CN104848753A - Rock blasting control construction method implemented near existing railway line - Google Patents

Rock blasting control construction method implemented near existing railway line Download PDF

Info

Publication number
CN104848753A
CN104848753A CN201510183959.8A CN201510183959A CN104848753A CN 104848753 A CN104848753 A CN 104848753A CN 201510183959 A CN201510183959 A CN 201510183959A CN 104848753 A CN104848753 A CN 104848753A
Authority
CN
China
Prior art keywords
hole
carry out
construction method
railway line
existing railway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510183959.8A
Other languages
Chinese (zh)
Inventor
张建慈
杨云
魏晓江
古辉荣
魏勇
欧剑
李飞龙
刘杰
邓熙
符望春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Original Assignee
China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 25th Bureau Group Co Ltd filed Critical China Railway 25th Bureau Group Co Ltd
Priority to CN201510183959.8A priority Critical patent/CN104848753A/en
Publication of CN104848753A publication Critical patent/CN104848753A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a rock blasting control construction method implemented near an existing railway line. The method comprises the steps of field investigation, design of a blasting and protecting scheme, hole arrangement, hole drilling, calculation of the single-hole explosive filling amount, explosive filling, blocking blasting and other steps. According to the rock blasting control construction method implemented near the existing railway line, an appropriate method is selected, blasting parameters are adjusted, blasting and protecting are combined, a blasted body only becomes loose after blasting, and the situation that flying stones fly disorderly to damage the existing railway line is avoided.

