CN104749473A - Testing method capable of simulating field power utilization information collecting terminal power failure events - Google Patents

Testing method capable of simulating field power utilization information collecting terminal power failure events Download PDF

Info

Publication number
CN104749473A
CN104749473A CN201510193470.9A CN201510193470A CN104749473A CN 104749473 A CN104749473 A CN 104749473A CN 201510193470 A CN201510193470 A CN 201510193470A CN 104749473 A CN104749473 A CN 104749473A
Authority
CN
China
Prior art keywords
terminal
electric energy
power
event
power failure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510193470.9A
Other languages
Chinese (zh)
Other versions
CN104749473B (en
Inventor
崔迎宾
严晶晶
张卫欣
刘卿
刘崇伟
单增礼
李蓓
王海巍
陈晓芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510193470.9A priority Critical patent/CN104749473B/en
Publication of CN104749473A publication Critical patent/CN104749473A/en
Application granted granted Critical
Publication of CN104749473B publication Critical patent/CN104749473B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a testing method capable of simulating field power utilization information collecting terminal power failure events. The method includes the steps of firstly, simultaneously allowing power failure of a terminal and an electric energy meter to test the effectiveness of terminal power failure event recording; secondly, allowing power failure of the terminal and continuously supplying power to the electric energy meter to effectiveness of terminal power failure event recording; thirdly, judging whether terminal power failure event collecting is qualified or not. The method has the advantages that the rules and features of power utilization information collecting terminal power failure events which frequently occur on site are analyzed strictly according to the requirements of Collecting Terminal and Electric Energy Meter Power Failure Event Data Reduction Regulations, the method is provided by combining with an actually-operated power utilization information collecting main station system, the method can well simulate field conditions, and is convenient to operate, accurate in testing result and capable of guaranteeing the reliable operation of the power utilization information collecting terminal.

Description

A kind of power information acquisition terminal of simulated field stops the event testing method that powers on
Technical field
The invention belongs to power consumer electricity consumption information and gather field, especially a kind of power information acquisition terminal of simulated field stops the event testing method that powers on.
Background technology
In order to advance Electric Power Quality On-line Monitor System construction, further raising is special, public becomes user's power-off event accuracy, improve power-off event collection, arrange efficiency, State Grid Corporation of China has worked out " acquisition terminal and electric energy meter power-off event data preparation rule ", stop the power on event of this rule to power information acquisition terminal and electric energy meter is defined, and defines the judgement of power-off event collection rule and rationality, validity.Guo Wang Tianjin Utilities Electric Co. has carried out power information acquisition terminal laboratory according to this rule and to have stopped powering on the test job of event acquisition, but finds that the power information acquisition terminal of test passes can not accurate acquisition report main website after stopping the event of powering at the scene.Therefore be badly in need of research stops the event of powering on method at laboratory simulation on-the-spot test power information acquisition terminal, improve the success ratio that the collection of power information acquisition terminal stops the event of powering on.
Through retrieval, do not find the identical technology of publication.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art part, provide a kind of reasonable in design, be easy to operation, accurately and reliably the power information acquisition terminal of simulated field stop the event testing method that powers on.
The present invention solves its technical matters and takes following technical scheme to realize:
The power information acquisition terminal of simulated field stops the event testing method that powers on, and it is characterized in that: detailed step is as follows:
(1) terminal and electric energy meter stop to power on simultaneously, the validity of test terminal power-off event record;
1. choose and carry out respectively stopping power on operation with three pieces of electric energy meters of tested power information acquisition terminal same carrier wave scheme, after completing wiring, power information acquisition terminal and electric energy meter are powered on simultaneously;
2. be connected to power information until power information acquisition terminal to gather after main website, clear terminal parameter, waits for a period of time, then re-issues terminal parameter and electric energy meter archive information, and determining can normal data such as copy reading electric energy meter electric energy indicating value;
3. power failure operation while of power information acquisition terminal and three pieces of electric energy meters being carried out; Have a power failure after waiting for a period of time, to terminal and three pieces of electric energy meters power on operation simultaneously, terminal should judge to stop the event of powering on as normally effectively having a power failure and report main website, checks that Ying Youting powers on event by power information collection main station system;
(2) terminal power failure, electric energy meter do not have a power failure, the validity of test terminal power-off event record;
1. wait for a period of time, have a power failure to terminal, electric energy meter continues normal power supply;
2. wait for a period of time, terminal powers on, and terminal should judge that stopping the event of powering on is that invalid power failure does not report main website, gathers main station system check that Ying Wuting powers on event by power information;
(3) whether qualifiedly judge that terminal collection stops the event of powering on, to step (1), whether step test result comprehensive descision (2) test and pass through.
And, step (1) in electric information acquisition terminal and electric energy meter choose and the mode of connection is: can test record and stop the event of powering on and time, and as do not prepared to record, more transducing accurate recording stops the electric energy meter of the event of powering on and time; After choosing three pieces of electric energy meters of test passes, on A, B, C phase that three pieces of electric energy meters are connected respectively to power information acquisition terminal and N phase connection terminal, guarantee the three-phase and four-line voltage that power information acquisition terminal 380V/220V is provided.
And, step (1), step (2) in wait for a period of time and be all set as wait 5 minutes.
And step (3) concrete decision method is: if step (1) in power information gather main station system and have and stop the logout that powers on, and step (2) in power information gather main station system without stopping the logout that powers on, then test is passed through; Otherwise need contrast message to carry out case study, amendment terminal stops the determining program that powers on.
Advantage of the present invention and good effect are:
The present invention is in strict accordance with the requirement of " acquisition terminal and electric energy meter power-off event data preparation rule ", analyze the rule trend that the on-the-spot power information acquisition terminal often occurred stops the event of powering on, power information in conjunction with actual motion gathers main station system, the power information acquisition terminal proposing simulated field stops the event testing method that powers on, this method can simulated field situation preferably, easy to operate, test result is accurate, ensures the reliability service of power information acquisition terminal.
Accompanying drawing explanation
Fig. 1 is method of testing process flow diagram of the present invention.
Embodiment
Below in conjunction with accompanying drawing, also by specific embodiment, the invention will be further described, and following examples are descriptive, are not determinate, can not limit protection scope of the present invention with this.
The power information acquisition terminal of simulated field stops the event testing method that powers on, and as shown in Figure 1, detailed step is as follows for the flow process of this method of testing:
(1) terminal and electric energy meter stop to power on simultaneously, the validity of test terminal power-off event record;
1. choose and carry out respectively stopping power on operation with three pieces of electric energy meters of tested power information acquisition terminal same carrier wave scheme, after completing wiring, power information acquisition terminal and electric energy meter are powered on simultaneously;
Can test record and stop the event of powering on and time, and as do not prepared to record, more transducing accurate recording stops the electric energy meter of the event of powering on and time; After choosing three pieces of electric energy meters of test passes, on A, B, C phase that three pieces of electric energy meters are connected respectively to power information acquisition terminal and N phase connection terminal, guarantee the three-phase and four-line voltage that power information acquisition terminal 380V/220V is provided;
2. be connected to after power information collection main website until power information acquisition terminal, clear terminal parameter, re-issue terminal parameter and electric energy meter archive information again, wait for 5 minutes, the data such as copy reading electric energy meter electric energy indicating value, determine that electric energy meter archives, messaging parameter etc. are correct, determining can normal data such as copy reading electric energy meter electric energy indicating value;
3. power failure operation while of power information acquisition terminal and three pieces of electric energy meters being carried out; Have a power failure after 5 minutes, to terminal and three pieces of electric energy meters power on operation simultaneously, terminal should judge to stop the event of powering on as normally effectively having a power failure and report main website, checks that Ying Youting powers on event by power information collection main station system;
(2) terminal power failure, electric energy meter do not have a power failure, the validity of test terminal power-off event record;
1. wait for 5 minutes, have a power failure to terminal, electric energy meter continues normal power supply;
2. wait for 5 minutes, terminal powers on, and terminal should judge that stopping the event of powering on is that invalid power failure does not report main website, gathers main station system check that Ying Wuting powers on event by power information;
(3) whether qualifiedly judge that terminal collection stops the event of powering on, to step (1), whether step test result comprehensive descision (2) test and pass through.
Be specially: if step (1) in power information gather main station system and have and stop the logout that powers on, and step (2) in power information gather main station system without stopping the logout that powers on, then test is passed through; Otherwise need contrast message to carry out case study, amendment terminal stops the determining program that powers on.
Although disclose embodiments of the invention and accompanying drawing for the purpose of illustration, but it will be appreciated by those skilled in the art that: in the spirit and scope not departing from the present invention and claims, various replacement, change and amendment are all possible, therefore, scope of the present invention is not limited to the content disclosed in embodiment and accompanying drawing.

