- Prior art keywords
- collecting unit
- control unit
- time
- data
- acquisition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Emergency Protection Circuit Devices (AREA)
- Selective Calling Equipment (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
本发明公开了一种用于电力电缆的光纤分布式装置的同步方法,包括:上位机向控制单元发送开始采集命令;控制单元接收到上位机发送的开始采集命令后,记录当前时间,向各采集单元发送触发信号,同时开始接收采集单元返回的信号;采集单元通过触发信号触发开始采集传感器所检测的信号,同时,采集单元向控制单元发送采集到的信号;采集单元采集预定时间或预定数据长度后停止采集,存储采集数据或通过光纤传输至上位机;上位机接收控制单元和采集单元返回的数据,计算出控制单元分别与各采集单元的时延,对采集单元的采集到的数据进行时间校正,删除同步时间之前的数据,保留采集单元的同步采集数据,并进行显示和存储。
Description
技术领域
本发明涉及一种用于电力电缆的光纤分布式装置的同步方法。
技术背景
分布式装置的同步测量是在智能电网、变电站等领域应用中亟需解决的问题,分布式采集装置的同步方法主要有命令同步和硬接点同步,命令同步方法是主控制单元与分布采集单元通过GPS获取卫星时间,或者GPS信号接收器实现信号同步;硬接点同步采用光纤通信传输,具有光纤通信容量大、损耗低、误码率低和抗电磁干扰强等特点。
但是,在光纤通信传输的过程中,由于各采集单元相隔距离相差较大,从几公里到数十公里不等,并且对于同步精度要求较高时,各采集单元的时延造成的误差不能忽视。
发明内容
本发明解决采用光纤通信传输的分布式装置在同步过程中存在时延问题,提供一种用于电力电缆的光纤分布式装置的同步方法。
为了解决上述问题,本发明具体采用如下具体方案:
一种用于电力电缆的光纤分布式装置的同步方法,所述光纤分布式装置包括上位机、控制单元及与控制单元相连接的若干个信号采集单元,每个采集单元与一个传感器相连;该光纤分布式装置的同步方法,具体包括以下步骤:
步骤S10:上位机向控制单元发送开始采集命令;
步骤S20:控制单元接收到上位机发送的开始采集命令后,记录当前时间,向各采集单元发送触发信号,同时开始接收采集单元返回的信号;
步骤S30:采集单元通过触发信号触发开始采集传感器所检测的信号,同时,采集单元向控制单元发送采集到的信号;采集单元采集预定时间或预定数据长度后停止采集,存储采集数据或通过光纤传输至上位机;
步骤S40:上位机接收控制单元和采集单元返回的数据,计算出控制单元分别与各采集单元的时延,对采集单元的采集到的数据进行时间校正,删除同步时间之前的数据,保留采集单元的同步采集数据,并进行显示和存储。
步骤S20中的所述当前时间,其获取方式为通过以晶振构件的时间基准电路获取的时间或通过以太网获取的时间。
所述步骤S40中上位机进行数据同步校正,具体过程包括:
步骤S41:上位机接收控制单元采集的数据,其中,控制单元的采样率为fs;
步骤S42:记录控制单元接收第i个采集单元返回信号的采样点数为Ni,其中,i=1,2……,m;采样率fs、采集时间t和采集点数Ni三者之间的关系为:
t=Ni/fs
第i个采集单元相对于控制单元的时延△ti为:
△ti=Ni/2fs;
步骤S43:求出最大时延△t:
△t=max{△t1,△t2…,△tm};
然后计算第i个采集单元相对于最大时延△t的时间差△t’i:
△t’i=△t-△ti;
第i个采集单元在经过△t’i时刻后实现分布式同步采集;
步骤S44:根据采集单元的采样率fs′删除同步时间之前的数据,显示及存储同步数据。
所述步骤S44中删除同步时间之前的数据的具体过程包括:
计算采集单元△t’i时间段的数据长度L,L=fs′×△t’i,则各采集单元数据减掉延时的数据长度L,即可实现同步采集。
本发明的有益效果为:
上位机通过控制单元对采集单元返回的信号进行延时判断和校正,使得采集单元实现同步采集,实现分布式同步采集,消除了采集单元之间的延时误差,有效提高了分布式装置的同步精度;这种分布式同步装置的同步精度由控制单元的采样率决定,可以根据实际需求进行调整,方便实用。
附图说明
图1为本发明的分布式装置同步结构示意图;
图2为本发明的分布式装置同步流程图。
具体实施方式
如图1所示,本发明的实例提供一种光纤分布式同步采集方法,所述分布式装置包括上位机,控制单元及与控制单元相连接的多个信号采集单元,其中信号采集单元与传感器相连。
如图2所示,本发明的分布式装置同步流程图,本实施例中的分布式装置包含三个采集单元:第一采集单元、第二采集单元和第三采集单元。
一种用于电力电缆的光纤分布式装置的同步方法,其步骤包括:
步骤S10:上位机向控制单元发送开始采集命令;
步骤S20:控制单元接收到上位机发送的开始采集命令后,记录当前时间,向各采集单元发送触发信号,同时开始接收采集单元返回的信号;
步骤S30:采集单元通过触发信号触发开始采集传感器所检测的信号,同时,采集单元向控制单元发送采集到的信号;采集单元采集预定时间或预定数据长度后停止采集,存储采集数据或通过光纤传输至上位机;
步骤S40:上位机接收控制单元和采集单元返回的数据,计算出控制单元分别与各采集单元的时延,对采集单元的采集到的数据进行时间校正,删除同步时间之前的数据,保留采集单元的同步采集数据,并进行显示和存储。
步骤S20中的所述当前时间,其获取方式为通过以晶振构件的时间基准电路获取的时间或通过以太网获取的时间。
所述步骤S40中上位机进行数据同步校正,具体过程包括:
步骤S41:上位机接收控制单元采集的数据,控制单元的采样率fs为10Ms/s;
步骤S42:计算出控制单元接收三个采集单元返回信号的采样点数分别为:200,300,500;则三个采集单元相对于控制单元的时延分别为:△t=N/2fs,即△t分别为10us,15us,25us;
步骤S43:找出三个采集单元相对于控制单元的最大时延△t,即25us,即第一采集单元和第二采集单元分别在15us、10us时刻后,与第三采集单元实现分布式同步采集;
步骤S44:根据采集单元的采样率fs′=1Ms/s,删除同步时间之前的数据,即删除第一采集单元返回数据的前15个采样点,以及删除第二采集单元返回数据的前10个采样点,最后显示及存储同步数据。
Claims (4)
1.一种用于电力电缆的光纤分布式装置的同步方法,所述光纤分布式装置包括上位机、控制单元及与控制单元相连接的若干个信号采集单元,每个采集单元与一个传感器相连;该光纤分布式装置的同步方法,其特征在于,包括:
步骤S10:上位机向控制单元发送开始采集命令;
步骤S20:控制单元接收到上位机发送的开始采集命令后,记录当前时间,向各采集单元发送触发信号,同时开始接收采集单元返回的信号;
步骤S30:采集单元通过触发信号触发开始采集传感器所检测的信号,同时,采集单元向控制单元发送采集到的信号;采集单元采集预定时间或预定数据长度后停止采集,存储采集数据或通过光纤传输至上位机;
步骤S40:上位机接收控制单元和采集单元返回的数据,计算出控制单元分别与各采集单元的时延,对采集单元的采集到的数据进行时间校正,删除同步时间之前的数据,保留采集单元的同步采集数据,并进行显示和存储。
2.如权利要求1所述的一种用于电力电缆的光纤分布式装置的同步方法,其特征在于,步骤S20中的所述当前时间,其获取方式为通过以晶振构件的时间基准电路获取的时间或通过以太网获取的时间。
3.如权利要求1所述的一种用于电力电缆的光纤分布式装置的同步方法,其特征在于,所述步骤S40中上位机进行数据同步校正,具体过程包括:
步骤S41:上位机接收控制单元采集的数据,其中,控制单元的采样率为fs;
步骤S42:记录控制单元接收第i个采集单元返回信号的采样点数为Ni,其中,i=1,2……,m;采样率fs、采集时间t和采集点数Ni三者之间的关系为:
t=Ni/fs
第i个采集单元相对于控制单元的时延△ti为:
△ti=Ni/2fs;
步骤S43:求出最大时延△t:
△t=max{△t1,△t2…,△tm};
然后计算第i个采集单元相对于最大时延△t的时间差△t’i:
△t’i=△t-△ti;
第i个采集单元在经过△t’i时刻后实现分布式同步采集;
步骤S44:根据采集单元的采样率fs′删除同步时间之前的数据,显示及存储同步数据。
4.如权利要求3所述的一种用于电力电缆的光纤分布式装置的同步方法,其特征在于,所述步骤S44中删除同步时间之前的数据的具体过程为:
计算采集单元△t’i时间段的数据长度L,L=fs′×△t’i,各采集单元数据减掉延时的数据长度L实现同步采集。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410836997.4A CN104579532B (zh) | 2014-12-29 | 2014-12-29 | 用于电力电缆的光纤分布式装置的同步方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410836997.4A CN104579532B (zh) | 2014-12-29 | 2014-12-29 | 用于电力电缆的光纤分布式装置的同步方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104579532A true CN104579532A (zh) | 2015-04-29 |
CN104579532B CN104579532B (zh) | 2017-06-20 |
Family
ID=53094846
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410836997.4A Active CN104579532B (zh) | 2014-12-29 | 2014-12-29 | 用于电力电缆的光纤分布式装置的同步方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104579532B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109683068A (zh) * | 2018-12-06 | 2019-04-26 | 国网江苏省电力有限公司扬州供电分公司 | 一种电缆同步局放测试系统 |
CN109818676A (zh) * | 2019-03-12 | 2019-05-28 | 武汉理工大学 | 一种适用于多环境的信号采集设备 |
WO2021093586A1 (zh) * | 2019-11-11 | 2021-05-20 | 北京嘀嘀无限科技发展有限公司 | 一种数据同步系统和方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103279058A (zh) * | 2013-05-04 | 2013-09-04 | 北京航空航天大学 | 一种面向无人机电力巡检用的光纤imu数据采集系统 |
CN103368676A (zh) * | 2012-03-28 | 2013-10-23 | 中国科学院声学研究所 | 一种基于周期性脉冲信号的异地数据同步采集方法及系统 |
CN103488112A (zh) * | 2013-09-29 | 2014-01-01 | 成都天奥测控技术有限公司 | 一种基于时间同步的多通道数据采集仪 |
EP2717509A1 (en) * | 2011-05-31 | 2014-04-09 | Nec Corporation | Synchronization device and synchronization method |
CN104092297A (zh) * | 2014-06-24 | 2014-10-08 | 国家电网公司 | 一种实时监测电网系统运行性能的监测系统及方法 |
-
2014
- 2014-12-29 CN CN201410836997.4A patent/CN104579532B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2717509A1 (en) * | 2011-05-31 | 2014-04-09 | Nec Corporation | Synchronization device and synchronization method |
CN103368676A (zh) * | 2012-03-28 | 2013-10-23 | 中国科学院声学研究所 | 一种基于周期性脉冲信号的异地数据同步采集方法及系统 |
CN103279058A (zh) * | 2013-05-04 | 2013-09-04 | 北京航空航天大学 | 一种面向无人机电力巡检用的光纤imu数据采集系统 |
CN103488112A (zh) * | 2013-09-29 | 2014-01-01 | 成都天奥测控技术有限公司 | 一种基于时间同步的多通道数据采集仪 |
CN104092297A (zh) * | 2014-06-24 | 2014-10-08 | 国家电网公司 | 一种实时监测电网系统运行性能的监测系统及方法 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109683068A (zh) * | 2018-12-06 | 2019-04-26 | 国网江苏省电力有限公司扬州供电分公司 | 一种电缆同步局放测试系统 |
CN109683068B (zh) * | 2018-12-06 | 2021-07-09 | 国网江苏省电力有限公司扬州供电分公司 | 一种电缆同步局放测试系统 |
CN109818676A (zh) * | 2019-03-12 | 2019-05-28 | 武汉理工大学 | 一种适用于多环境的信号采集设备 |
CN109818676B (zh) * | 2019-03-12 | 2021-11-23 | 武汉理工大学 | 一种适用于多环境的信号采集设备 |
WO2021093586A1 (zh) * | 2019-11-11 | 2021-05-20 | 北京嘀嘀无限科技发展有限公司 | 一种数据同步系统和方法 |
US11902378B2 (en) | 2019-11-11 | 2024-02-13 | Beijing Didi Infinity Technology And Development Co., Ltd. | Systems and methods for data synchronization |
Also Published As
Publication number | Publication date |
---|---|
CN104579532B (zh) | 2017-06-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109696172B (zh) | 一种多传感器航迹融合方法、装置及车辆 | |
CN102707300B (zh) | 一种gps轨迹优化方法、装置及系统 | |
WO2020177491A1 (zh) | 微动采集设备、无线遥测系统及数据质量监控方法 | |
CN109819512B (zh) | 工程ct无线分布式多路adc高精度同步系统及方法 | |
CN104579532A (zh) | 用于电力电缆的光纤分布式装置的同步方法 | |
US20170356989A1 (en) | System and method to monitor powerlines | |
CN104112363A (zh) | 多传感数据时空同步方法及道路多传感数据车载采集系统 | |
CN103823105B (zh) | 一种输电线路调试用无线测量系统 | |
CN104569965A (zh) | 一种机动配置双基地雷达的时间、频率同步方法 | |
CN104202534A (zh) | 基于gps和脉冲发生器的多摄像机同步控制装置及方法 | |
CN103809156A (zh) | 区域高分辨率闪电辐射源定位系统 | |
CN106093705A (zh) | 一种配电网单相接地故障行波波头的计算方法 | |
CN107843918B (zh) | 一种具有负延时功能的地震勘探仪及其数据采集方法 | |
CN108551378B (zh) | 一种射频信号远距离传输方法 | |
CN103684729A (zh) | 时钟同步装置及方法 | |
CN103884968A (zh) | 基于gps同步授时的xlpe电缆局部放电定位方法 | |
CN108414994A (zh) | 一种基于广域分布式短波网的电离层参数反演与大范围模型重构方法 | |
CN202141441U (zh) | 基于超声波传感器的自动测雪深装置 | |
CN110865411B (zh) | 地面浅井微地震采集实时监控系统及快速定位事件方法 | |
CN112564883A (zh) | 时间同步设备、方法以及自动驾驶系统 | |
CN111781474A (zh) | 一种时间同步的局部放电双端定位装置及其方法 | |
CN101860348A (zh) | 一种同步守时的自跟踪自补偿方法 | |
CN105527045A (zh) | 煤矿工作面支架压力数据分段拟合方法及装置 | |
CN106199665A (zh) | 一种基于北斗卫星的分布式电磁法仪器同步系统及方法 | |
CN207488476U (zh) | 行波测距校验装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |