CN104762987A CN201510107233.6A CN201510107233A CN104762987A CN 104762987 A CN104762987 A CN 104762987A CN 201510107233 A CN201510107233 A CN 201510107233A CN 104762987 A CN104762987 A CN 104762987A
Authority
CN
China
Prior art keywords
anchor rod
foundation
reinforcement
crab
concrete slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510107233.6A
Other languages
English (en)
Other versions
CN104762987B (zh
Inventor
龚素华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yan Ning Engineering Science and Technology Group Co., Ltd.
Original Assignee
Chengdu Xunde Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Xunde Technology Co Ltd filed Critical Chengdu Xunde Technology Co Ltd
Priority to CN201510107233.6A priority Critical patent/CN104762987B/zh
Publication of CN104762987A publication Critical patent/CN104762987A/zh
Application granted granted Critical
Publication of CN104762987B publication Critical patent/CN104762987B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/50Anchored foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明公开了一种锚杆基础结构,包括基础钢筋混凝土板,基础钢筋混凝土板内设有锚栓笼,锚栓笼为两个,且分别靠近基础钢筋混凝土板两侧面设置,锚栓笼内设有调节轴,调节轴顶部延伸在基础钢筋混凝土板上表面外侧面上,其底部与锚栓笼底部均固定在一垫层上,两锚栓笼之间连接有基础苯板,基础苯板两端均固定在锚栓笼上,垫层下表面与基础钢筋混凝土板下表面均固定在一加强底板上,且垫层下表面和基础钢筋混凝土板下表面与加强底板连接处均内置有固定螺钉。本锚杆基础结构降低了施工难度,增加了锚杆基础与地基的接触面,可以更好的分担竖向荷载,增加其锚固力度,也可避免锚杆与锚杆灌浆之间发生的粘接破坏现象,增大了安全性能。

Description

锚杆基础结构
技术领域
本发明涉及一种基础结构,特别涉及一种锚杆基础结构。
背景技术
目前对于大型或超大型的高耸支柱结构,多采用尺寸庞大的扩展基础,主要是通过大型扩展基础的重量提高稳定性,从而保证上部结构的稳定,保持良好的工作状态,同时将上部结构传导下来的荷载分散到较大面积的地基上,从而保证地基承载力可以达标,但这样会导致材料用量较大,成本很高,且不能更好的起到支撑防护性能,容易出现锚杆不稳定化现象,且成本很高,而且施工复杂,导致施工工期较长,不利于施工成本的节约。
发明内容
本发明要解决的技术问题是:克服上述问题,提供一种降低了施工难度,增加了锚杆基础与地基的接触面,可以更好的分担竖向荷载,增加其锚固力度的锚杆基础结构。
为了实现上述目的,本发明采用的技术方案是这样的:本发明的锚杆基础结构,包括基础钢筋混凝土板,基础钢筋混凝土板内设有锚栓笼,锚栓笼为两个,且分别靠近基础钢筋混凝土板两侧面设置,锚栓笼内设有调节轴,调节轴顶部延伸在基础钢筋混凝土板上表面外侧面上,其底部与锚栓笼底部均固定在一垫层上,两锚栓笼之间连接有基础苯板,基础苯板两端均固定在锚栓笼上,垫层下表面与基础钢筋混凝土板下表面均固定在一加强底板上,且垫层下表面和基础钢筋混凝土板下表面与加强底板连接处均内置有固定螺钉。
进一步的,作为一种具体的结构形式,本发明所述锚栓笼与调节轴之间连接有锥形螺母。
进一步的,作为一种具体的结构形式,本发明所述安装板采用钢材料制成。
进一步的,作为一种具体的结构形式,本发明所述基础苯板厚度在一至两厘米之间。
进一步的,作为一种具体的结构形式,本发明所述加强底板采用钢材料制成。
进一步的,作为一种具体的结构形式,本发明所述加强底板内置钢条。
进一步的,作为一种具体的结构形式,本发明所述基础钢筋混凝土板上穿设有钢结构架。
与现有技术相比,本发明的优点在于:本锚杆基础结构降低了施工难度,增加了锚杆基础与地基的接触面,可以更好的分担竖向荷载,增加其锚固力度,也可避免锚杆与锚杆灌浆之间发生的粘接破坏现象,增大了安全性能。
附图说明
下面结合附图和实施例对本发明进一步说明。
图1为本发明的结构示意图;
图中:1.基础钢筋混凝土板;2.锚栓笼;3.调节轴;4.安装板;5.垫层;6.基础苯板;7.加强底板。
具体实施方式
现在结合附图对本发明作进一步详细的说明。这些附图均为简化的示意图,仅以示意方式说明本发明的基本结构,因此其仅显示与本发明有关的构成。
如图1所示的本发明锚杆基础结构的优选实施例,包括基础钢筋混凝土板1,基础钢筋混凝土板1内设有锚栓笼2,锚栓笼2为两个,且分别靠近基础钢筋混凝土板1两侧面设置,锚栓笼2内设有调节轴3,调节轴3顶部延伸在基础钢筋混凝土板1上表面外侧面上,其底部与锚栓笼2底部均固定在一垫层上,两锚栓笼2之间连接有基础苯板6,基础苯板6两端均固定在锚栓笼2上,垫层5下表面与基础钢筋混凝土板1下表面均固定在一加强底板7上,且垫层5下表面和基础钢筋混凝土板1下表面与加强底板7连接处均内置有固定螺钉,所述锚栓笼2与调节轴3之间连接有锥形螺母,所述安装板4采用钢材料制成,所述基础苯板6厚度在一至两厘米之间,所述加强底板7采用钢材料制成,所述加强底板7内置钢条,所述基础钢筋混凝土板1上穿设有钢结构架。
本发明的锚杆基础结构降低了施工难度,增加了锚杆基础与地基的接触面,可以更好的分担竖向荷载,增加其锚固力度,也可避免锚杆与锚杆灌浆之间发生的粘接破坏现象,增大了安全性能。所述锚栓笼2与调节轴3之间连接有锥形螺母,可方便进行调节;安装结构更加牢固;所述加强底板7内置钢条,所述基础钢筋混凝土板1上穿设有钢结构架,提升了自身结构性能。
以上述依据本发明的理想实施例为启示,通过上述的说明内容,相关工作人员完全可以在不偏离本项发明技术思想的范围内,进行多样的变更以及修改。本项发明的技术性范围并不局限于说明书上的内容,必须要根据权利要求范围来确定其技术性范围。

Claims (7)

1.一种锚杆基础结构,包括基础钢筋混凝土板,其特征在于:基础钢筋混凝土板内设有锚栓笼,锚栓笼为两个,且分别靠近基础钢筋混凝土板两侧面设置,锚栓笼内设有调节轴,调节轴顶部延伸在基础钢筋混凝土板上表面外侧面上,其底部与锚栓笼底部均固定在一垫层上,两锚栓笼之间连接有基础苯板,基础苯板两端均固定在锚栓笼上,垫层下表面与基础钢筋混凝土板下表面均固定在一加强底板上,且垫层下表面和基础钢筋混凝土板下表面与加强底板连接处均内置有固定螺钉。
2.根据权利要求1所述的锚杆基础结构,其特征在于:所述锚栓笼与调节轴之间连接有锥形螺母。
3.根据权利要求1所述的锚杆基础结构,其特征在于:所述安装板采用钢材料制成。
4.根据权利要求1所述的锚杆基础结构,其特征在于:所述基础苯板厚度在一至两厘米之间。
5.根据权利要求1所述的锚杆基础结构,其特征在于:所述加强底板采用钢材料制成。
6.根据权利要求1所述的锚杆基础结构,其特征在于:所述加强底板内置钢条。
7.根据权利要求1所述的锚杆基础结构,其特征在于:所述基础钢筋混凝土板上穿设有钢结构架。
CN201510107233.6A 2015-03-12 2015-03-12 锚杆基础结构 Active CN104762987B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510107233.6A CN104762987B (zh) 2015-03-12 2015-03-12 锚杆基础结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510107233.6A CN104762987B (zh) 2015-03-12 2015-03-12 锚杆基础结构

Publications (2)

Publication Number Publication Date
CN104762987A true CN104762987A (zh) 2015-07-08
CN104762987B CN104762987B (zh) 2016-08-17

Family

ID=53645054

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510107233.6A Active CN104762987B (zh) 2015-03-12 2015-03-12 锚杆基础结构

Country Status (1)

Country Link
CN (1) CN104762987B (zh)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070065234A1 (en) * 2005-09-21 2007-03-22 Nordex Energy Gmbh Method for the earthwork of a foundation sunk for a wind energy facility
US20080155907A1 (en) * 2004-04-02 2008-07-03 Aloys Wobben Method for Erecting a Tower
US20130255169A1 (en) * 2012-03-30 2013-10-03 Allan P. Henderson Cementitious foundation cap with post-tensioned helical anchors
CN203583512U (zh) * 2013-12-10 2014-05-07 李娜 塔式基础可调定位锚笼
CN103938647A (zh) * 2014-05-14 2014-07-23 闵怡红 一种风力发电塔预应力锚栓笼
CN203924099U (zh) * 2014-07-07 2014-11-05 闵怡红 粘结改进型岩石锚杆基础
CN203925895U (zh) * 2014-07-07 2014-11-05 闵怡红 用于风力发电塔的锚栓可更换式基础
CN204715390U (zh) * 2015-03-12 2015-10-21 成都迅德科技有限公司 锚杆基础结构

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080155907A1 (en) * 2004-04-02 2008-07-03 Aloys Wobben Method for Erecting a Tower
US20070065234A1 (en) * 2005-09-21 2007-03-22 Nordex Energy Gmbh Method for the earthwork of a foundation sunk for a wind energy facility
US20130255169A1 (en) * 2012-03-30 2013-10-03 Allan P. Henderson Cementitious foundation cap with post-tensioned helical anchors
CN203583512U (zh) * 2013-12-10 2014-05-07 李娜 塔式基础可调定位锚笼
CN103938647A (zh) * 2014-05-14 2014-07-23 闵怡红 一种风力发电塔预应力锚栓笼
CN203924099U (zh) * 2014-07-07 2014-11-05 闵怡红 粘结改进型岩石锚杆基础
CN203925895U (zh) * 2014-07-07 2014-11-05 闵怡红 用于风力发电塔的锚栓可更换式基础
CN204715390U (zh) * 2015-03-12 2015-10-21 成都迅德科技有限公司 锚杆基础结构

Also Published As

Publication number Publication date
CN104762987B (zh) 2016-08-17

Similar Documents

Publication Publication Date Title
CN203452266U (zh) H型钢柱的固定和调平结构
CN203451114U (zh) 用于桥塔施工的塔吊附着装置
CN201011174Y (zh) 钢结构建筑物抗震抗变形双重保护结构
CN206204766U (zh) 独柱墩桥梁抗倾覆斜撑加固装置
CN204715390U (zh) 锚杆基础结构
CN208136711U (zh) 一种适用于钢桥或钢混组合梁桥的抗拉拔支座
CN203361183U (zh) 一种输电塔基础
CN104762987B (zh) 锚杆基础结构
CN105464004A (zh) 一种不中断交通的装配式板桥底部钢横梁加固方法
CN203099228U (zh) 一种地脚螺栓调平结构
CN202866002U (zh) 型钢混凝土非埋入式柱脚
CN201381642Y (zh) 大梁槽钢托梁支模系统
CN205654125U (zh) 一种可调标高的加固支撑柱
CN204662477U (zh) 梁基础结构
CN203939279U (zh) 用于连接高耸结构与地基的连接装置
CN208023838U (zh) 一种新型自复位耗能钢柱柱脚连接结构
CN203855883U (zh) 一种侧向固定的板式橡胶支座
CN104762986B (zh) 梁基础结构
CN204658640U (zh) 模板调节结构
CN207362673U (zh) 一种无支座单肢薄壁墩连续刚构桥
CN104760125B (zh) 模板调节结构
CN204454362U (zh) 塔吊附着支撑座
CN211257499U (zh) 装配式建筑的内嵌式楼盖系统
CN208934457U (zh) 一种新增钢柱的外包式刚性柱脚
CN204491893U (zh) 一种钢板剪力墙结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Liu Guoqing

Inventor after: Zhu Hongwei

Inventor after: Geng Xiaoping

Inventor after: Gu Jixiang

Inventor after: Xiong Huabo

Inventor before: Gong Suhua

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160701

Address after: 210019 room B, building, Yunlong mountain road, Jiangsu, Nanjing, China, 88

Applicant after: CHENGDU XUNDE SCIENCE & TECHNOLOGY CO., LTD.

Address before: Jinjiang District Jinhua Road Chengdu City, Sichuan province 610000 section of No. 8 Building 1 11 unit 18 floor No. 1846

Applicant before: CHENGDU XUNDE TECHNOLOGY CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 210017 4, building 223, Shui Simen street, Jianye District, Nanjing, Jiangsu.

Patentee after: Jiangsu Yan Ning Engineering Science and Technology Group Co., Ltd.

Address before: 210019 room 1501, building B, 88 Yunlong Shan Road, Nanjing, Jiangsu.

Patentee before: Jiangsu Yearning Construction Co., Ltd.

CP03 Change of name, title or address