Description

One closes on Existing Railway Line stone excavation construction method
Technical field
The present invention relates to Blasting Control technical field of construction, particularly relate to one and close on Existing Railway Line stone excavation construction method.
Background technology
Both wired stone excavation construction, be close to the other cutting that carries out of the existing route run to expand the construction of moat rock blasting, require when not affecting train and normally running, train operation gap is utilized to implement explosion, accomplish by quick-fried rock-mass relaxing simultaneously and do not cave in, effectively ensureing the safety of existing line and affiliated facility.Because concussion of blasting is strong, can slungshot be produced in the process of explosion, produce huge threat to closing on both wired operations, therefore, need continuous summing up experience, reach and weaken concussion of blasting, eliminate the effect of slungshot, but existing blasting method effect not very desirable.
Summary of the invention
In order to solve the problem in background technology, the present invention proposes one and close on Existing Railway Line stone excavation construction method, it is by selecting suitable method, and adjust blasting parameter, explosion and protection are combined, after explosion, blasting body only produces loosening, avoids the random destruction flown existing line of slungshot.
The one that the present invention proposes closes on Existing Railway Line stone excavation construction method, comprises the following steps:
A, field investigation, then carry out explosion and protectiving scheme design according to field condition;
B, according to protectiving scheme design carry out cloth hole and set up protection framed bent;
Carry out holing after terminating and carry out the inspection of big gun hole in C, cloth hole; Wherein, the boring direction maintaining each artillery salvo hole in the process of boring is parallel, adopt angling hole, and inclination angle, big gun hole is 70-80 °;
D, according to geology, ambient conditions, calculate single hole explosive payload powder charge; In the process of powder charge, powder charge is monitored and checks;
E, by multiple-row blasting post-tensioning warning line and discharge signal, carry out covered protection and totally-enclosed by wall type protection framed bent simultaneously;
F, properly protect after detonate;
G, detonate terminate after carry out inspection and to go forward side by side post processing of doing good works.
Preferably, in B, the mode of carrying out cloth hole is the combination of a kind of in many row rectangular cloth holes and triangle cloth hole or two kinds.
Preferably, in C, inclination angle, big gun hole is 72-78 °.
Preferably, in C, inclination angle, big gun hole is 75 °.
Preferably, in C, the degree of depth in institute's brill big gun hole is 2.5-3.8m, and borehole spacing is 1.8-3m.
Preferably, in E, stemming length is 0.8-1m.
The one that the present invention proposes closes on Existing Railway Line stone excavation construction method, it by selecting suitable method, and adjusts blasting parameter, and explosion and protection are combined, after explosion, blasting body only produces loosening, avoids the random destruction flown existing line of slungshot.
Detailed description of the invention
Below, by specific embodiment, technical scheme of the present invention is described in detail.
Embodiment 1
One closes on Existing Railway Line stone excavation construction method, comprises the following steps:
A, field investigation, then carry out explosion and protectiving scheme design according to field condition;
B, according to protectiving scheme design carry out cloth hole and set up protection framed bent;
Carry out holing after terminating and carry out the inspection of big gun hole in C, cloth hole; Wherein, the boring direction maintaining each artillery salvo hole in the process of boring is parallel, adopt angling hole, and inclination angle, big gun hole is 70 °;
D, according to geology, ambient conditions, calculate single hole explosive payload powder charge; In the process of powder charge, powder charge is monitored and checks;
E, by multiple-row blasting post-tensioning warning line and discharge signal, carry out covered protection and totally-enclosed by wall type protection framed bent simultaneously;
F, properly protect after detonate;
G, detonate terminate after carry out inspection and to go forward side by side post processing of doing good works.
Embodiment 2
One closes on Existing Railway Line stone excavation construction method, comprises the following steps:
A, field investigation, then carry out explosion and protectiving scheme design according to field condition;
B, according to protectiving scheme design carry out cloth hole and set up protection framed bent;
Carry out holing after terminating and carry out the inspection of big gun hole in C, cloth hole; Wherein, the boring direction maintaining each artillery salvo hole in the process of boring is parallel, adopt angling hole, and inclination angle, big gun hole is 80 °;
D, according to geology, ambient conditions, calculate single hole explosive payload powder charge; In the process of powder charge, powder charge is monitored and checks;
E, by multiple-row blasting post-tensioning warning line and discharge signal, carry out covered protection and totally-enclosed by wall type protection framed bent simultaneously;
F, properly protect after detonate;
G, detonate terminate after carry out inspection and to go forward side by side post processing of doing good works.
Embodiment 3
One closes on Existing Railway Line stone excavation construction method, comprises the following steps:
A, field investigation, then carry out explosion and protectiving scheme design according to field condition;
B, according to protectiving scheme design carry out cloth hole and set up protection framed bent; Wherein, pattern is many row rectangular cloth holes;
Carry out holing after terminating and carry out the inspection of big gun hole in C, cloth hole; Wherein, the boring direction maintaining each artillery salvo hole in the process of boring is parallel, and adopt angling hole, and inclination angle, big gun hole is 72 °, the degree of depth in institute's brill big gun hole is 2.5m, and borehole spacing is 3m;
D, according to geology, ambient conditions, calculate single hole explosive payload powder charge; In the process of powder charge, powder charge is monitored and checks;
E, by multiple-row blasting post-tensioning warning line and discharge signal, carry out covered protection and totally-enclosed by wall type protection framed bent simultaneously; Wherein, stemming length is 0.8m;
F, properly protect after detonate;
G, detonate terminate after carry out inspection and to go forward side by side post processing of doing good works.
Embodiment 4
One closes on Existing Railway Line stone excavation construction method, comprises the following steps:
A, field investigation, then carry out explosion and protectiving scheme design according to field condition;
B, according to protectiving scheme design carry out cloth hole and set up protection framed bent; Wherein, pattern is triangle cloth hole;
Carry out holing after terminating and carry out the inspection of big gun hole in C, cloth hole; Wherein, the boring direction maintaining each artillery salvo hole in the process of boring is parallel, and adopt angling hole, and inclination angle, big gun hole is 78 °, the degree of depth in institute's brill big gun hole is 3.8m, and borehole spacing is 1.8m;
D, according to geology, ambient conditions, calculate single hole explosive payload powder charge; In the process of powder charge, powder charge is monitored and checks;
E, by multiple-row blasting post-tensioning warning line and discharge signal, carry out covered protection and totally-enclosed by wall type protection framed bent simultaneously; Wherein, stemming length is 1m;
F, properly protect after detonate;
G, detonate terminate after carry out inspection and to go forward side by side post processing of doing good works.
Embodiment 5
One closes on Existing Railway Line stone excavation construction method, comprises the following steps:
A, field investigation, then carry out explosion and protectiving scheme design according to field condition;
B, according to protectiving scheme design carry out cloth hole and set up protection framed bent; Wherein, pattern is the combination in many row rectangular cloth holes and two kinds, triangle cloth hole;
Carry out holing after terminating and carry out the inspection of big gun hole in C, cloth hole; Wherein, the boring direction maintaining each artillery salvo hole in the process of boring is parallel, and adopt angling hole, and inclination angle, big gun hole is 75 °, the degree of depth in institute's brill big gun hole is 3.5m, and borehole spacing is 2.2m;
D, according to geology, ambient conditions, calculate single hole explosive payload powder charge; In the process of powder charge, powder charge is monitored and checks;
E, by multiple-row blasting post-tensioning warning line and discharge signal, carry out covered protection and totally-enclosed by wall type protection framed bent simultaneously; Wherein, stemming length is 0.9m;
F, properly protect after detonate;
G, detonate terminate after carry out inspection and to go forward side by side post processing of doing good works.
The above; be only the present invention's preferably detailed description of the invention; but protection scope of the present invention is not limited thereto; anyly be familiar with those skilled in the art in the technical scope that the present invention discloses; be equal to according to technical scheme of the present invention and inventive concept thereof and replace or change, all should be encompassed within protection scope of the present invention.

Claims (6)

1. close on an Existing Railway Line stone excavation construction method, it is characterized in that, comprise the following steps:
A, field investigation, then carry out explosion and protectiving scheme design according to field condition;
B, according to protectiving scheme design carry out cloth hole and set up protection framed bent;
Carry out holing after terminating and carry out the inspection of big gun hole in C, cloth hole; Wherein, the boring direction maintaining each artillery salvo hole in the process of boring is parallel, adopt angling hole, and inclination angle, big gun hole is 70-80 °;
D, according to geology, ambient conditions, calculate single hole explosive payload powder charge; In the process of powder charge, powder charge is monitored and checks;
E, by multiple-row blasting post-tensioning warning line and discharge signal, carry out covered protection and totally-enclosed by wall type protection framed bent simultaneously;
F, properly protect after detonate;
G, detonate terminate after carry out inspection and to go forward side by side post processing of doing good works.
2. close on Existing Railway Line stone excavation construction method according to claim 1, it is characterized in that, in B, the mode of carrying out cloth hole is the combination of a kind of in many row rectangular cloth holes and triangle cloth hole or two kinds.
3. close on Existing Railway Line stone excavation construction method according to claim 1, it is characterized in that, in C, inclination angle, big gun hole is 72-78 °.
4. close on Existing Railway Line stone excavation construction method according to claim 3, it is characterized in that, in C, inclination angle, big gun hole is 75 °.
5. close on Existing Railway Line stone excavation construction method according to claim 1, it is characterized in that, in C, the degree of depth in institute's brill big gun hole is 2.5-3.8m, and borehole spacing is 1.8-3m.
6. according to any one of claim 1-5, close on Existing Railway Line stone excavation construction method, it is characterized in that, in E, stemming length is 0.8-1m.
CN201510183959.8A 2015-04-20 2015-04-20 Rock blasting control construction method implemented near existing railway line Pending CN104848753A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510183959.8A CN104848753A (en) 2015-04-20 2015-04-20 Rock blasting control construction method implemented near existing railway line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510183959.8A CN104848753A (en) 2015-04-20 2015-04-20 Rock blasting control construction method implemented near existing railway line

Publications (1)

Publication Number Publication Date
CN104848753A true CN104848753A (en) 2015-08-19

Family

ID=53848583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510183959.8A Pending CN104848753A (en) 2015-04-20 2015-04-20 Rock blasting control construction method implemented near existing railway line

Country Status (1)

Country Link
CN (1) CN104848753A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105698619A (en) * 2016-02-03 2016-06-22 中铁隧道集团有限公司 Blasting construction method used before construction of mountain shortcuts above existing roads
CN114877765A (en) * 2022-06-14 2022-08-09 保利长大工程有限公司 Blasting control method for temporary traffic road section
CN116771273A (en) * 2023-06-21 2023-09-19 中国水利水电第三工程局有限公司 High-short-circuit cutting stone blasting excavation method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102419140A (en) * 2011-11-25 2012-04-18 中铁十二局集团第三工程有限公司 Multielement three-dimensional safety protection method
CN103629980A (en) * 2013-12-16 2014-03-12 中铁二十三局集团第四工程有限公司 Adjacent existing railway steep mountain loosen control blast construction method
CN204027464U (en) * 2014-08-21 2014-12-17 中铁二十局集团第三工程有限公司 The major diameter of the closing on existing railway line basic shallow blasting excavation construction structure that digs a well

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102419140A (en) * 2011-11-25 2012-04-18 中铁十二局集团第三工程有限公司 Multielement three-dimensional safety protection method
CN103629980A (en) * 2013-12-16 2014-03-12 中铁二十三局集团第四工程有限公司 Adjacent existing railway steep mountain loosen control blast construction method
CN204027464U (en) * 2014-08-21 2014-12-17 中铁二十局集团第三工程有限公司 The major diameter of the closing on existing railway line basic shallow blasting excavation construction structure that digs a well

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
何广沂等: "《电气化铁路既有线扩堑石方控制爆破安全快速施工技术》", 《中国工程科学》 *
叶宗毅: "《既有铁路扩堑石方控制爆破施工技术》", 《铁道工程学报》 *
黄忠恩: "《铁路既有线扩堑石方控制爆破施工技术》", 《现代企业文化》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105698619A (en) * 2016-02-03 2016-06-22 中铁隧道集团有限公司 Blasting construction method used before construction of mountain shortcuts above existing roads
CN114877765A (en) * 2022-06-14 2022-08-09 保利长大工程有限公司 Blasting control method for temporary traffic road section
CN116771273A (en) * 2023-06-21 2023-09-19 中国水利水电第三工程局有限公司 High-short-circuit cutting stone blasting excavation method
CN116771273B (en) * 2023-06-21 2024-03-19 中国水利水电第三工程局有限公司 High-short-circuit cutting stone blasting excavation method

Similar Documents

Publication Publication Date Title
CN102914226B (en) Hollow-hole rhombic parallel cut blasting damping method
CN104634198B (en) Close on controlled blasting construction method in the massif excavation of highway limit
CN103061781B (en) Method for preventing rock burst by manually regulating tunnel surrounding rock support energy dissipation damping characteristics
CN103924956B (en) A kind of lump coal exploitation Advance presplitting method
CN103629980A (en) Adjacent existing railway steep mountain loosen control blast construction method
CN104848753A (en) Rock blasting control construction method implemented near existing railway line
CN102692164B (en) Stress unloading, water injecting and drilling and blasting method for longitudinal structure surface structural strong rockburst regions
CN102494571A (en) Construction method for damped blasting of tunnels
CN107339920B (en) The method of superdeep holes presplit blasting
CN105823387A (en) Rapid construction method for deep hole blasting of vertical shaft frozen bedrock
CN109855496B (en) Comprehensive melon breaking type deep hole cutting blasting method for hard rock in tunnel
CN103075933A (en) Large-wedge-shaped multi-repeated cutting groove construction process
CN102607353A (en) Open bench inter-hole differential control blasting method
CN105466290A (en) Cutting excavation blasting method
CN102735124A (en) Deep hole explosion top board attenuation method
CN104482817A (en) Deep-buried tunnel stress relieving pre-splitting blasting method
CN111521069A (en) Carbon dioxide phase change directional pressure relief fracturing device for tunneling and use method thereof
CN109186390B (en) Open-air deep hole blasting water interval-coupled charging blasting method and special water column bag
CN103398639B (en) A kind of destructor of removing obstacles for broken stone
Sazid et al. Effective explosive energy utilization for engineering blasting–initial results of an inventive stemming plug, SPARSH
CN102269544A (en) One-end-closed cumulative blasting slotted pipe device
CN102494570A (en) Energy collecting blasting and smooth surface blasting combined control blasting method
CN107300454A (en) Chip stream safeguard structure impact test device
CN102980453B (en) Water injection drilling and blasting method for unloading stress of structural strong rock burst area of horizontal structural surface
CN105588479A (en) Three-times elementary error vibration reduction major blasting method using rock flour spaced loading in blasting holes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150819

RJ01 Rejection of invention patent application after publication