CN104514798A - Connection shaft for gas drainage blower of coal mine underground drill rig - Google Patents
Connection shaft for gas drainage blower of coal mine underground drill rig Download PDFInfo
- Publication number
- CN104514798A CN104514798A CN201410780052.5A CN201410780052A CN104514798A CN 104514798 A CN104514798 A CN 104514798A CN 201410780052 A CN201410780052 A CN 201410780052A CN 104514798 A CN104514798 A CN 104514798A
- Authority
- CN
- China
- Prior art keywords
- blower
- section
- rig
- construction section
- changeover portion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
A connection shaft for a gas drainage blower of a coal mine underground drill rig includes a variable diameter comprising a drill rig cooperative section for connecting a drill rig gearbox, a disc section used to transmit torque, a blower mounting section used to install the blower and a taper thread section connected with the drill rod, wherein the sections are connected in order. the invention realizes fast connection of the drill rig gearbox, changes left and right bolt connection structure into a left and right bolt integrated structure, eliminates the frequent disassembling of bolt and broken wires, obviously improves the service life of the connecting shaft strength, improves the work efficiency, and reduces the labor intensity of miners.
Description
Technical field
The present invention relates to a kind of connection set, especially relate to a kind of coupling shaft of coal mine gallery drilling rig gas extraction blower.
Background technique
Because gas emission in coal mine is very large, when being difficult to dilution eliminating by ventilation, the method for available extraction, gets rid of gas, reduces burden of ventilating.Often need to adopt gas extraction blower to get rid of gas, and in use installation process, need to adopt coupling shaft, existing coupling shaft when being arranged on rig gearbox due to design structure adopt be that the mode offering a circle tapped hole at collapsable shaft disk place is fixed, in use dismantle trouble, the collapsable shaft ubiquity simultaneously thought problem be exactly in use connecting screw easily rupture, working life is short.
Summary of the invention
The object of the invention is, for solving the problem that the dismounting of existing transmission shaft bothers and working life is short, to provide a kind of coupling shaft of coal mine gallery drilling rig gas extraction blower.
The present invention is the deficiency solved the problems of the technologies described above, and the technological scheme adopted is:
A kind of coupling shaft of coal mine gallery drilling rig gas extraction blower, comprise a collapsable shaft, collapsable shaft coordinates section by the rig for connecting rig gearbox successively, for the disk segments of transmitting torque, connect and compose for the blower construction section of installing blower and the tapered thread section that is connected with drilling rod, the outer wall of described rig cooperation section is milled with six homalographics and coordinates section outer wall one week equally distributed plane along rig, section is coordinated away from one end of disk segments offers tapped hole so that be fixed on by coupling shaft on rig gearbox at rig, one end of disk segments coordinates section to be connected by changeover portion I with rig so that form the location shaft shoulder that rig coordinates section, the other end of disk segments is connected so that form the location shaft shoulder of blower construction section by changeover portion II with blower construction section, tapered thread section is connected with one end of blower construction section by changeover portion III, fixed card slot is provided with so that fixing blower between blower construction section and changeover portion III, blower construction section offers the radial hole radially distributed, coupling shaft also offers one section through blower construction section, axial bore in changeover portion III and tapered thread section, radial hole is communicated with axial bore so that the hearsay in blower delivered in drilling rod.
Described disk, changeover portion II, blower construction section, changeover portion I and rig coordinate the diameter of section to reduce successively.
The diameter of described changeover portion III and the diametric fit of blower construction section, can adopt same diameter.
The distance of shaft shoulder place, the location plane of the distance between center line blower construction section of described radial hole is the 1/6-1/2 of blower construction section length.
The center line of described axial bore overlaps with the center line of described coupling shaft.
The invention has the beneficial effects as follows: realization of the present invention is connected with the quick of rig gearbox, changing left and right bolt fastening structure is left-right integrated formula structure, frequent demounting bolt and fracture of wire phenomenon are stopped, intensity and the life-span of coupling shaft significantly improve, improve working efficiency, alleviate the labor intensity of miner.
