CN104631719A - 预制钢筋混凝土防震楼梯及施工方法 - Google Patents
预制钢筋混凝土防震楼梯及施工方法 Download PDFInfo
- Publication number
- CN104631719A CN104631719A CN201510033120.6A CN201510033120A CN104631719A CN 104631719 A CN104631719 A CN 104631719A CN 201510033120 A CN201510033120 A CN 201510033120A CN 104631719 A CN104631719 A CN 104631719A
- Authority
- CN
- China
- Prior art keywords
- welded
- platform
- landing beam
- support member
- stair
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Steps, Ramps, And Handrails (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
一种预制钢筋混凝土防震楼梯及施工方法。楼梯由梯段板、平台支撑构件、外侧平台梁、内侧平台梁、支撑梁、聚四氟乙烯板、密封条、倒L形板、框架梁、边柱和中柱组成。梯段板的踏步端固定在支撑梁上,平台端搭接在外侧平台梁和内侧平台梁上;倒L形板的突出端固定在支撑梁上,平面端固定在框架梁上;平台支撑构件固定在边柱和中柱上;内侧平台梁和支撑梁固定在平台支撑构件上。楼梯构件中梁柱的固定连接采用企口式连接。楼梯施工中,构件之间通过焊接连接,外侧平台梁和内侧平台梁固定后,在上表面粘贴聚四氟乙烯板,使梯段板能相对外层平台梁和内侧平台梁滑动。本发明能减小地震时预制楼梯的震害,确保楼梯安全。
Description
技术领域
本发明涉及装配式钢筋混凝土结构中的预制楼梯领域。
背景技术
装配式钢筋混凝土结构是由工厂生产的预制构件在现场安装而成,具有节约现场劳动力、施工周期短,便于工业化和机械化生产等优点。目前,国内、外的建筑行业都越来越重视装配式钢筋混凝土结构,在预制柱、预制梁、预制板和预制节点等方面进行了研究,能够组成基本的预制混凝土框架结构体系,但是,还需要一种预制钢筋混凝土楼梯,起竖向交通和疏散作用。另一方面,地震震害调查中发现钢筋混凝土框架结构的楼梯损坏较为严重,楼梯在地震中承担了较大的水平力,《建筑抗震设计规范》中规定宜采取构造措施,减少楼梯构件对主体结构刚度的影响,同时也减小了楼梯在地震时的受力,确保楼梯的安全,预制钢筋混凝土楼梯也要满足抗震规范的要求。目前装配式钢筋混凝土框架结构体系还不够完善,需要一种预制钢筋混凝土防震楼梯及相应的施工方法。
发明内容
为了解决装配式钢筋混凝土结构的竖向交通问题,并满足抗震规范的要求,本发明公开一种预制钢筋混凝土防震楼梯及施工方法,楼梯具有构件简单、传力可靠、抗震性能好等优点。
本发明的预制钢筋混凝土防震楼梯的技术方案是:由梯段板、平台支撑构件、外侧平台梁、内侧平台梁、支撑梁、聚四氟乙烯板、密封条、倒L形板、框架梁、边柱和中柱组成。梯段板一侧为踏步,另一侧为平台,梯段板的踏步端固定在支撑梁上,平台端搭接在外侧平台梁和内侧平台梁上,梯段板平台端与外侧平台梁和内侧平台梁的接触处设置聚四氟乙烯板。两块梯段板平台端之间的缝隙、梯段板平台端与边柱之间的缝隙采用密封条封堵。倒L形板的突出端固定在支撑梁上,平面端固定在框架梁上。外侧平台梁固定在边柱上,框架梁固定在中柱上,平台支撑构件固定在边柱和中柱上。内侧平台梁固定在平台支撑构件的短柱上,支撑梁固定在平台支撑构件的横梁上。楼梯构件中梁柱的固定连接都采用企口式连接,支撑构件留下凸槎,被支撑构件留上凸槎,在上凸槎和下凸槎处设置预埋钢板,通过焊接将构件连接起来。平台支撑构件两端留上凸槎,与边柱和中柱的下凸槎对应;侧面留下凸槎,与支撑梁的上凸槎对应;上部设置短柱,短柱上留下凸槎,与内侧平台梁的上凸槎对应。外侧平台梁两端留上凸槎,与边柱的下凸槎对应。内侧平台梁两端留上凸槎,与平台支撑构件短柱上的下凸槎对应。支撑梁两端留上凸槎,与平台支撑构件横梁上的下凸槎对应。框架梁两端留上凸槎,与中柱的下凸槎对应。边柱上留有多个下凸槎,分别与平台支撑构件和外侧平台梁的上凸槎对应。中柱上留有多个下凸槎,分别与平台支撑构件和框架梁的上凸槎对应。
梯段板的平台端搭接在外侧平台梁和内侧平台梁上,并在梯段板平台端与外侧平台梁和内侧平台梁的接触处设置聚四氟乙烯板,同时,两块梯段板平台端之间、梯段板平台端与边柱之间留有缝隙,所以梯段板与外侧平台梁和内侧平台梁能相对滑动,减小了地震时楼梯构件的受力,有利于楼梯和主体结构的抗震。
本发明的预制钢筋混凝土防震楼梯的施工方法是:按照楼梯间尺寸定位边柱和中柱,将下层平台支撑构件焊接在边柱和中柱上,下层框架梁焊接在两根中柱上,外侧平台梁焊接在两根边柱上,内侧平台梁焊接在两根平台支撑构件的短柱上,下层支撑梁焊接在两根平台支撑构件的横梁上;在外侧平台梁和内侧平台梁的上表面粘贴聚四氟乙烯板;将下层倒L形板的突出端焊接在下层支撑梁上,平面端焊接在下层框架梁上,将下层梯段板的平台端搭接在外侧平台梁和内侧平台梁上,踏步端焊接在下层支撑梁上;将上层平台支撑构件焊接在边柱和中柱上,上层框架梁焊接在两根中柱上,上层支撑梁焊接在两根平台支撑构件的横梁上;将上层倒L形板的突出端焊接在上层支撑梁上,平面端焊接在上层框架梁上,将上层梯段板的平台端搭接在外侧平台梁和内侧平台梁上,踏步端焊接在上层支撑梁上;两块梯段板平台端之间的缝隙、梯段板平台端与边柱之间的缝隙用密封条封堵。
本发明的预制钢筋混凝土防震楼梯构件简单、传力可靠,地震时梯段板与平台梁能相对滑动,减小了地震时楼梯的受力,有利于楼梯和主体结构的抗震;所述的施工方法工序简单,能够实现楼梯构件与主体结构的不完全固接。本发明能够减小地震时预制楼梯的震害,确保楼梯安全,具有较大的社会效益。
附图说明
下面结合附图对本发明进一步说明。
图1是本发明的预制钢筋混凝土防震楼梯的轴测图。
图2是本发明的预制钢筋混凝土防震楼梯的俯视图。
图3是本发明的预制钢筋混凝土防震楼梯的剖视图。
图4是本发明的梯段板的轴测图。
图5是本发明的平台支撑构件的轴测图。
图6是本发明的倒L形板的轴测图。
图7是本发明的外侧平台梁、内侧平台梁、支撑梁和框架梁的轴测图。
图8是本发明的边柱和中柱的轴测图。
图9是本发明的企口式连接示意图。
图10是本发明的施工过程图。
图中:1—梯段板,2—平台支撑构件,3—外侧平台梁,4—内侧平台梁,5—支撑梁,6—聚四氟乙烯板,7—密封条,8—倒L形板,9—框架梁,10—边柱,11—中柱,12—预埋钢板,13—短柱。
具体实施方式
如图1-3所示,一种预制钢筋混凝土防震楼梯,由梯段板(1)、平台支撑构件(2)、外侧平台梁(3)、内侧平台梁(4)、支撑梁(5)、聚四氟乙烯板(6)、密封条(7)、倒L形板(8)、框架梁(9)、边柱(10)和中柱(11)组成。梯段板(1)的踏步端固定在支撑梁(5)上,平台端搭接在外侧平台梁(3)和内侧平台梁(4)上,梯段板(1)的平台端与外侧平台梁(3)和内侧平台梁(4)的接触处设置聚四氟乙烯板(6)。两块梯段板(1)平台端之间的缝隙、梯段板(1)平台端与边柱(10)之间的缝隙采用密封条(7)封堵。倒L形板(8)的突出端固定在支撑梁(5)上,平面端固定在框架梁(9)上。外侧平台梁(3)固定在边柱(10)上,框架梁(9)固定在中柱(11)上,平台支撑构件(2)固定在边柱(10)和中柱(11)上。内侧平台梁(4)固定在平台支撑构件(2)的短柱上,支撑梁(5)固定在平台支撑构件(2)的横梁上。梯段板(1)能够相对外侧平台梁(3)和内侧平台梁(4)滑动,减小了地震时楼梯构件的受力,有利于楼梯和主体结构的抗震。
如图4所示,梯段板(1)一侧为踏步,另一侧为平台。
如图5所示,平台支撑构件(2)两端留上凸槎,与边柱和中柱的下凸槎对应;侧面留下凸槎,与支撑梁的上凸槎对应;上部设置短柱(13),短柱(13)上留下凸槎,与内侧平台梁的上凸槎对应。
如图6所示,倒L形板(8)的一端向下突出,为了与梯段板的端踏步厚度相一致。
