CN104534439A - System and method for indirectly heating air heater through extracted low-level steam in waste heat cascade utilization mode - Google Patents
System and method for indirectly heating air heater through extracted low-level steam in waste heat cascade utilization mode Download PDFInfo
- Publication number
- CN104534439A CN104534439A CN201510010396.2A CN201510010396A CN104534439A CN 104534439 A CN104534439 A CN 104534439A CN 201510010396 A CN201510010396 A CN 201510010396A CN 104534439 A CN104534439 A CN 104534439A
- Authority
- CN
- China
- Prior art keywords
- low
- heater
- heat
- steam
- air heater
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E20/00—Combustion technologies with mitigation potential
- Y02E20/34—Indirect CO2mitigation, i.e. by acting on non CO2directly related matters of the process, e.g. pre-heating or heat recovery
Landscapes
- Air Supply (AREA)
Abstract
余热梯级利用的低能级抽汽间接加热暖风器系统及方法,该系统包括安装在锅炉尾部烟道空气预热器与电除尘器间的烟气换热器,安装在空气预热器空气侧入口前的暖风器,连接烟气换热器和暖风器与凝结水的循环水管路;利用7号低压加热器出口的凝结水加热暖风器中的一、二次冷风,暖风器出口的回水送回8号低压加热器入口,8号低压加热器和7号低压加热器的凝结水流量增加,使得8抽抽汽和7抽抽汽流量增加,实现利用8抽抽汽和7抽抽汽间接加热暖风器的目的;由6号低压加热器入口引出的部分凝结水送入烟气换热器中吸热,并由6号低压加热器出口引回回热系统,流经6号低压加热器的凝结水流量减少,使得6抽抽汽的汽流量也相应减少,被排挤的部分6抽抽汽送入汽轮机做功,机组的经济性提高。
A low-energy extraction steam indirect heating air heater system and method for waste heat cascade utilization, the system includes a flue gas heat exchanger installed between the flue air preheater and the electrostatic precipitator at the tail of the boiler, and installed on the air side of the air preheater The air heater in front of the inlet is connected to the flue gas heat exchanger, the air heater and the circulating water pipeline of the condensed water; the condensed water at the outlet of the No. 7 low-pressure heater is used to heat the primary and secondary cold air in the air heater, and the air heater The return water from the outlet is sent back to the inlet of No. 8 low-pressure heater, and the condensate flow of No. 8 low-pressure heater and No. 7 low-pressure heater increases, which increases the flow rate of 8 extraction steam and 7 extraction steam, and realizes the utilization of 8 extraction steam and 7 extraction steam The purpose of the indirect heating heater; part of the condensed water drawn from the inlet of the No. 6 low-pressure heater is sent to the flue gas heat exchanger to absorb heat, and is led back to the heat recovery system from the outlet of the No. 6 low-pressure heater, and flows through the No. 6 low-pressure heater The condensed water flow of the device is reduced, so that the steam flow of the 6 extraction steam is also reduced correspondingly, and the displaced part of the 6 extraction steam is sent to the steam turbine to do work, and the economy of the unit is improved.
Description
技术领域technical field
本发明涉及火力发电技术领域,具体涉及余热梯级利用的低能级抽汽间接加热暖风器系统及方法。The invention relates to the technical field of thermal power generation, in particular to a low-energy extraction steam indirect heating air heater system and method for cascaded utilization of waste heat.
背景技术Background technique
随着全球能源价格的不断上涨、世界范围内气候不断恶化,国家对节能降耗的要求更加严格,如何深入挖掘现有电站机组节能的潜力,降低企业的生产运行成本,成为每个企业共同关心的重要问题。With the rising global energy prices and the deteriorating climate around the world, the country has more stringent requirements for energy conservation and consumption reduction. How to deeply tap the energy-saving potential of existing power plant units and reduce the production and operation costs of enterprises has become a common concern of every enterprise. important question.
我国北方大部分电站锅炉机组均安装暖风器系统,以解决冬季空气预热器入口空气温度低或低负荷下排烟温度低所造成的空气预热器冷端低温腐蚀、积灰堵塞等问题。目前的暖风器系统多采用4抽抽汽加热或6抽抽汽加热方式,热源能级较高、不经济。若利用较低能级的抽汽热量直接加热则需要在负压状态下抽汽,且抽汽的密度较低、体积流量大,需要较粗的输汽管道,问题也较多。因此,需考虑其它的更经济的热源加热暖风器,以提高机组的经济性。Most power plant boiler units in northern my country are equipped with heater systems to solve the problems of low-temperature corrosion at the cold end of the air preheater and clogging of dust accumulation caused by low air temperature at the inlet of the air preheater in winter or low exhaust gas temperature under low load . The current heater system mostly adopts 4-exhaust steam heating or 6-exhaust steam heating, and the energy level of the heat source is relatively high, which is uneconomical. If the heat of extraction steam with a lower energy level is used for direct heating, steam extraction is required under negative pressure, and the density of extraction steam is low, the volume flow rate is large, thicker steam transmission pipelines are required, and there are many problems. Therefore, it is necessary to consider other more economical heat sources to heat the air heater to improve the economy of the unit.
我国现役火电机组中锅炉排烟温度普遍维持在125~150℃左右水平,高于设计值。一般情况下排烟温度每升高20℃,排烟热损失增加0.6%~1.0%,对机组的经济性产生不利的影响。随着暖风器出口冷空气温度的提高,锅炉排烟温度将进一步升高。为保证机组的经济性不随暖风器的投运而降低,需对锅炉烟气余热加以回收利用。在空气预热器之后安装烟气换热器可以有效的回收烟气余热,并降低进入后续电除尘、脱硫塔及引风机的烟气温度及流量,保证机组经济性不随暖风器投运而降低。The exhaust gas temperature of boilers in my country's active thermal power units is generally maintained at around 125-150 °C, which is higher than the design value. Generally, every 20°C increase in exhaust gas temperature will increase the heat loss of exhaust gas by 0.6% to 1.0%, which will have a negative impact on the economy of the unit. As the temperature of the cold air at the outlet of the heater increases, the exhaust gas temperature of the boiler will further increase. In order to ensure that the economy of the unit does not decrease with the operation of the heater, it is necessary to recover and utilize the waste heat of the boiler flue gas. Installing the flue gas heat exchanger after the air preheater can effectively recover the waste heat of the flue gas, and reduce the temperature and flow of the flue gas entering the subsequent electrostatic precipitator, desulfurization tower and induced draft fan, so as to ensure that the economical efficiency of the unit will not be affected by the operation of the heater. reduce.
发明内容Contents of the invention
为了克服上述现有技术存在的问题,本发明的目的在于提供一种余热梯级利用的低能级抽汽间接加热暖风器系统及方法,利用低能级的抽汽间接加热暖风器,同时利用烟气换热器回收烟气余热并用于替换较高能级的抽汽,实现暖风器热源的优化布置及低能级热量的梯级利用。In order to overcome the above-mentioned problems in the prior art, the object of the present invention is to provide a low-energy-level extraction steam indirect heating air heater system and method for cascaded utilization of waste heat, using low-energy extraction steam to indirectly heat the air heater, and at the same time using smoke The gas heat exchanger recovers the waste heat of the flue gas and uses it to replace the higher energy level extraction steam, so as to realize the optimal arrangement of the heat source of the heater and the cascaded utilization of low energy level heat.
为了实现上述发明目的,本发明采取的技术方案是:In order to realize the above-mentioned purpose of the invention, the technical scheme that the present invention takes is:
余热梯级利用的低能级抽汽间接加热暖风器系统,包括安装在锅炉尾部烟道空气预热器1与电除尘器3之间的烟气换热器2,安装在空气预热器1空气侧入口前的暖风器10,连接烟气换热器2和暖风器10与凝结水的循环水管路,所述暖风器10与凝结水的循环水管路的连接关系为:7号低压加热器8凝结水出口分两路,一路接入暖风器10的入口,暖风器10的出口依次连接8号低压加热器9和回热系统,7号低压加热器8凝结水出口的另一路连接6号低压加热器7凝结水进口;所述烟气换热器2与凝结水的循环水管路的连接关系为:6号低压加热器7凝结水进口引出一路接入烟气换热器2,烟气换热器2的凝结水出口通过6号低压加热器7出口接入回热系统。The low-energy steam extraction indirect heating air heater system utilizing the waste heat cascade includes the flue gas heat exchanger 2 installed between the flue air preheater 1 and the electrostatic precipitator 3 at the tail of the boiler, and the air preheater 1 installed in the air The air heater 10 in front of the side entrance connects the flue gas heat exchanger 2 and the air heater 10 with the circulating water pipeline of condensed water. The connection relationship between the air heater 10 and the circulating water pipeline of condensed water is: No. The condensate outlet of the heater 8 is divided into two routes, one of which is connected to the inlet of the heater 10, and the outlet of the heater 10 is connected to the No. One way is connected to the condensed water inlet of No. 6 low-pressure heater 7; the connection relationship between the flue gas heat exchanger 2 and the condensed water circulating water pipeline is: No. 6 low-pressure heater 7 condensed water inlet leads one way to the flue gas heat exchanger 2. The condensed water outlet of the flue gas heat exchanger 2 is connected to the heat recovery system through the outlet 7 of the No. 6 low-pressure heater.