Claims (4)

1. the power information acquisition terminal of simulated field stops the event testing method that powers on, and it is characterized in that: detailed step is as follows:
(1) terminal and electric energy meter stop to power on simultaneously, the validity of test terminal power-off event record;
1. choose and carry out respectively stopping power on operation with three pieces of electric energy meters of tested power information acquisition terminal same carrier wave scheme, after completing wiring, power information acquisition terminal and electric energy meter are powered on simultaneously;
2. be connected to power information until power information acquisition terminal to gather after main website, clear terminal parameter, waits for a period of time, then re-issues terminal parameter and electric energy meter archive information, and determining can normal data such as copy reading electric energy meter electric energy indicating value;
3. power failure operation while of power information acquisition terminal and three pieces of electric energy meters being carried out; Have a power failure after waiting for a period of time, to terminal and three pieces of electric energy meters power on operation simultaneously, terminal should judge to stop the event of powering on as normally effectively having a power failure and report main website, checks that Ying Youting powers on event by power information collection main station system;
(2) terminal power failure, electric energy meter do not have a power failure, the validity of test terminal power-off event record;
1. wait for a period of time, have a power failure to terminal, electric energy meter continues normal power supply;
2. wait for a period of time, terminal powers on, and terminal should judge that stopping the event of powering on is that invalid power failure does not report main website, gathers main station system check that Ying Wuting powers on event by power information;
(3) whether qualifiedly judge that terminal collection stops the event of powering on, to step (1), whether step test result comprehensive descision (2) test and pass through.
2. the power information acquisition terminal of simulated field according to claim 1 stops the event testing method that powers on, it is characterized in that: step (1) in electric information acquisition terminal and electric energy meter choose and the mode of connection is: can test record and stop the event of powering on and time, and as do not prepared to record, more transducing accurate recording stops the electric energy meter of the event of powering on and time; After choosing three pieces of electric energy meters of test passes, on A, B, C phase that three pieces of electric energy meters are connected respectively to power information acquisition terminal and N phase connection terminal, guarantee the three-phase and four-line voltage that power information acquisition terminal 380V/220V is provided.
3. the power information acquisition terminal of simulated field according to claim 1 stops the event testing method that powers on, and it is characterized in that: step (1), step (2) in wait for a period of time and be all set as wait 5 minutes.
4. the power information acquisition terminal of simulated field according to claim 1 stops the event testing method that powers on, it is characterized in that: step (3) concrete decision method is: if step (1) in power information gather main station system and have and stop the logout that powers on, and step (2) in power information gather main station system without stopping the logout that powers on, then test pass through; Otherwise need contrast message to carry out case study, amendment terminal stops the determining program that powers on.
CN201510193470.9A 2015-04-21 2015-04-21 A kind of power information acquisition terminal for simulating scene stops upper electric event testing method Active CN104749473B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510193470.9A CN104749473B (en) 2015-04-21 2015-04-21 A kind of power information acquisition terminal for simulating scene stops upper electric event testing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510193470.9A CN104749473B (en) 2015-04-21 2015-04-21 A kind of power information acquisition terminal for simulating scene stops upper electric event testing method

Publications (2)

Publication Number Publication Date
CN104749473A true CN104749473A (en) 2015-07-01
CN104749473B CN104749473B (en) 2017-08-29

Family

ID=53589454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510193470.9A Active CN104749473B (en) 2015-04-21 2015-04-21 A kind of power information acquisition terminal for simulating scene stops upper electric event testing method

Country Status (1)

Country Link
CN (1) CN104749473B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108123544A (en) * 2017-12-05 2018-06-05 国网浙江省电力公司台州供电公司 For the power failure check method of supply line
CN108152578A (en) * 2017-12-15 2018-06-12 国网陕西省电力公司电力科学研究院 Taiwan area intelligent electric energy meter power-off event active reporting and analysis method
CN111596126A (en) * 2019-07-12 2020-08-28 青岛鼎信通讯股份有限公司 Method for judging affiliation of area meter by using intelligent meter power-off record
CN113589103A (en) * 2021-08-03 2021-11-02 贵州电网有限责任公司 Method for judging power failure of user in real time based on terminal power failure alarm

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006033130A (en) * 2004-07-13 2006-02-02 Matsushita Electric Ind Co Ltd Information terminal, method for information processing, and program
CN102024318A (en) * 2009-09-09 2011-04-20 浙江省电力公司 Automatic adjustment method based on planned power utilization information collection terminal
CN103150690A (en) * 2013-03-29 2013-06-12 山东电力集团公司 Client side power supply quality index calculation system and method based on SMART (specific, measurable, attainable, realistic and time-based) criterion
CN103197138A (en) * 2013-02-22 2013-07-10 王金泽 Intelligent electric meter with function of detecting power supply reliability and voltage qualified rate and detecting method thereof
CN103532778A (en) * 2013-10-11 2014-01-22 光一科技股份有限公司 Intelligent testing method for electricity consumption information collection equipment
CN203747502U (en) * 2014-03-20 2014-07-30 谭守军 Power outage reporting device used for power utilization information acquisition terminal

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006033130A (en) * 2004-07-13 2006-02-02 Matsushita Electric Ind Co Ltd Information terminal, method for information processing, and program
CN102024318A (en) * 2009-09-09 2011-04-20 浙江省电力公司 Automatic adjustment method based on planned power utilization information collection terminal
CN103197138A (en) * 2013-02-22 2013-07-10 王金泽 Intelligent electric meter with function of detecting power supply reliability and voltage qualified rate and detecting method thereof
CN103150690A (en) * 2013-03-29 2013-06-12 山东电力集团公司 Client side power supply quality index calculation system and method based on SMART (specific, measurable, attainable, realistic and time-based) criterion
CN103532778A (en) * 2013-10-11 2014-01-22 光一科技股份有限公司 Intelligent testing method for electricity consumption information collection equipment
CN203747502U (en) * 2014-03-20 2014-07-30 谭守军 Power outage reporting device used for power utilization information acquisition terminal

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
朱彬若 等: "电力用户用电信息采集系统数据分析与处理技术", 《华东电力》 *
王者龙 等: "用电信息采集终端在智能配网中的应用", 《山东电力技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108123544A (en) * 2017-12-05 2018-06-05 国网浙江省电力公司台州供电公司 For the power failure check method of supply line
CN108152578A (en) * 2017-12-15 2018-06-12 国网陕西省电力公司电力科学研究院 Taiwan area intelligent electric energy meter power-off event active reporting and analysis method
CN111596126A (en) * 2019-07-12 2020-08-28 青岛鼎信通讯股份有限公司 Method for judging affiliation of area meter by using intelligent meter power-off record
CN113589103A (en) * 2021-08-03 2021-11-02 贵州电网有限责任公司 Method for judging power failure of user in real time based on terminal power failure alarm

Also Published As

Publication number Publication date
CN104749473B (en) 2017-08-29

Similar Documents

Publication Publication Date Title
CN103163397B (en) Universal analog quantity plate detection system for nuclear plant and method
CN104811224A (en) Test system for power line carrier communication module
CN104360922A (en) Method for automatically monitoring BMC working state based on ipmitool
CN105279952A (en) Whole-event acquisition testing system of intelligent ammeter based on virtual ammeter module
CN104749473A (en) Testing method capable of simulating field power utilization information collecting terminal power failure events
CN105425201A (en) Metering chip simulation test method used for intelligent electric energy meter software reliability detection
CN103885438A (en) Automatic test system and method for transformer substation measurement and control device
CN102331570A (en) Electric energy meter on-line detection method
CN101702008B (en) Portable electric machine fault on-line diagnostic device
CN102262190A (en) Device and method for online discharge monitoring of ultrahigh voltage power transmission line
CN105467355A (en) Automatic testing method of electric energy meter and automatic testing device of same
CN201522549U (en) Portable device for online diagnosing motor fault
CN203324466U (en) Verification system capable of verifying multiple electric-energy meters with different current specifications at the same time
CN103728510B (en) Excitation unit on-site test system and method
CN204331017U (en) Intelligent electric energy meter proving installation and system
CN202522658U (en) System for automatically testing and diagnosing corrosion fault points of substation grounding grid
CN203366114U (en) Relay protection and secondary loop state on-line maintenance system based on SOA
CN204028346U (en) A kind of electric energy meter Auto-Test System
CN101957401A (en) Power-distribution electric energy comprehensive measuring apparatus and measuring method thereof
CN105204999A (en) Method for achieving automated testing of CPU VR Static LL test
CN201919002U (en) Carrier communication test instrument
CN205786889U (en) Dynamic passive compensation response wave shape acquisition system
CN205230339U (en) Test system is gathered to smart electric meter total event based on virtual electric energy meter module
CN104158852A (en) Information interaction detection system for low-voltage meter reading concentrator and local communication module
CN104765348A (en) Energy amount measuring system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant