CN104852362A - 适用于含分布式电源的配电网过流保护方法和网架结构 - Google Patents

适用于含分布式电源的配电网过流保护方法和网架结构 Download PDF

Info

Publication number
CN104852362A
CN104852362A CN201510189339.5A CN201510189339A CN104852362A CN 104852362 A CN104852362 A CN 104852362A CN 201510189339 A CN201510189339 A CN 201510189339A CN 104852362 A CN104852362 A CN 104852362A
Authority
CN
China
Prior art keywords
protection
power source
distribution network
distributed power
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510189339.5A
Other languages
English (en)
Inventor
唐诚
郝留成
高树同
杨志勇
关永刚
李万岭
汪宁
张明礼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsinghua University
State Grid Corp of China SGCC
Pinggao Group Co Ltd
Original Assignee
Tsinghua University
State Grid Corp of China SGCC
Pinggao Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsinghua University, State Grid Corp of China SGCC, Pinggao Group Co Ltd filed Critical Tsinghua University
Priority to CN201510189339.5A priority Critical patent/CN104852362A/zh
Publication of CN104852362A publication Critical patent/CN104852362A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

本发明涉及适用于含分布式电源的配电网过流保护方法和网架结构,在馈线上的母线两侧均设置断路器;对含分布式电源的馈线,根据分布式电源的数量进行分段,在分布式电源接入点两侧均设置断路器;所有保护配置功率方向元件和无通道保护判据;根据双端供电配电网阶梯时间整定原则,对各保护进行延时时间整定;每段线路两侧保护分别按不同套的阶梯时间整定:一侧的保护按照由大到小整定,另一侧的按照由小到大整定。本发明将定时限方向过电流保护和无通道加速保护相结合运用到含DG配电网继电保护中,完成故障的快速定位与隔离,实现全线路相继速动,是一种兼顾经济与可靠性的方案。

Description

适用于含分布式电源的配电网过流保护方法和网架结构
技术领域
本发明涉及一种适用于含分布式电源的配电网过流保护方法和网架结构。
背景技术
传统配电网一般采用“闭环网络,开环运行”运行方式,线路故障时短路电流从电源端流向故障点;分布式电源(DG)接入后,单电源辐射型网络变成了多电源网络,故障时短路电流的来源、方向和分布将受到分布式电源的类型、接入位置以及容量的影响。DG接入后对传统继电保护的影响:
如图1所示,当K1点发生非金属性短路故障时,断路器B1处电流仍由系统S提供,DG1、DG2的接入使故障电流增大、故障点电压升高,导致断路器B1处故障电流降低,使B1处保护灵敏性降低甚至拒动。断路器B2处短路电流由DG2提供,B2跳闸使DG2隔离,但DG1必须依靠自身解列与故障点隔离。
当K2点发生短路故障时,断路器B1、B2处均流过短路电流,DG1提供的短路电流使断路器B2处短路电流大于B1处,利于B2处保护动作,增加了保护灵敏度。但DG2必须依靠自身解列与故障点隔离。
当K3点发生非金属接地故障时,断路器B1~B3处均流过短路电流,若DG容量较大,会导致B1或B2处速断保护误动。
由以上分析可知:传统的三段式电流保护在含DG配电网中并不适用,DG的存在易使保护拒动或误动。在双端供电配网中应用广泛的定时限方向过电流保护,也不适合含DG配电网,因为DG数量众多,线路分级、分段较多,根据阶梯时间整定原则难以与上级保护相配合。
申请号为200910067641.8的中国专利申请提出了一种《含分布式电源配电网保护方法》,用于解决含分布式电源的配电网继电保护问题,其中主要使用纵联保护,而纵联保护属于通道保护,保护较为复杂。
发明内容
本发明的目的是提供一种适用于含分布式电源的配电网过流保护方法,用以解决现有过电流保护不适用于带分布式电源的配电网的问题。基于以上方法,本发明还提供一种含分布式电源的配电网新型网架结构。
本发明提供了一种适用于含分布式电源的配电网过流保护方法,在馈线上的母线两侧均设置断路器;对含分布式电源的馈线,根据分布式电源的数量进行分段,在分布式电源接入点两侧均设置断路器;所有保护配置功率方向元件和无通道保护判据;根据双端供电配电网定时限过流保护阶梯时间整定原则,对各保护进行延时时间整定;每段线路两侧保护分别按不同套的阶梯时间整定:一侧的保护按照由大到小整定,另一侧的按照由小到大整定;发生不对称故障时,根据短路功率方向启动保护,经整定时间延时后,故障线路一端断路器动作跳闸,造成健全相电流发生突变,根据所述无通道保护判据,另一端保护在对应的整定时间内检测到电流突变,则判断为区内故障,加速本端断路器动作。
进一步的,根据保护之间的配合和实际结构整定时间。
本发明还提供了一种含分布式电源的网架结构,在馈线上的母线两侧均设置断路器;对含分布式电源的馈线,根据分布式电源的数量进行分段,在分布式电源接入点两侧均设置断路器。
本发明将定时限方向过电流保护和无通道加速保护相结合运用到含DG配电网继电保护中,完成故障的快速定位与隔离,实现全线路相继速动。虽然增加一些设备(断路器和功率方向元件),但是其投入相对于配电自动化主站的建设可忽略不计,是一种兼顾经济与可靠性的方案。并且采用无通道保护,保护相对简单。
附图说明
图1是含DG的配电网传统网架结构图;
图2是含DG的配电网新型网架结构图。
具体实施方式
方法实施例
为了保护的实施,需要对传统网架结构进行改进,形成一种新的配电网网架结构,如图2所示,即在馈线上的母线两侧均设置断路器,以及对含DG的馈线,根据DG的数量进行分段,在DG接入点两侧加装断路器。
对于保护装置,所有保护处增加功率方向元件。功率方向:由母线流向线路为正。各保护处添加无通道保护判据,进行加速保护。
根据双端供电配电网定时限过流保护阶梯时间整定原则,对各保护进行延时时间整定。每段线路两侧保护分别按不同套的阶梯时间整定。例如断路器B1、B2处保护按一套时间,由大到小整定;断路器B4、B5处保护按另一套时间,由小到大整定。
发生短路故障后,只有短路功率方向为正时,保护才会启动。经整定时间延时后,故障线路一端断路器动作跳闸,引起系统结构发生变化,造成健全相电流发生突变,根据无通道保护判据,另一端继电器在整定时间内检测到电流突变,则判断为区内故障,加速本端断路器动作。
举例来说,图2中,K1点发生不对称故障时,断路器B1、B4、B5处短路功率方向为正,过电流保护启动;经过一定延时后,断路器B4首先动作跳闸(B4处整定时间短于B1处整定时间),断路器B5过电流保护返回;断路器B1处在整定时间里检测到非故障相电流突变,加速跳闸。
图2中K2点发生不对称故障时,断路器B1、B2、B5处短路功率方向为正,过电流保护启动;经过一定延时后,断路器B5动作跳闸;断路器B1、B2处均检测到非故障相电流突变,断路器B2处突变发生在预先整定时间内,动作跳闸;短路器B1处突变不在预先整定时间内,不会加速动作,在断路器B2跳闸后过电流保护返回。
图2中K3点发生不对称故障时,断路器B3、B4处短路功率方向正,过电流保护启动;一般情况断路器B4处保护整定时间小于B3处,为了避免B4误动,断路器B3应由其对侧断路器加速跳闸;断路器B4过电流保护返回。
含有DG配电网过电流保护时间整定应综合考虑所有馈线保护延时时间,如图2中K3故障时,应保证断路器B3在B4动作之前加速动作,即B3线路对侧保护整定时间小于B4处保护整定时间。
上述含DG配电网过电流保护加速方法的说明,没有给出过流保护具体整定时间,是因为配电网结构复杂多变,应根据实际结构整定时间,注意保护之间的配合。也没有给出具体的无通道保护判据,无通道保护判据可以在现有技术手段中进行选取。
含分布式电源的网架结构实施例
本实施例中的网架结构与实施例1中图2应用的网架结构完全相同,故不再赘述。
以上给出了本发明涉及两个主题的具体的实施方式,但本发明不局限于所描述的实施方式。在本发明给出的思路下,采用对本领域技术人员而言容易想到的方式对上述实施例中的技术手段进行变换、替换、修改,并且起到的作用与本发明中的相应技术手段基本相同、实现的发明目的也基本相同,这样形成的技术方案是对上述实施例进行微调形成的,这种技术方案仍落入本发明的保护范围内。

Claims (3)

1.适用于含分布式电源的配电网过流保护方法,其特征在于,在馈线上的母线两侧均设置断路器;对含分布式电源的馈线,根据分布式电源的数量进行分段,在分布式电源接入点两侧均设置断路器;
所有保护配置功率方向元件和无通道保护判据;
根据双端供电配电网定时限过流保护阶梯时间整定原则,对各保护进行延时时间整定;每段线路两侧保护分别按不同套的阶梯时间整定:一侧的保护按照由大到小整定,另一侧的按照由小到大整定;
发生不对称故障时,根据短路功率方向启动保护,经整定时间延时后,故障线路一端断路器动作跳闸,造成健全相电流发生突变,根据所述无通道保护判据,另一端保护在对应的整定时间内检测到电流突变,则判断为区内故障,加速本端断路器动作。
2.根据权利要求1所述的适用于含分布式电源的配电网过流保护方法,其特征在于,根据保护之间的配合和实际结构整定时间。
3.含分布式电源的网架结构,其特征在于,在馈线上的母线两侧均设置断路器;对含分布式电源的馈线,根据分布式电源的数量进行分段,在分布式电源接入点两侧均设置断路器。
CN201510189339.5A 2015-04-20 2015-04-20 适用于含分布式电源的配电网过流保护方法和网架结构 Pending CN104852362A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510189339.5A CN104852362A (zh) 2015-04-20 2015-04-20 适用于含分布式电源的配电网过流保护方法和网架结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510189339.5A CN104852362A (zh) 2015-04-20 2015-04-20 适用于含分布式电源的配电网过流保护方法和网架结构

Publications (1)

Publication Number Publication Date
CN104852362A true CN104852362A (zh) 2015-08-19

Family

ID=53851802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510189339.5A Pending CN104852362A (zh) 2015-04-20 2015-04-20 适用于含分布式电源的配电网过流保护方法和网架结构

Country Status (1)

Country Link
CN (1) CN104852362A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106786413A (zh) * 2016-11-14 2017-05-31 国网江苏省电力公司常州供电公司 含分布式光伏电源配电网的电流保护方法
CN112510657A (zh) * 2020-11-11 2021-03-16 广西电网有限责任公司电力科学研究院 含分布式电源接入的馈线自动化线路故障处理方法及系统

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0564355A (ja) * 1991-08-30 1993-03-12 Toyoda Gosei Co Ltd ネツトワーク配電用逆電力保護方法
CN1960106A (zh) * 2006-10-16 2007-05-09 北京交通大学 一种基于多种传统保护技术的集成保护系统
CN102270835A (zh) * 2011-01-30 2011-12-07 武汉百叡电力技术有限公司 配电网分布式过电流保护和相间故障隔离的方法
CN103022993A (zh) * 2012-11-23 2013-04-03 上海交通大学 基于goose的自适应级联方向闭锁继电保护方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0564355A (ja) * 1991-08-30 1993-03-12 Toyoda Gosei Co Ltd ネツトワーク配電用逆電力保護方法
CN1960106A (zh) * 2006-10-16 2007-05-09 北京交通大学 一种基于多种传统保护技术的集成保护系统
CN102270835A (zh) * 2011-01-30 2011-12-07 武汉百叡电力技术有限公司 配电网分布式过电流保护和相间故障隔离的方法
CN103022993A (zh) * 2012-11-23 2013-04-03 上海交通大学 基于goose的自适应级联方向闭锁继电保护方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
魏嫔: "微型电网的过电流保护问题及其对策", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑(月刊)》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106786413A (zh) * 2016-11-14 2017-05-31 国网江苏省电力公司常州供电公司 含分布式光伏电源配电网的电流保护方法
CN106786413B (zh) * 2016-11-14 2018-10-30 国网江苏省电力公司常州供电公司 含分布式光伏电源配电网的电流保护方法
CN112510657A (zh) * 2020-11-11 2021-03-16 广西电网有限责任公司电力科学研究院 含分布式电源接入的馈线自动化线路故障处理方法及系统

Similar Documents

Publication Publication Date Title
Zamani et al. A protection strategy and microprocessor-based relay for low-voltage microgrids
Zamani et al. A communication-assisted protection strategy for inverter-based medium-voltage microgrids
CN103378583A (zh) 一种基于智能快速真空断路器的馈线自动化技术方案
Lee et al. A study on wind-turbine generator system sizing considering overcurrent relay coordination with SFCL
CN105932658B (zh) 一种利用配电网消弧装置进行配电网消弧的方法
CN104852361B (zh) 配电网故障切除加速方法和继电保护装置
Sherbilla et al. Modified setting of overcurrent protection for distribution feeders with distributed generation
Manditereza et al. Introducing a new type of protection zone for the smart grid incorporating distributed generation
CN104852362A (zh) 适用于含分布式电源的配电网过流保护方法和网架结构
CN105024360A (zh) 配网开关站继电保护运行优化方法
CN204012700U (zh) 配电网中性点接地系统
Pawar et al. Transient overvoltages in power system
CN103560501A (zh) 可控型小电阻消弧装置和方法
Lou et al. Delayed current zero crossing characteristics for circuit breaker interrupting short-circuit current following permanent single-phase ground fault on short 1000kV AC lines
Martinez-Velasco et al. EMTP model for analysis of distributed generation impact on voltage sags
Johnnerfelt et al. Coordination of arrester and disconnector characteristics for optimized application of line arresters
Mubarak et al. An analytical study of power system under The fault conditions using different methods of fault analysis
Horsfall et al. Relay Coordination Analysis in SPDC Forcados Distribution Network for Operation, Planning and Future Expansion.
Karady et al. Feasibility of fast pilot protection for multi-load distribution systems
Zeqo et al. Impact of replacement of conventional recloser with PulseCloser
CN110401177A (zh) 一种10kv线路保护装置及其使用方法
CN105322512B (zh) 一种基于自学习的微电网保护方法
CN104158160A (zh) E型基于柱上开关的10kv配电线路及故障检测方法
Tian et al. The analysis of distributed generation influence on feeder protection
Tahata et al. Investigation of suppression effect of short-circuit current and voltage drop in multi-terminal HVDC by DC reactor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150819