CN104572834A - Method and device for constructing process meta-model - Google Patents

Method and device for constructing process meta-model Download PDF

Info

Publication number
CN104572834A
CN104572834A CN201410758168.9A CN201410758168A CN104572834A CN 104572834 A CN104572834 A CN 104572834A CN 201410758168 A CN201410758168 A CN 201410758168A CN 104572834 A CN104572834 A CN 104572834A
Authority
CN
China
Prior art keywords
task
model
project
meta
activity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410758168.9A
Other languages
Chinese (zh)
Other versions
CN104572834B (en
Inventor
陈争
冯永华
杜健
王晓东
聂双双
宋红
焦京海
丁叁叁
梁建英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Qingdao Sifang Co Ltd
Original Assignee
CSR Qingdao Sifang Locomotive and Rolling Stock Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CSR Qingdao Sifang Locomotive and Rolling Stock Co Ltd filed Critical CSR Qingdao Sifang Locomotive and Rolling Stock Co Ltd
Priority to CN201410758168.9A priority Critical patent/CN104572834B/en
Publication of CN104572834A publication Critical patent/CN104572834A/en
Application granted granted Critical
Publication of CN104572834B publication Critical patent/CN104572834B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/28Databases characterised by their database models, e.g. relational or object models
    • G06F16/284Relational databases
    • G06F16/288Entity relationship models

Landscapes

  • Engineering & Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • Theoretical Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention provides a method and a device for constructing a process meta-model. The method comprises the following steps: obtaining process meta-information of a vehicle, wherein the process meta-information comprises an item set, a task set and an activity set, the item set comprises at least one item, the task set comprises at least one task, and the activity set comprises at least one activity; obtaining structure tree data of the vehicle from a structure tree database, wherein the structure tree data of the vehicle comprises component parts of the vehicle as well as a hierarchical relationship among the component parts; constructing at least one process meta-model through the process meta-information and the structure tree data, wherein the process meta-model is used for representing a mapping relationship among at least one item, at least one task and at least one activity; storing the at least one process-meta model into the process-meta model database. Therefore, while performing subsequent vehicle development, the method can be used for obtaining an actual developing process of the vehicle based on the process-meta model, and is beneficial to improving the developing efficiency.