上述所述系统间接加热暖风器和排烟余热梯级利用的方法为:由7号低压加热器8出口引出部分凝结水加热暖风器10中的一、二次冷风,提高空气预热器1入口空气温度;暖风器中10释放热量后的凝结水由8号低压加热器9入口引回回热系统,使得流经8号低压加热器9和7号低压加热器8的凝结水流量增加、热功率增加,相应的分别与8号低压加热器9和7号低压加热器8的连接的8抽抽汽11和7抽抽汽12的流量增加,从而实现了8抽抽汽11和7抽抽汽12的热量间接加热暖风器10中一、二次风的目的;由6号低压加热器7入口引出的部分凝结水送入烟气换热器2中吸热,并由6号低压加热器7出口引回回热系统,流经6号低压加热器7的凝结水流量减少,与6号低压加热器7连接的6抽抽汽13的汽流量也相应减少,被排挤的部分6抽抽汽13送入汽轮机做功;由于6抽抽汽13的能级高于8抽抽汽11和7抽抽汽12,被排挤的6抽抽汽13的做功能力高于8抽抽汽11和7抽抽汽12流量增加损失的做功能力,机组的经济性提高。The method for indirect heating of the air heater and cascade utilization of exhaust waste heat in the above-mentioned system is as follows: part of the condensed water is drawn from the outlet of the No. 7 low-pressure heater 8 to heat the primary and secondary cold air in the air heater 10, and the air preheater 1 Inlet air temperature; the condensed water released by No. 8 low-pressure heater 9 in the air heater is led back to the heat recovery system by the inlet of No. 8 low-pressure heater 9, so that the flow of condensed water flowing through No. 8 low-pressure heater 9 and No. 7 low-pressure heater 8 increases, As the thermal power increases, the flow rates of the 8 extraction steam 11 and the 7 extraction steam 12 respectively connected to the No. The heat indirectly heats the primary and secondary air in the heater 10; part of the condensed water drawn from the inlet of the No. 6 low-pressure heater 7 is sent to the flue gas heat exchanger 2 to absorb heat, and is discharged from the outlet of the No. 6 low-pressure heater 7 Leading back to the heat recovery system, the flow of condensed water flowing through the No. 6 low-pressure heater 7 decreases, and the steam flow of the 6 extraction steam 13 connected to the No. 6 low-pressure heater 7 also decreases accordingly, and the displaced part 6 extraction steam 13 is sent to the steam turbine Work; because the energy level of 6 extraction steam extraction 13 is higher than 8 extraction steam extraction 11 and 7 extraction steam extraction 12, the working ability of the displaced 6 extraction steam extraction 13 is higher than that of 8 extraction steam extraction 11 and 7 extraction steam extraction 12 flow increase loss function power, the economy of the unit is improved.
本发明和现有技术相比,具有如下优点:Compared with the prior art, the present invention has the following advantages:
采用本发明系统后,使暖风器的热源得以间接利用低能级抽汽,热源得到了合理优化,同时提高了锅炉排烟余热的能级,使之可以利用到较高能级的低压加热器中,实现了排烟余热的梯级利用。本发明采用低能级抽汽加热凝结水,再使用凝结水加热暖风器的方案,既降低了加热热源的能级,又避免了使用低能级抽汽直接加热暖风器时需在负压状态下抽汽及抽汽体积流量较大的问题,使得机组的经济性得以提高。After adopting the system of the present invention, the heat source of the air heater can be indirectly used to extract steam at a low energy level, and the heat source has been rationally optimized, and at the same time, the energy level of the exhaust heat of the boiler is improved, so that it can be used in a higher energy level low-pressure heater , to realize the cascade utilization of exhaust heat. The present invention adopts the scheme of heating the condensed water by low-energy level steam extraction, and then uses the condensed water to heat the air heater, which not only reduces the energy level of the heating heat source, but also avoids the need to be in a negative pressure state when using low-energy level steam extraction to directly heat the air heater The lower extraction steam and the large volume flow rate of the extraction steam improve the economical efficiency of the unit.
附图说明Description of drawings
附图为本发明的结构示意图。Accompanying drawing is the structural representation of the present invention.
其中,1为空气预热器,2为烟气换热器,3为电除尘器,4为引风机,5为脱硫塔,6为烟囱,7为6号低压加热器,8为7号低压加热器,9为8号低压加热器,10为暖风器,11为8抽抽汽,12为7抽抽汽,13为6抽抽汽。Among them, 1 is the air preheater, 2 is the flue gas heat exchanger, 3 is the electric precipitator, 4 is the induced draft fan, 5 is the desulfurization tower, 6 is the chimney, 7 is the No. 6 low-pressure heater, and 8 is the No. 7 low-pressure heater. Heater, 9 is No. 8 low-pressure heaters, 10 is air heater, 11 is 8 extractions, 12 is 7 extractions, and 13 is 6 extractions.
具体实施方式Detailed ways
以下结合附图及具体实施例,对本发明作进一步的详细描述。The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.
如附图所示,本发明余热梯级利用的低能级抽汽间接加热暖风器系统,包括安装在锅炉尾部烟道空气预热器1与电除尘器3之间的烟气换热器2,安装在空气预热器1空气侧入口前的暖风器10,连接烟气换热器2和暖风器10与凝结水的循环水管路,所述暖风器10与凝结水的循环水管路的连接关系为:7号低压加热器8凝结水出口分两路,一路接入暖风器10的入口,暖风器10的出口依次连接8号低压加热器9和回热系统,7号低压加热器8凝结水出口的另一路连接6号低压加热器7凝结水进口;所述烟气换热器2与凝结水的循环水管路的连接关系为:6号低压加热器7凝结水进口引出一路接入烟气换热器2,烟气换热器2的凝结水出口通过6号低压加热器7出口接入回热系统。As shown in the drawings, the low-energy-level steam extraction indirect heating air heater system for waste heat cascade utilization of the present invention includes a flue gas heat exchanger 2 installed between the flue air preheater 1 at the boiler tail and the electric precipitator 3, The air heater 10 installed in front of the air side inlet of the air preheater 1 connects the flue gas heat exchanger 2 and the air heater 10 with the circulating water pipeline of the condensed water, and the air heater 10 is connected with the condensed water circulating water pipeline The connection relationship is as follows: No. 7 low-pressure heater 8 condensate outlet is divided into two routes, one way is connected to the inlet of heater 10, and the outlet of heater 10 is connected to No. 8 low-pressure heater 9 and the heat recovery system in turn, and No. The other path of the condensed water outlet of heater 8 is connected to the condensed water inlet of No. 6 low-pressure heater 7; the connection relationship between the flue gas heat exchanger 2 and the condensed water circulating water pipeline is: the condensed water inlet of No. One way is connected to the flue gas heat exchanger 2, and the condensed water outlet of the flue gas heat exchanger 2 is connected to the heat recovery system through the outlet 7 of the No. 6 low-pressure heater.
如附图所示,本发明所述系统间接加热暖风器和排烟余热梯级利用的方法为:由7号低压加热器8出口引出部分凝结水加热暖风器10中的一、二次冷风,提高空气预热器1入口空气温度;暖风器中10释放热量后的凝结水由8号低压加热器9入口引回回热系统,使得流经8号低压加热器9和7号低压加热器8的凝结水流量增加、热功率增加,相应的分别与8号低压加热器9和7号低压加热器8的连接的8抽抽汽11和7抽抽汽12的流量增加,从而实现了8抽抽汽11和7抽抽汽12的热量间接加热暖风器10中一、二次风的目的。As shown in the accompanying drawings, the method for indirect heating of the air heater and cascade utilization of exhaust waste heat in the system of the present invention is as follows: part of the condensed water is drawn from the outlet of No. 7 low-pressure heater 8 to heat the primary and secondary cold air in the air heater 10 , to increase the air temperature at the inlet of air preheater 1; the condensed water after the heat released by 10 in the air heater is led back to the heat recovery system from the inlet of No. 8 low-pressure heater 9, so that it flows through No. 8 low-pressure heater 9 and No. 7 low-pressure heater The condensed water flow rate of 8 increases, the thermal power increases, and the flow rate of 8 extraction steam 11 and 7 extraction steam 12 connected to No. 8 low-pressure heater 9 and No. 7 low-pressure heater 8 respectively increases, thereby realizing 8 extraction steam 11 and 7 extract the heat of steam extraction 12 to indirectly heat the purpose of the primary and secondary air in the air heater 10.
如附图所示,由于暖风器10出口的一、二次风温提高,空气预热器1出口的排烟温度提高,烟气余热的能级提高,锅炉排烟余热依靠布置在空气预热器1之后的烟气换热器2吸收。由6号低压加热器7入口引出的部分凝结水送入烟气换热器2中吸热,并由6号低压加热器7出口引回回热系统,流经6号低压加热器7的凝结水流量减少,与6号低压加热器7连接的6抽抽汽13的汽流量也相应减少,被排挤的部分6抽抽汽13送入汽轮机做功;烟气换热器2出口的烟气依次经过电除尘器3、引风机4、脱硫塔5和烟囱6排空。As shown in the figure, due to the increase of the temperature of the primary and secondary air at the outlet of the air heater 10, the temperature of the exhaust gas at the outlet of the air preheater 1 increases, and the energy level of the waste heat of the flue gas increases. The flue gas heat exchanger 2 after the heater 1 absorbs. Part of the condensed water drawn from the inlet of No. 6 low-pressure heater 7 is sent to the flue gas heat exchanger 2 to absorb heat, and is led back to the heat recovery system by the outlet of No. 6 low-pressure heater 7, and the condensed water flowing through No. 6 low-pressure heater 7 As the flow rate decreases, the steam flow rate of the 6 extraction steam 13 connected to the No. 6 low-pressure heater 7 also decreases accordingly, and the displaced part 6 extraction steam 13 is sent to the steam turbine for work; the flue gas at the outlet of the flue gas heat exchanger 2 passes through the electric precipitator in turn Device 3, induced draft fan 4, desulfurization tower 5 and chimney 6 are emptied.
由于6抽抽汽13的能级高于8抽抽汽11和7抽抽汽12,被排挤的6抽抽汽13的做功能力高于8抽抽汽11和7抽抽汽12流量增加损失的做功能力,上述系统布置方案中,由于间接利用8抽抽汽11和7抽抽汽12加热暖风器10中的一、二次风温度,而使排烟温度升高,所产生的能级较高的排烟余热则用于排挤6抽抽汽13,从而实现了使用低品味的抽汽热量替换高品位抽汽热量的目的,机组整体的经济性得以提高。Because the energy level of the 6 extraction steam extraction 13 is higher than the 8 extraction steam extraction 11 and the 7 extraction steam extraction 12, the working ability of the displaced 6 extraction steam extraction 13 is higher than the working ability of the 8 extraction steam extraction 11 and the 7 extraction steam extraction 12 flow rate increase loss, In the above-mentioned system layout plan, since the temperature of the primary and secondary air in the heater 10 is indirectly heated by the 8 extraction steam extraction 11 and the 7 extraction steam extraction 12, the temperature of the exhaust gas is increased, and the exhaust gas with a higher energy level is generated. The waste heat is used to displace 6 and extract steam 13, thereby achieving the purpose of using low-grade extraction steam heat to replace high-grade extraction steam heat, and the overall economic efficiency of the unit is improved.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510010396.2A CN104534439A (en) | 2015-01-07 | 2015-01-07 | System and method for indirectly heating air heater through extracted low-level steam in waste heat cascade utilization mode |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510010396.2A CN104534439A (en) | 2015-01-07 | 2015-01-07 | System and method for indirectly heating air heater through extracted low-level steam in waste heat cascade utilization mode |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN104534439A true CN104534439A (en) | 2015-04-22 |
Family
ID=52850018
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510010396.2A Pending CN104534439A (en) | 2015-01-07 | 2015-01-07 | System and method for indirectly heating air heater through extracted low-level steam in waste heat cascade utilization mode |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104534439A (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106051805A (en) * | 2016-06-24 | 2016-10-26 | 福建龙净环保股份有限公司 | Waste heat recovery system and method with discharged smoke waste heat as heat source of air heater |
| CN106091580A (en) * | 2016-06-16 | 2016-11-09 | 西安交通大学 | The predrying brown coal electricity generation system of a kind of integrated steam air heater and method |
| CN106287771A (en) * | 2016-09-14 | 2017-01-04 | 西安热工研究院有限公司 | A kind of coal-fired power station boiler fume afterheat utilizes system with moisture combined recovery |
| CN108534126A (en) * | 2018-03-23 | 2018-09-14 | 中国大唐集团科学技术研究院有限公司火力发电技术研究院 | It is a kind of with pressure matcher machine stove waste heat coupling utilize system |
| CN109871624A (en) * | 2019-02-26 | 2019-06-11 | 华北电力科学研究院有限责任公司 | Energy consumption analysis method and device after thermal power plant's steam air heater heat source reforming |
| CN110578931A (en) * | 2019-07-31 | 2019-12-17 | 西安航天源动力工程有限公司 | System and method for adjusting temperature of primary air and secondary air by utilizing condensed water to improve air heater |
| CN110594774A (en) * | 2019-09-12 | 2019-12-20 | 中国电力工程顾问集团西南电力设计院有限公司 | A thermal power plant air preheater cold end heater heating system |
| CN113154358A (en) * | 2021-04-21 | 2021-07-23 | 中国电力工程顾问集团华北电力设计院有限公司 | Cold air heating and flue gas waste heat cascade utilization system for power station |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201866755U (en) * | 2010-10-19 | 2011-06-15 | 上海成信建业节能科技有限公司 | Flue gas waste heat recovery system for boiler in thermal power plant |
| WO2012111495A1 (en) * | 2011-02-17 | 2012-08-23 | バブコック日立株式会社 | Coal fired boiler system provided with carbon dioxide collecting system |
| CN103104907A (en) * | 2013-01-31 | 2013-05-15 | 华北电力大学 | Heating structure and heating method of boiler based on partitioned flue and multistage air preheating |
| CN203298285U (en) * | 2013-06-18 | 2013-11-20 | 华北电力大学 | Power station machine and furnace integrating type waste heat utilization system based on air preheated by extraction steam |
| CN103486567A (en) * | 2013-07-15 | 2014-01-01 | 华北电力大学 | Boiler-turbine coupled flue gas waste heat utilization system capable of preheating air based on condensed water |
| CN204438069U (en) * | 2015-01-07 | 2015-07-01 | 西安热工研究院有限公司 | The low-lying level of exhaust heat stepped utilization is drawn gas indirect steam air heater system |
-
2015
- 2015-01-07 CN CN201510010396.2A patent/CN104534439A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201866755U (en) * | 2010-10-19 | 2011-06-15 | 上海成信建业节能科技有限公司 | Flue gas waste heat recovery system for boiler in thermal power plant |
| WO2012111495A1 (en) * | 2011-02-17 | 2012-08-23 | バブコック日立株式会社 | Coal fired boiler system provided with carbon dioxide collecting system |
| CN103104907A (en) * | 2013-01-31 | 2013-05-15 | 华北电力大学 | Heating structure and heating method of boiler based on partitioned flue and multistage air preheating |
| CN203298285U (en) * | 2013-06-18 | 2013-11-20 | 华北电力大学 | Power station machine and furnace integrating type waste heat utilization system based on air preheated by extraction steam |
| CN103486567A (en) * | 2013-07-15 | 2014-01-01 | 华北电力大学 | Boiler-turbine coupled flue gas waste heat utilization system capable of preheating air based on condensed water |
| CN204438069U (en) * | 2015-01-07 | 2015-07-01 | 西安热工研究院有限公司 | The low-lying level of exhaust heat stepped utilization is drawn gas indirect steam air heater system |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106091580A (en) * | 2016-06-16 | 2016-11-09 | 西安交通大学 | The predrying brown coal electricity generation system of a kind of integrated steam air heater and method |
| CN106091580B (en) * | 2016-06-16 | 2018-07-17 | 西安交通大学 | A kind of the predrying lignite electricity generation system and method for integrated steam air heater |
| CN106051805A (en) * | 2016-06-24 | 2016-10-26 | 福建龙净环保股份有限公司 | Waste heat recovery system and method with discharged smoke waste heat as heat source of air heater |
| CN106051805B (en) * | 2016-06-24 | 2018-12-14 | 福建龙净环保股份有限公司 | A kind of residual neat recovering system and method using smoke discharging residual heat as steam air heater heat source |
| CN106287771A (en) * | 2016-09-14 | 2017-01-04 | 西安热工研究院有限公司 | A kind of coal-fired power station boiler fume afterheat utilizes system with moisture combined recovery |
| CN108534126A (en) * | 2018-03-23 | 2018-09-14 | 中国大唐集团科学技术研究院有限公司火力发电技术研究院 | It is a kind of with pressure matcher machine stove waste heat coupling utilize system |
| CN109871624A (en) * | 2019-02-26 | 2019-06-11 | 华北电力科学研究院有限责任公司 | Energy consumption analysis method and device after thermal power plant's steam air heater heat source reforming |
| CN109871624B (en) * | 2019-02-26 | 2022-12-20 | 华北电力科学研究院有限责任公司 | Energy consumption analysis method and device after heat source transformation of heater in thermal power plant |
| CN110578931A (en) * | 2019-07-31 | 2019-12-17 | 西安航天源动力工程有限公司 | System and method for adjusting temperature of primary air and secondary air by utilizing condensed water to improve air heater |
| CN110578931B (en) * | 2019-07-31 | 2024-08-02 | 西安航天源动力工程有限公司 | System and method for adjusting secondary air temperature by utilizing condensation water to improve heater |
| CN110594774A (en) * | 2019-09-12 | 2019-12-20 | 中国电力工程顾问集团西南电力设计院有限公司 | A thermal power plant air preheater cold end heater heating system |
| CN113154358A (en) * | 2021-04-21 | 2021-07-23 | 中国电力工程顾问集团华北电力设计院有限公司 | Cold air heating and flue gas waste heat cascade utilization system for power station |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102305413B (en) | Exhaust gas waste heat recovery and emission reduction comprehensive application system for coal-fired boiler in thermal power plant | |
| CN103062754B (en) | Power station machine furnace integrated cold end comprehensive optimization system | |
| CN206347555U (en) | A kind of economic benefits and social benefits supplementary heat exchanger system for MGGH | |
| CN103104907B (en) | Heating structure and heating method of boiler based on partitioned flue and multistage air preheating | |
| WO2018014768A1 (en) | Residual heat reuse system for turbine-boiler integrated heat energy circulation | |
| CN204494453U (en) | A kind of energy-saving and emission-reduction system based on the exhaust heat stepped utilization of coal steam-electric plant smoke | |
| CN102767821B (en) | Smoke waste heat deep utilization system of power station boiler for heating supplied water at high pressure | |
| CN103486567A (en) | Boiler-turbine coupled flue gas waste heat utilization system capable of preheating air based on condensed water | |
| CN102230615B (en) | Combined type flue gas residual heat comprehensive utilization system | |
| CN205783992U (en) | A kind of energy conserving system utilizing heat pump heat smoke again | |
| CN106016416A (en) | Boiler smoke and steam turbine exhaust coupled high-back-pressure combined heat and power generation system | |
| CN108253443A (en) | A kind of coal-fired plant flue gas water recycling and complementary energy synthesis utilize system | |
| CN107366897A (en) | A kind of Pollutant in Coal Burning Boiler emission reduction optimization collaboration fume afterheat deep exploitation system | |
| CN105402761A (en) | Deep coupling utilization system for turbine steam exhaust waste heat and boiler flue gas waste heat | |
| CN102767822B (en) | Integrated system for pre-heating air and condensed water of turbine in grading manner by using boiler smoke | |
| CN205137624U (en) | Boiler waste heat heating system economizer | |
| CN204593353U (en) | A kind of integrated system of deep exploitation residual heat from boiler fume | |
| CN112128732B (en) | Waste steam and flue gas waste heat energy quality coupling and improving system | |
| CN202762308U (en) | Deep energy-saving system based on flue gas desulfurization and denitrification process optimization | |
| CN201866755U (en) | Flue gas waste heat recovery system for boiler in thermal power plant | |
| CN204421044U (en) | Based on the flue gas waste heat utilization device of cold and heat combined supply | |
| CN208687705U (en) | A system for removing coupling between low-pressure cylinder inlet steam operation and low-pressure economizer | |
| CN205606619U (en) | Air preheater bypass type flue gas waste heat cascade utilization system | |
| CN107166377A (en) | A kind of recirculating fluidized bed thermal power plant unit slag cooler residual heat using device | |
| CN203052622U (en) | Boiler heated structure based on separated flue and multi-stage air preheating |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
| WD01 | Invention patent application deemed withdrawn after publication |