如图7所示,外侧平台梁(3)、内侧平台梁(4)、支撑梁(5)和框架梁(9)的两端都留有上凸槎。外侧平台梁(3)的上凸槎与边柱的下凸槎对应,内侧平台梁(4)的上凸槎与平台支撑构件短柱上的下凸槎对应,支撑梁(5)的上凸槎与平台支撑构件横梁上的下凸槎对应,框架梁(9)的上凸槎与中柱的下凸槎对应。
如图8所示,边柱(10)和中柱(11)上留有多个下凸槎,分别与平台支撑构件、外侧平台梁和框架梁的上凸槎对应。
如图9所示,在构件的上凸槎和下凸槎处设置预埋钢板(12),预埋钢板(12)上开坡口,将两块接触的预埋钢板(12)焊接起来,实现两个构件之间的连接。
图10为本发明的预制钢筋混凝土防震楼梯的施工过程图,整个施工过程分为a、b、c、d、e、f六个步骤,具体的施工过程为:施工步骤a,按照楼梯间尺寸定位边柱(10)和中柱(11),将下层平台支撑构件(2)焊接在边柱(10)和中柱(11)上,下层框架梁(9)焊接在两根中柱(11)上,外侧平台梁(3)焊接在两根边柱(10)上,内侧平台梁(4)焊接在两根平台支撑构件(2)的短柱上,下层支撑梁(5)焊接在两根平台支撑构件(2)的横梁上;施工步骤b,在外侧平台梁(3)和内侧平台梁(4)的上表面上粘贴聚四氟乙烯板(6);施工步骤c,将下层倒L形板(8)的突出端焊接在下层支撑梁(5)上,平面端焊接在下层框架梁(9)上,将下层梯段板(1)的平台端搭接在外侧平台梁(3)和内侧平台梁(4)上,踏步端焊接在下层支撑梁(5)上;施工步骤d,将上层平台支撑构件(2)焊接在边柱(10)和中柱(11)上,上层框架梁(9)焊接在两根中柱(11)上,上层支撑梁(5)焊接在两根平台支撑构件(2)的横梁上;施工步骤e,将上层倒L形板(8)的突出端焊接在上层支撑梁(5)上,平面端焊接在上层框架梁(9)上,将上层梯段板(1)的平台端搭接在外侧平台梁(3)和内侧平台梁(4)上,踏步端焊接在上层支撑梁(5)上;施工步骤f,两块梯段板(1)平台端之间的缝隙、梯段板(1)平台端与边柱(10)之间的缝隙用密封条(7)封堵。
Claims (4)
1. 一种预制钢筋混凝土防震楼梯,由梯段板、平台支撑构件、外侧平台梁、内侧平台梁、支撑梁、聚四氟乙烯板、密封条、倒L形板、框架梁、边柱和中柱组成,其特征是:梯段板的踏步端固定在支撑梁上,平台端搭接在外侧平台梁和内侧平台梁上;倒L形板的突出端固定在支撑梁上,平面端固定在框架梁上;平台支撑构件固定在边柱和中柱上;内侧平台梁固定在平台支撑构件的短柱上,支撑梁固定在平台支撑构件的横梁上。
2. 根据权利要求1所述的预制钢筋混凝土防震楼梯,其特征是:梯段板一侧为踏步,另一侧为平台。
3. 根据权利要求1所述的预制钢筋混凝土防震楼梯,其特征是:平台支撑构件两端留上凸槎,与边柱和中柱的下凸槎对应;侧面留下凸槎,与支撑梁的上凸槎对应;上部设置短柱,短柱上留下凸槎,与内侧平台梁的上凸槎对应。
4. 一种实现权利要求1所述的预制钢筋混凝土防震楼梯的施工方法,其特征是:按照楼梯间尺寸定位边柱和中柱,将下层平台支撑构件焊接在边柱和中柱上,下层框架梁焊接在两根中柱上,外侧平台梁焊接在两根边柱上,内侧平台梁焊接在两根平台支撑构件的短柱上,下层支撑梁焊接在两根平台支撑构件的横梁上;在外侧平台梁和内侧平台梁的上表面粘贴聚四氟乙烯板;将下层倒L形板的突出端焊接在下层支撑梁上,平面端焊接在下层框架梁上,将下层梯段板的平台端搭接在外侧平台梁和内侧平台梁上,踏步端焊接在下层支撑梁上;将上层平台支撑构件焊接在边柱和中柱上,上层框架梁焊接在两根中柱上,上层支撑梁焊接在两根平台支撑构件的横梁上;将上层倒L形板的突出端焊接在上层支撑梁上,平面端焊接在上层框架梁上,将上层梯段板的平台端搭接在外侧平台梁和内侧平台梁上,踏步端焊接在上层支撑梁上;两块梯段板平台端之间的缝隙、梯段板平台端与边柱之间的缝隙用密封条封堵。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510033120.6A CN104631719B (zh) | 2015-01-23 | 2015-01-23 | 预制钢筋混凝土防震楼梯及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510033120.6A CN104631719B (zh) | 2015-01-23 | 2015-01-23 | 预制钢筋混凝土防震楼梯及施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104631719A true CN104631719A (zh) | 2015-05-20 |
CN104631719B CN104631719B (zh) | 2017-04-12 |
Family
ID=53210914
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510033120.6A Expired - Fee Related CN104631719B (zh) | 2015-01-23 | 2015-01-23 | 预制钢筋混凝土防震楼梯及施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104631719B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104947865A (zh) * | 2015-07-03 | 2015-09-30 | 山东科技大学 | 中分式钢筋混凝土防震楼梯及施工方法 |
CN105155791A (zh) * | 2015-09-25 | 2015-12-16 | 山东科技大学 | 组合结构防震楼梯及施工方法 |
CN107268904A (zh) * | 2017-06-21 | 2017-10-20 | 广州大学 | 装配式隔震楼梯及其施工方法 |
CN108824919A (zh) * | 2018-07-24 | 2018-11-16 | 同济大学 | 新型减震防倒塌筒体结构 |
WO2021184540A1 (zh) * | 2020-03-18 | 2021-09-23 | 常州工程职业技术学院 | 一种全装配式楼梯体系及装配方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11303349A (ja) * | 1998-04-21 | 1999-11-02 | Takenaka Komuten Co Ltd | 階高の異なる階段対応のプレキャストコンクリート階段及びその製作方法 |
CN2349289Y (zh) * | 1998-11-28 | 1999-11-17 | 李岭群 | 预制整体式楼梯板 |
KR100905806B1 (ko) * | 2008-09-11 | 2009-07-02 | 정민선 | 조립식 계단 |
CN104032905A (zh) * | 2014-06-20 | 2014-09-10 | 山东科技大学 | 上梯段滑动式钢筋混凝土减震楼梯 |
CN204531232U (zh) * | 2015-01-23 | 2015-08-05 | 山东科技大学 | 预制钢筋混凝土防震楼梯 |
-
2015
- 2015-01-23 CN CN201510033120.6A patent/CN104631719B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11303349A (ja) * | 1998-04-21 | 1999-11-02 | Takenaka Komuten Co Ltd | 階高の異なる階段対応のプレキャストコンクリート階段及びその製作方法 |
CN2349289Y (zh) * | 1998-11-28 | 1999-11-17 | 李岭群 | 预制整体式楼梯板 |
KR100905806B1 (ko) * | 2008-09-11 | 2009-07-02 | 정민선 | 조립식 계단 |
CN104032905A (zh) * | 2014-06-20 | 2014-09-10 | 山东科技大学 | 上梯段滑动式钢筋混凝土减震楼梯 |
CN204531232U (zh) * | 2015-01-23 | 2015-08-05 | 山东科技大学 | 预制钢筋混凝土防震楼梯 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104947865A (zh) * | 2015-07-03 | 2015-09-30 | 山东科技大学 | 中分式钢筋混凝土防震楼梯及施工方法 |
CN105155791A (zh) * | 2015-09-25 | 2015-12-16 | 山东科技大学 | 组合结构防震楼梯及施工方法 |
CN107268904A (zh) * | 2017-06-21 | 2017-10-20 | 广州大学 | 装配式隔震楼梯及其施工方法 |
CN108824919A (zh) * | 2018-07-24 | 2018-11-16 | 同济大学 | 新型减震防倒塌筒体结构 |
WO2021184540A1 (zh) * | 2020-03-18 | 2021-09-23 | 常州工程职业技术学院 | 一种全装配式楼梯体系及装配方法 |
US11692356B2 (en) | 2020-03-18 | 2023-07-04 | Changzhou Vocational Institute Of Engineering | Fully-assembled staircase system and assembly method |
Also Published As
Publication number | Publication date |
---|---|
CN104631719B (zh) | 2017-04-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631719A (zh) | 预制钢筋混凝土防震楼梯及施工方法 | |
CN103206014B (zh) | 实现节点刚性连接的多高层装配式钢结构框架支撑体系 | |
CN103184762B (zh) | 实现节点刚性连接的多高层装配式钢结构预应力支撑体系 | |
CN105756227B (zh) | 一种多层斜向开槽的自防屈曲钢板剪力墙及其制作方法 | |
CN103195163B (zh) | 一种实现节点刚性连接的多高层装配式钢结构体系 | |
CN103276799B (zh) | 一种工业化装配式柱贯通梁实腹式钢结构框架偏心支撑体系 | |
CN102182276B (zh) | 一种双亚字形巨型柱的制作方法 | |
CN209053231U (zh) | 一种用于钢结构梁柱连接的分离式牛腿节点结构及住宅结构体系 | |
CN204531232U (zh) | 预制钢筋混凝土防震楼梯 | |
CN203531421U (zh) | 一种可移动塔式爬梯 | |
CN105971117A (zh) | 一种采用箱型截面梁的仿古建筑钢框架结构 | |
CN203145273U (zh) | 可拆装钢-混凝土组合楼板 | |
CN103195162B (zh) | 一种标准单元装配式耗能减震结构体系 | |
CN105369890A (zh) | 抗震民居钢构架及其安装方法 | |
CN109356338A (zh) | 钢骨架女儿墙结构 | |
CN209854935U (zh) | 一种复式钢管混凝土角柱—钢梁节点 | |
JP2015055038A (ja) | 建築物のラーメン架構 | |
CN203546900U (zh) | 建筑物 | |
CN103510665A (zh) | 新型预制悬挂木楼梯 | |
CN103882941B (zh) | 模块化的多高层装配式钢结构框架中心支撑体系 | |
CN209144634U (zh) | 一种有较高承载能力的钢结构简易桥梁 | |
CN203546908U (zh) | 一种装配式建筑墙梁稳定连接结构 | |
CN206319463U (zh) | 一种楼板系统框架及楼板系统 | |
CN106760100A (zh) | 一种楼板系统框架及楼板系统 | |
KR101148546B1 (ko) | 장스팬용 조립 철골 보 및 그를 이용한 철골 골조 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170412 Termination date: 20220123 |