CN104759089B CN201510180171.1A CN201510180171A CN104759089B CN 104759089 B CN104759089 B CN 104759089B CN 201510180171 A CN201510180171 A CN 201510180171A CN 104759089 B CN104759089 B CN 104759089B
Authority
CN
China
Prior art keywords
slabstone
metal
monolithic
billiard table
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510180171.1A
Other languages
Chinese (zh)
Other versions
CN104759089A (en
Inventor
刘政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changde Hunan Province City Imperial Crown Pool Table Head Factory
Original Assignee
Changde Hunan Province City Imperial Crown Pool Table Head Factory
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changde Hunan Province City Imperial Crown Pool Table Head Factory filed Critical Changde Hunan Province City Imperial Crown Pool Table Head Factory
Priority to CN201510180171.1A priority Critical patent/CN104759089B/en
Publication of CN104759089A publication Critical patent/CN104759089A/en
Application granted granted Critical
Publication of CN104759089B publication Critical patent/CN104759089B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a combined billiard table slate board and a manufacturing method thereof. The combined billiard table slate board is made by the combination of 2 to 9 single slate boards. Metal plates are arranged around each single slate board, metal semicircle angle beads are arranged at the pocket mouth positions of the slate board, the metal plates and the metal semicircle angle beads are connected into a metal frame wholly at one side face of the slate board, and the metal frames are connected with reinforcing ribs inside the slate board. Fastening pieces are welded to the metal frames arranged at the edge locking position of the slate board, and the fastening pieces are connected with the reinforcing ribs inside the slate board. Positioning taper pins are arranged at the splicing positions of each two single slate boards, one metal frame of a single slate board is connected with one end of the positioning taper pin, a positioning holes are formed in the metal frame of the other single slate board, and the other end of the positioning taper pin is inserted into the slate board after penetrating through the positioning hole. The billiard table made by the combined slate boards is capable of moving freely, dislocation and deformation of the splicing positions cannot occurred, and the integrity of the slate board table face is stronger.

Description

Combined type billiard table stone slab and preparation method thereof
【Technical field】The present invention relates to sports equipment, more particularly to a kind of combined type billiard table stone slab and its making side Method.
【Background technology】Billiard ball are the sports popularized very much, each part matter of billiard table in this motion The stability of amount is extremely important with performance, and billiard table stone slab is no doubt one of most important part.But existing most natural groups Close slabstone billiard table be difficult when mounted by slabstone edge joint position debug it is smooth, and in use because slabstone deformation, stand loosen or The factors such as collision, often make slabstone edge joint position misplace, and need to reinstall leveling.Its reason is the metal that slabstone edge joint position is set Accurate, gap is not big for alignment pin;Slabstone is different from the material of metal fitting nail, and metal fitting nail is arranged on insecure on slabstone, Easily loosen, it is impossible to effectively position edge joint position, cause slabstone table top out-of-flatness, so that can not normally use.Due to natural composition There is above-mentioned defect in the metal fitting nail of slabstone, billiard table installs rear immovable, and inconvenience is brought to user.
Must exert oneself to lock storehouse side using lead screw when billiard table is installed, allow storehouse side to be close to the elasticity that slabstone just has, And lead screw is more, twisting must be tighter, elastic better.But often there is spiral shell when installing storehouse side in existing natural composition slabstone billiard table Screw mandrel is pulled off the phenomenon split, and causes storehouse side normally to lock, and causes slabstone to be scrapped when serious, and its reason is the screw for using Bar gauge lattice are less than normal.Because the nut on natural stone slab locking storehouse side is built-in in slabstone, lead screw stress point holds on stone material Powerful pulling force is can't stand, thus big specification lead screw can not be used, this defect is solved without effective measures so far.
Additionally, existing billiard table generally supports billiard table stone slab using wooden stand, billiard table is often received during use To collision, wooden stand is yielding in addition, loosen, and slabstone and wooden stand are not linked to be entirety, slabstone easily lose level and Out-of-flatness, influence is normally used.
【The content of the invention】The present invention is regarding to the issue above, there is provided a kind of combined type billiard table stone slab and preparation method thereof.
This combined type billiard table stone slab, by polylith cement or mixing building stones pour monolithic slabstone combine and Into monolithic slabstone bottom surface is provided with mounting hole A, and monolithic slabstone is internally provided with netted reinforcement, it is characterised in that the list The number of block slabstone is 2-9 blocks, and monolithic slabstone is formed around metallic plate, and the sack position of slabstone is provided with metal semicircle corner protector, Metallic plate is linked as that metal edge frame is integrally formed with metal semicircle corner protector in the side of monolithic slabstone, inside metal edge frame and slabstone Reinforcement is connected;Fastener is welded with the metal edge frame of slabstone lock storehouse side position, fastener connects with the reinforcement inside slabstone Connect;Locating taper pin is provided with the edge joint position of two adjacent monolithic slabstones, wherein the metal edge frame of a slabstone is welded with locating taper pin one end Connect, the metal edge frame of another slabstone is provided with location hole, and the other end of locating taper pin inserts the slabstone through location hole.
Sleeve is provided with the monolithic slabstone, sleeve is close to the location hole on metal edge frame.
The position of the mounting hole A is provided with the nut or T-shaped sleeve pipe being connected with reinforcement.
The two adjacent monolithic slabstone, the two ends of a slabstone are provided with groove, lead screw, the gold of slabstone side are provided with groove Category frame is provided with the mounting hole B corresponding with groove;Nut, gold of the lead screw through slabstone edge joint position are provided with another slabstone Category frame is connected with nut.
The metal edge frame of the monolithic slabstone is provided with mounting hole C.
The 2-9 blocks monolithic slabstone, is wherein provided with U-shaped ring in 1-8 blocks slabstone, U-shaped ring is close to the installation on metal edge frame Hole;Sleeve pipe and/or fastener are additionally provided with the monolithic slabstone, fastener is welded on the metal edge frame in slabstone, lead screw Through the connection of mounting hole C, U-shaped ring, sleeve pipe and fastener.
The 2-9 blocks monolithic slabstone, is wherein provided with U-shaped ring and sleeve pipe, the metal in remaining 1 block of slabstone in 1-8 blocks slabstone Fastener is welded with frame, lead screw is connected through mounting hole C, U-shaped ring, sleeve pipe and fastener.
The bottom of the monolithic slabstone is provided with support frame, and support frame is welded with the reinforcement inside slabstone.
The fastener being connected with reinforcement is provided with the monolithic slabstone, in the slabstone bottom combined by polylith monolithic slabstone Overall support frame is provided with, the support frame is connected by lead screw with the fastener in each monolithic slabstone.
Lockplate is provided between support frame as described above and slabstone, lockplate is connected respectively with support frame, billiard table stone slab.
Support frame as described above is one or more composition in steel pipe, angle bar, channel-section steel, I-steel, U-shaped steel, steel plate, iron plate.
The reinforcement is one or more in steel bar, iron bar, reinforcing bar, steel wire, steel plate, iron plate, steel pipe.
The metal edge frame is one or more in steel plate, iron plate, band iron, angle bar, U-shaped steel, channel-section steel.
The fastener includes nut and/or support.
The preparation method of combinations thereof formula billiard table stone slab, lays one layer of offset plate every mould on smooth workbench bed die, In offset plate every the outer frame mould that a whole set of combination billiard table stone slab is set on mould, it is characterised in that set metal in outer frame mould Plate, lead screw is locked through outer frame mould, metallic plate and fastener;In each edge joint position position of a whole set of slabstone, two blocks of gold are set Category plate, is closed tight, and sets corresponding location hole on two pieces of metallic plates, with rotary hinge borehole cleaning inwall in reamer patchhole Iron filings to smoothing out, insert locating taper pin, the stub end of locating taper pin and a metal plate weld, small head end stretch into another metallic plate Location hole in;Metal semicircle corner protector is set in the sack position of slabstone, respectively by the metallic plate in outer frame mould, metal semicircle Corner protector, the metal plate weld of edge joint position position, form the metal edge frame of multiple monolithic slabstones;Netted adding, is set in metal edge frame Strong muscle, reinforcement is respectively welded with metal edge frame, fastener;The position of mounting hole of slabstone bottom surface is provided with the spiral shell being connected with reinforcement Female or T-shaped sleeve pipe;To casting cement sandstone in metal edge frame or mixing building stones, the rear outer frame mould of dismounting to be solidified pries open piece The metal edge frame at place, as monolithic slabstone finished product;When polylith monolithic slabstone is assembled, is checked the number by original position and insert locating taper pin, obtained final product.
Further, support frame is placed on metal edge frame, first passes through lead screw by the nut and support frame of fastener Locking, support and the reinforcement of fastener are welded, then to casting cement sandstone in metal edge frame or mixing building stones.
Advantages of the present invention:1st, all reinforcements, metal edge frame, fastener are connected with each other in slabstone, make combination slabstone Intensity is higher, more smooth, indeformable.2nd, locating taper pin is set in advance on the metal edge frame of edge joint position, then watering pours water silt Stone solidifies to form slabstone, can make that gapless between locating taper pin and slabstone, intensity are big, not loosen, and can make combination slabstone edge joint position Never misplace;A whole set of slabstone checks the number assembled by situ, and slabstone table top is naturally smooth, sideline vertical, thoroughly solves billiard table The problem of slabstone edge joint position easily dislocation.The 3rd, fastener locking storehouse side is set on metal edge frame, and what is be stressed directly is metal edge frame With reinforcement rather than stone material, therefore big specification lead screw is can select, or any quantity that lead screw is set and position, so that Storehouse side elasticity is especially good, and screen resilience is uniform, sound is melodious.4th, sleeve pipe, U-shaped ring and fastener, spiral shell when assembled are preset in slabstone Screw mandrel is locked through the sleeve pipe in a slabstone with the fastener in another slabstone, and the whole series combination slabstone can be integrated, piece Close, slabstone table top globality is stronger.5th, support frame is poured after lead screw is connected with the fastener in slabstone and mixes building stones Slabstone is formed, when installing billiard table, support frame is connected to form one with default fastener in slabstone by lead screw, makes table top The plane of slabstone vertically turns into straight line, support slabstone that can firmly, overall, moreover it is possible to convenient debugging table-surface level, installation Billiard ball table surface it is sedate smooth, it is indeformable, for billiard movement and race activity provide an equipment for high-quality.6th, use The billiard table that present invention combination slabstone makes can be moved freely, and edge joint position is not misplaced, deformed, the need for meeting user.
【Brief description of the drawings】
Fig. 1 is present invention combination slabstone structural representation
Fig. 2 is the A-A sectional views of Fig. 1
Fig. 3 is the scheme of installation of locating taper pin and metal edge frame
Fig. 4 is the structural representation of fastener
Fig. 5 is the scheme of installation of T-shaped sleeve pipe and T-shaped sleeve pipe and lead screw
Fig. 6 is sleeve pipe and metal edge frame, the scheme of installation of fastener
Fig. 7 is the making figure that embodiment one combines slabstone
Fig. 8 is the making figure that embodiment two combines slabstone
Fig. 9 is that embodiment two installs reeded slabstone side view
Figure 10 is the T-shaped sleeve pipe of embodiment two and slabstone, the scheme of installation of reinforcement
Figure 11 is the making figure that embodiment three combines slabstone
Figure 12 is the making figure that example IV combines slabstone
Figure 13 is the making figure of the support frame of embodiment five and slabstone
Figure 14 is support frame, the connection diagram of reinforcement in embodiment five
Figure 15 is the making figure of the support frame of embodiment six and slabstone
Figure 16 is support frame, lockplate, reinforcement, the scheme of installation of fastener bracket in embodiment six
In figure:1st, monolithic slabstone, 2, metal edge frame, 3, locating taper pin, 4, metal semicircle corner protector, 5, fastener, 6, plus Strong muscle, 7, sleeve, 8, mounting hole A, 9, location hole, 10, nut, 11, mounting hole B, 12, groove, 13, lead screw, 14, T-shaped set Pipe, 15, sleeve pipe, 16, U-shaped ring, 17, mounting hole C, 18, support frame, 19, support, 20, lockplate, 21, outer frame mould.
【Specific embodiment】Implementation of the invention is described below below in conjunction with the accompanying drawings:
Embodiment one:Making is combined by three blocks of monolithic slabstones, and locating taper pin is installed at edge joint position middle part, and mounting hole A positions set Put the billiard table stone slab of nut.
Reference picture 2, Fig. 3, Fig. 4 and Fig. 7, sets metallic plate in the outer frame mould 21, lead screw 13 through outer frame mould 21, Metallic plate is locked with fastener 5.
Two pieces of metallic plates are respectively provided with two edge joint position positions of a whole set of slabstone, are closed tight, and in two pieces of metallic plates Upper to set corresponding location hole 9, the iron filings with rotary hinge borehole cleaning inwall in reamer patchhole insert locating taper pin 3 to smoothing out, The stub end of locating taper pin 3 and a metal plate weld, sleeve 7 is welded on the edge of location hole 9 of another metallic plate, locating taper pin 3 small head end is stretched into sleeve 7 through location hole 9.
Metal semicircle corner protector 4 is set in the sack position of slabstone, by the metallic plate in outer frame mould 21, metal semicircle corner protector 4th, the metallic plate of edge joint position position is respectively welded, and forms three metal edge frames of monolithic slabstone 12;Set laterally in metal edge frame 2 With the reinforcement 6 of longitudinal direction, reinforcement 6 welds with metal edge frame 2, fastener 5 respectively.
The positions of mounting hole A 8 of slabstone bottom surface set nut 10, and nut 10 is welded with reinforcement 6;To being poured in metal edge frame 2 Mixing building stones are filled, the rear outer frame mould 21 of dismounting to be solidified pries open the metal edge frame 2 of edge joint position, the as finished product of monolithic slabstone 1.
Reference picture 1 during installation, by three blocks of monolithic slabstones 1 by insertion locating taper pin 3 of checking the number in situ, a set of flatness is high Combination billiard table stone slab.
Nut 10 is set in the positions of mounting hole A 8, nut 10 is welded with reinforcement 6, positioning is easy to when pouring mixing building stones. And nut 10 is inside slabstone, slabstone table top is not in screw hole, and table top is clean and tidy smooth, attractive in appearance.
Embodiment two:Making is combined by three blocks of monolithic slabstones, and locating taper pin is installed at edge joint position middle part, and edge joint position two ends pass through Screw rod locking, mounting hole location A sets the billiard table stone slab of T-shaped sleeve pipe.
Reference picture 2, Fig. 3, Fig. 4 and Fig. 8, sets metallic plate, in two edge joint positions of a whole set of slabstone in outer frame mould 21 Position is respectively provided with two pieces of metallic plates, is closed tight, and two pieces of two ends of metallic plate are locked by lead screw 13 and nut 10 respectively; Two pieces of middle parts of metallic plate set corresponding location hole 9, with the iron filings of rotary hinge borehole cleaning inwall in reamer patchhole to smooth-going, Insertion locating taper pin 3, the stub end of locating taper pin 3 and a metal plate weld, sleeve 7 is welded on the location hole of another metallic plate 9 edges, the small head end of locating taper pin 3 is stretched into sleeve 7 through location hole 9.
Metal semicircle corner protector 4 is set in the sack position of slabstone, by the metallic plate in outer frame mould 21, metal semicircle corner protector 4th, the metallic plate of edge joint position position is respectively welded, and forms three metal edge frames of monolithic slabstone 12.
Reference picture 8 and Fig. 9, the two ends of edge joint position metal edge frame 2 are welded with metal groove 12, the metal edge frame of slabstone side The mounting hole B11 corresponding with groove 12 is provided with 2.
Netted reinforcing rib 6, reinforcement 6 and metal edge frame 2, fastening are set in reference picture 5, Fig. 8 and Figure 10, metal edge frame 2 Part 5 is respectively welded;T-shaped sleeve pipe 14 is set in the positions of mounting hole A 8 of slabstone bottom surface, T-shaped sleeve pipe 14 is welded with reinforcement 6.
To casting cement sandstone in metal edge frame 2, the rear outer frame mould 21 of dismounting to be solidified removes lead screw 13, pries open spelling Metal edge frame 2 at seam, the as finished product of monolithic slabstone 1.
During installation, by three blocks of monolithic slabstones 1 by insertion locating taper pin 3 of checking the number in situ, lead screw 13 is tightened in groove 12, The high combination billiard table stone slab of a set of flatness.
Groove 12 is set at the two ends of billiard table stone slab edge joint position, lead screw 13 in groove 12 is by the metal edges of edge joint position Frame 2 is tightened, and can close combination slabstone edge joint position, when being moved integrally after slabstone assembly is good edge joint position will not more separated, whole Set combines the assembled better of slabstone.T-shaped sleeve pipe 14 is set in the positions of mounting hole A 8, T-shaped sleeve pipe 14 is welded with reinforcement 6, It is easy to positioning when pouring mixing building stones, the stress point of lead screw 13 will not be damaged on T-shaped sleeve pipe 14 when installing slabstone bottom batten Slabstone.
Embodiment three:Making is combined by three blocks of monolithic slabstones, and locating taper pin is installed at edge joint position middle part, and mounting hole location A sets Put and sleeve pipe is installed in nut, monolithic slabstone(Mode one)Billiard table stone slab.
Reference picture 2, Fig. 3, Fig. 4 and Figure 11, sets metallic plate in outer frame mould 21, and lead screw 13 passes through outer frame mould 21st, metallic plate and fastener 5 are locked.
Two pieces of metallic plates are respectively provided with two edge joint position positions of a whole set of slabstone, are closed tight, and in two pieces of metallic plates Upper to set corresponding location hole 9, the iron filings with rotary hinge borehole cleaning inwall in reamer patchhole insert locating taper pin 3 to smoothing out, The stub end of locating taper pin 3 and a metal plate weld, sleeve 7 is welded on the edge of location hole 9 of another metallic plate, locating taper pin 3 small head end is stretched into sleeve 7 through location hole 9.
Reference picture 6 and Figure 11, set metal semicircle corner protector 4, by the metal in outer frame mould 21 in the sack position of slabstone Plate, the metal semicircle corner protector 4, metallic plate of edge joint position position are respectively welded, and form three metal edge frames of monolithic slabstone 12;Wherein Sleeve pipe 15 is provided with two metal edge frames 2, one end of sleeve pipe 15 is provided with the U-shaped ring 16 for communicating therewith, is provided with metal edge frame 2 The mounting hole C 17 corresponding with U-shaped ring 16, U-shaped ring 16 is welded on the edge of mounting hole C 17;The other end welding of sleeve pipe 15 On the metal edge frame 2 of edge joint position, fastener 5 is welded with another metal edge frame 2 of edge joint position, lead screw 13 passes through U-shaped ring 16th, the metal edge frame 2 of sleeve pipe 15, edge joint position is connected with fastener 5.
Netted reinforcing rib 6 is set in reference picture 11, metal edge frame 2, and reinforcement 6 is welded respectively with metal edge frame 2, fastener 5 Connect;The positions of mounting hole A 8 of slabstone bottom surface set nut 10, and nut 10 is welded with reinforcement 6;To watering pours water in metal edge frame 2 Silt stone, the rear lead screw 13 removed outer frame mould 21, remove in U-shaped ring 16 to be solidified, pries open the metal edge frame 2 of edge joint position, The as finished product of monolithic slabstone 1.
During installation, by three blocks of monolithic slabstones 1 by insertion locating taper pin 3 of checking the number in situ, lead screw 13 passes through U-shaped ring 16, set The metal edge frame 2 of pipe 15, edge joint position is locked with the fastener 5 in slabstone, and a set of flatness is high, combination billiard ball with sleeve pipe 15 Table slabstone.
Sleeve pipe 15 is set in a whole set of billiard table stone slab can make edge joint position gap small, and lead screw 13 is tightened in U-shaped ring 16 Can convenient assembled slabstone, close piece, slabstone it is assembled it is good after edge joint position will not more separated when moving integrally, a whole set of billiard table The globality of slabstone is strong.
Example IV:Making is combined by five blocks of monolithic slabstones, and locating taper pin is installed at edge joint position middle part, and mounting hole location A sets Put band sleeve pipe in nut, monolithic slabstone(Mode two)Billiard table stone slab.
Reference picture 2, Fig. 3, Fig. 4 and Figure 12, sets metallic plate in outer frame mould 21, and lead screw 13 passes through outer frame mould 21st, metallic plate and fastener 5 are locked.
Two pieces of metallic plates are respectively provided with four edge joint position positions of a whole set of slabstone, are closed tight, and in two pieces of metallic plates Upper to set corresponding location hole 9, the iron filings with rotary hinge borehole cleaning inwall in reamer patchhole insert locating taper pin 3 to smoothing out, The stub end of locating taper pin 3 and a metal plate weld, sleeve 7 is welded on the edge of location hole 9 of another metallic plate, locating taper pin 3 small head end is stretched into sleeve 7 through location hole 9.
Reference picture 6 and Figure 12, set metal semicircle corner protector 4, by the metal in outer frame mould 21 in the sack position of slabstone Plate, the metal semicircle corner protector 4, metallic plate of edge joint position position are respectively welded, and form five metal edge frames of monolithic slabstone 12.
Sleeve pipe 15 is provided with four metal edge frames 2, the edge joint position of a metal edge frame 2 is welded with fastener 5;
The two ends of the sleeve pipe 15 in two of which metal edge frame 2 are respectively welded on the metal edge frame 2 of edge joint position;Other two One end of sleeve pipe 15 in individual metal edge frame 2 is provided with the U-shaped ring 16 for communicating therewith, and is respectively arranged with the two metal edge frames 2 The mounting hole C 17 corresponding with U-shaped ring 16, U-shaped ring 16 is welded on the edge of mounting hole C 17;The other end welding of sleeve pipe 15 On the metal edge frame 2 of edge joint position, lead screw 13 connects through U-shaped ring 16, the metal edge frame 2 of sleeve pipe 15, edge joint position with fastener 5 Connect.
Netted reinforcing rib 6 is set in reference picture 12, metal edge frame 2, and reinforcement 6 is welded respectively with metal edge frame 3, fastener 5 Connect;The positions of mounting hole A 8 of slabstone bottom surface set nut 10, and nut 10 is welded with reinforcement 6;To watering pours water in metal edge frame 2 Silt stone, the rear lead screw 13 removed outer frame mould 21, remove in U-shaped ring 16 to be solidified, pries open the metal edge frame 2 of edge joint position, The as finished product of monolithic slabstone 1.
During installation, by five blocks of monolithic slabstones 1 by insertion locating taper pin 3 of checking the number in situ, lead screw 13 passes through U-shaped ring 16, set The metal edge frame 2 of pipe 15, edge joint position is locked with the fastener 5 in slabstone, and a set of flatness is high, combination billiard ball with sleeve pipe 15 Table slabstone.
Sleeve pipe 15 is set in a whole set of billiard table stone slab can make edge joint position gap small, and lead screw 13 is tightened in U-shaped ring 16 Can convenient assembled slabstone, close piece, slabstone it is assembled it is good after edge joint position will not more separated when moving integrally, a whole set of billiard table The globality of slabstone is strong.
Embodiment five:Making is combined by three blocks of monolithic slabstones, and mounting hole location A sets nut, and branch is arranged at monolithic slabstone bottom The billiard table stone slab of support.
Reference picture 2, Fig. 3, Fig. 4 and Fig. 7, sets metallic plate in the outer frame mould 21, lead screw 13 through outer frame mould 21, Metallic plate is locked with fastener 5.
Two pieces of metallic plates are respectively provided with two edge joint position positions of a whole set of slabstone, are closed tight, and in two pieces of metallic plates Upper to set corresponding location hole 9, the iron filings with rotary hinge borehole cleaning inwall in reamer patchhole insert locating taper pin 3 to smoothing out, The stub end of locating taper pin 3 and a metal plate weld, sleeve 7 is welded on the edge of location hole 9 of another metallic plate, locating taper pin 3 small head end is stretched into sleeve 7 through location hole 9.
Metal semicircle corner protector 4 is set in the sack position of slabstone, by the metallic plate in outer frame mould 21, metal semicircle corner protector 4th, the metallic plate of edge joint position position is respectively welded, and forms three metal edge frames of monolithic slabstone 12;Set laterally in metal edge frame 2 With the reinforcement 6 of longitudinal direction, reinforcement 6 welds with metal edge frame 2, fastener 5 respectively.
The positions of mounting hole A 8 of slabstone bottom surface set nut 10, and nut 10 is welded with reinforcement 6.
Reference picture 13 and Figure 14, the support frame 18 of monolithic slabstone 1 is made using steel pipe and angle bar, by support frame 18 and reinforcement Muscle 6 is welded, and is locked by lead screw 13 between support frame 18;To casting cement sandstone in metal edge frame 2, housing is removed after solidification Mould 21, removes lead screw 13, pries open the metal edge frame 2 of edge joint position, the finished product of monolithic slabstone 1 as with support frame 18.
The bottom of monolithic slabstone 1 sets support frame 18 can increase the intensity of slabstone, it is more unlikely to deform;By lead screw 13 mutually lock single support frame 18, can be integrally formed a whole set of slabstone, and globality is more preferable.
Embodiment six:Making is combined by three blocks of monolithic slabstones, and mounting hole location A sets nut, and combination slabstone bottom is installed There is the billiard table stone slab of integrated support frame, lockplate is provided between support frame and slabstone.
Reference picture 2, Fig. 3, Fig. 4 and Fig. 7, sets metallic plate in the outer frame mould 21, lead screw 13 through outer frame mould 21, Metallic plate is locked with fastener 5.
Two pieces of metallic plates are respectively provided with two edge joint position positions of a whole set of slabstone, are closed tight, and in two pieces of metallic plates Upper to set corresponding location hole 9, the iron filings with rotary hinge borehole cleaning inwall in reamer patchhole insert locating taper pin 3 to smoothing out, The stub end of locating taper pin 3 and a metal plate weld, sleeve 7 is welded on the edge of location hole 9 of another metallic plate, locating taper pin 3 small head end is stretched into sleeve 7 through location hole 9.
Metal semicircle corner protector 4 is set in the sack position of slabstone, by the metallic plate in outer frame mould 21, metal semicircle corner protector 4th, the metal plate weld of edge joint position position, forms three metal edge frames of monolithic slabstone 12 respectively;Set in metal edge frame 2 netted Reinforcement 6 and the fastener 5 with support 19, reinforcement 6 are respectively welded with metal edge frame 2, fastener 5.
The positions of mounting hole A 8 of slabstone bottom surface set nut 10, and nut 10 is welded with reinforcement 6.
Reference picture 15 and Figure 16, integrated support frame 18 is made using steel pipe and angle bar, and support frame 18 is placed on into metal edges On frame 2, first one end of lockplate 20 is connected with support frame 18, the other end of lockplate 20 is passed through into lead screw 13 and fastener 5 connections, then the support 19 of fastener 5 and reinforcement 6 are welded;Mix building stones to being poured in metal edge frame 2, rear dismounting to be solidified Outer frame mould 21, removes lead screw 13, removes support frame 18, pries open the metal edge frame 2 of edge joint position, the as finished product of monolithic slabstone 1.
During installation, by three blocks of monolithic slabstones 1 by insertion locating taper pin 3 of checking the number in situ, by lead screw 13, lockplate 20 will Support frame 18 is arranged on combination slabstone bottom, and a set of flatness is high, combination billiard table stone slab with integrated support frame 18 is Into.
Setting integrated support frame 18 in a whole set of slabstone bottom can increase the intensity of slabstone, it is more unlikely to deform, and pass through Lead screw 13 will overally support frame 18 and be locked with slabstone, support frame 18 is integrally formed with a whole set of slabstone, and globality is more preferable.
What is recorded above is only the preferred embodiments of the present invention, can not limit the interest field of the present invention with this certainly, Therefore the equivalent variations made according to the claims in the present invention, still belong to the scope that the present invention is covered.

Claims (14)

1. combined type billiard table stone slab, is combined by the monolithic slabstone of polylith cement or mixing building stones pouring, single Block slabstone bottom surface is provided with mounting hole A, and monolithic slabstone is internally provided with netted reinforcement, it is characterised in that the monolithic stone The number of plate is 2-9 blocks, and monolithic slabstone is formed around metallic plate, and the sack position of slabstone is provided with metal semicircle corner protector, metal Plate is linked as that metal edge frame, the reinforcement inside metal edge frame and slabstone is integrally formed with metal semicircle corner protector in the side of monolithic slabstone Muscle is connected;Fastener is welded with the metal edge frame of slabstone lock storehouse side position, fastener is connected with the reinforcement inside slabstone; The edge joint position of two adjacent monolithic slabstones is provided with locating taper pin, wherein the metal edge frame of a slabstone is welded with locating taper pin one end, separately The metal edge frame of one slabstone is provided with location hole, and the other end of locating taper pin inserts the slabstone through location hole;The reinforcement It is one or more in steel bar, iron bar, reinforcing bar, steel wire, steel plate, iron plate, steel pipe;The metal edge frame is steel plate, iron plate, flat One or more in iron, angle bar, U-shaped steel, channel-section steel.
2. combined type billiard table stone slab according to claim 1, it is characterised in that be provided with sleeve in the monolithic slabstone, Sleeve is close to the location hole on metal edge frame.
3. combined type billiard table stone slab according to claim 1 and 2, it is characterised in that the position of the mounting hole A is provided with The nut or T-shaped sleeve pipe being connected with reinforcement.
4. combined type billiard table stone slab according to claim 1 and 2, it is characterised in that the two adjacent monolithic slabstone, The two ends of slabstone are provided with groove, and lead screw is provided with groove, and the metal edge frame of slabstone side is provided with the peace corresponding with groove Dress hole B;Nut is provided with another slabstone, lead screw is connected through the metal edge frame of slabstone edge joint position with nut.
5. combined type billiard table stone slab according to claim 1 and 2, it is characterised in that the metal edges of the monolithic slabstone Frame is provided with mounting hole C.
6. combined type billiard table stone slab according to claim 5, it is characterised in that the 2-9 blocks monolithic slabstone, wherein 1- U-shaped ring is provided with 8 blocks of slabstones, U-shaped ring is close to the mounting hole C on metal edge frame;Be additionally provided with the monolithic slabstone sleeve pipe and/or Fastener, fastener is welded on the metal edge frame in slabstone, and lead screw connects through mounting hole C, U-shaped ring, sleeve pipe and fastener Connect.
7. combined type billiard table stone slab according to claim 5, it is characterised in that the 2-9 blocks monolithic slabstone, wherein 1- U-shaped ring and sleeve pipe are provided with 8 blocks of slabstones, fastener is welded with the metal edge frame in remaining 1 block of slabstone, lead screw is passed through to be installed The connection of hole C, U-shaped ring, sleeve pipe and fastener.
8. combined type billiard table stone slab according to claim 1 and 2, it is characterised in that the bottom of the monolithic slabstone sets There is support frame, support frame is welded with the reinforcement inside slabstone.
9. combined type billiard table stone slab according to claim 1 and 2, it is characterised in that be provided with the monolithic slabstone with The fastener of reinforcement connection, overall support frame is provided with the slabstone bottom combined by polylith monolithic slabstone, and the support frame leads to Lead screw is crossed to be connected with the fastener in each monolithic slabstone.
10. combined type billiard table stone slab according to claim 9, it is characterised in that set between support frame as described above and slabstone There is lockplate, lockplate is connected respectively with support frame, billiard table stone slab.
11. combined type billiard table stone slabs according to claim 10, it is characterised in that support frame as described above be steel pipe, angle bar, One or more composition in channel-section steel, I-steel, U-shaped steel, steel plate, iron plate.
12. combined type billiard table stone slabs according to claim 1, it is characterised in that the fastener include nut and/or Support.
The preparation method of 13. combined type billiard table stone slabs according to claim 1, lays on smooth workbench bed die One layer of offset plate combines the outer frame mould of billiard table stone slab, it is characterised in that in housing mould in offset plate every mould every setting the whole series on mould Metallic plate is set in tool, and lead screw is locked through outer frame mould, metallic plate and fastener;In each edge joint position position of a whole set of slabstone Two pieces of metallic plates are installed, is closed tight, and corresponding location hole is set on two pieces of metallic plates, with reamer patchhole inward turning The iron filings of turning hinge borehole cleaning inwall insert locating taper pin, the stub end of locating taper pin and a metal plate weld to smoothing out, and small head end is stretched Enter in the location hole of another metallic plate;Metal semicircle corner protector is set in the sack position of slabstone, respectively by the gold in outer frame mould Category plate, metal semicircle corner protector, the metal plate weld of edge joint position position, form the metal edge frame of multiple monolithic slabstones;Metal edge frame Interior to set netted reinforcement, reinforcement is respectively welded with metal edge frame, fastener;The mounting hole location A of slabstone bottom surface is provided with The nut or T-shaped sleeve pipe being connected with reinforcement;To casting cement sandstone in metal edge frame or mixing building stones, rear dismounting to be solidified is outer Frame mould, pries open the metal edge frame of edge joint position, as monolithic slabstone finished product;When polylith monolithic slabstone is assembled, is checked the number by original position and inserted Enter locating taper pin, obtain final product.
The preparation method of 14. combined type billiard table stone slabs according to claim 13, it is characterised in that place support frame On metal edge frame, first pass through lead screw and lock the nut of fastener and support frame, support and the reinforcement of fastener are welded, Again to casting cement sandstone in metal edge frame or mixing building stones.
CN201510180171.1A 2015-04-16 2015-04-16 Combined billiard table slate board and manufacturing method thereof Active CN104759089B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510180171.1A CN104759089B (en) 2015-04-16 2015-04-16 Combined billiard table slate board and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510180171.1A CN104759089B (en) 2015-04-16 2015-04-16 Combined billiard table slate board and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN104759089A CN104759089A (en) 2015-07-08
CN104759089B true CN104759089B (en) 2017-05-24

Family

ID=53641383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510180171.1A Active CN104759089B (en) 2015-04-16 2015-04-16 Combined billiard table slate board and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN104759089B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107048741A (en) * 2016-08-30 2017-08-18 广东乐惠购网络科技有限公司 A kind of multifunctional plastic wardrobe
CN113663315A (en) * 2021-07-19 2021-11-19 贵州晨春石业有限公司 Billiard table stone plate and processing technology thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB190827977A (en) * 1908-12-23 1909-04-29 Karl Albert August Bracher Improvements in and relating to the Beds of Billiard and the like Tables.
FR2641197B1 (en) * 1988-12-30 1991-05-24 Charton Ets Maurice BILLIARDS
CN2322469Y (en) * 1997-09-30 1999-06-09 乔元栩 Billiards table
CN2326306Y (en) * 1997-12-01 1999-06-30 北京星牌台球器械厂 British style snock billiard-table structure improvement
CN2912738Y (en) * 2006-04-29 2007-06-20 中山腾龙体育器材有限公司 Marlbe billiard table
CN201135758Y (en) * 2008-01-14 2008-10-22 吕剑都 Table board of billiard ball table
CN204522237U (en) * 2015-04-16 2015-08-05 湖南省常德市皇冠桌球台总厂 Combined type billiard table stone slab and the billiard table being convenient to movement made of this slabstone

Also Published As

Publication number Publication date
CN104759089A (en) 2015-07-08

Similar Documents

Publication Publication Date Title
CN104759089B (en) Combined billiard table slate board and manufacturing method thereof
CN207905122U (en) A kind of novel locating device of built-in fitting for building
CN107152092B (en) The installation method of buried water stop and its fixed frame used at a kind of construction joint
CN108297247A (en) A kind of production method of superimposed sheet, superimposed sheet production equipment and superimposed sheet
CN108104372A (en) For the precast combined constructional column and construction method of masonry structure
CN206233560U (en) Wall formwork erecting structure
CN105113781B (en) Device is set up in a kind of overhanging complete pre-buried installation in side of setting a roof beam in place
CN208379585U (en) A kind of architectural engineering anchor-rod positioner
CN106930238B (en) A kind of fixed device of hydraulic engineering waterstop and application method
CN106760522A (en) A kind of concrete structure seam crossing prevents swollen mould mortar leakage prevention fixing device and method
CN204522237U (en) Combined type billiard table stone slab and the billiard table being convenient to movement made of this slabstone
CN208068511U (en) A kind of production equipment of superimposed sheet and superimposed sheet
CN103495279A (en) Billiard table stone plate and manufacturing method thereof
CN207348283U (en) Prefabricated board mounting structure
CN109372133A (en) In buried rubber fastening band positioning construction method is installed
CN105507568B (en) A kind of tile work device and tile work method
JP4787119B2 (en) Concrete placing apparatus and concrete placing method
CN104453235B (en) Current conversion station fire wall construction technology
CN206703246U (en) Precast concrete mould
CN113279568A (en) Novel light steel plastic spraying template and supporting structure and construction method thereof
CN107119808A (en) Induce crack structure and its construction method
CN209653160U (en) Filled wall construction
CN207206688U (en) A kind of concrete pad fabricated device
CN103520904A (en) Billiard table whole stone slab and manufacturing method thereof
CN207775924U (en) Piping lane top die board mounting structure, piping lane template installation system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant