CN104631255B - A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual - Google Patents

A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual Download PDF

Info

Publication number
CN104631255B
CN104631255B CN201510020658.3A CN201510020658A CN104631255B CN 104631255 B CN104631255 B CN 104631255B CN 201510020658 A CN201510020658 A CN 201510020658A CN 104631255 B CN104631255 B CN 104631255B
Authority
CN
China
Prior art keywords
cement
roadbed
fiber
construction
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510020658.3A
Other languages
Chinese (zh)
Other versions
CN104631255A (en
Inventor
陈秋南
赵磊军
刘文骏
蒋林云
周翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University of Science and Technology
Original Assignee
Hunan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University of Science and Technology filed Critical Hunan University of Science and Technology
Priority to CN201510020658.3A priority Critical patent/CN104631255B/en
Publication of CN104631255A publication Critical patent/CN104631255A/en
Application granted granted Critical
Publication of CN104631255B publication Critical patent/CN104631255B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, comprise the following steps:Survey and construction scene, carries out field investigation and sampling, and laboratory test is determined, construction lofting, site clearing;Material prepares:Various improved materials and construction equipment needed thereby equipment are prepared according to result of the test;Drainage system is set;Optional test section carries out constructing and quality inspection, carries out next step after quality inspection is qualified;Calculating needs the earth volume of improvement, and cement and fiber total amount according to needed for Earthwork Calculation;Subgrade construction quality inspection, carry out next step after quality inspection is qualified;Road bed inspection, shaping, slope trimming.Former subgrade soil is carried out digging, is smashed by this construction method, mix proper amount of cement and glass fibre, flatten again, be compacted, conserve, form high stability, the modified soil subgrade of high intensity, can effectively reduce the harm that granite residual soil area roadbed water disintegration is caused to subgrade and pavement.

Description

A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual
Technical field
The present invention relates to a kind of roadbed construction method, more particularly to one kind cement and fiber suppress granite residual dirt road The construction method of base disintegrate.
Background technology
Granite residual soil has obvious disintegrative, meets water electrode and disintegrate easily occurs, and be swift in response, once intensity of disintegration Rapid drawdown.Under such geological conditions, easily occur road bank settlement, the landslide of roadbed side slope, roadbed along hillside slip etc. Geological disaster.Therefore, granite residual soil area roadbed in addition to wanting proof strength, rigidity, it is also expressly noted which is whole Body stability and water stability.
Content of the invention
In order to solve above-mentioned technical problem, the present invention provides a kind of intensity that can improve roadbed and stability in the large, effectively The use cement and fiber of suppression granite residual soil water disintegration phenomenon suppress the construction method of the earth roadbed disintegrate of granite residual.
Technical proposal that the invention solves the above-mentioned problems is:One kind cement and fiber suppress that granite residual is earth roadbed to be collapsed The construction method of solution, comprises the following steps:
1)Survey and construction scene, carries out field investigation and sampling, and laboratory test is determined, construction lofting, site clearing;
2)Material prepares:Various improved materials and construction equipment needed thereby equipment are prepared according to result of the test;
3) drainage system is set;
4)Optional test section carries out constructing and quality inspection, carries out next step after quality inspection is qualified;
5)Calculating needs the earth volume of improvement, and cement and fiber total amount according to needed for Earthwork Calculation;
6)Subgrade construction quality inspection, carry out next step after quality inspection is qualified;
7)Road bed inspection, shaping, slope trimming.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 1)In, adopt Indoor triaxial test determines cement proportion and fibre furnish, comprises the following steps that:Soil sample is air-dried, is pulverized, sieve after It is divided into two groups;Soil sample is divided into 6 parts by first group of test cement optimum proportioning, be separately added into 4% in 6 parts of soil samples, 5%, 6%, 7%th, 8% and 9% 6 kind of different quality containing cement mixed weight, measured by indoor triaxial test and when the mass fraction of cement be When 6%, its cohesion and internal friction angle are maximum;The optimum proportioning of second group of test fiber, it is 6% to mix mass fraction in soil sample Cement after, be divided into 6 parts, in 6 parts of soil samples again respectively mix 0.5 ‰, 1 ‰, 1.5 ‰, 2 ‰, 2.5 ‰ and of mass fraction 3 ‰ fiber, measures its cohesion, internal friction angle when the mass fraction of fiber is 1 ‰ by indoor triaxial test maximum;? Go out the optimal cement proportion mass fraction of conclusion and fibre furnish mass fraction is respectively 6% and 1 ‰.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 3)In, on road Basilar parts arrange gutter along roadbed direction in its both sides.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 4)In, will examination The subgrade soil for testing section digs, dry in the sun, smash, shelving 24 hours, add 6% cement and 1 ‰ fibers, mix be uniform, leveling, Compaction in layers through quality testing qualified after formally gone into operation.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 5)In, for Whether embankment embankment, the compactness of detection roadbed substrate undisturbed soil, intensity, stability meet the requirements:If through being measured by sampling Meet the requirements, then the total amount of cement and fiber needed for calculating according to amount of fill;If roadbed substrate undisturbed soil does not meet after measured Require, then it is that amount of fill improves earth volume sum with substrate to need the earth volume for improveing;For zero padding and cut subgrade, by roadbed The undisturbed soil of 0 ~ 80cm below bottom surface is improved and is conserved.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 6)Subgrade construction Concretely comprise the following steps:
(1)The earthwork that need to be improved is dug, dry in the sun, is smashed, the soil body that smashes is configured to moisture content for vexed after 23.85% Put 24 hours;
(2)6% cement and 1 ‰ glass fibre is sprinkled in the vexed good soil body, and mix is uniform;
(3)By the soil body paving and leveling for mixing, layered rolling, often rolled one layer detection compactness, qualified after carry out Next layer of making is rolled;
(4)Roadbed is rolled, closed to vehicles.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 6)Subgrade construction Concrete steps(2)In, glass fibre length is 5 ~ 8cm, glass fibre is scatter and be uniformly sprinkled into again in the vexed good soil body, instead Multiple stirring, until without conglomeration and substantially exposed glass fibre.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 6)Subgrade construction Concrete steps(3)In, adjacent wheelmark coincidence more than 1/3 in roller compaction process, every layer of loose laying depth is not more than 30cm, roadbed top surface The compacted depth of last layer is more than 10cm.
Above-mentioned use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, the step 1)In cement For portland cement, portland slag cement or pozzolan cement, the final setting time of cement is more than 6h.
The beneficial effects of the present invention is:
1st, script is unsatisfactory for requiring needing changing the subgrade soil filled out and carries out digging, smashes, appropriate mix by this construction method Cement and glass fibre, then flatten, be compacted, conserve, so as to form the modified soil subgrade of a kind of high stability, high intensity, can Effectively to reduce the harm that granite residual soil area roadbed water disintegration is caused to subgrade and pavement;
2nd, appropriate glass fibre is added in the roadbed after constructing, change the failure mode of light water soil, broken by fragility The bad elastoplasticity that is changed into is destroyed, and can alleviate the brittle break that roadbed is produced because of the impact of larger load, to the road for wrecking Great cushioning effect is played on base road surface, extends the service life of roadbed;
3rd, this construction method script needs can be changed the soil layer that fills out and made full use of, and significantly improve the stability of roadbed and resist Pressure performance, substantially reduces workload and working time, and then reduces construction cost.
Description of the drawings
Fig. 1 is the construction process figure of the present invention.
Fig. 2 is roadbed section schematic diagram.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
As shown in figure 1, the invention discloses a kind of use cement and fiber suppress the construction of the earth roadbed disintegrate of granite residual Method, comprises the following steps:
1)Survey and construction scene, carries out field investigation and sampling, determines cement proportion and fibre furnish by indoor triaxial test, its The optimal cement proportion mass fraction of middle granite residual soil is 6%, and optimal fibre furnish mass fraction is 1 ‰, construction lofting, Site clearing.Carry out during indoor triaxial test air-drying soil sample, pulverize, sieve, and be divided into two groups;First group is used for Soil sample is divided into 6 parts by test cement optimum proportioning, is separately added into 4%, 5%, 6%, 7%, 8% and 9% 6 kind of different quality containing Cement, measures its cohesion and internal friction angle maximum when the mass fraction of cement is 6% by indoor triaxial test, and intensity is big, Therefore optimal cement mixed weight is chosen for 6%;Second group of optimum proportioning for being used for testing fiber, mixes mass fraction in soil sample After for 6% cement, 6 parts are divided into, mix mass fraction 0.5 ‰, 1 ‰, 1.5 ‰, 2 ‰, 2.5 ‰ in 6 parts of soil samples again respectively Fiber with 3 ‰, measures when the mass fraction of fiber is 1 ‰ its cohesion, internal friction angle and strong by indoor triaxial test Degree is maximum, and particularly stress-strain diagram is clearly distinguishable from soil cement, and failure mode is changed into compression failure by failure by shear;Cause This determines optimal cement proportion by indoor triaxial test and fibre furnish is respectively 6% and 1 ‰;
2)Material prepares:Various improved materials and construction equipment needed thereby equipment are prepared according to result of the test;
3) drainage system is set:Gutter is set in roadbed bottom in its both sides along roadbed direction;
4)Optional test section, the subgrade soil of test section is dug, dry in the sun, smash, shelving is after 24 hours, adds 6% Cement and 1 ‰ fibers, mix are uniform, leveling, compaction in layers, through quality testing qualified after formally gone into operation;
5)Calculating needs the earth volume of improvement, and cement and fiber total amount according to needed for Earthwork Calculation:For embankment road Whether dike, the compactness of detection roadbed substrate undisturbed soil, intensity, stability meet the requirements:If conformed to through sampling and measuring Ask, then the total amount of cement and fiber needed for calculating according to amount of fill;If roadbed substrate undisturbed soil is undesirable after measured, The earth volume for needing improvement is that amount of fill improves earth volume sum with substrate;For zero padding and cut subgrade, by roadbed bottom surface with The undisturbed soil of lower 0 ~ 80cm is improved and is conserved;
6)Subgrade construction quality inspection;
(1)The earthwork that need to be improved is dug, dry in the sun, is smashed, field investigation and sampling measures the soil body most by standard compaction test Big dry density is 1.54g/cm, and optimum moisture content is 23.85%, and the soil body that smashes is configured to vexed after optimum moisture content state Put 24 hours;
(2)6% cement and 1 ‰ glass fibre is sprinkled in the vexed good soil body, and mix is uniform;Glass fibre length is 8cm, uneven for cement and fiber mix, mainly take both sides measure:First, will be uniform for satisfactory cement It is sprinkled in the soil body, through mix repeatedly.The glass fibre of conglomeration should be disperseed by glass fibre easily conglomeration in its natural state Open and be uniformly sprinkled in the soil body to be improved again, stir repeatedly, until without conglomeration and substantially exposed glass fibre.Second, consideration water Mix process setting time of mud should not adopt artificial mix, should adopt powerful mix plant;
(3)The soil body for mixing uniformly is paved, precompressed leveling, layered rolling, roll follow first light-duty after heavy, speed First slow rear fast, adjacent wheelmark coincidence more than 1/3 in roller compaction process is answered, every layer of loose laying depth is not more than 30cm, and roadbed top surface is last One layer of compacted depth is more than 10cm;Often rolled one layer detection compactness k value, qualified after can carry out next layer making grind Pressure;
In roller compaction process, for the process of seam and switch area:The joining place of two active sections that constructs on the same day should be adopted With joint form, after the last period mix shaping, stay 5m not rolled, afterwards during one section of construction, should stay with the last period and not press Mix is rolled again together for part;Mixing machinery and other equipment are not reversed end for end on the road bed for completing has been rolled, if Must reverse end for end, carry out on the work surface not rolled as far as possible;
(4)Roadbed is rolled, closed to vehicles.
7)Road bed inspection, shaping, slope trimming;Fig. 2 is roadbed section schematic diagram, and roadbed adopts compaction in layers, roadbed Surface is conducive to draining the water away into two-way horizontal wall inscription.
During roadbed design and build, should be taken according to local hydrological geological conditions and arrange with technical in structure Apply, make the humidity and range of temperature of roadbed conditioned soil be down to minimum, the maintenance stage particularly after subgrade compaction, must Stablizing for moisture content and temperature must be ensured, to guarantee that roadbed there are enough strength and stabilities.Therefore, can fit during build When the height for improving roadbed filling, to prevent water point from penetrating into from side, or level of ground water ascends into roadbed work area scope;Must Water barrier can also be set when wanting, to block the passage of capillary water rising;Or take appropriate slope reinforcement measure, build gear Native structures are improving roadbed stability in the large.

Claims (5)

1. a kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, comprise the following steps:
1) survey and construction scene, carries out field investigation and sampling, and laboratory test is determined, construction lofting, site clearing;
2) material prepares:Various improved materials and construction equipment needed thereby equipment are prepared according to result of the test;
3) drainage system is set;
4) optional test section carries out constructing and quality inspection, carries out next step after quality inspection is qualified;
5) calculating needs the earth volume of improvement, and cement and fiber total amount according to needed for Earthwork Calculation;
6) subgrade construction quality inspection, carry out next step after quality inspection is qualified;
7) road bed inspection, shaping, slope trimming;
The step 1) in, cement proportion and fibre furnish are determined using indoor triaxial test, is comprised the following steps that:To be fetched earth Sample air-dries, pulverizes, sieve after be divided into two groups;Soil sample is divided into 6 parts by first group of test cement optimum proportioning, in 6 parts of soil samples In be separately added into the cement mixed weight of 4%, 5%, 6%, 7%, 8% and 9% 6 kind of different quality containing, tried by indoor three axle When the mass fraction of the proper cement of test is 6%, its cohesion and internal friction angle are maximum;The optimum proportioning of second group of test fiber, After incorporation mass fraction is 6% cement in soil sample, 6 parts are divided into, mix mass fraction in 6 parts of soil samples again respectively 0.5 ‰, 1 ‰, 1.5 ‰, 2 ‰, 2.5 ‰ and 3 ‰ fiber, is measured by indoor triaxial test and when the mass fraction of fiber is When 1 ‰, its cohesion, internal friction angle are maximum;The cement proportion mass fraction for reaching a conclusion optimal and fibre furnish mass fraction point Wei 6% and 1 ‰;
The step 4) in, the subgrade soil of test section is dug, dry in the sun, smash, shelving 24 hours, add 6% cement and 1 ‰ fibers, mix are uniform, leveling, compaction in layers through quality testing qualified after formally gone into operation;
The step 6) subgrade construction concretely comprises the following steps:
(1) earthwork that need to be improved dug, dry in the sun, smashed, the soil body that smashes is configured to moisture content and 24 is put for vexed after 23.85% Hour;
(2) 6% cement and 1 ‰ glass fibre are sprinkled in the vexed good soil body, and mix is uniform;
(3) by the soil body paving and leveling for mixing, layered rolling, often rolled one layer detection compactness, qualified after carry out next The making of layer is rolled;
(4) preservative film maintenance is covered after roadbed is rolled and finished, closed to vehicles;
The step 6) subgrade construction concrete steps (2) in, glass fibre length be 5~8cm, glass fibre is scatter again Uniformly it is sprinkled in the vexed good soil body, stirs repeatedly, until without conglomeration and substantially exposed glass fibre.
2. use cement as claimed in claim 1 and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, its feature It is:The step 3) in, gutter is set in roadbed bottom in its both sides along roadbed direction.
3. use cement as claimed in claim 1 and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, its feature It is:The step 5) in, for embankment embankment, whether the compactness of detection roadbed substrate undisturbed soil, intensity, stability meet Require:If met the requirements through sampling and measuring, the total amount of cement and fiber needed for calculating according to amount of fill;If after measured Roadbed substrate undisturbed soil is undesirable, then it is that amount of fill improves earth volume sum with substrate to need the earth volume for improveing;For The undisturbed soil of 0~80cm below roadbed bottom surface is improved and is conserved by zero padding and cut subgrade.
4. use cement as claimed in claim 1 and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, its feature It is:The step 6) subgrade construction concrete steps (3) in, in roller compaction process, adjacent wheelmark overlaps more than 1/3, per layer of pine paving Thickness is not more than 30cm, and the compacted depth of roadbed top surface last layer is more than 10cm.
5. use cement as claimed in claim 1 and fiber suppress the construction method of the earth roadbed disintegrate of granite residual, its feature It is:The step 1) in cement be portland cement, portland slag cement or pozzolan cement, the final setting time of cement For more than 6h.
CN201510020658.3A 2015-01-16 2015-01-16 A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual Expired - Fee Related CN104631255B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510020658.3A CN104631255B (en) 2015-01-16 2015-01-16 A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510020658.3A CN104631255B (en) 2015-01-16 2015-01-16 A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual

Publications (2)

Publication Number Publication Date
CN104631255A CN104631255A (en) 2015-05-20
CN104631255B true CN104631255B (en) 2017-03-15

Family

ID=53210456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510020658.3A Expired - Fee Related CN104631255B (en) 2015-01-16 2015-01-16 A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual

Country Status (1)

Country Link
CN (1) CN104631255B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155378B (en) * 2015-09-02 2017-08-18 湖州浩诚环境工程有限公司 A kind of rendzinas subgrade construction technique
CN106917388A (en) * 2017-03-14 2017-07-04 广东省长大公路工程有限公司 The check dam and construction method of a kind of use Fill Reinforced With Geogrids modified cement soil clad
CN110419289A (en) * 2019-07-09 2019-11-08 中国一冶集团有限公司 A kind of road Red Sandstone soil improvement construction method
CN110528346A (en) * 2019-07-24 2019-12-03 中国一冶集团有限公司 A kind of Red Sandstone improvement construction method
CN113373749A (en) * 2021-06-22 2021-09-10 湖南工程学院 Improved construction method for granite residual soil roadbed

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04189903A (en) * 1990-11-22 1992-07-08 Sumitomo Metal Ind Ltd Quick-hardening subgrade improvement material
JP2002013102A (en) * 2000-06-28 2002-01-18 Shiima Consultant:Kk Soil improvement method
CN1963022A (en) * 2006-11-22 2007-05-16 天津市市政工程设计研究院 Use method of industrial caustic dross in treatment of road bed and foundation
CN102153303A (en) * 2010-12-13 2011-08-17 中铁第四勘察设计院集团有限公司 Chemical improving method using soft rock weathered material as high-speed railway subgrade filler

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04189903A (en) * 1990-11-22 1992-07-08 Sumitomo Metal Ind Ltd Quick-hardening subgrade improvement material
JP2002013102A (en) * 2000-06-28 2002-01-18 Shiima Consultant:Kk Soil improvement method
CN1963022A (en) * 2006-11-22 2007-05-16 天津市市政工程设计研究院 Use method of industrial caustic dross in treatment of road bed and foundation
CN102153303A (en) * 2010-12-13 2011-08-17 中铁第四勘察设计院集团有限公司 Chemical improving method using soft rock weathered material as high-speed railway subgrade filler

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
花岗岩残积土崩解试验研究;兰泽鑫;《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》;20131215(第S2期);第33-34、50-52页 *
高等级公路全风化花岗岩路基处理及沉降规律研究;傅励;《中国优秀博硕士学位论文全文数据库(硕士工程科技Ⅱ辑)》;20051115(第07期);第1、36-45页 *

Also Published As

Publication number Publication date
CN104631255A (en) 2015-05-20

Similar Documents

Publication Publication Date Title
CN104631255B (en) A kind of use cement and fiber suppress the construction method of the earth roadbed disintegrate of granite residual
CN104404838B (en) The above railway collapsible loess subgrade substrate treating method of speed 200km
Vanícek et al. Earth structures: in transport, water and environmental engineering
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN105297571A (en) Mudstone filled roadbed structure and construction method thereof
CN111962350A (en) Geocell reinforced cement concrete pavement structure and method for calculating thickness of surface slab
CN110777588A (en) Pressure filling construction method for soil-stone mixed high-filling roadbed
RU2392387C2 (en) Device and method for reinforcement of mast base
CN111778796A (en) Roadbed construction process
CN102839683B (en) Granular pile-permeable concrete stake dual compound foundation and processing method
CN110820456A (en) Anti-settling and replacement-filling alternate airport runway and construction method thereof
Chua et al. Structured soil mixture for solving deformation issue in GeoBarrier System
CN102031743A (en) Construction method of mudstone-filled embankment
Li et al. Mechanical behavior of reinforced embankment with different recycling waste fillers
CN106703013A (en) Water-proof curtain for treating built loess roadbed subsidence damages
Yang et al. Addressing expansive soils
Wilson et al. The use of low grade rockfill at Roadford Dam
CN111206598B (en) Method for cooperatively utilizing construction waste in hillock landscaping project
Dronamraju Studies on field stabilization methods to prevent surficial slope failures of earthfill dams
CN103449784B (en) Be applicable to the cement-based waterproof anticracking material of swelled ground area railway cutting bedding
CN202787295U (en) Dispersive pile-permeable concrete pile novel dual compound foundation
Yang et al. Soil erosion caused by highway construction in expansive soils districts and its prevention measures
Kumbhare et al. Experimental studies on alternate foundations for load transfer in deep clay deposits
CN211312046U (en) Soil-rock mixed filling roadbed structure
Yang et al. High fill embankment of collapsible loess settlement observation and research

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170315