CN104836190A - Relay protection setting calculating method of power plant electric power system - Google Patents

Relay protection setting calculating method of power plant electric power system Download PDF

Info

Publication number
CN104836190A
CN104836190A CN201510244269.9A CN201510244269A CN104836190A CN 104836190 A CN104836190 A CN 104836190A CN 201510244269 A CN201510244269 A CN 201510244269A CN 104836190 A CN104836190 A CN 104836190A
Authority
CN
China
Prior art keywords
power plant
relay protection
power
protection setting
loaded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510244269.9A
Other languages
Chinese (zh)
Other versions
CN104836190B (en
Inventor
李雪冬
蔡宁宁
杨敏
胡凯波
于乐
屈国际
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING JOIN BRIGHT ELECTRIC POWER TECHNOLOGY Co Ltd
Zhejiang Co Ltd Of Zhe Neng Institute For Research And Technology
Original Assignee
BEIJING JOIN BRIGHT ELECTRIC POWER TECHNOLOGY Co Ltd
Zhejiang Co Ltd Of Zhe Neng Institute For Research And Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING JOIN BRIGHT ELECTRIC POWER TECHNOLOGY Co Ltd, Zhejiang Co Ltd Of Zhe Neng Institute For Research And Technology filed Critical BEIJING JOIN BRIGHT ELECTRIC POWER TECHNOLOGY Co Ltd
Priority to CN201510244269.9A priority Critical patent/CN104836190B/en
Publication of CN104836190A publication Critical patent/CN104836190A/en
Application granted granted Critical
Publication of CN104836190B publication Critical patent/CN104836190B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a relay protection setting calculating method of a power plant electric power system. When a computer algorithm is adopted, power network models (the primary wiring relations of power networks) need to be converted into mathematic models of the power networks, a conventionally adopted method involves converting all the power network models, yet the method provided by the invention only involves converting a part of the power network models. The method provided by the invention greatly reduces the size of the loaded mathematic models, reduces the dimension number of a node admittance matrix, shortens the matrix inversion time and greatly accelerates the operation speed. According to the relay protection setting calculating method of the power plant electric power system, the power network models are loaded towards a last load layer according to the position of a fault branch, the power network models are not loaded for devices at the same layer or at a lower load layer, and the power network models are all loaded for a primary wiring portion.

Description

The relay protection setting calculation method of a kind of power plant electric power system
Technical field
The invention belongs to the technical field of electric power system adaptive setting, relate to the relay protection setting calculation method of a kind of power plant electric power system particularly.
Background technology
For a long time; factory's net integration runs; power plant relay protection management and fixed value adjusting calculate to be responsible for by relevant electric network protection specialty always; so power plant calculates the calculation of fault analysis of relaying protection specialty, fixed value adjusting and management work attention degree is inadequate; after causing separating the factory and network, power plant relaying protection specialty becomes a weak link.
At present, all adopt software of adjusting at transmission line adaptive setting, its rapidity calculated and accuracy obtain general accreditation.And shortcoming is also compared in the work in power plant protection seting, most of power plant still adopts the mode of artificial hand computation to carry out fault analysis and protection and adjusts, and the epoch that this and computer nowadays develop rapidly are not suitable with.
Now modeling is carried out to power plant, carry out setting parameter calculating.Because power plant forms primarily of three digest journals, coal burning system, boiler circuit and electrical system.When modeling, electrical system is called main electrical scheme part, coal burning system and boiler circuit are called the loaded portion of power plant.Each part is made up of a lot of mini system, and wherein combustion system comprises fuel system, boiler combustion system, dedusting ash disposal system and ventilating system; Boiler circuit comprises water supply system, cooling water system unifies water charging system; Electrical system comprises turbine control system, Auxiliary Power Control System, directly sends circuit or boosting transformation station control system.Therefore, the electric parameter of power plant is numerous and complicated, and computational process is obviously also extremely complicated.Power plant's internal loading layer is more, and along with the increase of load layer, during calculation of fault, nodes sharply increases, and for computer, causes very large workload.
Summary of the invention
Technology of the present invention is dealt with problems and is: overcome the deficiencies in the prior art; the relay protection setting calculation method of a kind of power plant electric power system is provided; which greatly reduce the size loading electric network model; reduce the dimension of node admittance battle array; shorten the time of matrix inversion, accelerate arithmetic speed greatly.
Technical solution of the present invention is: the relay protection setting calculation method of this power plant electric power system; the method is according to the position of a fault branch upwards load layer loading electric network model; equipment for same layer or a low load layer does not load electric network model, all loads electric network model for main electrical scheme part.
This method is according to a fault branch position upwards load layer loading electric network model, for the equipment of same layer or a low load layer, its resistance value and operational mode can not have impact to result of calculation, so do not need to load this part electric network model, all load for main electrical scheme part.Due to when calculating, first node admittance matrix will be generated, then Node impedance matrix is obtained after admittance matrix being inverted, because relate to a large amount of calculating operations to inverting of matrix, along with its used time exponentially of inverting of increase of nodes rises, reduced the operation of nodes by loading section electric network model, greatly reduce the size of stress model, reduce the dimension of node admittance battle array, shorten the time of matrix inversion, accelerate arithmetic speed greatly.
Accompanying drawing explanation
Fig. 1 shows the flow chart of the relay protection setting calculation method according to power plant of the present invention electric power system;
Fig. 2 shows the primary connection figure of certain power plant.
Embodiment
The relay protection setting calculation method of this power plant electric power system; the method is according to the position of a fault branch upwards load layer loading electric network model; equipment for same layer or a low load layer does not load electric network model, all loads electric network model for main electrical scheme part.
This method is according to a fault branch position upwards load layer loading electric network model, for the equipment of same layer or a low load layer, its resistance value and operational mode can not have impact to result of calculation, so do not need to load this part electric network model, all load for main electrical scheme part.Due to when calculating, first node admittance matrix will be generated, then Node impedance matrix is obtained after admittance matrix being inverted, because relate to a large amount of calculating operations to inverting of matrix, along with its used time exponentially of inverting of increase of nodes rises, reduced the operation of nodes by loading section electric network model, greatly reduce the size loading electric network model, reduce the dimension of node admittance battle array, shorten the time of matrix inversion, accelerate arithmetic speed greatly.
Preferably, as shown in Figure 1, the method comprises the following steps:
(1) start;
(2) fault branch is determined;
(3) judge whether this fault branch is positioned at main electrical scheme scope, if it is perform step (6), otherwise perform step (4);
(4) using this bus as starting point, check upper level bus;
(5) judge whether upper level bus is positioned at main electrical scheme scope, if it is perform step (6), otherwise perform step (4);
(6) whole electric network models of main wiring diagram are loaded;
(7) Mathematical Modeling has generated.
Provide a specific embodiment below.The primary connection figure of certain power plant as shown in Figure 2, eliminates the loaded portion of 6kV1B, 6kV2A and 6kV2B in figure, and the loaded portion of 400V steam turbine PC section, 400V defeated coal PC1 section and 400V defeated coal PC2 section.As fault occurs in 400V steam turbine PC section, the higher level's bus so upwards finding fault point is 6kV1A section, bus 400V steamer PC section and 1# steamer are become to be loaded in computational mathematics model, because bus 6kV1A section is the main wiring diagram of power plant, no longer upwards search the Mathematical Modeling directly main wiring diagram all being loaded the calculating being just this, the Mathematical Modeling of so final loading is that accompanying drawing 2 removes dotted portion.
The above; it is only preferred embodiment of the present invention; not any pro forma restriction is done to the present invention, every above embodiment is done according to technical spirit of the present invention any simple modification, equivalent variations and modification, all still belong to the protection range of technical solution of the present invention.

Claims (2)

1. the relay protection setting calculation method of a power plant electric power system; it is characterized in that: the method is according to the position of a fault branch upwards load layer loading electric network model; equipment for same layer or a low load layer does not load electric network model, all loads electric network model for main electrical scheme part.
2. the relay protection setting calculation method of power plant according to claim 1 electric power system, is characterized in that: the method comprises the following steps:
(1) start;
(2) fault branch is determined;
(3) judge whether this fault branch is positioned at main electrical scheme scope, if it is perform step (6), otherwise perform step (4);
(4) using this bus as starting point, check upper level bus;
(5) judge whether upper level bus is positioned at main electrical scheme scope, if it is perform step (6), otherwise perform step (4);
(6) whole models of main wiring diagram are loaded;
(7) Mathematical Modeling has generated.
CN201510244269.9A 2015-05-13 2015-05-13 A kind of relay protection setting calculation method of power plant electric system Expired - Fee Related CN104836190B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510244269.9A CN104836190B (en) 2015-05-13 2015-05-13 A kind of relay protection setting calculation method of power plant electric system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510244269.9A CN104836190B (en) 2015-05-13 2015-05-13 A kind of relay protection setting calculation method of power plant electric system

Publications (2)

Publication Number Publication Date
CN104836190A true CN104836190A (en) 2015-08-12
CN104836190B CN104836190B (en) 2018-06-15

Family

ID=53813893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510244269.9A Expired - Fee Related CN104836190B (en) 2015-05-13 2015-05-13 A kind of relay protection setting calculation method of power plant electric system

Country Status (1)

Country Link
CN (1) CN104836190B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108233324A (en) * 2017-12-29 2018-06-29 国家电网公司 Electric network model and computational methods based on more power type relay protection setting calculations
CN112366665A (en) * 2020-11-05 2021-02-12 北京中恒博瑞数字电力科技有限公司 Method and device for quickly breaking N-1 turns of line in relay protection setting calculation
CN112417372A (en) * 2020-12-07 2021-02-26 国网新疆电力有限公司 Fixed value setting calculation method and system suitable for power grid of any scale

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103001170A (en) * 2012-11-15 2013-03-27 宁波天灵信息科技有限公司 Setting calculation method and system of power grid relay protection setting values
CN103227452A (en) * 2012-01-31 2013-07-31 上海利乾电力科技有限公司 Computing method of protection fixed value of relay of power plant
CN103632308A (en) * 2013-11-01 2014-03-12 广东电网公司电力调度控制中心 Grid-related power plant relay protection fixed value risk evaluation system based on expert system
CN104392065A (en) * 2014-12-08 2015-03-04 国网甘肃省电力公司刘家峡水电厂 Method for generating model of power protection device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103227452A (en) * 2012-01-31 2013-07-31 上海利乾电力科技有限公司 Computing method of protection fixed value of relay of power plant
CN103001170A (en) * 2012-11-15 2013-03-27 宁波天灵信息科技有限公司 Setting calculation method and system of power grid relay protection setting values
CN103632308A (en) * 2013-11-01 2014-03-12 广东电网公司电力调度控制中心 Grid-related power plant relay protection fixed value risk evaluation system based on expert system
CN104392065A (en) * 2014-12-08 2015-03-04 国网甘肃省电力公司刘家峡水电厂 Method for generating model of power protection device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
谭李师: "《基于母线的节点导纳矩阵计算机生成方法》", 《电力建设》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108233324A (en) * 2017-12-29 2018-06-29 国家电网公司 Electric network model and computational methods based on more power type relay protection setting calculations
CN112366665A (en) * 2020-11-05 2021-02-12 北京中恒博瑞数字电力科技有限公司 Method and device for quickly breaking N-1 turns of line in relay protection setting calculation
CN112417372A (en) * 2020-12-07 2021-02-26 国网新疆电力有限公司 Fixed value setting calculation method and system suitable for power grid of any scale
CN112417372B (en) * 2020-12-07 2024-02-09 国网新疆电力有限公司 Fixed value setting calculation method and system suitable for power grid of any scale

Also Published As

Publication number Publication date
CN104836190B (en) 2018-06-15

Similar Documents

Publication Publication Date Title
CN103985058B (en) Available transfer capability calculation method based on improved multiple centrality-correction interior point method
CN111008468A (en) Test method and test system of comprehensive energy management system
US11616365B2 (en) Decentralized hardware-in-the-loop scheme
CN109918762B (en) AC/DC power grid hybrid simulation comparison model construction method
CN111061986A (en) Load flow calculation method of thermoelectric integrated energy system with multiple operation modes
CN109782625B (en) Real-time simulation method and system for circuit model
CN104836190A (en) Relay protection setting calculating method of power plant electric power system
CN103956775A (en) Micro-grid analogue simulation system based on real-time digital simulation platform
CN107784168A (en) The full working scope analogue system of nuclear power station half speed turbine system
CN109066768A (en) The double-fed fan motor unit combined simulation system and method for multiple-variable flow device parallel connection
CN104485661B (en) A kind of trend automatic adjusting method based on node type conversion
CN110162843B (en) Real-time simulation modeling method and device for power grid primary system and secondary system
CN112072692A (en) Impedance equivalence method and device for new energy power generation station
CN111092427B (en) Path optimization method for parallel recovery of power system
CN105406517A (en) Finite time average consistency algorithm-based economic dispatching method for power system
Pico et al. Reachability analysis of power system frequency dynamics with new high-capacity HVAC and HVDC transmission lines
CN111339624B (en) PSASP and EMTP/ATP-based short-circuit current direct-current component calculation method
CN108615121B (en) Thermoelectric load distribution method and system based on multi-factor influence
CN105302979A (en) Modeling method and system of valve groups in two-phase fluid network model
CN112182905B (en) Heat supply pipe network simulation method and device for comprehensive energy system
CN101546179B (en) Nonlinear simulation device of overheater of power generating set
CN104332205A (en) Simulation method, device and system for sequence control function of nuclear auxiliary plant local control system
KR101759893B1 (en) Virtual device management apparatus based on scenario for distributed energy resources
Hayes et al. Viable computation of the largest Lyapunov characteristic exponent for power systems
CN204302786U (en) The hardware-in-the-loop simulation system of combustion gas distributed generation system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180615

CF01 Termination of patent right due to non-payment of annual fee