The present invention is by the Shang Xiliu of cylndrical surface, form the rig coordinated with the mounting hole of rig gearbox and coordinate section, can realize inserting fast or extracting, a large amount of like this decreases the installation and removal time, be provided with the location shaft shoulder simultaneously and can determine mounting point easily, and coordinate installation to ensure axial restraint by the tapped hole of axle head.Such design eliminates middle connecting bolt, stop the phenomenon that original bolt fractures because of the shearing stress be subject to, thus improve the working life of whole transmission shaft, be provided with multistage simultaneously and blower can be installed and the axial bore and the radial hole that are provided with cooperation, achieve and the hearsay of blower is delivered to a formation air channel in drilling rod.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
Fig. 2 is the sectional view in B-B direction in Fig. 1 of the present invention.
Fig. 3 is the sectional view in C-C direction in Fig. 1 of the present invention.
Graphical indicia: 1, rig coordinates section; 2, tapped hole; 3, disk segments; 4, blower construction section; 5, radial hole; 6, axial bore; 7, tapered thread section.
Embodiment
Shown in figure, embodiment is as follows:
A kind of coupling shaft of coal mine gallery drilling rig gas extraction blower, comprise a collapsable shaft, collapsable shaft divides for ease of quick insertion or the rig cooperation section 1 of extracting rig gearbox successively, ensure the disk segments 3 of transmitting torque, for installing the blower construction section 4 of blower and the tapered thread section 7 being convenient to be connected with drilling rod, rig coordinates section 1 to be that one section of cylndrical surface is milled with the cylinder of six aspects so that coordinate with rig gearbox, and rig cooperation section 1 one end away from disk segments 3 offers tapped hole 2 so that be fixed on by coupling shaft on rig gearbox, one end of disk segments 3 coordinates section 1 to be connected by changeover portion I with rig so that form the location shaft shoulder that rig coordinates section 1, the other end of disk segments is connected with blower construction section 4 by changeover portion II so that form the location shaft shoulder of blower construction section 4, tapered thread section 7 is connected with one end of blower construction section 4 by changeover portion III, fixed card slot is provided with so that fixing blower between blower construction section 4 and changeover portion III, blower construction section 4 offers the radial hole 5 radially distributed, coupling shaft also offers one section through blower construction section 4, axial bore 6 in changeover portion III and tapered thread section 7, radial hole 5 is communicated with so that the hearsay in blower delivered in drilling rod with axial bore 6.
Described disk 3, changeover portion II, blower construction section 4, changeover portion I and rig coordinate the diameter of section 1 to reduce successively.
The diameter of described changeover portion III is identical with the diameter of blower construction section 4.
The distance of shaft shoulder place, the location plane of the distance between center line blower construction section 4 of described radial hole is the 1/6-1/2 of blower construction section 4 length.
The center line of described axial bore 6 overlaps with the center line of described coupling shaft.
The structure that the present invention adopts realizes being connected with the quick of rig gearbox, changing original left and right bolt fastening structure is left-right integrated formula structure, frequent demounting bolt and bolt fracture of wire phenomenon are stopped, intensity and the life-span of coupling shaft significantly improve, improve working efficiency, alleviate the labor intensity of miner.
Technological scheme cited by the present invention and mode of execution be not restriction, be equal to the technological scheme cited by the present invention and mode of execution or effect same approach all in the scope that the present invention protects.
Claims (5)
1. the coupling shaft of a coal mine gallery drilling rig gas extraction blower, it is characterized in that: comprise a collapsable shaft, collapsable shaft coordinates section (1) by the rig for connecting rig gearbox successively, for the disk segments (3) of transmitting torque, connect and compose for the blower construction section (4) of installing blower and the tapered thread section (7) that is connected with drilling rod, the outer wall of described rig cooperation section (1) is milled with six homalographics and coordinates section (1) outer wall one week equally distributed plane along rig, coordinate on section (1) one end away from disk segments (3) at rig and offer tapped hole (2) so that be fixed on by coupling shaft on rig gearbox, one end of disk segments (3) coordinates section (1) to be connected by changeover portion I with rig so that form the location shaft shoulder that rig coordinates section (1), the other end of disk segments is connected with blower construction section (4) so that form the location shaft shoulder of blower construction section (4) by changeover portion II, tapered thread section (7) is connected with one end of blower construction section (4) by changeover portion III, fixed card slot is provided with so that fixing blower between blower construction section (4) and changeover portion III, blower construction section (4) offers the radial hole (5) radially distributed, coupling shaft also offers one section through blower construction section (4), axial bore (6) in changeover portion III and tapered thread section (7), radial hole (5) is communicated with so that the hearsay in blower delivered in drilling rod with axial bore (6).
2. the coupling shaft of a kind of coal mine gallery drilling rig gas extraction blower according to claim 1, is characterized in that: described disk (3), changeover portion II, blower construction section (4), changeover portion I and rig coordinate the diameter of section (1) to reduce successively.
3. the coupling shaft of a kind of coal mine gallery drilling rig gas extraction blower according to claim 1, is characterized in that: the diameter of described changeover portion III and the diametric fit of blower construction section (4).
4. the coupling shaft of a kind of coal mine gallery drilling rig gas extraction blower according to claim 1, is characterized in that: the distance of shaft shoulder place, the location plane of the distance between center line blower construction section (4) of described radial hole is the 1/6-1/2 of blower construction section (4) length.
5. the coupling shaft of a kind of coal mine gallery drilling rig gas extraction blower according to claim 1, is characterized in that: the center line of described axial bore (6) overlaps with the center line of described coupling shaft.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410780052.5A CN104514798A (en) | 2014-12-17 | 2014-12-17 | Connection shaft for gas drainage blower of coal mine underground drill rig |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410780052.5A CN104514798A (en) | 2014-12-17 | 2014-12-17 | Connection shaft for gas drainage blower of coal mine underground drill rig |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104514798A true CN104514798A (en) | 2015-04-15 |
Family
ID=52790541
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410780052.5A Pending CN104514798A (en) | 2014-12-17 | 2014-12-17 | Connection shaft for gas drainage blower of coal mine underground drill rig |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104514798A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114148424A (en) * | 2021-10-28 | 2022-03-08 | 江苏大学 | Small-size crawler-type fire-extinguishing robot |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1924281A (en) * | 2006-09-29 | 2007-03-07 | 重庆科技学院 | Full-hydraulic multifunctional driller for gas extraction, drainage and discharge |
CN200952347Y (en) * | 2006-09-29 | 2007-09-26 | 重庆科技学院 | Chuck and water swivel integrated device for gas drainage full hydraulic drilling machine |
CN201747262U (en) * | 2010-07-29 | 2011-02-16 | 重庆平山矿山机电设备有限公司 | Power head for underground drill rig |
CN101994484A (en) * | 2009-08-29 | 2011-03-30 | 张建平 | Wind-water dual-purpose inserted outburst-prevention drill rod |
CN202117704U (en) * | 2011-05-17 | 2012-01-18 | 重庆创泰矿山机械有限公司 | High pressure prepositive water braid |
CN202176271U (en) * | 2011-06-30 | 2012-03-28 | 郑州光力科技股份有限公司 | Air drill for gas drainage hole and venturi tube joint of air drill |
CN102966319A (en) * | 2012-11-23 | 2013-03-13 | 重庆松藻煤电有限责任公司 | Drill rod detaching device for hydraulic rig |
CN202882782U (en) * | 2012-07-26 | 2013-04-17 | 田召 | Connector of air supply and water supply of drill rod |
CN204357921U (en) * | 2014-12-17 | 2015-05-27 | 河南龙腾新型钻具制造有限公司 | A kind of coupling shaft of coal mine gallery drilling rig gas extraction blower |
-
2014
- 2014-12-17 CN CN201410780052.5A patent/CN104514798A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1924281A (en) * | 2006-09-29 | 2007-03-07 | 重庆科技学院 | Full-hydraulic multifunctional driller for gas extraction, drainage and discharge |
CN200952347Y (en) * | 2006-09-29 | 2007-09-26 | 重庆科技学院 | Chuck and water swivel integrated device for gas drainage full hydraulic drilling machine |
CN101994484A (en) * | 2009-08-29 | 2011-03-30 | 张建平 | Wind-water dual-purpose inserted outburst-prevention drill rod |
CN201747262U (en) * | 2010-07-29 | 2011-02-16 | 重庆平山矿山机电设备有限公司 | Power head for underground drill rig |
CN202117704U (en) * | 2011-05-17 | 2012-01-18 | 重庆创泰矿山机械有限公司 | High pressure prepositive water braid |
CN202176271U (en) * | 2011-06-30 | 2012-03-28 | 郑州光力科技股份有限公司 | Air drill for gas drainage hole and venturi tube joint of air drill |
CN202882782U (en) * | 2012-07-26 | 2013-04-17 | 田召 | Connector of air supply and water supply of drill rod |
CN102966319A (en) * | 2012-11-23 | 2013-03-13 | 重庆松藻煤电有限责任公司 | Drill rod detaching device for hydraulic rig |
CN204357921U (en) * | 2014-12-17 | 2015-05-27 | 河南龙腾新型钻具制造有限公司 | A kind of coupling shaft of coal mine gallery drilling rig gas extraction blower |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114148424A (en) * | 2021-10-28 | 2022-03-08 | 江苏大学 | Small-size crawler-type fire-extinguishing robot |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100593625C (en) | Central cable type high-strength large-through-hole rod | |
CN203961814U (en) | Jumbolter drilling rod quick-connect machanism | |
CN204357921U (en) | A kind of coupling shaft of coal mine gallery drilling rig gas extraction blower | |
CN104514798A (en) | Connection shaft for gas drainage blower of coal mine underground drill rig | |
CN102839973A (en) | Cutting head structure used for heading machine and heading machine | |
CN205370450U (en) | Colliery fire prevention drilling tool for slip casting | |
CN208152957U (en) | Drill bit assembly and driving rock drill | |
CN102337844A (en) | Directional drilling signal transmission drill pipe | |
CN202249812U (en) | Drill rod capable of directional drilling and signal transmission | |
CN204899776U (en) | Dropping assembly | |
EP3854985A1 (en) | Lengthwise section, flexible drill rod and method | |
CN102865045A (en) | Rock drilling quick replacing drilling rod with taper thread | |
CN204591161U (en) | Powerful dust suction drilling rod | |
CN208718560U (en) | Transmission device is driven on rig top, rig top is driven and rig | |
CN207332783U (en) | A kind of combined type oil drilling well drilling bar | |
CN202190049U (en) | Cable connecting seat | |
CN108590541A (en) | Drill bit assembly and driving rock drill | |
CN206448994U (en) | A kind of Coal Mine Ventilator wind pressure detection device | |
CN103495859A (en) | Guiding device for full-automatic screwing device | |
CN203394355U (en) | Positively rotating and reversely cutting PDC combined drill | |
CN104929557A (en) | Anti-dropping strong magnetic fishing rod | |
CN109025797A (en) | Transmission device is driven on rig top, rig top is driven and rig | |
CN204754845U (en) | Prevent falling strong magnetism fishing rod | |
CN203499658U (en) | Waterpower sand blast perforator and nozzle fixing sleeve thereof | |
CN204186303U (en) | With the supporter for turbine drilling tool of PDC thrust bearing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150415 |