CN104534491A - Ultralow-dust rear smoke channel system of boiler - Google Patents

Ultralow-dust rear smoke channel system of boiler Download PDF

Info

Publication number
CN104534491A
CN104534491A CN201510001578.3A CN201510001578A CN104534491A CN 104534491 A CN104534491 A CN 104534491A CN 201510001578 A CN201510001578 A CN 201510001578A CN 104534491 A CN104534491 A CN 104534491A
Authority
CN
China
Prior art keywords
dust
boiler
flue gas
heat recovery
waste heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510001578.3A
Other languages
Chinese (zh)
Inventor
孙奉仲
张一坤
史月涛
魏伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201510001578.3A priority Critical patent/CN104534491A/en
Publication of CN104534491A publication Critical patent/CN104534491A/en
Pending legal-status Critical Current

Links

Landscapes

  • Chimneys And Flues (AREA)
  • Air Supply (AREA)

Abstract

The invention relates to an ultralow-dust rear smoke channel system of a boiler. The ultralow-dust rear smoke channel system comprises an economizer, a denitration system and an air pre-heater. A high-temperature dust removal system is arranged in back of the economizer and in front of the denitration system, the denitration system is communicated with a desulfurization system through the air pre-heater, a smoke waste heat recovery system and a draught fan, the air pre-heater, the smoke waste heat recovery system and the draught fan are sequentially connected, and the desulfurization system is connected with a chimney. The equipment size of the denitration system, the air pre-heater, the smoke waste heat recovery system and the desulfurization system can be reduced, and original measures for preventing abrasion, corrosion, dust deposition and dust clogging can be omitted, so that the cost is lowered, the structure is simplified, and space is saved.

Description

A kind of boiler ultra low-ash back-end ductwork system
Technical field
The present invention relates to a kind of boiler flue system, particularly a kind of can boiler economizer outlet dust contained flue gas concentration significantly reduce, make whole back-end ductwork all be in the boiler flue system of almost ashless duty, belong to thermal power generation field.
Background technology
Current boiler back end ductwork system, in the flue after flue gas dust collecting system is generally arranged on air preheater, before desulfurizer.During due to boiler combustion, especially during coal-fired boiler combustion, can produce a large amount of ashes, the equipment worked under high dust flue gas environment is all subject to the impact of ash.
When ash-laden gas flows through denitrating system, the elements such as Na, K, Si, As of containing in flying dust can make catalyst contamination or poisoning, and contain the flue gas wearing and tearing reactor of dust particale and make cellular catalyst blockage, reduce denitration efficiency, increase operating cost.Also scholar is had to make improvement to denitrating system; cleaner is increased to remove the bulky grain dust entering denitrating system at the intake section of denitrating system; but this cleaner is only to remove the bulky grain dust entering denitrating system; for denitrating system service; its dust removing effects does not reach the emission request of country far away, and the further cleaner in flue is still indispensable.And the flue after denitration device has still been in dust state, these equipment have still been operated in the environment of ash.
Air preheater and flue gas waste heat recovery system are subject to the wearing and tearing of ash, the impact of dust stratification, heat transfer coefficient are declined, reliability decrease; The heat exchange corrugated plating of air preheater, owing to will consider the effect of dust stratification, so wave pitch is comparatively large, result also in the reduction of the coefficient of heat transfer.Gas cooler after being positioned at air preheater, more can be subject to the impact may blocking up ash, cause heat exchange property to decline fast, flow resistance sharply raises.
Figure 1 shows that the existing boiler flue system before transformation, the ash-laden gas produced that burns in boiler furnace (not shown) enters economizer, denitrating system, air preheater, flue gas waste heat recovery system, electrostatic precipitator, air-introduced machine and desulphurization system successively under the effect of flue entrance at air-introduced machine, eventually passes through chimney and discharges.Denitrating system adopts selective catalytic reduction, i.e. SCR method.When temperature about 300 DEG C, catalyst is in greater activity, therefore the denitration efficiency of 90% can be reached, but the elements such as Na, K, Si, As of containing in flying dust, cause catalyst contamination or poisoning, reduce catalyst life, and contain the flue gas wearing and tearing reactor of dust particale and make cellular catalyst blockage, therefore the denitration efficiency of 90% will be kept then to need higher investment and operating cost.Air preheater runs in high concentration flying dust environment, and this brings the problem of two aspects.On the one hand, there is more serious wear problem in air preheater.Through measuring, in rated load operation situation, the average flying dust concentration of air preheater position reaches 18.6g/kg.Because flying dust concentration is higher, cigarette speed is fast, air preheater serious wear, and therefore need to adopt rigidity is high, abrasion resistance properties is good steel as heat exchange tube material during design, the manufacturing cost of air preheater is very high.On the other hand, because the dust particale in flue gas is attached on heat exchange surface, cause heat exchanger heat exchange thermal resistance to increase, make exhaust gas temperature higher.In the actual moving process of this comparative example, time at full capacity, exhaust gas temperature is 150 DEG C, higher than design load 130 DEG C.And exhaust gas temperature often raises 10 DEG C, boiler efficiency reduces by 0.5%.Flue gas waste heat recovery system is arranged between air preheater and electrostatic precipitation, and flue gas heat recovery system comprises inlet header 61, outlet header 62 and heat-exchanging tube bundle 63, and heat-exchanging tube bundle is spiral fin coil.Because the flue gas heat recovery system works in this comparative example is in the flue gas environment of high ash concentration, be very easy to dust stratification between the fin of heat-exchanging tube bundle and cause flue blockage, flue gas waste heat recovery system heat exchange efficiency is caused to decline on the one hand, bring very large resistance on the other hand whole flue running environment, air-introduced machine is caused to exert oneself increase, therefore be generally not less than 10mm according to spiral fin coil when the spacing of fin of heat-exchanging tube bundle designs in dusty circumstances, H type finned tube is not less than 17mm and designs.In the prior art, spacing of fin is designed to 10mm.In rated power operation situation, the cigarette temperature of entering of flue gas waste heat recovery system is 135 DEG C, and exhaust gas temperature is 110 DEG C, and now the inflow temperature of flue gas waste heat recovery system is 80 DEG C, and flow is 65t/h, and leaving water temperature is 95-105 DEG C.Electrostatic precipitator is arranged in the port of export of air preheater, and design efficiency of dust collection is 99.4%, and house outlet dust content is 200mg/m 3.This electrostatic precipitator initial cost and operating cost higher, by boiler load variable effect in running, can not absolute guarantee's efficiency of dust collection, the discharge standard that country is stricter from now on cannot be tackled.Flue gas after dedusting is discharged boiler exhaust gas system through air-introduced machine, desulfurizer and chimney and is entered air.
Therefore, the reliability and the economy that are arranged at the various equipment of boiler back end ductwork are all subject to the impact of flue gas containing ash concentration, cause performance degradation.The normal operation of boiler can also be affected time serious.
Summary of the invention
The object of the invention is to the deficiency overcoming above-mentioned existing equipment technology, and a kind of boiler ultra low-ash back-end ductwork system is provided, bring the guarantee of environment can to the reliably working of equipment and efficient work, substantially be in ashless environment, thus the reliability in boiler and even whole power plant can be improved.
The technical scheme that the present invention takes is:
A kind of boiler ultra low-ash back-end ductwork system, comprise economizer, denitrating system, air preheater, high-temperature dust removal system is provided with before denitrating system after economizer, denitrating system is communicated with desulphurization system by the air preheater that connects successively, flue gas waste heat recovery system, air-introduced machine, and desulphurization system is connected with chimney.
The dust content of the back-end ductwork after hot precipitator is all in reduced levels, and equipment all thereafter is all in clean environment.
Described high-temperature dust removal system adopts hot electrostatic precipitator.
Described high-temperature dust removal system adopts high-temperature ceramic materials deduster.
The pattern that described high-temperature dust removal system adopts high-temperature ceramic materials deduster and hot electrostatic precipitator to combine, hot electrostatic precipitator is elementary dedusting, and Ceramic dust collector is degree of depth dedusting.
Described flue gas heat recovery system, the finned tube of employing is spiral fin coil or H type finned tube, and heat exchanger tube spacing of fin reduces, and is generally 3-5mm, makes the coefficient of heat transfer higher.
Described spacing of fin is preferably 4mm.
The present invention changes the subversiveness of traditional boiler back end ductwork system, dust pelletizing system by traditional be positioned at air preheater after, before moving forward to denitrating system, define the low cloud of dust compression ring border of whole boiler back end ductwork, for boiler improvement, denitrating catalyst serviceability temperature can be made to broaden, and efficiency is higher, avoids catalyst poisoning; Improve the coefficient of heat transfer of air preheater and flue gas waste heat recovery system, reduce the spacing of air preheater heat exchange corrugated plating, keep from heat area ash, wearing and tearing, corrosion, can deeply reducing exhausted smoke temperature, improves the energy recovery rate of flue gas waste heat recovery system; Alleviate the wearing and tearing of air-introduced machine, reduce the power consumption of air-introduced machine; Improve the efficiency of wet desulfurization system, ensure that the recovery quality of gypsum.Therefore the present invention can improve economy and the reliability of power plant boiler, improves the efficiency of environmental protection equipment, reduces the maintenance workload of boiler tail equipment.
The present invention overcomes the deficiencies in the prior art completely, and just up hill and dale dust is reduced to the numerical value of national standard requirement in the high-temperature dust removal stage, back-end ductwork is in almost completely clean state.The present invention can reduce the equipment volume of denitrating system, air preheater, flue gas waste heat recovery system, desulphurization system etc., can the original measure removal for preventing and treating wearing and tearing, burn into dust stratification, stifled ash, reduce cost, simplify the structure, decrease space.
In addition, structure provided by the invention also provides possibility for improving flue other system further.Based on this structure, the denitrating system under clean environment can be built, reduce the requirement of the catalyst that denitrating system adopts, without the need to considering possibility poisoning in operation; Benitration reactor can design compact, reduces and takes up an area space, without the need to considering the clogging of reactor honeycomb; New clean environment air preheater can be built.Heat exchange corrugated plating conduit gap can be more intensive, makes the coefficient of heat transfer higher, can reduce the volume of air preheater.
Accompanying drawing explanation
Fig. 1 is the boiler flue system architecture schematic diagram of prior art;
Fig. 2 is structural representation of the present invention;
Fig. 3 is the structural representation of flue gas waste heat recovery system in the present invention.
Wherein 1 is flue entrance, and 2 is economizer, and 3 is high-temperature dust removal system, and 4 is denitrating system, and 5 is air preheater, 6 is flue gas waste heat recovery system, and 7 is air-introduced machine, and 8 is desulphurization system, and 9 is chimney, 10 is deduster, and 61 is inlet header, and 62 is outlet header, and 63 is heat-exchanging tube bundle.
Detailed description of the invention
To illustrate below in conjunction with accompanying drawing and embodiment further illustrates the present invention:
Boiler smoke ultra low-ash back-end ductwork system provided by the invention comprises flue entrance 1, economizer 2, high-temperature dust removal system 3, denitrating system 4, air preheater 5, flue gas waste heat recovery system 6, air-introduced machine 7, desulphurization system 8 and chimney 9, the exiting flue gas dust concentration of high-temperature dust removal system 3 meets discharging standards, such as key area, control discharge dust concentration is 20mg/Nm 3.Back-end ductwork like this after this dust pelletizing system, is all in the flue gas environment of ultra low-ash concentration, creates clean working environment for being positioned at later equipment.
Embodiment 1
Figure 2 shows that specific embodiments of the invention, it also adopts 125MW coal-burning boiler, described boiler uses the high-temperature dust removal system 3 be arranged in before denitrating system 4 to instead of traditional electrostatic precipitator 11, the ash-laden gas that boiler furnace (not shown) is discharged enters economizer 2 through flue entrance 1, after high-temperature dust removal system 3 dedusting, enter denitrating system 4 and air preheater 5, flue gas waste heat recovery system 6, air-introduced machine 7 and desulphurization system 8 successively, eventually pass through chimney 9 and discharge.
In the present embodiment running, high-temperature dust removal system 3 adopts the hot electrostatic precipitator that can tolerate 400 DEG C of temperature, normally to operate in the high-temperature area between economizer 2 and denitrating system 4.High-temperature dust removal system 3 is hot electrostatic precipitator, comprises 5 electric fields, makes outlet dust emission concentration all the time lower than 20mg/m 3, discharge capacity is up to state standards, without the need to arranging other dust arresters at flue afterbody.High-temperature dust removal system 3 efficiency of dust collection can reach 99.8%, and not by the impact of Inlet dust concentration ratio, ratio resistance.In the present embodiment, high-temperature dust removal system 3 also can use the arrangement of 6 electric fields, with the requirement making discharge capacity reach higher standard.
In the present embodiment, dust particale in flue gas environment residing for denitrating system 4 is removed, denitrating system 4 works in clean cigarette environment, thus avoid the pollution of catalyst and poisoning, make denitration efficiency can remain on more than 90% for a long time, in simultaneously extending catalyst service life, decrease operation and maintenance cost.
The wear problem of air preheater 5 and flue gas waste heat recovery system 6 is resolved equally.
The prior minimizing due to equipment inner wall dust stratification, heat transfer effect improves.When running under operating mode at full capacity, it is even lower that the exhaust gas temperature of air preheater 5 can reach design load 130 DEG C, directly brings considerable economic benefit.The structure of flue gas waste heat recovery system 6 in the present embodiment and identical in comparative example.Because the flue gas waste heat recovery system 6 in embodiment is in clean cigarette environment, therefore there is not problem, wear problem that the dust stratification mentioned in comparative example causes overall heat exchange efficiency to decline.In the present embodiment, in rated power operation situation, the cigarette temperature of entering of flue gas waste heat recovery system 6 is 132 DEG C, and when exhaust gas temperature is 107 DEG C, the inflow temperature of flue gas waste heat recovery system 6 is 80 DEG C, and flow is 65t/h, and leaving water temperature is 100-110 DEG C.
In the present embodiment, directly discharge boiler exhaust gas system through air-introduced machine 7, desulfurizer 8 and chimney 9 by the flue gas of flue gas waste heat recovery system 6 and enter air.
Embodiment 2
The present embodiment difference compared with embodiment 1 is to use refractory ceramics deduster to instead of hot electrostatic precipitator, refractory ceramics deduster is inner primarily of porous ceramic filter pipe and structure stand composition, can run under the hot environment of the highest 1000 DEG C, variations in temperature is less on efficiency of dust collection impact, running resistance is little, and refractory ceramics deduster can make efficiency of dust collection up to more than 99.96%, than general electric cleaner height 0.1%-0.5%, and first cost is low, does not change by boiler load and affect.
In addition, the pattern that described high-temperature dust removal system of the present invention can also adopt high-temperature ceramic materials deduster and hot electrostatic precipitator to combine, hot electrostatic precipitator is elementary dedusting, and Ceramic dust collector is degree of depth dedusting.
Embodiment 3
The present embodiment is the further improvement to embodiment 1, has mainly made transformation to the structure of flue gas waste heat recovery system 6.
Identical with embodiment 1, before the high-temperature dust removal system 3 of the present embodiment is arranged in denitrating system 4, the ash-laden gas that boiler furnace (not shown) is discharged enters economizer 2 through flue entrance 1, after high-temperature dust removal system 3 dedusting, enter denitrating system 4 and air preheater 5, flue gas waste heat recovery system 6, air-introduced machine 7 and desulphurization system 8 successively, eventually pass through chimney 9 and discharge.
Flue gas waste heat recovery system 6 in the present embodiment comprises inlet header 61, outlet header 62 and heat-exchanging tube bundle 63, and heat-exchanging tube bundle 63 is spiral fin coil, and spacing of fin is 4mm.Because the flue gas waste heat recovery system 6 in embodiment is in clean cigarette environment, therefore there is not the problem that the dust stratification mentioned in comparative example causes flue blockage, layout fin that can be more intensive in the tube bank of equal length, thus heat exchange area is increased under the prerequisite not reducing cigarette speed, improve the overall heat exchange efficiency of flue gas waste heat recovery system 6.In the present embodiment, in rated power operation situation, the cigarette temperature of entering of flue gas waste heat recovery system 6 is 132 DEG C, and when exhaust gas temperature is 105 DEG C, the inflow temperature of flue gas waste heat recovery system 6 is 80 DEG C, and flow is 65t/h, and leaving water temperature is 105-115 DEG C.
Applicant builds lab platform according to reynolds analogue criterion and measures, and calculates primary operating parameter comparable situation when flue gas waste heat recovery system 6 under identical boiler load, identical heat exchanger tube length, diameter condition adopts various heat-exchanging tube bundle in dust-laden and non-dusty circumstances:
Table 1
Known by contrasting, in identical spacing of fin situation, the heat exchanger tube heat exchange property in dustfree environment is obviously better than the heat exchanger tube in dusty circumstances.In dustfree environment, along with the reduction of spacing of fin, heat exchanger tube heat exchange property is constantly strengthened, and this is that spacing of fin is less, and heat exchange area is larger, and therefore heat exchanger tube heat exchange property is stronger due in identical heat exchanger tube length situation.Along with spacing of fin is reduced to 3mm from 4mm, the raising of heat exchanger tube heat exchange property is also not obvious, this is due to when spacing of fin reaches 3mm, the resistance of heat exchanger tube to flue gas causes cigarette speed to decline, heat exchanger tube heat exchange property is affected, therefore, even if in dustfree environment, the fin of heat exchanger tube also should be avoided to arrange too intensive.
The flue gas waste heat recovery system 6 of the present embodiment structurally difference with the prior art is mainly spacing of fin, it comprises inlet header 61, outlet header 62 and heat-exchanging tube bundle 63, heat-exchanging tube bundle 63 is spiral fin coil, and spacing of fin can be 3-5mm, preferred 4mm.Because the heat exchanger coefficient of heat transfer is improved, the heat exchange efficiency of flue gas waste heat recovery system 6 is improved significantly, and the efficiency that fume afterheat utilizes is higher, and effects of energy saving and emission reduction is better.
In addition, when adopting heat-exchanging tube bundle to adopt H type finned tube, its dust stratification and heat transfer characteristic have identical Changing Pattern with spiral fin coil, reach more excellent effect when spacing of fin 3-5mm, take 4mm as optimum.That is, in neat stress environment, the fin of H type finned tube is arranged and also than prior art more crypto set, thus can be improved the coefficient of heat transfer of heat exchanger.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, within the spirit and principles in the present invention all, any amendment made, equivalent replacement, improvement etc., all should be included within the scope of protection of the invention.

Claims (5)

1. a boiler ultra low-ash back-end ductwork system, comprise economizer, denitrating system, air preheater, flue gas waste heat recovery system, it is characterized in that, high-temperature dust removal system is provided with before denitrating system after economizer, denitrating system is communicated with desulphurization system by the air preheater that connects successively, flue gas waste heat recovery system, air-introduced machine, and desulphurization system is connected with chimney.
2. a kind of boiler ultra low-ash back-end ductwork system according to claim 1, it is characterized in that, described high-temperature dust removal system is hot electrostatic precipitator or refractory ceramics deduster.
3. a kind of boiler ultra low-ash back-end ductwork system according to claim 1, it is characterized in that, the pattern that described high-temperature dust removal system adopts high-temperature ceramic materials deduster and hot electrostatic precipitator to combine, hot electrostatic precipitator is elementary dedusting, and Ceramic dust collector is degree of depth dedusting.
4. a kind of boiler ultra low-ash back-end ductwork system according to claim 1, it is characterized in that, described flue gas waste heat recovery system comprises inlet header, outlet header and heat-exchanging tube bundle, and heat-exchanging tube bundle is spiral fin coil or H type finned tube, and spacing of fin is 3-5mm.
5. a kind of boiler ultra low-ash back-end ductwork system according to claim 1, it is characterized in that, described spacing of fin elects 4mm as.
CN201510001578.3A 2015-01-04 2015-01-04 Ultralow-dust rear smoke channel system of boiler Pending CN104534491A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510001578.3A CN104534491A (en) 2015-01-04 2015-01-04 Ultralow-dust rear smoke channel system of boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510001578.3A CN104534491A (en) 2015-01-04 2015-01-04 Ultralow-dust rear smoke channel system of boiler

Publications (1)

Publication Number Publication Date
CN104534491A true CN104534491A (en) 2015-04-22

Family

ID=52850070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510001578.3A Pending CN104534491A (en) 2015-01-04 2015-01-04 Ultralow-dust rear smoke channel system of boiler

Country Status (1)

Country Link
CN (1) CN104534491A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105465762A (en) * 2015-04-28 2016-04-06 无锡华光锅炉股份有限公司 Arrangement structure of boiler tail heated surface
CN108679594A (en) * 2018-04-17 2018-10-19 华电电力科学研究院有限公司 Station boiler is adjustable high temperature dust pelletizing system and application process
CN109364668A (en) * 2018-11-27 2019-02-22 宜兴市海纳环境工程有限公司 A kind of energy-saving and emission-reduction flue gas and desulfurizing and denitrifying device and device special-purpose coat
CN110145754A (en) * 2019-06-14 2019-08-20 上海昊熙能源科技有限公司 It can prevent the boiler flue gas treatment system and method for back-end surfaces low-temperature corrosion
CN111470568A (en) * 2020-04-03 2020-07-31 中国能源建设集团广东省电力设计研究院有限公司 Coupling treatment system and method based on circulating flue gas and desulfurization wastewater

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201930723U (en) * 2010-05-18 2011-08-17 浙江大学 SCR (Semiconductor Control Rectifier) smoke denitration system with structure for optimizing flow field at upstream of ammonia spraying device
CN102188904A (en) * 2011-05-11 2011-09-21 宝钢工程技术集团有限公司 Denitration system and method for sintering flue gas without ammonia reducing agent
CN202203971U (en) * 2011-07-28 2012-04-25 中国电力工程顾问集团西南电力设计院 Discharged smoke afterheat recycling and emission reduction comprehensive application system for coal-fired boiler in thermal power plant
CN202338915U (en) * 2011-11-30 2012-07-18 辽宁赛沃斯节能技术有限公司 Corrosion-resisting heat pipe flue gas waste heat recovery system of coal power plant
CN202955681U (en) * 2012-12-13 2013-05-29 袁吉增 Boiler residual heat utilizing economizer
CN203222484U (en) * 2013-04-28 2013-10-02 中国华能集团清洁能源技术研究院有限公司 Circulating fluidized bed boiler structure for extracting selenium from stone coal
CN204007277U (en) * 2014-08-20 2014-12-10 美景(北京)环保科技有限公司 A kind of little spacing finned tube and finned tube exchanger
CN104214769A (en) * 2014-08-29 2014-12-17 中国华能集团清洁能源技术研究院有限公司 Stone coal power generation selenium extraction comprehensive utilization system and method combining high-temperature dust removing and low-temperature dust removing
CN104214770A (en) * 2014-08-29 2014-12-17 中国华能集团清洁能源技术研究院有限公司 Stone coal power generation selenium extraction comprehensive utilization system and method
CN204042942U (en) * 2014-07-22 2014-12-24 山东神华山大能源环境有限公司 A kind of device utilizing coupling technique to realize boiler smoke qualified discharge
CN204404203U (en) * 2015-01-04 2015-06-17 山东大学 A kind of boiler ultra low-ash back-end ductwork system

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201930723U (en) * 2010-05-18 2011-08-17 浙江大学 SCR (Semiconductor Control Rectifier) smoke denitration system with structure for optimizing flow field at upstream of ammonia spraying device
CN102188904A (en) * 2011-05-11 2011-09-21 宝钢工程技术集团有限公司 Denitration system and method for sintering flue gas without ammonia reducing agent
CN202203971U (en) * 2011-07-28 2012-04-25 中国电力工程顾问集团西南电力设计院 Discharged smoke afterheat recycling and emission reduction comprehensive application system for coal-fired boiler in thermal power plant
CN202338915U (en) * 2011-11-30 2012-07-18 辽宁赛沃斯节能技术有限公司 Corrosion-resisting heat pipe flue gas waste heat recovery system of coal power plant
CN202955681U (en) * 2012-12-13 2013-05-29 袁吉增 Boiler residual heat utilizing economizer
CN203222484U (en) * 2013-04-28 2013-10-02 中国华能集团清洁能源技术研究院有限公司 Circulating fluidized bed boiler structure for extracting selenium from stone coal
CN204042942U (en) * 2014-07-22 2014-12-24 山东神华山大能源环境有限公司 A kind of device utilizing coupling technique to realize boiler smoke qualified discharge
CN204007277U (en) * 2014-08-20 2014-12-10 美景(北京)环保科技有限公司 A kind of little spacing finned tube and finned tube exchanger
CN104214769A (en) * 2014-08-29 2014-12-17 中国华能集团清洁能源技术研究院有限公司 Stone coal power generation selenium extraction comprehensive utilization system and method combining high-temperature dust removing and low-temperature dust removing
CN104214770A (en) * 2014-08-29 2014-12-17 中国华能集团清洁能源技术研究院有限公司 Stone coal power generation selenium extraction comprehensive utilization system and method
CN204404203U (en) * 2015-01-04 2015-06-17 山东大学 A kind of boiler ultra low-ash back-end ductwork system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
唐国山: "《工业电除尘器应用技术》", 28 February 2006 *
环境保护部等: "《GB13271-2014 锅炉大气污染物排放标准》", 1 July 2014 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105465762A (en) * 2015-04-28 2016-04-06 无锡华光锅炉股份有限公司 Arrangement structure of boiler tail heated surface
CN105465762B (en) * 2015-04-28 2017-11-21 无锡华光锅炉股份有限公司 A kind of heated surface at the end of boiler arrangement
CN108679594A (en) * 2018-04-17 2018-10-19 华电电力科学研究院有限公司 Station boiler is adjustable high temperature dust pelletizing system and application process
CN109364668A (en) * 2018-11-27 2019-02-22 宜兴市海纳环境工程有限公司 A kind of energy-saving and emission-reduction flue gas and desulfurizing and denitrifying device and device special-purpose coat
CN110145754A (en) * 2019-06-14 2019-08-20 上海昊熙能源科技有限公司 It can prevent the boiler flue gas treatment system and method for back-end surfaces low-temperature corrosion
CN111470568A (en) * 2020-04-03 2020-07-31 中国能源建设集团广东省电力设计研究院有限公司 Coupling treatment system and method based on circulating flue gas and desulfurization wastewater
CN111470568B (en) * 2020-04-03 2022-03-29 中国能源建设集团广东省电力设计研究院有限公司 Coupling treatment system and method based on circulating flue gas and desulfurization wastewater

Similar Documents

Publication Publication Date Title
CN103968401B (en) Dedusting-desulfurization-UTILIZATION OF VESIDUAL HEAT IN integral system of low PM2.5 discharge
CN104534491A (en) Ultralow-dust rear smoke channel system of boiler
CN108380041A (en) A kind of coke oven flue gas system for desulfuration and denitration and method based on activated carbon/coke
CN108355420A (en) A kind of limekiln flue gas recirculation system
CN115301014B (en) Cement raw material mill high temperature flue gas purification device and cement production system
CN204404203U (en) A kind of boiler ultra low-ash back-end ductwork system
CN201184586Y (en) Energy-saving and emission-reducing hot water tank for boiler
CN105021051B (en) A kind of waste heat of cupola furnace utilizes dedusting and desulphurization integrated system
CN108654374B (en) Ultra-clean treatment process system for flue gas
CN208320222U (en) A kind of limekiln flue gas recirculation system
CN206234838U (en) Built-in air preheater and the CO boilers with it
CN103090403B (en) The integrated apparatus of dedusting and flue gas waste heat recovery after a kind of boiler and application thereof
CN108426458A (en) A kind of glass furnace fume bypass system for desulfuration and denitration
CN102600695B (en) Energy-saving desulfuration and denitrification dust collector for large boiler
CN109701323A (en) The axis stream Combined dust removal system and method for the high ash-laden gas of high temperature
CN214718423U (en) Activated carbon regeneration material dust separation system
CN115671910A (en) High-temperature flue gas purification device of cement burning clinker cooling machine and cement production system
CN103055619A (en) Ferroalloy electric furnace flue gas purifying and dust recovering novel technology and device thereof
CN211176862U (en) Dust removal denitration integration arrangement structure
CN105889963B (en) A kind of heat-exchanger rig for wet desulfurization system
CN209138350U (en) A kind of flue gas denitrification system for realizing grid-connected i.e. investment
CN203177191U (en) Boiler back dedusting and flue gas waste heat recovery integrated device
CN207085571U (en) A kind of methanol-to-olefins regenerated flue gas UTILIZATION OF VESIDUAL HEAT IN and dust arrester
CN206320777U (en) A kind of smoke comprehensive processing unit
CN201688715U (en) Kiln head waste heat boiler with fly ash separating chamber

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150422

RJ01 Rejection of invention patent application after publication