Description

A kind of Process Meta-Model construction method and device
Technical field
The present invention relates to communication technical field, be specifically related to a kind of Process Meta-Model construction method and device.
Background technology
In existing bullet train performance history, after Vehicle manufacturers receives order, need artificially the technical indicator of order to be decomposed each component module, e.g., carrying component, traveling component, power component, etc.After decomposition like this, then by the designer of research and development department corresponding to each component, according to the design experiences of self, develop the vehicle meeting and decompose the requirement of the technical indicator of this component.
Existing bullet train performance history, when there being new development task, Vehicle manufacturers all can re-start the exploitation of new model, and development efficiency is low, wastes the resources such as a large amount of human and material resources, financial resources.
Summary of the invention
The Process Meta-Model construction method of the embodiment of the present invention and device, by building the Process Meta-Model of vehicle development, contribute to the development efficiency improving new model, saving is exploited natural resources.
For this reason, the embodiment of the present invention provides following technical scheme:
A kind of Process Meta-Model construction method, described method comprises:
Obtain the process metamessage of vehicle, described process metamessage comprises project set, set of tasks and active set, and described project set comprises at least one project, and described set of tasks comprises at least one task, and described active set comprises at least one activity;
From structure tree database, obtain the structure tree data of described vehicle, the structure tree data of described vehicle comprise the hierarchical relationship between the building block of described vehicle and each building block;
Utilize described process metamessage and described structure tree data, build at least one Process Meta-Model, described Process Meta-Model is for representing a project, mapping relations between at least one task and at least one activity;
At least one Process Meta-Model described is stored to Process Meta-Model database.
Alternatively, described project comprises following information: the technical indicator that what the relation between the task identification of at least one task described that project label, item description information, project calendar, project are corresponding, at least one task described, project were corresponding exploits natural resources, project is corresponding.
Alternatively, described task comprises following information: activity mark, the input information of task, the output information of task of at least one activity described that what development teams corresponding to task identification, task description information, task calendar, task, task were corresponding exploits natural resources, task status, task are corresponding.
Alternatively, described activity comprises following information: movable mark, Activity Description information, calendar of events, movable corresponding execution team, movable beginning condition, movable termination condition, movable input information, movable output information.
Alternatively, describedly utilize described process metamessage and described structure tree data, build at least one Process Meta-Model, comprising:
Set up each project in described process metamessage, task and activity, and the incidence relation between the building block in described structure tree data;
From the building block described structure tree data, extract a current building block, and search the project of described current building block association, task and activity, generate the Process Meta-Model that described current building block is corresponding.
Alternatively, described method also comprises:
Assignment operation is carried out to described Process Meta-Model, generative process meta-model example;
Described Process Meta-Model example is stored to Process Meta-Model instance database.
A kind of Process Meta-Model construction device, described device comprises:
Process metamessage acquiring unit, for obtaining the process metamessage of vehicle, described process metamessage comprises project set, set of tasks and active set, and described project set comprises at least one project, described set of tasks comprises at least one task, and described active set comprises at least one activity;
Structure tree data capture unit, for obtaining the structure tree data of described vehicle from structure tree database, the structure tree data of described vehicle comprise the hierarchical relationship between the building block of described vehicle and each building block;
Process Meta-Model construction unit, for utilizing described process metamessage and described structure tree data, builds at least one Process Meta-Model, and described Process Meta-Model is for representing a project, mapping relations between at least one task and at least one activity;
Process Meta-Model storage unit, for being stored to Process Meta-Model database by least one Process Meta-Model described.
Alternatively, described project comprises following information: the technical indicator that what the relation between the task identification of at least one task described that project label, item description information, project calendar, project are corresponding, at least one task described, project were corresponding exploits natural resources, project is corresponding;
Described task comprises following information: activity mark, the input information of task, the output information of task of at least one activity described that what development teams corresponding to task identification, task description information, task calendar, task, task were corresponding exploits natural resources, task status, task are corresponding;
Described activity comprises following information: movable mark, Activity Description information, calendar of events, movable corresponding execution team, movable beginning condition, movable termination condition, movable input information, movable output information.
Alternatively, described Process Meta-Model construction unit comprises:
Set up unit, for setting up each project in described process metamessage, task and activity, and the incidence relation between the building block in described structure tree data;
Generation unit, for extracting a current building block from the building block in described structure tree data, and searching the project of described current building block association, task and activity, generating the Process Meta-Model that described current building block is corresponding.
Alternatively, described device also comprises:
Assignment operating unit, for carrying out assignment operation to described Process Meta-Model, generative process meta-model example;
Process Meta-Model instance storage element, for being stored to Process Meta-Model instance database by described Process Meta-Model example.
The Process Meta-Model construction method of the embodiment of the present invention and device, utilize process metamessage and structure tree data, building process meta-model, so, follow-up carry out bullet train exploitation time, just can Kernel-based methods meta-model, obtain the actual development process of vehicle.Thus optimize the performance history of train, avoid duplicating exploitation phenomenon in train performance history, contribute to improving development efficiency, effectively save the resource such as human and material resources and financial resources.
Accompanying drawing explanation
In order to be illustrated more clearly in the technical scheme in the embodiment of the present application, below the accompanying drawing used required in describing embodiment is briefly described, apparently, the accompanying drawing that the following describes is only some embodiments recorded in the application, for those of ordinary skill in the art, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the process flow diagram of embodiment of the present invention Process Meta-Model construction method;
Fig. 2 is process metamessage in the embodiment of the present invention, graph of a relation between Process Meta-Model and Process Meta-Model example;
Fig. 3 is the schematic diagram of embodiment of the present invention Process Meta-Model construction device.
Embodiment
In order to make those skilled in the art person understand the present invention program better, below in conjunction with drawings and embodiments, the embodiment of the present invention is described in further detail.
See Fig. 1, show the process flow diagram of embodiment of the present invention Process Meta-Model construction method, can comprise:
101, obtain the process metamessage of vehicle, described process metamessage comprises project set, set of tasks and active set, and described project set comprises at least one project, described set of tasks comprises at least one task, and described active set comprises at least one activity.
102, from structure tree database, obtain the structure tree data of described vehicle, the structure tree data of described vehicle comprise the hierarchical relationship between the building block of described vehicle and each building block.
103, utilize described process metamessage and described structure tree data, build at least one Process Meta-Model, described Process Meta-Model is for representing a project, mapping relations between at least one task and at least one activity.
104, at least one Process Meta-Model described is stored to Process Meta-Model database.
When prior art carries out bullet train exploitation, do not carry out standardization constraint to performance history, there is task duplication exploitation phenomenon, development process is complicated, not easy.The embodiment of the present invention by the Work flow model of abstract train performance history, building process meta-model, so as follow-up carry out bullet train exploitation time, can Kernel-based methods meta-model, obtain the actual development process of vehicle.So, just can optimize train performance history, avoid in train performance history, overlapping development phenomenon, contribute to improving development efficiency, effectively save the resource such as human and material resources and financial resources.
The embodiment of the present invention, when building process meta-model, relates to following two aspect data:
(1) process metamessage
It should be noted that, the process metamessage in the embodiment of the present invention refers to the information related in vehicle development process, particularly, at least can comprise project set, set of tasks and active set.
In the embodiment of the present invention, vehicle development process is defined by project, and project comprises a series of task, and task is realized by the activity with certain logical relation.That is, in vehicle development process, project, task and activity are the staples of formation process, and vehicle development process abstractly can be divided into three levels: item layer, task layer, mobile layer.
In the embodiment of the present invention, and project (English: Project) to describe by seven tuples, particularly, Project=(PID, D, Cal, T, RT, R, M).Wherein, PID represents project label; D represents the descriptor of project, and descriptor can be project objective, item source etc.; Cal represents project calendar; T represents the task identification of at least one task that project is corresponding, namely the set of tasks after Project decomposition, T=(T1 can be expressed as, T2, Tn), generally, project can comprise several large tasks such as product demand, conceptual design, technical design, job design, scheduling and planning; RT represents the relation between at least one task that project is corresponding, can be expressed as RT=(rt1, rt2 ... rtn), the relation between task can for starting-starting, start-terminate, terminate-start, terminate-terminate; R represents corresponding the exploiting natural resources of project; M represents the technical indicator that project is corresponding.
In the embodiment of the present invention, (English: Task) to refer to that having of completing needed for project each stage one sets the goal, semantic complete and relatively independent behavior, task is basic composition and the operating unit of project to task.For example, task can be overall design task, General layout Plan evaluation etc.In the embodiment of the present invention, task describes by nine tuples, particularly, and Task=(TID, D, IPT, R, Cal, S, I, O, A).Wherein, TID represents task identification; D represents the descriptor of task; IPT represents the development teams that task is corresponding; R represents corresponding the exploiting natural resources of task; Cal represents task calendar; S represents task status, task status can for ready, perform, hang up, complete etc.; I represents the input information of task, input information can for task object (as required time of finishing the work, finish the work needed for the target that reaches etc.), resource, input parameter etc.; O represents task output information, and output information can be the output parameter of task operating result; A represents the activity mark of at least one activity that task is corresponding.
In the embodiment of the present invention, movable (English: Activity) to refer to the abstractdesription to an execution step in process.Activity describes by eight tuples, particularly, and Activity=(AID, D, Cal, Person, SC, EC, IND, OUD).Wherein, AID expression activity mark; D represents Activity Description information; Cal represents calendar of events; The execution team that Person expression activity is corresponding; SC expression activity beginning condition; EC represents activity end condition; IND expression activity input information; OUD expression activity output information.
As a kind of example, by the mode of typing, receive the process metamessage of outside designer's typing, specifically can be divided into project typing, task typing, activity typing.
(2) structure tree data
In the embodiment of the present invention, vehicle structure tree refers to the structure dendrogram describing the physical composition parts of a certain vehicle and the level of each building block.Vehicle structure tree data mainly comprise following two class data: a class is hierarchical data, expression be the hierarchical information of each building block in vehicle structure tree; One class is topological data, expression be mutual relationship in vehicle structure tree between the information of each building block and each building block.
In the embodiment of the present invention, vehicle structure tree data at least can comprise: at least one in level title, father node title, child node title, structure description information.
Vehicle structure tree data are kept in structure tree database, when needed, can read relevant vehicle structure tree data from structure tree database.
So, after procurement process metamessage and structure tree data, just can utilize the two building process meta-model, and be stored in Process Meta-Model database, to use in follow-up vehicle development process.In the embodiment of the present invention, Process Meta-Model can be understood as, be the Work flow model in order to define pedigree bullet train performance history and the abstract model defined, for describe comprise in performance history process content, annexation between process, implementation constrained input, etc.Introduced from above-mentioned, the mode of embodiment of the present invention building process meta-model is: utilize and represent each abstract process unit in pedigree bullet train performance history, connected, obtain the specific R&D process needed for train exploitation, i.e. Process Meta-Model by combination.
For example, Process Meta-Model can be expressed as Process={<Project>LEssT.LTssT .LTTasks><ActivitysGreatT.Gre aT.GT}, as a kind of example, Process Meta-Model can embody as follows:
Process1=<P1,{T1{A1,…,A4},…,T9{A1,…,A6}}>
Project P1
PID: overall design
Describe: XXXX
Calendar: { XX days on working day }
Set of tasks: T1 designs input, T2 technical indicator, T3 train marshalling list placement scheme, and T4 draws calculating,
T5 brake calculation, T6 meta-model assignment, T7 configures design, T8 Variant Design, and T9 design objective issues } and task nexus: terminate-start
Resource: design resource, human resources, computer software and hardware resource,
Technical indicator: design rate, axle weight, gauge,
Task T1
……
Task T3
TID: train marshalling list placement scheme
Describe: XXXX
Development teams: XXXX
Resource: design resource, computing machine
Calendar: { XX days on working day }
Task status: perform
Input: train demand marshalling quantity, staffing etc.
Export: train marshalling list pattern, flat section layout etc.
Active set: A3 Section Design, arranges under A4 car for A1 power configuration, layout in A2 car ... movable A1
AID: power configuration
Describe: the dynamic of train drags than design
Perform team: { XXX, XXX, XXX, XXX, technique center }
Calendar: { XX days on working day }
Beginning condition: technical indicator maps
Termination condition: move and drag than determining
Input information: train marshalling list quantity
Output information: move and drag ratio, vehicle marshalling pattern
……
Movable Ak:
……
Task Tn:
……
In the embodiment of the present invention, utilize process metamessage and structure tree data, building process meta-model, can comprise: set up each project in described process metamessage, task and activity, and the incidence relation between the building block in described structure tree data; From the building block described structure tree data, extract a current building block, and search the project of described current building block association, task and activity, generate the Process Meta-Model that described current building block is corresponding.
Based on structure tree data, first each project in process metamessage, each task, each activity are corresponded on a building block of structure tree, or can be understood as and correspond on a node of structure tree.And then a current building block is extracted from structure tree, and search all correspond to this current building block project, task, activity, mapping relations between the project that foundation finds, task, movable three, obtain the Process Meta-Model that current building block is corresponding.Process like this, utilizes each building block in structure tree, attempts structure Process Meta-Model, if there is the project corresponding with building block, task and activity, then builds a Process Meta-Model; If there is no corresponding with building block project, task and activity, then illustrate the Process Meta-Model do not existed corresponding to this building block.
From the scheme of above-mentioned building process meta-model, a Process Meta-Model is corresponding to a node on structure tree, and the multiple Process Meta-Models so constructed also can be similar to structure tree, is rendered as the tree structure of layering.
Alternatively, in order to obtain the actual development process of vehicle, the embodiment of the present invention also can carry out assignment operation to Process Meta-Model, and namely generative process meta-model example also obtains the actual development process of train, and be stored in Process Meta-Model database.Particularly, process metamessage, relation between Process Meta-Model and Process Meta-Model example, can schematic diagram shown in Figure 2.
Corresponding to embodiment of the method shown in Fig. 1, the embodiment of the present invention additionally provides a kind of Process Meta-Model construction device, and see Fig. 3, described device comprises:
Process metamessage acquiring unit 201, for obtaining the process metamessage of vehicle, described process metamessage comprises project set, set of tasks and active set, described project set comprises at least one project, described set of tasks comprises at least one task, and described active set comprises at least one activity;
Structure tree data capture unit 202, for obtaining the structure tree data of described vehicle from structure tree database, the structure tree data of described vehicle comprise the hierarchical relationship between the building block of described vehicle and each building block;
Process Meta-Model construction unit 203, for utilizing described process metamessage and described structure tree data, builds at least one Process Meta-Model, and described Process Meta-Model is for representing a project, mapping relations between at least one task and at least one activity;
Process Meta-Model storage unit 204, for being stored to Process Meta-Model database by least one Process Meta-Model described.
Alternatively, described project comprises following information: the technical indicator that what the relation between the task identification of at least one task described that project label, item description information, project calendar, project are corresponding, at least one task described, project were corresponding exploits natural resources, project is corresponding;
Described task comprises following information: activity mark, the input information of task, the output information of task of at least one activity described that what development teams corresponding to task identification, task description information, task calendar, task, task were corresponding exploits natural resources, task status, task are corresponding;
Described activity comprises following information: movable mark, Activity Description information, calendar of events, movable corresponding execution team, movable beginning condition, movable termination condition, movable input information, movable output information.
Alternatively, described Process Meta-Model construction unit comprises:
Set up unit, for setting up each project in described process metamessage, task and activity, and the incidence relation between the building block in described structure tree data;
Generation unit, for extracting a current building block from the building block in described structure tree data, and searching the project of described current building block association, task and activity, generating the Process Meta-Model that described current building block is corresponding.
Alternatively, described device also comprises:
Assignment operating unit, for carrying out assignment operation to described Process Meta-Model, generative process meta-model example;
Process Meta-Model instance storage element, for being stored to Process Meta-Model instance database by described Process Meta-Model example.
It should be noted that, each embodiment in this instructions all adopts the mode of going forward one by one to describe, between each embodiment identical similar part mutually see, what each embodiment stressed is the difference with other embodiments.Especially, for device embodiment, because it is substantially similar to embodiment of the method, so describe fairly simple, relevant part illustrates see the part of embodiment of the method.Device embodiment described above is only schematic, the unit wherein illustrated as separating component or can may not be and physically separates, parts as unit display can be or may not be physical location, namely can be positioned at a place, or also can be distributed in multiple network element.Some or all of module wherein can be selected according to the actual needs to realize the object of the present embodiment scheme.Those of ordinary skill in the art, when not paying creative work, are namely appreciated that and implement.
The above is only Alternate embodiments of the present invention, is not intended to limit protection scope of the present invention.It should be pointed out that for those skilled in the art, under the premise without departing from the principles of the invention, can also make some improvements and modifications, these improvements and modifications also should be considered as protection scope of the present invention.

Claims (10)

1. a Process Meta-Model construction method, is characterized in that, described method comprises:
Obtain the process metamessage of vehicle, described process metamessage comprises project set, set of tasks and active set, and described project set comprises at least one project, and described set of tasks comprises at least one task, and described active set comprises at least one activity;
From structure tree database, obtain the structure tree data of described vehicle, the structure tree data of described vehicle comprise the hierarchical relationship between the building block of described vehicle and each building block;
Utilize described process metamessage and described structure tree data, build at least one Process Meta-Model, described Process Meta-Model is for representing a project, mapping relations between at least one task and at least one activity;
At least one Process Meta-Model described is stored to Process Meta-Model database.
2. method according to claim 1, it is characterized in that, described project comprises following information: the technical indicator that what the relation between the task identification of at least one task described that project label, item description information, project calendar, project are corresponding, at least one task described, project were corresponding exploits natural resources, project is corresponding.
3. method according to claim 1 and 2, it is characterized in that, described task comprises following information: activity mark, the input information of task, the output information of task of at least one activity described that what development teams corresponding to task identification, task description information, task calendar, task, task were corresponding exploits natural resources, task status, task are corresponding.
4. the method according to any one of claims 1 to 3, it is characterized in that, described activity comprises following information: movable mark, Activity Description information, calendar of events, movable corresponding execution team, movable beginning condition, movable termination condition, movable input information, movable output information.
5. the method according to any one of Claims 1-4, is characterized in that, describedly utilizes described process metamessage and described structure tree data, builds at least one Process Meta-Model, comprising:
Set up each project in described process metamessage, task and activity, and the incidence relation between the building block in described structure tree data;
From the building block described structure tree data, extract a current building block, and search the project of described current building block association, task and activity, generate the Process Meta-Model that described current building block is corresponding.
6. the method according to any one of claim 1 to 5, is characterized in that, described method also comprises:
Assignment operation is carried out to described Process Meta-Model, generative process meta-model example;
Described Process Meta-Model example is stored to Process Meta-Model instance database.
7. a Process Meta-Model construction device, is characterized in that, described device comprises:
Process metamessage acquiring unit, for obtaining the process metamessage of vehicle, described process metamessage comprises project set, set of tasks and active set, and described project set comprises at least one project, described set of tasks comprises at least one task, and described active set comprises at least one activity;
Structure tree data capture unit, for obtaining the structure tree data of described vehicle from structure tree database, the structure tree data of described vehicle comprise the hierarchical relationship between the building block of described vehicle and each building block;
Process Meta-Model construction unit, for utilizing described process metamessage and described structure tree data, builds at least one Process Meta-Model, and described Process Meta-Model is for representing a project, mapping relations between at least one task and at least one activity;
Process Meta-Model storage unit, for being stored to Process Meta-Model database by least one Process Meta-Model described.
8. device according to claim 7, is characterized in that,
Described project comprises following information: the technical indicator that what the relation between the task identification of at least one task described that project label, item description information, project calendar, project are corresponding, at least one task described, project were corresponding exploits natural resources, project is corresponding;
Described task comprises following information: activity mark, the input information of task, the output information of task of at least one activity described that what development teams corresponding to task identification, task description information, task calendar, task, task were corresponding exploits natural resources, task status, task are corresponding;
Described activity comprises following information: movable mark, Activity Description information, calendar of events, movable corresponding execution team, movable beginning condition, movable termination condition, movable input information, movable output information.
9. the device according to claim 7 or 8, is characterized in that, described Process Meta-Model construction unit comprises:
Set up unit, for setting up each project in described process metamessage, task and activity, and the incidence relation between the building block in described structure tree data;
Generation unit, for extracting a current building block from the building block in described structure tree data, and searching the project of described current building block association, task and activity, generating the Process Meta-Model that described current building block is corresponding.
10. the device according to any one of claim 7 to 9, is characterized in that, described device also comprises:
Assignment operating unit, for carrying out assignment operation to described Process Meta-Model, generative process meta-model example;
Process Meta-Model instance storage element, for being stored to Process Meta-Model instance database by described Process Meta-Model example.
CN201410758168.9A 2014-12-10 2014-12-10 A kind of Process Meta-Model construction method and device Active CN104572834B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410758168.9A CN104572834B (en) 2014-12-10 2014-12-10 A kind of Process Meta-Model construction method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410758168.9A CN104572834B (en) 2014-12-10 2014-12-10 A kind of Process Meta-Model construction method and device

Publications (2)

Publication Number Publication Date
CN104572834A true CN104572834A (en) 2015-04-29
CN104572834B CN104572834B (en) 2019-06-21

Family

ID=53088896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410758168.9A Active CN104572834B (en) 2014-12-10 2014-12-10 A kind of Process Meta-Model construction method and device

Country Status (1)

Country Link
CN (1) CN104572834B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105224712A (en) * 2015-06-29 2016-01-06 南车青岛四方机车车辆股份有限公司 A kind of disposal route of bullet train product meta-model and device
CN105589992A (en) * 2015-12-11 2016-05-18 南车青岛四方机车车辆股份有限公司 Process control method and device for rapid design of high speed train

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1766835A (en) * 2004-10-01 2006-05-03 微软公司 A framework for seamlessly authoring and editing workflows at design and runtime
JP2006252255A (en) * 2005-03-11 2006-09-21 Dainippon Printing Co Ltd Database system, database retrieval server, program and recording medium
CN101038604A (en) * 2007-04-26 2007-09-19 上海交通大学 Vehicle impact strength computer synergic design and simulation system
CN101246509A (en) * 2008-02-28 2008-08-20 上海交通大学 Entire car personalized configuration system based on case illation technology
CN101794315A (en) * 2010-03-31 2010-08-04 袁梅宇 Object relationship mapping model with fixed database schema
CN103150450A (en) * 2013-03-26 2013-06-12 北京经纬恒润科技有限公司 Method for establishing dynamics real-time model of rail transit vehicle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1766835A (en) * 2004-10-01 2006-05-03 微软公司 A framework for seamlessly authoring and editing workflows at design and runtime
JP2006252255A (en) * 2005-03-11 2006-09-21 Dainippon Printing Co Ltd Database system, database retrieval server, program and recording medium
CN101038604A (en) * 2007-04-26 2007-09-19 上海交通大学 Vehicle impact strength computer synergic design and simulation system
CN101246509A (en) * 2008-02-28 2008-08-20 上海交通大学 Entire car personalized configuration system based on case illation technology
CN101794315A (en) * 2010-03-31 2010-08-04 袁梅宇 Object relationship mapping model with fixed database schema
CN103150450A (en) * 2013-03-26 2013-06-12 北京经纬恒润科技有限公司 Method for establishing dynamics real-time model of rail transit vehicle

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105224712A (en) * 2015-06-29 2016-01-06 南车青岛四方机车车辆股份有限公司 A kind of disposal route of bullet train product meta-model and device
CN105589992A (en) * 2015-12-11 2016-05-18 南车青岛四方机车车辆股份有限公司 Process control method and device for rapid design of high speed train

Also Published As

Publication number Publication date
CN104572834B (en) 2019-06-21

Similar Documents

Publication Publication Date Title
CN102810057B (en) A kind of method of log
US20200090085A1 (en) Digital twin graph
CN107766402A (en) A kind of building dictionary cloud source of houses big data platform
Lodhi et al. An extension of bpmn meta-model for evaluation of business processes
CN105243528A (en) Financial IT system graphical centralized reconciliation system and method under big data environment
CN104572833B (en) A kind of mapping ruler creation method and device
JP2012510687A5 (en)
CN107016501A (en) A kind of efficient industrial big data multidimensional analysis method
CN103338135A (en) Real-time monitoring method of cluster storage capacity
DE102020108374A1 (en) METHOD AND DEVICE FOR THE MULTIPLE RUN-TIME PLANNING OF SOFTWARE EXECUTED IN A HETEROGENIC SYSTEM
CN113721892A (en) Domain modeling method, domain modeling device, computer equipment and storage medium
CN105719126A (en) System and method for internet big data task scheduling based on life cycle model
CN104820733A (en) A high-speed train requirement meta model establishing method and device
CN103714133A (en) Data operation and maintenance management method and device
CN101901265A (en) Objectification management system of virtual test data
CN103744647A (en) Java workflow development system and method based on workflow GPD
CN103235811A (en) Data storage method and device
Gröger et al. Supporting manufacturing design by analytics, continuous collaborative process improvement enabled by the advanced manufacturing analytics platform
CN103164774A (en) Automobile complete vehicle development system based on workflow
CN104572832A (en) Requirement meta model construction method and device
CN104572834A (en) Method and device for constructing process meta-model
CN105320508A (en) System for obtaining service integration workflow engine
CN104572835B (en) A kind of Process Meta-Model construction method and device
EP2343658A1 (en) Federation as a process
CN101968747B (en) Cluster application management system and application management method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: Chengyang District of Shandong city of Qingdao province Jinhong road 266111 No. 88

Applicant after: CRRC QINGDAO SIFANG CO., LTD.

Address before: Chengyang District of Shandong city of Qingdao province Jinhong road 266111 No. 88

Applicant before: CSR Qingdao Sifang Locomotive and Rolling Stock Co., Ltd.

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant