnel at the top of hard-wired track, also include the pneumatic traction devices being installed on track, gas Dynamic traction apparatuss are rolled by the wheel group of its grip track and promote its orbital motion, also include promoting edge by pneumatic traction devices The suspension device of slide, suspension device are slidably mounted on track by its bogey, bogey and pneumatic traction Device connects, and suspension device also includes the supporting umbrella being connected with bogey one end;Roadway support transport integrated device also includes By the assistant conveyance device of pneumatic traction devices drives edge slide, assistant conveyance device include along slide coaster and The air hoist being connected is installed with coaster.Using complete supporting arrange and bore dress anchor pole tunnel in arrange top rail, And pneumatic traction devices are installed in orbit, promoting forward suspension device to reach using pneumatic traction devices does not carry out track laying Work surface meet head on pick section new to tunnel carry out before spy gib, put and complete supporting using gas-operated integrated makeup, pacify On installation tool device basic, use compressed air as the power of operation supporting, being largely avoided workman is directly carried out Supporting is operated, and completes support work by only needing the minority Manpower operating device, and suspension device can be with need to enter to enter temporarily Enter or withdraw from work convenient, once assembling can carry out multiple support work, and work efficiency is greatly improved, while it also avoid work People directly carries out a variety of danger of support work;Additionally, being also equipped with the assistant conveyance promoted by pneumatic traction devices on track Device, the assistant conveyance device can carry out the handling back and forth of weight along track, it is to avoid manpower carries out lift to move, and machinery replaces people Power substantially increases work efficiency, and it also avoid workman carries out the too high work of intensity, reduces the damage of workman's body of knowing clearly.Comprehensive Upper described, the structure design of the roadway support transport integrated device efficiently solves pure artificial operation carries out gib and its phase Close the inefficiency of work, the problem that labor strength is excessive and safety is relatively low.
Description of the drawings
For the technical scheme being illustrated more clearly that in the embodiment of the present invention, below will be to making needed for embodiment description Accompanying drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the present invention, for For those of ordinary skill in the art, on the premise of not paying creative work, can be obtaining other according to these accompanying drawings Accompanying drawing.
Fig. 1 is the structural representation that integrated device is transported in roadway support provided in an embodiment of the present invention;
Fig. 2 is the side structure schematic view of suspension device provided in an embodiment of the present invention;
Fig. 3 is the overlooking the structure diagram of suspension device provided in an embodiment of the present invention;
Fig. 4 is the positive structure diagram of the suspension arm away from supporting umbrella provided in an embodiment of the present invention;
Fig. 5 is the positive structure diagram of supporting umbrella provided in an embodiment of the present invention;
Fig. 6 is the overlooking the structure diagram of supporting umbrella provided in an embodiment of the present invention;
Fig. 7 is the side structure schematic view of supporting umbrella provided in an embodiment of the present invention;
In wherein Fig. 5, what dotted portion was presented is the structure under supporting umbrella tightening state.
In accompanying drawing, labelling is as follows:
1 is track, 2 is pneumatic traction devices, 3 is complemental brake system, 4 is suspension device, 41 is supporting umbrella, 411 are Bow beam, 412 be the toggle that opens an umbrella, 413 for support cylinder, 414 be bracing frame, 42 be support chassis, 43 be suspension arm, 431 be Adjusting screw, 44 be push-tight cylinder, 45 be support cylinder, 5 for auxiliary conveying arrangement, 51 be coaster, 52 be air hoist.
Specific embodiment
The embodiment of the invention discloses a kind of material transportation and work surface for tunnelling visits gib before meeting head on Roadway support transport integrated device, carry out the inefficiency of gib and its related work to solve pure artificial operation, The problem that labor strength is excessive and safety is more low.
Accompanying drawing in below in conjunction with the embodiment of the present invention, to the embodiment of the present invention in technical scheme carry out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiment.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
Fig. 1-Fig. 7 is referred to, Fig. 1 to Fig. 7 is respectively roadway support transport integrated device provided in an embodiment of the present invention Structural representation;The side-looking of suspension device, vertical view and positive structure diagram;Supporting umbrella 41 is faced, is overlooked and side-looking structure Schematic diagram.
The present invention provide roadway support transport integrated device, for tunnelling material transportation and work surface meet head on before Visit gib, including with tunnel at the top of hard-wired track 1, also include the pneumatic traction devices being installed on track 1 2, pneumatic traction devices 2 are rolled by the wheel group of its grip track 1 and promote which to move along track 1, also include being filled by pneumatic traction The suspension device 4 that 2 promotions are slided along track 1 is put, suspension device 4 is slidably mounted on track 1 by its bogey, carry dress Put and be connected with pneumatic traction devices 2, suspension device 4 also includes the supporting umbrella 41 being connected with bogey one end;Roadway support is transported Defeated integrated device also includes that the assistant conveyance device 5 slided by 2 drives edge track 1 of pneumatic traction devices, assistant conveyance device 5 are wrapped Include the coaster 51 slided along track 1 and the air hoist 52 being connected with the installation of coaster 51.
Wherein it should be noted that track 1 is fixedly installed in by the common technology means such as anchor pole complete supporting whitewashing Tunnel section top;The wheel group of grip track 1 is provided with pneumatic traction devices 2, and is provided with the pneumatic dynamic of drive wheel group rotation Power structure, including parts such as air motor, decelerators, due to the existing usual usage paradigm of the technology of pneumatic power structure, therefore does not exist This enumerates;Promoted from pneumatic traction devices 2 and referred specifically to suspension device 4 to work along the suspension device 4 that track 1 slides As face meet head on before visit and promote, make suspension device 4 reach the position for needing to carry out gib that track 1 had not been laid, or temporarily Supporting has been completed, and is needed to pack up suspension device 4 to rear haulage or is carried out other operations;Bogey is used for suspension device 4 with track 1 to being connected, and support the weight of of suspension device 4 itself and support force needed for supporting be provided.
Using complete supporting arrange and bore dress anchor pole tunnel in arrange top rail 1, and on path 1 install gas Dynamic traction apparatuss 2, using pneumatic traction devices 2 promote forward suspension device 4 reach do not carry out track 1 laying work surface meet head on The gib that pick section new to tunnel is visited before carrying out, is put using gas-operated integrated makeup and completes supporting, installing machinery base On plinth, use compressed air as the power of operation supporting, being largely avoided workman directly carries out supporting operation, only needs The minority Manpower operating device can complete support work, and suspension device 4 can be entered or withdraw from work temporarily with entering Convenient, once assembling can carry out multiple support work, and work efficiency is greatly improved, while it also avoid workman directly to carry out propping up A variety of danger that nurse makees;Additionally, being also equipped with the assistant conveyance device 5 promoted by pneumatic traction devices 2 on track 1, this is auxiliary Help the conveying arrangement 5 can to carry out the handling back and forth of weight along track 1, it is to avoid manpower carries out lift to move, machinery replaces manpower significantly Work efficiency is improve, it also avoid workman carries out the too high work of intensity, reduces the damage of workman's body of knowing clearly.To sum up institute State, the structure design of the roadway support transport integrated device efficiently solves pure artificial operation carries out gib and its related labor The inefficiency of work, the problem that labor strength is excessive and safety is relatively low.
Design with the connection of bogey for further optimizing suspension device 4 in above-mentioned technical proposal, in above-described embodiment On the basis of, suspension device 4 also includes the support chassis 42 for supporting supporting umbrella 41, and supporting umbrella 41 is by support chassis 42 and carrying Device connects.Wherein it should be noted that support chassis 42 are the rigid structure with certain length, its length bearing of trend is put down Row, because which is responsible for for supporting umbrella 41 stretching out track 1 forwards and is needed to support supporting due to which in 1 bearing of trend of track Umbrella 41 conducts power to bogey, so support chassis 42 will have enough rigidity.
Using this design for connecting bogey and supporting umbrella 41 by support chassis 42, make the supporting umbrella 41 can There is enough supporting distances and the global design of suspension device 4 is optimized from structure, structure is simple and reliable effectively to be completed Technical assignment.
Design with the connection of bogey for further optimizing suspension device 4 in above-mentioned technical proposal, in above-described embodiment On the basis of, bogey includes the suspension arm 43 being hung on before and after two groups side by side on track 1, and a group away from supporting umbrella 41 hangs Upper arm 43 is provided with the adjusting screw 431 of 41 position and attitude of adjustment supporting umbrella.Wherein it should be noted that two groups of suspension arms 43 1 Previous 1 bearing of trend of tailing edge track is arranged side by side;In addition adjusting screw 431 described herein actually includes more than one set leading screw Structure, respectively referring to 431 horizontally set of adjusting screw in Fig. 3 and Fig. 4, Fig. 3 is used for carrying out one to 41 right position of supporting umbrella Fixed rotation is adjusted, and the adjusting screw 431 in Fig. 4 is longitudinally disposed for being finely adjusted to 41 height of supporting umbrella.
Using this technical scheme, using the weight of two groups of supporting suspension devices 4 of suspension arm 43 in front and back, the stability of carrying Higher, prevent 42 sagging deflections of support chassis or in improperly operating attitude, and due to one group of suspension away from supporting umbrella 41 Arm 43 is provided with the adjusting screw 431 of 41 position and attitude of adjustment supporting umbrella, and ensure that in structure to carry out operations described below:When When shield umbrella 41 needs to carry out pitching or the regulation of right position operation, suspension device 4 can be with the suspension arm near supporting umbrella 41 43 is fulcrum with the contact point of track 1, and rotating the regulation screw mandrel away from one group of suspension arm 43 of supporting umbrella 41 carries out pitching or a left side Right position adjustment.
For further optimizing the support effect of suspension device 4 in above-mentioned technical proposal, on the basis of above-described embodiment, far Support cylinder 45 is fixedly installed on one group of suspension arm 43 of supporting umbrella 41,45 one end of support cylinder is connected with suspension arm 43, Offset at the top of the other end and tunnel.Using the design of this support cylinder 45, with one group of suspension arm 43 near supporting umbrella 41 Supporting umbrella 41 is held out against upward for fulcrum and carry out supporting at the top of tunnel, and contribute to power source by the use of pneumatic as power Unified.
For further optimizing the support effect of suspension device 4 in above-mentioned technical proposal, on the basis of above-described embodiment, Push-tight cylinder 44 is additionally provided between support chassis 42 and supporting umbrella 41, and 44 one end of push-tight cylinder is fixed with 42 position of support chassis and connected Connect, the other end is connected with supporting umbrella 41.Using the design of this push-tight cylinder 44, supporting umbrella 41 can be held out against forwards in lane Supporting is carried out at the top of road, and by the use of the pneumatic unification for contributing to power source as power.
For further optimizing the design of supporting umbrella 41 in above-mentioned technical proposal, on the basis of above-described embodiment, Shield umbrella 41 includes the support cylinder 413 that many bars are hinged the umbrella body for strutting or tightening up of composition and drive umbrella body to strut or tighten up, Umbrella body surface is equipped with protecting wire net.The operability that folding be ensure that using this umbrella body design being hinged, using support cylinder 413 Umbrella body is driven to strut or pack up, the umbrella body being easy under collapsed state is strutted after entering different top working environments again, or It is easy to pack up after the completion of support work withdraw from, and by the use of the pneumatic unification for contributing to power source as power.
For further optimizing the design of supporting umbrella 41 in above-mentioned technical proposal, on the basis of above-described embodiment, umbrella Body includes the bracing frame 414 of horizontally set between several bow beams 411 and bow beam 411 for support being arranged side by side, bow Ellbeam 411 and support chassis 42 are provided with the toggle 412 that opens an umbrella, and support cylinder 413 to be connected with the toggle 412 that opens an umbrella, drive the hinge that opens an umbrella 412 activity of bar is strutting or tighten up umbrella body.
For further optimize above-mentioned technical proposal in 5 position adjustment of suspension device 4 and assistant conveyance device motility and Safety, on the basis of above-described embodiment, pneumatic traction devices 2 are connected with complemental brake system 3, complemental brake system side by side The normally closed braking vane of brake of fitting with track 1 is provided with 3, and normally closed braking vane is connected with and changes normally closed braking vane operating attitude Brake cylinder.Using this complemental brake system 3, only in the case of brake cylinder ventilation, i.e. pneumatic traction devices 2 start Ability take-off the brake on the premise of towage is carried out, largely ensure that the overall safety of device, it is to avoid in anon-normal In the case of often, on track 1 there is the situation of uncontrollable shift in position in suspension device 4 or assistant conveyance device 5, it is ensured that Ren Yuanan Complete and construction is smoothed out.
For further optimizing the connection on above-mentioned technical proposal middle orbit 1 between each building block, in above-described embodiment On the basis of, pneumatic traction devices 2 pass through the pull bar being hinged and universal joint is filled with bogey, coaster 51 and auxiliary braking respectively Put 3 connections.Effectively prevent as track 1 is distorted and it is irregular right to install using the interconnection technique scheme of universal joint plus draw bar The motion of the miscellaneous part that installs on pneumatic traction devices 2 and track 1 is impacted.
For further optimizing the safety in utilization of assistant conveyance device 5 in above-mentioned technical proposal, in the base of above-described embodiment On plinth, air hoist 52 includes pneumatic cord winder and pneumatic braking system, and pneumatic braking system is to open air valve just to open Normally closed brake unit.There is improper falling in the case of the lifting weight of air hoist 52 is avoided using this normally closed mode of braking Situation.
In this specification, each embodiment is described by the way of going forward one by one, and what each embodiment was stressed is and other The difference of embodiment, between each embodiment identical similar portion mutually referring to.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or using the present invention. Multiple modifications of these embodiments will be apparent for those skilled in the art, as defined herein General Principle can be realized without departing from the spirit or scope of the present invention in other embodiments.Therefore, the present invention The embodiments shown herein is not intended to be limited to, and is to fit to and principles disclosed herein and features of novelty phase one The most wide scope for causing.

Claims (8)

1. integrated device is transported in a kind of roadway support, for tunnelling material transportation and work surface meet head on before visit interim Shield, it is characterised in that include and hard-wired track (1) at the top of tunnel, also includes being installed on pneumatic on the track (1) Traction apparatuss (2), are provided with wheel group of grip track (1) in pneumatic traction devices (2), and wheel group is rolled and promotes described pneumatic lead Leading-in device (2) is moved along track (1), also includes being promoted the suspension device slided along track (1) by the pneumatic traction devices (2) (4), suspension device (4) are slidably mounted on the track (1) by its bogey, the bogey and the gas Dynamic traction apparatuss (2) connect, and suspension device (4) also include the supporting umbrella (41) being connected with described bogey one end;Institute The assistant conveyance that roadway support transport integrated device also includes being slided is stated by the pneumatic traction devices (2) drives edge track (1) Device (5), assistant conveyance device (5) are included the coaster (51) slided along the track (1) and are pacified with the coaster (51) The air hoist (52) that load connects;
Suspension device (4) also include the support chassis (42) for supporting supporting umbrella (41), and supporting umbrella (41) pass through Support chassis (42) are connected with the bogey;
Bogey includes the suspension arm (43) being hung on before and after two groups side by side on the track (1), away from the supporting umbrella (41) suspension arm (43) described in one group is provided with the adjusting screw (431) of adjustment supporting umbrella (41) position and attitude.
2. integrated device is transported in roadway support according to claim 1, it is characterised in that away from supporting umbrella (41) Support cylinder (45), support cylinder (45) one end and the suspension arm is fixedly installed on suspension arm (43) described in a group (43) connect, offset at the top of the other end and tunnel.
3. integrated device is transported in roadway support according to claim 1, it is characterised in that support chassis (42) and institute State and between supporting umbrella (41), be additionally provided with push-tight cylinder (44), push-tight cylinder (44) one end and the support chassis (42) position It is fixedly connected, the other end is connected with supporting umbrella (41).
4. integrated device is transported in roadway support according to claim 3, it is characterised in that described supporting umbrella (41) include many The support cylinder (413) that bar is hinged the umbrella body for strutting or tightening up of composition and drives the umbrella body to strut or tighten up, the umbrella Body surface face is equipped with protecting wire net.
5. integrated device is transported in roadway support according to claim 4, it is characterised in that the umbrella body include several side by side The bracing frame (414) of horizontally set, the bow between the bow beam (411) for support for arranging and the bow beam (411) Ellbeam (411) and the support chassis (42) are provided with the toggle that opens an umbrella (412), support cylinder (413) and the hinge that opens an umbrella Bar (412) connects, and drives the toggle (412) that opens an umbrella movable to strut or tighten up umbrella body.
6. the roadway support transport integrated device according to any one of claim 1 to 5, it is characterised in that described pneumatic lead Leading-in device (2) is connected with side by side to be provided with complemental brake system (3), complemental brake system (3) and is pasted with the track (1) The normally closed braking vane of brake is closed, the normally closed braking vane is connected with the brake cylinder for changing the normally closed braking vane operating attitude.
7. integrated device is transported in roadway support according to claim 6, it is characterised in that pneumatic traction devices (2) Connected with the bogey, the coaster (51) and the complemental brake system (3) by the pull bar and universal joint that are hinged respectively Connect.
8. integrated device is transported in roadway support according to claim 1, it is characterised in that air hoist (52) include Pneumatic cord winder and pneumatic braking system, the pneumatic braking system are to open the normally closed brake unit that air valve is just opened.
CN201510161317.8A 2015-04-07 2015-04-07 Integrated device is transported in roadway support Active CN104863621B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510161317.8A CN104863621B (en) 2015-04-07 2015-04-07 Integrated device is transported in roadway support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510161317.8A CN104863621B (en) 2015-04-07 2015-04-07 Integrated device is transported in roadway support

Publications (2)

Publication Number Publication Date
CN104863621A CN104863621A (en) 2015-08-26
CN104863621B true CN104863621B (en) 2017-03-15

Family

ID=53909744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510161317.8A Active CN104863621B (en) 2015-04-07 2015-04-07 Integrated device is transported in roadway support

Country Status (1)

Country Link
CN (1) CN104863621B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106285752B (en) * 2016-09-14 2018-06-08 安徽理工大学 It is a kind of can local directed complete set rigidity immediate support device
CN106837398B (en) * 2017-04-24 2019-10-25 北京双泰气动设备有限公司 The comprehensive pneumatic temporary support device of pick
CN108046125B (en) * 2017-10-23 2019-04-30 太原科技大学 Lifting conveyer for air return lane fully-mechanized mining equipment maintenance part
CN110182230B (en) * 2019-07-01 2024-01-30 中铁二院工程集团有限责任公司 Suspended track beam and pneumatic system
CN111561334B (en) * 2020-05-21 2021-12-14 湖南新田岭钨业有限公司 Temporary protection supporting equipment for ore mining working face and supporting method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4269547A (en) * 1978-05-25 1981-05-26 Harding John D Tunnel roof supporting apparatus
CN202031619U (en) * 2011-04-15 2011-11-09 山西大同大学 Suspended mobile temporary supporting device of excavation roadway
CN102587951A (en) * 2012-03-17 2012-07-18 河南理工大学 Hydraulic U-type steel bracket supporting machine
CN103790602A (en) * 2014-02-14 2014-05-14 山东兖煤黑豹矿业装备有限公司 Single track hydraulic temporary support device
CN203669906U (en) * 2014-01-15 2014-06-25 煤炭科学研究总院南京研究所 Suspension type hydraulic temporary support device for coal mine tunnel
CN204163746U (en) * 2014-09-29 2015-02-18 四川省华蓥山煤业股份有限公司绿水洞煤矿 Hang the scalable forestope of automatic moving type

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4269547A (en) * 1978-05-25 1981-05-26 Harding John D Tunnel roof supporting apparatus
CN202031619U (en) * 2011-04-15 2011-11-09 山西大同大学 Suspended mobile temporary supporting device of excavation roadway
CN102587951A (en) * 2012-03-17 2012-07-18 河南理工大学 Hydraulic U-type steel bracket supporting machine
CN203669906U (en) * 2014-01-15 2014-06-25 煤炭科学研究总院南京研究所 Suspension type hydraulic temporary support device for coal mine tunnel
CN103790602A (en) * 2014-02-14 2014-05-14 山东兖煤黑豹矿业装备有限公司 Single track hydraulic temporary support device
CN204163746U (en) * 2014-09-29 2015-02-18 四川省华蓥山煤业股份有限公司绿水洞煤矿 Hang the scalable forestope of automatic moving type

Also Published As

Publication number Publication date
CN104863621A (en) 2015-08-26

Similar Documents

Publication Publication Date Title
CN104863621B (en) Integrated device is transported in roadway support
CN106837392B (en) Tunnel gantry type multifunctional supporting trolley
CN107524454A (en) Tunnelling supporting robot, matched bracket and method for protecting support
CN2934580Y (en) Dust-removing device of fully-mechanized coal driving workface
CN202148909U (en) Operation vehicle for mounting tunnel arch trusses
CN102278131B (en) Duct piece conveying device for shield construction of tunnel with diameter of less than 6 meters and operation method
CN107473102B (en) A kind of miniature crawler belt derrick car of substation equipment maintenance and repair
CN108331603A (en) A kind of multi-functional trolley and its construction method
CN201148278Y (en) Hydraulic belt winding apparatus
CN205855853U (en) A kind of underground mine use track hoisting machine
CN204984431U (en) Tunnelling protects platform with single track cat
CN208502802U (en) A kind of multi-functional trolley
CN202266295U (en) Duct piece conveying device for shield construction of tunnels with diameters smaller than six meters
CN103449115B (en) The collapsible fuselage of belt conveyer and extension band type conveyor
CN105240035A (en) Hydraulic bracket mounting carrier vehicle
CN204492846U (en) Movable type with inverted arch lining device crosses car trestle
CN206409251U (en) A kind of double rail type waterproof cloth chassis
CN109519199B (en) Shield tunnel segment supporting trolley
CN108999570A (en) Tunnel drill carriage
CN201826859U (en) U-shaped support mounting machine
CN208024369U (en) A kind of multifunctional tunnel arch Mobile workbench
CN105239515A (en) Device and method for bracket installation of railway protective scaffolding in combined highway and railway bridge
CN206972279U (en) The tunnel basket steel arch-shelf fitting machine of two-arm two
CN203362166U (en) Supporting work platform for heading roadway
CN206448809U (en) Pick, branch, anchor, drill integrated fully-mechanized digging machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant