CN104794365B - 一种基于数学模型预测锚杆极限承载力的计算方法 - Google Patents
一种基于数学模型预测锚杆极限承载力的计算方法 Download PDFInfo
- Publication number
- CN104794365B CN104794365B CN201510226191.8A CN201510226191A CN104794365B CN 104794365 B CN104794365 B CN 104794365B CN 201510226191 A CN201510226191 A CN 201510226191A CN 104794365 B CN104794365 B CN 104794365B
- Authority
- CN
- China
- Prior art keywords
- bearing capacity
- anchor pole
- anchor
- shear stress
- anchor rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及锚杆锚固中对锚杆承载力进行检测的方法技术领域,具体涉及一种基于数学模型预测锚杆极限承载力的计算方法,包括以下步骤:步骤一:建立锚固界面剪切滑移模型;步骤二:确定锚杆的极限抗拔荷载;步骤三:确定锚固长度对粘结强度的影响系数ψ,确定岩体的裂隙间距对粘结强度的影响系数K1、确定岩体的裂隙张开度与充填物对粘结强度的影响系数K2;步骤四:确定预测锚杆极限承载力的数学模型。本发明通过对实际工程锚杆承载力影响因素的分析与探讨,对锚杆承载力计算公式进行修正,得到综合条件下锚杆承载力计算模型。可准确预测出锚杆极限承载力,且精准度和稳定度较高,可广泛应用于实际工程中。
Description
技术领域
本发明涉及锚杆锚固中对锚杆承载力进行检测的方法技术领域,具体涉及一种基于数学模型预测锚杆极限承载力的计算方法。
背景技术
锚杆锚固技术具有成本低廉、加工简便、安装方便、施工速度快等优点,其在岩土工程中发挥着越来越重要的作用,但其极限承载力的精准确定一直是一大难题。我国锚杆的实际抗拔力大多是通过现场拉拔实验得出来的,而拉拔实验常常是带有破坏性的,而且拉拔的数量也有限定,需要寻找合理的模型计算并预测其极限抗拔力。有许多学者提出了锚杆承载力的计算理论,但这些理论方法还是存在一定的局限性:难以满足在复杂环境下围岩支护技术的要求;极限承载力预测建立在弹塑性锚杆剪应力与位移的线性关系上;不能精确地预测出实际工程锚杆极限承载力。
针对锚杆承载力计算模型,浆体与岩土体界面是锚固系统的薄弱面,在弹性状态下,全长粘结式锚杆所受的剪应力范围较小,而最大剪应力数值较大,锚杆的剪应力与锚杆运动位移成线性关系。大量工程实践表明,周围环境的综合性与复杂性使得锚杆剪应力—位移关系趋于曲线,该曲线基本包括3个特征段:第I阶段为弹性变形阶段;第II阶段为弹塑性混合变形阶段,随着荷载的增大,锚固段部分区域内剪应力达到极限值而开始产生塑性变形,形成局部塑性区且塑性区随着荷载的增大而逐步扩展,第III阶段为塑性变形段或破坏阶段,塑性变形贯通锚固界面,锚杆的抗拔荷载主要由锚固界面的残余剪切强度提供,此时即使增加较小的轴向荷载也会产生很大位移。为了确定锚杆的极限抗拔荷载,在实际应用中,通常采用合理的数学模型对实测荷载位移数据进行拟合以预测锚杆的极限抗拔荷载值,根据弹性力学中的物理关系知锚杆的抗拔荷载与锚杆的剪应力成正相关,二者的变化趋势基本相同。
现有技术中也出现了一些采用针对数学模型锚杆承载力的预测方法,例如专利号为201410391795.3的发明专利,公开了一种基于三次多项式模型的锚杆承载力预测方法,其步骤主要包括:(1)建立一个三次多项式模型,用线性回归法求解所述三次多项式模型参数;(2)使用该模型预测锚杆极限位移值SU和锚杆极限静荷载值PU;(3)将所得极限位移值SU与已知的所有实测位移值进行对比,重新确定三次多项式模型;(4)根据所建立的三次多项式模型,已知位移Si对锚杆承载力进行预测。该发明建立的三次多项式模型模拟精确度和稳定度较高,而且受锚杆P-S曲线的不光滑度影响较小一些,使用范围更广。但发明的锚杆承载力预测方法并没有综合考虑影响锚杆承载力的关键因素,不能较好的反映出锚固界面荷载传递的非线性特性,预测的结果往往与工程实际还是存在一定的偏差。
由此可见,能否发明出一种新的理论体系来建立锚杆极限承载力数学计算模型,该数学计算模型考虑到锚杆的锚固段荷载传递涉及到注浆体和岩土材料的物理非线性、几何非线性、非均质性和非连续性以及锚固交界面的接触非线性等力学特性,可实现准确预测锚杆极限承载力的计算方法成为本领域技术人员亟待解决的技术问题。
发明内容
本发明的目的之一是为解决锚杆极限承载力的预测结果往往与工程实际还是存在一定的偏差的问题,提供一种基于数学模型预测锚杆极限承载力的计算方法。本发明修正了锚杆剪应力与位移的关系,建立全长粘结式锚杆剪应力与锚杆位移关系的指数模型。另外,在工程实际中,锚杆的承载力计算公式不能准确地预算出极限承载力,究其原因在于计算模型没能综合考虑影响锚杆承载力的关键因素,造成计算结果与实际值相差很大。本发明通过对实际工程锚杆承载力影响因素的分析与探讨,对锚杆承载力计算公式进行修正,得到综合条件下锚杆承载力计算模型。
为了达到上述技术效果,本发明的技术方案包括:
一种基于数学模型预测锚杆极限承载力的计算方法,所述构建方法包括以下步骤:
步骤一:建立锚固界面剪切滑移模型:建立全长粘结式锚杆剪应力与锚杆位移关系的指数模型,确定剪应力表达式;
步骤二:确定锚杆的极限抗拔荷载:建立数学模型对实测荷载位移数据进行拟合以预测锚杆的极限抗拔荷载值,对锚杆锚固段荷载传递特征进行有效分析;计算锚固体的轴力,基于静力平衡条件和变形协调条件,结合步骤一所得到的剪应力表达式,确定锚固体的轴力公式,进一步根据边界条件确定锚杆的最大抗拔力计算公式;
步骤三:确定锚固长度对粘结强度的影响系数ψ,确定岩体的裂隙间距对粘结强度的影响系数K1、确定岩体的裂隙张开度与充填物对粘结强度的影响系数K2;
步骤四:确定预测锚杆极限承载力的数学模型:结合步骤三确定的所述锚固长度对粘结强度的影响系数ψ、岩体的裂隙间距对粘结强度的影响系数K1、岩体的裂隙张开度与充填物对粘结强度的影响系数K2,确定预测锚杆极限承载力的计算公式。
所述步骤一中的确定剪应力表达式包括:假定τ(0)=m(0)且满足m(+∞)=τ(max)得剪应力-位移关系曲线为指数函数,现将锚杆抗拔作用下的剪应力-位移曲线简化,得出剪应力的表达式:τx=τp(mx>mp),式中:a为衰减因子,反映图形形状,一般根据剪应力和位移的边界值,利用最优化技术分析确定;τp为剪应力峰值岩层和砂浆之间的抗剪强度,τp=0.1min(fg,f0),fg,f0分别为砂浆和岩体的抗压强度,土层与砂浆之间的抗剪强度应取决于土层的抗剪强度c为砂浆与土层之间的粘聚力,σ为剪切滑移面上法向总应力,为土体的内摩擦角,mt为剪应力达到峰值时所需最小的锚杆位移;mx为x断面处锚杆的位移;
所述步骤二确定锚杆的极限抗拔荷载具体包括:设杆端受力为F,锚杆的长度为L,以锚杆的尾端为坐标原点,锚杆轴线为坐标轴建立坐标系,沿坐标方向,在距离坐标原点x处取一长度为dx的单元体进行分析,根据单元平衡条件:Tx+dTx-(Tx+πDτdx)=0,化简可得:其中Tx为锚固体的轴力,在x断面处,有物理条件:其中,Sx为断面处锚杆的变形位移,E为锚固体弹性模量,Eg,Eb分别为浆体和杆体的弹性模量;Ag,Ab分别为浆体和杆体的截面积,且A=Ag+Ab,由静力平衡条件:即:由变形协调条件:mx=mg+sx对x求一阶导数得:取力绝对值的大小,进行联立式得:和求得联立式(1)的通解得到求得联立式(2)的通解为:式中,C1,C2,C3,C4为待求的数学参数,将所述的联立式(1)和联立式(2)的通解分别代入步骤一所述的剪应力的表达式中,得到ux≤up和τx=τp,ux>up,将得到个该方程式代入所述的式中得锚固体的轴力公式:其中 由得到:代入方程式中可得:由边界条件Tx|x=l=F,Tx|x=0=0,τ'x|x=l=0,得:
取τmax为粘结材料与岩土体的极限粘结应力τp,可得锚杆的最大抗拔力为:
式中:
所述步骤四确定预测锚杆极限承载力的数学模型为:式中:
本发明的有益效果包括:本发明提供一种基于数学模型预测锚杆极限承载力的计算方法,修正了锚杆剪应力与位移的关系,建立全长粘结式锚杆剪应力与锚杆位移关系的指数模型,综合考虑影响锚杆承载力的关键因素,对锚杆承载力计算公式进行修正,得到综合条件下锚杆承载力计算模型,考虑到锚杆的锚固段荷载传递涉及到注浆体和岩土材料的物理非线性、几何非线性、非均质性和非连续性以及锚固交界面的接触非线性等力学特性,可准确预测出锚杆极限承载力,且精准度和稳定度较高,可广泛应用于实际工程中。
附图说明
图1所示为本发明一种基于数学模型预测锚杆极限承载力的计算方法流程图。
图2所示为本发明的剪应力-位移曲线图。
图3所示为本发明锚杆轴线为坐标轴的坐标系图。
图4所示为本发明锚杆拉拔试验计算简图。
图5所示为本发明锚杆变形后拉拔试验计算简图。
具体实施方式
下文将结合具体详细描述本发明具体实施例。应当注意的是,下述实施例中描述的技术特征或者技术特征的组合不应当被认为是孤立的,它们可以被相互组合从而达到更好的技术效果。
实施例1:
一种基于数学模型预测锚杆极限承载力的计算方法,如图1可知,所述构建方法包括以下步骤:
步骤一:建立锚固界面剪切滑移模型:建立全长粘结式锚杆剪应力与锚杆位移关系的指数模型,确定剪应力表达式;
假定:τ(0)=m(0)且满足m(+∞)=τ(max)得剪应力-位移关系曲线为指数函数,现将锚杆抗拔作用下的剪应力-位移曲线简化如图2所示本发明的剪应力-位移曲线图:
由图2可得出下面的表达式:
τx=τp (mx>mp) (2)
式中:a为衰减因子,反映图形形状,一般根据剪应力和位移的边界值,利用最优化技术分析确定;τp为剪应力峰值岩层和砂浆之间的抗剪强度,τp=0.1min(fg,f0),fg,f0分别为砂浆和岩体的抗压强度,土层与砂浆之间的抗剪强度应取决于土层的抗剪强度τp=c+σtanφ,c为砂浆与土层之间的粘聚力,σ为剪切滑移面上法向总应力,mt为剪应力达到峰值时所需最小的锚杆位移;mx为x断面处锚杆的位移。
步骤二:确定锚杆的极限抗拔荷载:建立数学模型对实测荷载位移数据进行拟合以预测锚杆的极限抗拔荷载值,对锚杆锚固段荷载传递特征进行有效分析;计算锚固体的轴力,基于静力平衡条件和变形协调条件,结合步骤一所得到的剪应力表达式,确定锚固体的轴力公式,进一步根据边界条件确定锚杆的最大抗拔力计算公式;
设杆端受力为F,锚杆的长度为L,以锚杆的尾端为坐标原点,锚杆轴线为坐标轴建立如图3所示的本发明锚杆轴线为坐标轴的坐标系图。沿坐标方向,在距离坐标原点x处取一长度为dx的单元体进行分析。如图4所示为本发明锚杆拉拔试验计算简图、图5所示为本发明锚杆变形后拉拔试验计算简图。
根据单元平衡条件:
Tx+dTx-(Tx+πDτdx)=0 (3)
化简可得:
在x断面处,有物理条件:
其中,Sx为断面处锚杆的变形位移,E为锚固体弹性模量,Eg,Eb分别为浆体和杆体的弹性模量;Ag,Ab分别为浆体和杆体的截面积,且A=Ag+Ab。
由静力平衡条件:
即:
由变形协调条件:
mx=mg+sx
对x求一阶导数得:
取力绝对值的大小,联立式(5)~式(7)得:
方程(8)的通解为:
方程(9)的通解为:
式中,C1,C2,C3,C4为待求的数学参数,
将式(10),(11)分别代入式(1),(2)中,可得到:
τx=τp,ux>up (13)
将(12)式代入(6)式得锚固体的轴力公式:
式中:
由得:
代入式(12)可得:
由边界条件Tx|x=l=F,Tx|x=0=0,τ'x|x=l=0,得:
取τmax为粘结材料与岩土体的极限粘结应力τp,由式(16)可得锚杆的最大抗拔力为:
式中:
步骤三:确定锚固长度对粘结强度的影响系数ψ,确定岩体的裂隙间距对粘结强度的影响系数K1、确定岩体的裂隙张开度与充填物对粘结强度的影响系数K2;
在实际工程中裂缝的分布对锚杆的承载力有较大的影响,用锚杆加固风化岩体时,岩体的裂隙发育情况和裂隙的杂物对锚固体界面的粘结强度也有影响。表1与表2分别列出了裂隙间距、裂隙张开度对粘结强度的影响。
表1裂缝间距对粘结强度的影响系数K1
表2裂隙张开度与充填物对粘结强度的影响系数K2
又因锚杆在外部荷载作用下,锚固段界面的粘结应力沿锚固长度方向的分布极不均匀,因此它对粘结强度的影响也不可忽略,我们得出了锚固长度对粘结强度的影响系数ψ如表3:
表3锚杆长度对粘结强度的影响
步骤四:确定预测锚杆极限承载力的数学模型:结合步骤三确定的所述锚固长度对粘结强度的影响系数、岩体的裂隙间距对粘结强度的影响系数K1、岩体的裂隙张开度与充填物对粘结强度的影响系数K2,确定预测锚杆极限承载力的计算公式。
综上得出锚杆在实际工程中承载力的预测模型:
式中:
本发明提供一种基于数学模型预测锚杆极限承载力的计算方法,修正了锚杆剪应力与位移的关系,建立全长粘结式锚杆剪应力与锚杆位移关系的指数模型,综合考虑影响锚杆承载力的关键因素,对锚杆承载力计算公式进行修正,得到综合条件下锚杆承载力计算模型,考虑到锚杆的锚固段荷载传递涉及到注浆体和岩土材料的物理非线性、几何非线性、非均质性和非连续性以及锚固交界面的接触非线性等力学特性,可准确预测出锚杆极限承载力,且精准度和稳定度较高,可广泛应用于实际工程中。
实施例2利用本发明数学模型预测锚杆极限承载力
本发明对工程实例进行检验,计算误差范围小,预算结果准确性高,从而说明了本发明应用于实际工程的可靠性高;本发明将在未来广泛应用于实际工程中,用于更加准确的预测出锚杆在实际工程中的承载力,提高工程的安全性与可靠性,促进工程的技术进步。
上述详细说明是针对发明的可行实施例的具体说明,该实施例并非用以限制本发明的专利范围,凡未脱离本发明的等效实施或变更,均应当包含于本发明的专利范围内。
另外,本领域技术人员还可在本发明权利要求公开的范围和精神内做其它形式和细节上的各种修改、添加和替换。当然,这些依据本发明精神所做的各种修改、添加和替换等变化,都应包含在本发明所要求保护的范围之内。
Claims (2)
1.一种基于数学模型预测锚杆极限承载力的构建方法,其特征在于,所述构建方法包括以下步骤:
步骤一:建立锚固界面剪切滑移模型:建立全长粘结式锚杆剪应力与锚杆位移关系的指数模型,确定剪应力表达式;
步骤二:确定锚杆的极限抗拔荷载:建立数学模型对实测荷载位移数据进行拟合以预测锚杆的极限抗拔荷载值,对锚杆锚固段荷载传递特征进行有效分析;计算锚固体的轴力,基于静力平衡条件和变形协调条件,结合步骤一所得到的剪应力表达式,确定锚固体的轴力公式,进一步根据边界条件确定锚杆的最大抗拔力计算公式;
步骤三:确定锚固长度对粘结强度的影响系数ψ,确定岩体的裂隙间距对粘结强度的影响系数k1、确定岩体的裂隙张开度与充填物对粘结强度的影响系数k2;
步骤四:确定预测锚杆极限承载力的数学模型:结合步骤三确定的所述锚固长度对粘结强度的影响系数ψ、岩体的裂隙间距对粘结强度的影响系数k1、岩体的裂隙张开度与充填物对粘结强度的影响系数k2,确定预测锚杆极限承载力的计算公式;
设杆端受力为F,锚杆的长度为l,所述步骤四确定预测锚杆极限承载力的数学模型为:式中:a为衰减因子,反映图形形状,τp为剪应力峰值岩层和砂浆之间的抗剪强度,D为锚杆直径,E为锚固体弹性模量,A为锚固体的截面积。
2.根据权利要求1所述的一种基于数学模型预测锚杆极限承载力的构建方法,其特征在于,所述步骤一中的确定剪应力表达式包括:假定τ(0)=m(0)且满足m((+∞))=τ(max)得剪应力-位移关系曲线为指数函数,现将锚杆抗拔作用下的剪应力-位移曲线简化,得出剪应力的表达式:(mx≤mp)、τx=τp(mx﹥mp),式中:a为衰减因子,反映图形形状,根据剪应力和位移的边界值,利用最优化技术分析确定;τp为剪应力峰值岩层和砂浆之间的抗剪强度,τp=0.1min(fs,f0),其中fs,f0分别为砂浆和岩体的抗压强度,土层与砂浆之间的抗剪强度应取决于土层的抗剪强度c为砂浆与土层之间的粘聚力,σ为剪切滑移面上法向总应力,为土体的内摩擦角,mp为剪应力达到峰值时所需最小的锚杆位移;mx为x断面处锚杆的位移。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510226191.8A CN104794365B (zh) | 2015-05-06 | 2015-05-06 | 一种基于数学模型预测锚杆极限承载力的计算方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510226191.8A CN104794365B (zh) | 2015-05-06 | 2015-05-06 | 一种基于数学模型预测锚杆极限承载力的计算方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104794365A CN104794365A (zh) | 2015-07-22 |
CN104794365B true CN104794365B (zh) | 2018-01-09 |
Family
ID=53559156
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510226191.8A Expired - Fee Related CN104794365B (zh) | 2015-05-06 | 2015-05-06 | 一种基于数学模型预测锚杆极限承载力的计算方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104794365B (zh) |
Families Citing this family (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106096288A (zh) * | 2016-06-15 | 2016-11-09 | 浙江大学 | 吸力式贯入板锚的安全评估及预警方法 |
CN106709123B (zh) * | 2016-08-26 | 2020-07-21 | 西安工业大学 | 一种巷道离层型顶板锚杆支护的设计方法 |
CN106638718B (zh) * | 2016-10-19 | 2018-06-26 | 湖南工程学院 | 全长粘结性土锚脱粘长度及动态锚固力测定方法 |
CN108334690B (zh) * | 2018-01-30 | 2021-05-11 | 中冶沈勘工程技术有限公司 | 多锚杆反力梁加载试验的反力梁结构设计方法及多锚杆反力梁加载试验设计方法 |
CN109883780B (zh) * | 2019-01-21 | 2021-11-05 | 绍兴文理学院 | 基于大型足尺试验的锚固结构面尺寸阈值确定方法 |
CN109883345B (zh) * | 2019-03-07 | 2020-08-18 | 北京卫星环境工程研究所 | 抛物面天线真空低温变形测量的空间网形强度确定方法 |
CN110306548B (zh) * | 2019-07-12 | 2021-01-08 | 中南大学 | 穿越全填充型溶洞长锚索锚固力的计算方法 |
CN110378013B (zh) * | 2019-07-16 | 2022-09-13 | 西安建筑科技大学 | 一种含纵向裂隙夯土城墙遗址楠竹锚杆抗震加固设计方法 |
CN110512623B (zh) * | 2019-08-23 | 2021-04-16 | 郑州安源工程技术有限公司 | 临坡面岩体锚固设置方法 |
CN111062087B (zh) * | 2020-01-10 | 2022-06-21 | 西南交通大学 | 地下工程中基于位移差/梯度的锚固件长度设计方法 |
CN111400790A (zh) * | 2020-02-13 | 2020-07-10 | 浙江大学城市学院 | 一种基于幂函数弹塑性模型的全长粘结式锚杆极限抗拔力计算方法 |
CN111428336A (zh) * | 2020-02-13 | 2020-07-17 | 浙江大学城市学院 | 基于莫尔库仑屈服条件的弹塑性模型的全长粘结式锚杆极限抗拔力计算方法 |
CN111398063B (zh) * | 2020-03-31 | 2021-04-27 | 中国地质大学(武汉) | 基于轴力计锚固节理面剪切荷载-剪切位移曲线预测方法 |
CN111691906B (zh) * | 2020-05-12 | 2021-09-03 | 同济大学 | 一种运营隧道锚杆加固方法 |
CN112861214A (zh) * | 2021-01-11 | 2021-05-28 | 中国人民解放军军事科学院国防工程研究院工程防护研究所 | 一种全长注浆锚杆有效锚固长度的计算方法 |
CN113239434B (zh) * | 2021-05-11 | 2022-07-12 | 青岛理工大学 | 一种确定锚杆衰减系数的方法 |
CN113569416B (zh) * | 2021-08-02 | 2023-12-01 | 中国地质科学院探矿工艺研究所 | 土体中多段扩孔式锚杆极限承载力计算方法 |
CN115470694B (zh) * | 2022-08-16 | 2023-09-08 | 中国地质大学(武汉) | 一种考虑锚杆破坏模式的节理岩体锚杆剪切抗力预测方法 |
CN116306054B (zh) * | 2023-05-25 | 2023-08-01 | 长江三峡集团实业发展(北京)有限公司 | 自锚式承插接口极限抗拔力分析方法、装置、设备及介质 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1793897A (zh) * | 2005-12-09 | 2006-06-28 | 重庆大学 | 一种锚杆极限承载力的无损检测方法 |
CN104535420A (zh) * | 2014-12-29 | 2015-04-22 | 西南交通大学 | 测定静载下铁路路基土体变形状态荷载阈值的方法 |
-
2015
- 2015-05-06 CN CN201510226191.8A patent/CN104794365B/zh not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1793897A (zh) * | 2005-12-09 | 2006-06-28 | 重庆大学 | 一种锚杆极限承载力的无损检测方法 |
CN104535420A (zh) * | 2014-12-29 | 2015-04-22 | 西南交通大学 | 测定静载下铁路路基土体变形状态荷载阈值的方法 |
Non-Patent Citations (9)
Title |
---|
Effect of Loading Direction on the Bearing Capacity of Cold-Reduced Steel Sheets;Teh L H,et al.,;《Journal of Structural Engineering》;20141231;第140卷(第12期);06014005-1-06014005-5 * |
Modeling of end-plate bolted composite connection in fire considering axial force effects;Li G Q, et al.;《Journal of Constructional Steel Research》;20120429;第76卷(第76期);133-143 * |
全长粘结式锚杆抗拔力计算公式的探讨;魏新江,等;《岩土工程学报》;20080731;第28卷(第7期);902-905 * |
全长粘结式锚杆的受力分析;尤春安;《岩石力学与工程学报》;20000531;第19卷(第3期);339-341 * |
全长粘结式锚杆锚固段荷载传递机制非线性分析;黄明华,等;《岩石力学与工程学报》;20140831;第33卷(第2增刊期);3992-3997 * |
锚杆P-S曲线的双折线荷载传递解析算法;张洁,等;《岩石力学与工程学报》;20050331;第24卷(第6期);1072-1076 * |
锚杆抗拔承载机理及其在桩自锚测试技术中的应用;龙照,;《中国优秀硕士学位论文全文数据库工程科技II辑(月刊)》;20080515(第05期);C038-320 * |
锚杆荷载-位移曲线的指数函数模型研究;应志民,等;《岩土力学》;20050831;第26卷(第8期);1331-1334 * |
预应力锚杆柔性支护法机理与力学行为研究;涂兵雄;《中国博士学位论文全文数据库工程科技II辑(月刊)》;20140515(第05期);C038-83 * |
Also Published As
Publication number | Publication date |
---|---|
CN104794365A (zh) | 2015-07-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104794365B (zh) | 一种基于数学模型预测锚杆极限承载力的计算方法 | |
Ji et al. | Experimental investigation of the anisotropic mechanical properties of a columnar jointed rock mass: observations from laboratory-based physical modelling | |
Tang et al. | Influences of normal loading rate and shear velocity on the shear behavior of artificial rock joints | |
Liu et al. | Variable parameter creep model based on the separation of viscoelastic and viscoplastic deformations | |
She et al. | Study of the peak shear strength of a cement-filled hard rock joint | |
Chiriatti et al. | A study of bond between steel rebar and concrete under a friction-based approach | |
CN103471940A (zh) | 面内及面外统一拘束与材料延性断裂韧性关系的确定方法 | |
CN105115821A (zh) | 一种基于有限元的材料断裂韧性确定方法 | |
Pavlovich et al. | Estimation of rock mass strength in open-pit mining | |
Zhang et al. | Experimental investigation of pullout behavior of fiber-reinforced polymer reinforcements in sand | |
Yang et al. | Uplift behavior of belled short piles in weathered sandstone | |
Tian et al. | Modification and application of limestone HJC constitutive model under the impact load | |
Zinnurov et al. | Numerical modeling of composite reinforcement with concrete | |
Prieto-Muñoz et al. | Mechanics of an adhesive anchor system subjected to a pullout load. I: Elastic analysis | |
Dang et al. | Strain evolution and fatigue damage characteristics analysis of sandstones during multi-level triaxial cyclic loading and unloading under varying stress limits | |
Zhang et al. | Creep characteristics and model of key unit rock in slope potential slip surface | |
Liu et al. | Shear relaxation characteristics of rock joints under stepwise loadings | |
Li et al. | Stress relaxation of grouted entirely large diameter B-GFRP soil nail | |
Artkhonghan et al. | Effects of stress path on shear strength of a rock salt | |
Miao et al. | Microcrack growth behavior and cwfs criterion parameters optimization of granite with PFC | |
CN103512812A (zh) | 一种粗粒土直剪试验抗剪强度取值方法 | |
Sharafutdinov et al. | A study of the ground volume loss modeling technique influence the soil displacement in course of shield tunneling | |
Liu et al. | Experimental study of the direct shear characteristics of cement grout under constant normal loading and stiffness boundary conditions | |
Nežerka et al. | Fracture-micromechanics based model of mortars susceptible to shrinkage | |
Manaras | Investigations of backfill-rock mass interface failure mechanisms |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180109 Termination date: 20200506 |