CN104591049B - Greater trochanter immersion lifting device - Google Patents
Greater trochanter immersion lifting device Download PDFInfo
- Publication number
- CN104591049B CN104591049B CN201510077992.2A CN201510077992A CN104591049B CN 104591049 B CN104591049 B CN 104591049B CN 201510077992 A CN201510077992 A CN 201510077992A CN 104591049 B CN104591049 B CN 104591049B
- Authority
- CN
- China
- Prior art keywords
- connecting plate
- plates
- column
- track
- footing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F11/00—Lifting devices specially adapted for particular uses not otherwise provided for
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F2700/00—Lifting apparatus
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Crystals, And After-Treatments Of Crystals (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The lifting device the invention discloses a kind of greater trochanter soaks,Including two front upright footing plates、Two rear column footing pieces、Big cooling bay and little cooling bay,It is respectively and fixedly provided with front column on two front upright footing plates,It is respectively and fixedly provided with rear column on two rear column footing pieces,The upper end of front column and rear column is equipped with upright post connecting plate,Between two front columns, front beam is fixed with by upright post connecting plate,Between two rear columns, rear cross beam is fixed with by upright post connecting plate,Front beam is provided with four the first connecting plates,Rear cross beam is provided with four the second connecting plates,It is provided with buttress brace between first connecting plate on both sides and the second connecting plate,It is provided with hoisting frame between the first middle connecting plate and the second connecting plate,The upper end of two hoisting frames is fixed with electric block,The lower end of two hoisting frames is respectively and fixedly provided with track plates,Track is equipped with track plates,Stay hook is connected with track.Present configuration consolidates, and using safety, stability is good, soaks for greater trochanter and is lifted.
Description
Technical field
The lifting device the present invention relates to a kind of greater trochanter soaks.
Background technology
In the industrial production, rotor need to immerse in cooling bay cooling, and greater trochanter volume is big, weight is big, to the liter of rotor
Fall brings difficulty.
Content of the invention
The invention aims to meeting above needs, provide a kind of stabilized structure, using safety, stability
Good, for the greater trochanter immersion lifting device of greater trochanter immersion lifting.
The purpose of invention is achieved through the following technical solutions:A kind of greater trochanter immersion lifting device, greater trochanter immersion carries
Rise device and include two front upright footing plates, two rear column footing pieces, big cooling bay and little cooling bay, two front upright footings
It is respectively and fixedly provided with front column on plate, two rear column footing pieces are respectively and fixedly provided with rear column, the upper end of front column and rear column is all provided with
There is upright post connecting plate, between two front columns, front beam is fixed with by upright post connecting plate, between two rear columns, pass through column
Connecting plate is fixed with rear cross beam, and front beam is provided with four the first connecting plates, and rear cross beam is provided with four the second connecting plates, and first
Connecting plate and the second connecting plate are in symmetric position, are provided with buttress brace between first connecting plate on both sides and the second connecting plate,
It is provided with hoisting frame, the upper end of two hoisting frames is fixed with electric block between the first middle connecting plate and the second connecting plate, two
The lower end of individual hoisting frame is respectively and fixedly provided with track plates, and track plates are placed in big cooling bay, and track plates are equipped with track, track and electricity
Dynamic calabash is connected, and track is connected with stay hook.
That invents further improvement is that:It is fixed with the first reinforcement and second between front upright footing plate and front column to add
Strong muscle, is fixed with the 3rd reinforcement between rear column footing piece and rear column.
That invents further improvement is that:It is provided with baffle plate between stay hook and track plates.
Invention compared with prior art has advantages below:
Be fixed with the first reinforcement and the second reinforcement between front upright footing plate and front column, rear column footing piece and after
It is fixed with the 3rd reinforcement, the connection at each position is all connected by corresponding connecting plate, and stabilized structure, using peace between column
Entirely, stability is good;Be provided with baffle plate between stay hook and track plates so that on track and stay hook connection more firm, simultaneously
Situations such as in lifting process, minimizing collision is rocked, reduces dangerous incidence rate;Convenient, labour-saving carries out carrying of greater trochanter immersion
Rise, improve work efficiency.
Brief description:
Fig. 1 is the structural representation of the present invention;
In figure label:Vertical after the big cooling bay of 1-, the little cooling bay of 2-, 3- front upright footing plate, 4- rear column footing piece, 5-
Post, 6- front column, 7- first reinforcement, 8- second reinforcement, 9- the 3rd reinforcement, 10- front beam, 11- rear cross beam, 12-
Two connecting plates, 13- first connecting plate, 14- buttress brace, 15- hoisting frame, 16- electric block, 17- track plates, 18- stay hook,
19- baffle plate, 20- track, 21- upright post connecting plate.
Specific embodiment:
In order to deepen the understanding to invention, below in conjunction with embodiment and accompanying drawing, invention is described in further detail, this enforcement
Example is only used for explaining invention, does not constitute the restriction to invention protection domain.
As Fig. 1 shows a kind of embodiment of invention greater trochanter immersion lifting device, greater trochanter immersion lifting device bag
Include 3, two rear column footing pieces 4 of two front upright footing plates, big cooling bay 1 and little cooling bay 2, two front upright footing plates 3
On be respectively and fixedly provided with front column 6, two rear column footing pieces 4 are respectively and fixedly provided with rear column 5, the upper end of front column 6 and rear column 5 is equal
Be provided with upright post connecting plate 21, between two front columns 6, front beam 10 be fixed with by upright post connecting plate 21, two rear columns 5 it
Between rear cross beam 11 is fixed with by upright post connecting plate 21, front beam 10 is provided with four the first connecting plates 13, and rear cross beam 11 sets
Four the second connecting plates 12, the first connecting plate 13 and the second connecting plate 12 is had to be in symmetric position, first connecting plate on both sides
13 and second are provided with buttress brace 14 between connecting plate 12, are provided with lifting between the first middle connecting plate 13 and the second connecting plate 12
Frame 15, the upper end of two hoisting frames 15 is fixed with electric block 16, and the lower end of two hoisting frames 15 is respectively and fixedly provided with track plates 17, rail
Guidance tape 17 is placed in big cooling bay 1, and track plates 17 are equipped with track 20, and track 20 is connected with electric block 16, on track 20
It is connected with stay hook 18, be fixed with the first reinforcement 7 and the second reinforcement 8 between front upright footing plate 3 and front column 6, stand afterwards
It is fixed with the 3rd reinforcement 9 between post footing piece 4 and rear column 5, between stay hook 18 and track plates 17, be provided with baffle plate 19.Work
When, greater trochanter is placed in stay hook 18, electric block 16 drives track 20 to operate, the operating of track 20 drives stay hook 18
Lifting.
The foregoing is only explanation embodiments of the present invention, be not limited to the present invention, for the technology of this area
For personnel, all any modification, equivalent substitution and improvement within the spirit and principles in the present invention, made etc., should be included in
Within protection scope of the present invention.
Claims (1)
1. a kind of greater trochanter immersion lifting device it is characterised in that:Described greater trochanter immersion lifting device includes two front columns
Footing piece(3), two rear column footing pieces(4), big cooling bay(1)With little cooling bay(2), described two front upright footing plates
(3)On be respectively and fixedly provided with front column(6), described two rear column footing pieces(4)On be respectively and fixedly provided with rear column(5), described front column
(6)And rear column(5)Upper end be equipped with upright post connecting plate(21), described two front columns(6)Between pass through upright post connecting plate
(21)It is fixed with front beam(10), described two rear columns(5)Between pass through upright post connecting plate(21)It is fixed with rear cross beam(11),
Described front beam(10)It is provided with four the first connecting plates(13), described rear cross beam(11)It is provided with four the second connecting plates
(12), described first connecting plate(13)With the second connecting plate(12)It is in symmetric position, described first connecting plate on both sides
(13)With the second connecting plate(12)Between be provided with buttress brace(14), described first connecting plate of centre(13)With the second connecting plate
(12)Between be provided with hoisting frame(15), described two hoisting frames(15)Upper end be fixed with electric block(16), described two carry
Rise frame(15)Lower end be respectively and fixedly provided with track plates(17), described track plates(17)It is placed in big cooling bay(1)In, described track plates
(17)On be equipped with track(20), described track(20)With electric block(16)It is connected, described track(20)On be connected with support
Hook(18);Described front upright footing plate(3)And front column(6)Between be fixed with the first reinforcement(7)With the second reinforcement(8),
Described rear column footing piece(4)And rear column(5)Between be fixed with the 3rd reinforcement(9);Described stay hook(18)With track plates
(17)Between be provided with baffle plate(19).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510077992.2A CN104591049B (en) | 2015-02-14 | 2015-02-14 | Greater trochanter immersion lifting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510077992.2A CN104591049B (en) | 2015-02-14 | 2015-02-14 | Greater trochanter immersion lifting device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104591049A CN104591049A (en) | 2015-05-06 |
CN104591049B true CN104591049B (en) | 2017-03-01 |
Family
ID=53117178
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510077992.2A Active CN104591049B (en) | 2015-02-14 | 2015-02-14 | Greater trochanter immersion lifting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104591049B (en) |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103084294A (en) * | 2013-01-30 | 2013-05-08 | 无锡市顺达物流涂装设备有限公司 | Slag collection frame lifting mechanism for coating equipment |
CN103303847B (en) * | 2013-06-27 | 2015-12-02 | 长城汽车股份有限公司 | A kind of large-scale workpiece that is welded hangs the equipment of liter |
CN103569872B (en) * | 2013-11-25 | 2016-03-23 | 环球石材(福建)有限公司 | Stone material dimension board row panel assembly |
CN104210992B (en) * | 2014-08-19 | 2016-08-24 | 苏州汇科机电设备有限公司 | The auxiliary equipment jacking adjusting apparatus of electronic kiln |
CN104184271B (en) * | 2014-09-12 | 2016-05-18 | 苏州石丸英合精密机械有限公司 | Rotor automatic assembling machine |
CN204607527U (en) * | 2015-02-14 | 2015-09-02 | 马鞍山纽泽科技服务有限公司 | Greater trochanter immersion bont |
-
2015
- 2015-02-14 CN CN201510077992.2A patent/CN104591049B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104591049A (en) | 2015-05-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104591049B (en) | Greater trochanter immersion lifting device | |
CN206289944U (en) | For the tool-type protective platform of Super High exterior frame column | |
CN205894345U (en) | Assembled multipurpose metal damper | |
CN204607527U (en) | Greater trochanter immersion bont | |
CN207467204U (en) | Floor support plate fixed frame | |
CN203029885U (en) | Multifunctional bodybuilding equipment | |
CN202897720U (en) | Roller connection device for building hoist | |
CN206306965U (en) | A kind of mounting bracket of electric-control system | |
CN205999791U (en) | A kind of prestressed stretch-draw combination type tensioning stand | |
CN204917745U (en) | Portable portal crane | |
CN205742217U (en) | A kind of increase the device of single bracing members stability in foundation ditch | |
CN208235587U (en) | A kind of large-span deep foundation pit underground power house rack assembling construction platform | |
CN202144673U (en) | Integrated base station fixing structure | |
CN202897842U (en) | Turnover device applied to bottom of large component | |
CN206476307U (en) | A kind of frock placed for bus front bridge | |
CN205400059U (en) | Novel aluminum alloy template is to pulling -on piece system | |
CN205034948U (en) | Rack formula hanging beam device | |
CN205497408U (en) | Spliced pole | |
CN213509537U (en) | Horizontal connecting frame for bottom layer of scaffold | |
CN203889915U (en) | Hoist trolley frame device | |
CN203939532U (en) | A kind of steam turbine high strength band fuel tank chassis | |
CN103626045A (en) | Load hoisting apparatus | |
CN209481048U (en) | A kind of carrying pole device of auxiliary lifting | |
CN210221464U (en) | Self-checking device for door frame | |
CN202499437U (en) | Suspension support for large spherical tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20191119 Address after: 215434 Jiangsu city of Suzhou province Taicang City Bridge Town Village Patentee after: TAICANG RONGCHI MOTOR CO., LTD. Address before: 243000 Anhui city of Ma'anshan province high tech Zone at 1669 North Road Huo sparkle Building No. 2 Patentee before: Ma'an Mountain Niu Ze science service Co., Ltd |