CN104793262A - 一种地层分层位移的监测方法 - Google Patents

一种地层分层位移的监测方法 Download PDF

Info

Publication number
CN104793262A
CN104793262A CN201510179835.2A CN201510179835A CN104793262A CN 104793262 A CN104793262 A CN 104793262A CN 201510179835 A CN201510179835 A CN 201510179835A CN 104793262 A CN104793262 A CN 104793262A
Authority
CN
China
Prior art keywords
displacement
monitoring
platform
monitoring method
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510179835.2A
Other languages
English (en)
Other versions
CN104793262B (zh
Inventor
江华
江玉生
武福美
周刘刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Beijing Urban Construction Group Co Ltd
Original Assignee
China University of Mining and Technology Beijing CUMTB
Beijing Urban Construction Design and Development Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB, Beijing Urban Construction Design and Development Group Co Ltd filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN201510179835.2A priority Critical patent/CN104793262B/zh
Publication of CN104793262A publication Critical patent/CN104793262A/zh
Application granted granted Critical
Publication of CN104793262B publication Critical patent/CN104793262B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明公开了一种地层分层位移的监测方法,所述监测方法采用单点位移和静力水准仪相结合的方式实现分层位移的监测,将纵向不同深度的测点通过坐标转化方式转化到同一位置,从而实现分层沉降监测的目的,包括如下步骤:步骤1:在测点的地表位置设置硬化平台,以便于监测;步骤2:钻孔开挖及单点位移计安装;步骤3:安装完单点位移计后,在钢筒侧壁焊接一个干净脚架,然后安装静力水准仪;步骤4:将单点位移计和静力水准仪中引出的电缆接到自动化采集仪中进行实时监测。

Description

一种地层分层位移的监测方法
技术领域
本发明涉及地层监测技术领域,特别是涉及一种地层分层位移的监测方法。
背景技术
随着我国国民经济的快速发展和城市化进程的不断加快,城市交通拥堵问题日益严峻,为解决日益严峻的交通问题,各大城市纷纷开始发展城市轨道交通。盾构法因其具有机械化程度高、施工速度快及对周围环境扰动小的优点已逐渐成为我国城市轨道交通隧道建设的主力军,以北京为例,目前盾构工法在区间隧道建设中所占比例已经超过矿山法,成为了北京地铁隧道建设的第一大工法,某些线路盾构法所占比例更是超过了80%。虽然盾构法相比其他工法具有一系列的优点,但是由盾构本身结构特征可知,盾构开挖仍然会造成地层变形。目前,在曾是轨道交通工程中,国内外对盾构施工诱发的地层变形的监测主要是通过人工或自动化的方式进行地表变形的监测。然而,随着城市地下工程的不断发展,越来越多的城市轨道交通隧道需下穿、上跨既有线、铁路轨道、重要市政管线等重要风险工程,因此仅对地表变形监测是无法满足盾构施工诱发地层变形控制要求的,应充分发挥盾构工法自身的优势,摸清盾构诱发地层变形机理和分层沉降规律,根据不同条件进行变形分级,研发盾构施工诱发的地层沉降控制技术,实现盾构开挖诱发沉降达到微沉降的控制目标,总结形成一套盾构施工诱发地层变形分级方法和竖向分层控制技术对于确保盾构下穿重大风险工程或区域的安全,提高盾构施工技术水平,合理确定盾构施工方案,具有重大的工程意义,也会带来巨大的社会、经济效益,课题研究十分必要。
目前,国内外对地层分层位移的监测通常采用多点位移计和沉降磁环两种方法。多点位移计通常假定地层最深点为基点(位移为零),其他点相对于几点产生相对位移,大多岩石地层中,磁环分层沉降仪在土层中有所使用,但是测量精度较低,精度通常大于2mm,很难满足盾构施工分层沉降控制的要求,盾构穿越重大风险工程时,通常要求变形控制在3mm以内,测量精度要求在0.1mm以内。
因此希望有一种地层分层位移的监测方法来克服或至少减轻上述的缺陷。
发明内容
本发明的目的在于提供一种地层分层位移的监测方法来克服现有技术中存在的上述问题。
为实现上述目的,本发明提供一种地层分层位移的监测方法,采用单点位移和静力水准仪相结合的方式实现分层位移的监测,将纵向不同深度的测点通过坐标转化方式转化到同一位置,从而实现分层沉降监测的目的,包括如下步骤:
步骤1:在测点的地表位置设置硬化平台,以便于监测;
步骤2:钻孔开挖及单点位移计安装;
步骤3:安装完单点位移计后,在钢筒侧壁焊接一个干净脚架,然后安装静力水准仪;
步骤4:将单点位移计和静力水准仪中引出的电缆接到自动化采集仪中进行实时监测。
优选地,步骤1中所述硬化平台以测点坐标为中心设置平台平面,挖取一立方体,在所述立方体内预留圆形槽,并在所述圆形槽内插入钢筒,在所述圆形槽内浇筑混凝土以硬化地表平台,而且在所述圆形槽外侧区域采用素填土填充。
优选地,所述步骤2中的所述钻孔开挖为根据测点深度进行钻孔。
优选地,步骤2中单点位移计的安装为所述单点位移计安装在所述钻孔的预定位置;首先回填与开挖地层相近的介质,所述介质回填至所述硬化平台底部后,再回填混凝土,最后等混凝土硬化后回填素填土。确保硬化平台混凝土、钢筒及钢筒内混凝土三者形成一个整体。
本发明提供了一种地层分层位移的监测方法,通过采用单点位移和静力水准仪精确监测地层分层位移,确保了盾构下穿重大风险工程或区域的安全,提高了盾构施工技术水平,对合理确定盾构施工方案,具有重大的工程意义。
附图说明
图1是单点位移和静力水准仪的安装示意图。
图2是测点布置平面图。
图3是分层测点纵剖面图。
附图标记:
1 单点位移计 4 钢筒
2 静力水准仪 5 混凝土
3 回填土
具体实施方式
为使本发明实施的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行更加详细的描述。在附图中,自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。所描述的实施例是本发明一部分实施例,而不是全部的实施例。下面通过参考附图描述的实施例是示例性的,旨在用于解释本发明,而不能理解为对本发明的限制。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。下面结合附图对本发明的实施例进行详细说明。
在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明保护范围的限制。
在本发明一宽泛实施例中:一种地层分层位移的监测方法,采用单点位移和静力水准仪相结合的方式实现分层位移的监测,将纵向不同深度的测点通过坐标转化方式转化到同一位置,从而实现分层沉降监测的目的,包括如下步骤:
步骤1:在测点的地表位置设置硬化平台,以便于监测;
步骤2:钻孔开挖及单点位移计安装;
步骤3:安装完单点位移计后,在钢筒侧壁焊接一个干净脚架,然后安装静力水准仪;
步骤4:将单点位移计和静力水准仪中引出的电缆接到自动化采集仪中进行实时监测。
通过采用单点位移和静力水准仪精确监测地层分层位移,确保了盾构下穿重大风险工程或区域的安全,提高了盾构施工技术水平,对合理确定盾构施工方案,具有重大的工程意义。
如图1所示,地层分层位移的监测方法,采用单点位移和静力水准仪相结合的方式实现分层位移的监测,将纵向不同深度的测点通过坐标转化方式转化到同一位置,从而实现分层沉降监测的目的,包括如下步骤:
步骤1:在测点的地表位置设置硬化平台,以便于监测;
步骤2:钻孔开挖及单点位移计1的安装;
步骤3:安装完单点位移计1后,在钢筒4侧壁焊接一个干净脚架,然后安装静力水准仪2;
步骤4:将单点位移计1和静力水准仪2中引出的电缆接到自动化采集仪中进行实时监测。
如图1所示,步骤1中所述硬化平台以测点坐标为中心设置平台平面,挖取宽度50cm,长度50cm,深度50cm的正方体。正方体中心预留直径18cm、高度50cm的圆形槽,插入直径为18cm的钢筒4,周边浇筑高度为20cm混凝土以硬化地表平台,其余区域采用回填土3填充。
如图1所示,步骤2中钻孔开挖及单点位移计1安装。根据测点深度进行钻孔,拔出护筒后将单点位移计1钻孔预定位置,首先回填与开挖地层相近的介质,然后待介质回填至硬化平台底部后,再回填约20cm厚的混凝土5,最后等混凝土5硬化后回填土3。确保硬化平台混凝土、钢筒及钢筒内混凝土三者形成一个整体。
最后需要指出的是:以上实施例仅用以说明本发明的技术方案,而非对其限制。尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的精神和范围。

Claims (4)

1.一种地层分层位移的监测方法,其特征在于:采用单点位移和静力水准仪相结合的方式实现分层位移的监测,将纵向不同深度的测点通过坐标转化方式转化到同一位置,从而实现分层沉降监测的目的,包括如下步骤:
步骤1:在测点的地表位置设置硬化平台,以便于监测;
步骤2:钻孔开挖及单点位移计安装;
步骤3:安装完单点位移计后,在钢筒侧壁焊接一个干净脚架,然后安装静力水准仪;
步骤4:将单点位移计和静力水准仪中引出的电缆接到自动化采集仪中进行实时监测。
2.如权利要求1所述的地层分层位移的监测方法,其特征在于,步骤1中所述硬化平台以测点坐标为中心设置平台平面,挖取一立方体,在所述立方体内预留圆形槽,并在所述圆形槽内插入钢筒,在所述圆形槽内浇筑混凝土以硬化地表平台,而且在所述圆形槽外侧区域采用素填土填充。
3.如权利要求1所述的地层分层位移的监测方法,其特征在于,所述步骤2中的所述钻孔开挖为根据测点深度进行钻孔。
4.如权利要求3所述的地层分层位移的监测方法,其特征在于,步骤2中单点位移计的安装为所述单点位移计安装在所述钻孔的预定位置;首先回填与开挖地层相近的介质,所述介质回填至所述硬化平台底部后,再回填混凝土,最后等混凝土硬化后回填素填土。确保硬化平台混凝土、钢筒及钢筒内混凝土三者形成一个整体。
CN201510179835.2A 2015-04-17 2015-04-17 一种地层分层位移的监测方法 Active CN104793262B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510179835.2A CN104793262B (zh) 2015-04-17 2015-04-17 一种地层分层位移的监测方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510179835.2A CN104793262B (zh) 2015-04-17 2015-04-17 一种地层分层位移的监测方法

Publications (2)

Publication Number Publication Date
CN104793262A true CN104793262A (zh) 2015-07-22
CN104793262B CN104793262B (zh) 2016-11-02

Family

ID=53558223

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510179835.2A Active CN104793262B (zh) 2015-04-17 2015-04-17 一种地层分层位移的监测方法

Country Status (1)

Country Link
CN (1) CN104793262B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403300A (zh) * 2018-12-12 2019-03-01 中国矿业大学(北京) 一种双层土体沉降监测系统及其安装方法
CN113982599A (zh) * 2021-10-09 2022-01-28 中铁七局集团有限公司 一种含水砂卵石层下穿文物保护区盾构掘进施工方法
CN114739359A (zh) * 2022-04-20 2022-07-12 广州市城市规划勘测设计研究院 一种土体沉降自动化监测装置及其安装方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476337B (zh) * 2009-01-15 2011-01-19 北京交通大学 路基分层垂直沉降与横向位移自动监测装置及其监测方法
CN103276714A (zh) * 2013-05-17 2013-09-04 上海隧道工程股份有限公司 分层测量土体位移的装置及方法
CN103471648A (zh) * 2013-08-21 2013-12-25 国家电网公司 一种顶管隧道的扰动施工监测方法
CN102508110B (zh) * 2011-10-10 2014-07-09 上海大学 基于纹理的绝缘子缺陷诊断方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476337B (zh) * 2009-01-15 2011-01-19 北京交通大学 路基分层垂直沉降与横向位移自动监测装置及其监测方法
CN102508110B (zh) * 2011-10-10 2014-07-09 上海大学 基于纹理的绝缘子缺陷诊断方法
CN103276714A (zh) * 2013-05-17 2013-09-04 上海隧道工程股份有限公司 分层测量土体位移的装置及方法
CN103471648A (zh) * 2013-08-21 2013-12-25 国家电网公司 一种顶管隧道的扰动施工监测方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
卫俊杰等人: "复合地层盾构施工土体分层沉降原位试验研究", <第六届全国土木工程研究生学术论坛 (清华大学)> *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403300A (zh) * 2018-12-12 2019-03-01 中国矿业大学(北京) 一种双层土体沉降监测系统及其安装方法
CN113982599A (zh) * 2021-10-09 2022-01-28 中铁七局集团有限公司 一种含水砂卵石层下穿文物保护区盾构掘进施工方法
CN114739359A (zh) * 2022-04-20 2022-07-12 广州市城市规划勘测设计研究院 一种土体沉降自动化监测装置及其安装方法
CN114739359B (zh) * 2022-04-20 2023-08-15 广州市城市规划勘测设计研究院 一种土体沉降自动化监测装置及其安装方法

Also Published As

Publication number Publication date
CN104793262B (zh) 2016-11-02

Similar Documents

Publication Publication Date Title
CN111058855B (zh) 一种盾构下穿的结构物的形变控制方法及评估系统
Cao et al. Movements of ground and existing structures induced by slurry pressure-balance tunnel boring machine (SPB TBM) tunnelling in clay
CN107229812B (zh) 一种高水压岩溶隧道衬砌水压力计算方法
CN104612700B (zh) 一种纵向沉降变形引起盾构隧道附加内力的确定方法
CN106649912A (zh) 一种地铁隧道盾构下穿既有铁路设施的沉降预测方法
CN107130592B (zh) 长螺旋钻和冲击钻双机复合成孔灌注桩施工工法
Zhang et al. Surface settlement induced by subway tunnel construction based on modified peck formula
Yang et al. Performance of overlapped shield tunneling through an integrated physical model tests, numerical simulations and real-time field monitoring
CN104251688A (zh) 顶管工程中利用激光直线定向测量工法
CN203422091U (zh) 一种动态实时测量顶管机位置和姿态的测量装置
CN109458185A (zh) 上下重叠交叉并行隧道盾构施工方法
CN101592487A (zh) 磁环式分层沉降水平测试系统
CN103471648A (zh) 一种顶管隧道的扰动施工监测方法
CN103471647A (zh) 一种盾构隧道远程自动化监测方法
CN205748469U (zh) 一种水库滑坡多场信息现场监测系统
CN111539052B (zh) 地铁盾构区间近距离下穿顶管隧道沉降控制标准制定方法
CN108444423B (zh) 一种下穿公路的隧道围岩全位移测量方法
Ning et al. Deformation characteristics observed during multi-step excavation of underground oil storage caverns based on field monitoring and numerical simulation
Li et al. Development of the safety control framework for shield tunneling in close proximity to the operational subway tunnels: case studies in mainland China
CN106556376A (zh) 一种监测地下空间及地下管线变形的装置及其测量方法
CN112576265A (zh) 一种盾构下穿老旧村庄沉降控制方法
CN104793262A (zh) 一种地层分层位移的监测方法
CN103176220A (zh) 一种隧道水压力模型试验方法
CN111075460A (zh) 一种下穿城市密集建筑物的盾构施工及监测方法
CN107100213A (zh) 桥梁群桩施工对邻近隧道的土体扰动监测系统及监测方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Zhang Jinxun

Inventor after: Jiang Hua

Inventor after: Jiang Yusheng

Inventor after: Wu Fumei

Inventor after: Zhou Liugang

Inventor after: Yang Zhiyong

Inventor before: Jiang Hua

Inventor before: Jiang Yusheng

Inventor before: Wu Fumei

Inventor before: Zhou Liugang

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160512

Address after: 100088 Haidian District, North Beijing, Tai Ping Road, No. 18

Applicant after: BEIJING URBAN CONSTRUCTION GROUP Co.,Ltd.

Applicant after: CHINA University OF MINING AND TECHNOLOGY BEIJING

Applicant after: BEIJING URBAN CONSTRUCTION DESIGN & DEVELOPMENT GROUP Co.,Ltd.

Address before: 100083 Beijing City, Haidian District Institute of Rutosids No. 11

Applicant before: CHINA University OF MINING AND TECHNOLOGY BEIJING

Applicant before: BEIJING URBAN CONSTRUCTION DESIGN & DEVELOPMENT GROUP Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190621

Address after: 100088 No. 18 North Taipingzhuang Road, Haidian District, Beijing

Co-patentee after: CHINA University OF MINING AND TECHNOLOGY BEIJING

Patentee after: BEIJING URBAN CONSTRUCTION GROUP Co.,Ltd.

Address before: 100088 No. 18 North Taipingzhuang Road, Haidian District, Beijing

Co-patentee before: CHINA University OF MINING AND TECHNOLOGY BEIJING

Patentee before: BEIJING URBAN CONSTRUCTION GROUP Co.,Ltd.

Co-patentee before: BEIJING URBAN CONSTRUCTION DESIGN & DEVELOPMENT GROUP Co.,Ltd.

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Jiang Hua

Inventor after: Zhang Jinxun

Inventor after: Jiang Yusheng

Inventor after: Wu Fumei

Inventor after: Zhou Liugang

Inventor after: Yang Zhiyong

Inventor before: Zhang Jinxun

Inventor before: Jiang Hua

Inventor before: Jiang Yusheng

Inventor before: Wu Fumei

Inventor before: Zhou Liugang

Inventor before: Yang Zhiyong

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190724

Address after: 100083 Beijing City, Haidian District Institute of Rutosids No. 11

Co-patentee after: BEIJING URBAN CONSTRUCTION GROUP Co.,Ltd.

Patentee after: CHINA University OF MINING AND TECHNOLOGY BEIJING

Address before: 100088 Haidian District, North Beijing, Tai Ping Road, No. 18

Co-patentee before: CHINA University OF MINING AND TECHNOLOGY BEIJING

Patentee before: BEIJING URBAN CONSTRUCTION GROUP Co.,Ltd.

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhang Jinxun

Inventor after: Jiang Hua

Inventor after: Jiang Yusheng

Inventor after: Wu Fumei

Inventor after: Zhou Liugang

Inventor after: Yang Zhiyong

Inventor before: Jiang Hua

Inventor before: Zhang Jinxun

Inventor before: Jiang Yusheng

Inventor before: Wu Fumei

Inventor before: Zhou Liugang

Inventor before: Yang Zhiyong

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100088 No. 18 Taiping Road, Haidian District, Beijing

Patentee after: BEIJING URBAN CONSTRUCTION GROUP Co.,Ltd.

Patentee after: China University of mining and Technology (Beijing)

Address before: 100083 Beijing City, Haidian District Institute of Rutosids No. 11

Patentee before: CHINA University OF MINING AND TECHNOLOGY BEIJING

Patentee before: BEIJING URBAN CONSTRUCTION GROUP Co.,Ltd.