CN104500090A - Method for treating coal-mine roadway roof caving by roof filling through foam-material filler - Google Patents

Method for treating coal-mine roadway roof caving by roof filling through foam-material filler Download PDF

Info

Publication number
CN104500090A
CN104500090A CN201410691048.1A CN201410691048A CN104500090A CN 104500090 A CN104500090 A CN 104500090A CN 201410691048 A CN201410691048 A CN 201410691048A CN 104500090 A CN104500090 A CN 104500090A
Authority
CN
China
Prior art keywords
roof
hole
tunnel
mine roadway
coal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410691048.1A
Other languages
Chinese (zh)
Inventor
朱敬
李付臣
程发祥
时萌萌
孔德顺
李华
柳泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yanzhou Coal Mining Co Ltd
Yanzhou Coal Industry Co Ltd
Original Assignee
Yanzhou Coal Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yanzhou Coal Industry Co Ltd filed Critical Yanzhou Coal Industry Co Ltd
Priority to CN201410691048.1A priority Critical patent/CN104500090A/en
Publication of CN104500090A publication Critical patent/CN104500090A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling

Abstract

The invention relates to a method for treating coal-mine roadway roof caving by roof filling through foam-material filler and aims to solve the problems of high construction difficulty, secondary roof caving and gas leak in roof-suspending operation and overhead operation during roadway roof caving treatment. The method includes firstly constructing injection holes obliquely upwards in well-supported section of the roadway in a roof caving area, injecting foaming filling fluid, foaming the filling materials to form an integral solid filler so as to compact and close the roof after reaching pressure intensity. On this basis, an H-shaped steel shed support is erected and can quickly, safely and reliably pass the roof caving area. The method is simple, easy to operate and good in effect and provides reliable guarantee for construction safety.

Description

Expanded material obturation is utilized to connect the method for top process coal mine roadway roof collapse
Technical field
The present invention relates to colliery treatment of roof collapse technical field, is a kind of method utilizing obturation to connect top, the roof fall of Seal treatment colliery.
Background technology
Roof collapse is one of five large disasters of coal production, and roof fall region back is dealt with improperly, again collapsing of top board easily occurs and emits, cause casualties and the damage of equipment, along empty roof fall, easily there is the hidden danger such as pernicious gas exposes, affect the safety in production in colliery.
At present, the method for home and abroad colliery process fall of ground mainly contains: Bolt net and jet note method, metallic support grillage method, wedging method etc.Said method all needs constructor's operation under the back of non-support for a long time, usual roof fall region back lithology is poor, loose crushing, self-bearing capacity are poor, very easily there is roof fall again, cause secondary disaster, as gob side entry roof fall, pernicious gas may be caused to overflow, and therefore the safety of constructor is difficult to ensure.Simultaneously when roof collapse is higher, need to set up scaffold and carry out ascend operation, complex procedures, construction speed is slow, further increases the insecurity of construction.The employing such as metallic support grillage method, wedging method timber carries out connecing to be determined, and it is unreal that existence connects top, and timber holds perishable problem in wet condition.Therefore a kind of simple, safe and reliable coal mine roadway roof collapse processing method is badly in need of.
Summary of the invention
The technical problem to be solved in the present invention is the above-mentioned defect how overcoming prior art, and provide a kind of construction technology simple, speed of application is fast, construction effect is good, safety of workers coefficient is high, and efficiency of construction is high, has the method for the advantages such as anti-secondary roof fall, anti-gas overflowing.
For solving the problems of the technologies described above, this utilizes expanded material obturation to connect the method for top process coal mine roadway roof collapse, comprises the steps:
1.. in roof fall areas outside erection temporary lining, guarantee personnel's operating environment safety;
2.. in the middle of the section of complete tunnel and side direction roof fall region, tunnel two is each makes a call to a material hole, the elongated central line of above-mentioned material hole and horizontal plane angle are 15 ~ 25 ° of angles, deflect in the elongated central alignment tunnel of the material hole of both sides, tunnel, and be 15 ~ 20 ° of angles with the vertical bisector plane angle in tunnel, middle material hole and both sides, tunnel material hole are carried in a row, or emit a region large, can beat and arrange material hole more, array pitch 3 meters, hole depth is as the criterion to penetrate coal rock layer top board
3.. in material hole, install Grouting Pipe, by note rifle to foam-injection type packing fluid in Grouting Pipe, when pressure is increased to 6Mpa in hole, should stop immediately, change hole pressure injection, must not excessive pressure injection, in order to avoid note bad coal body;
4.. in Grouting Pipe lower end, sealer is installed, hole packer insertion depth 1.5 ~ 5m, broken eye or coal dust in boring must be blown off before lower hole packer, prevent from extruding between hole packer and rib sternly not causing spillage,
5.. form overall solid-state charges after foaming, obtain solid top board; Inbreak bastard coal below cleaning roof fall region, and carry out shed shoring.
As optimization, the temporary lining near the normal tunnel section erection in roof fall region is monomer temporary lining, requires that array pitch can not be greater than 800mm.
As optimization, described filling tube is no less than two rows, exposes 100-400mm, guarantees that empty top zone can be filled with.
As optimization, the solid-state charges of described entirety are expansion type packing fluid, require that foaming ratio is not less than 1:15.
The present invention is directed in fall of ground processing procedure, need empty top operation, ascend operation, construction safety is difficult to the problems such as guarantee, first near roof fall district erection hydraulic monomer canopy, provides temporary lining, ensures the safety of operating area; On request material hole is beaten to roof fall region afterwards, and stay and establish filling tube; Finally by the curing materials staying the filling tube established roof fall region to be injected with to intensity, reinforce roof fall region and neighbouring country rock thereof and play confining gas effect, fast, safety, reliably processing coal mine roadway roof collapse.In whole work progress, do not need long-time operation under the top board of inbreak region, do not need ascend operation simultaneously, can fast, safe, reliably process coal mine roadway roof collapse.Its method is simple, and speed is fast, easy to operate, effective, has practicality widely in fall of ground process field.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the method that this utilizes expanded material obturation to connect top process coal mine roadway roof collapse is described further:
Fig. 1 is roof fall regional structure generalized section (moving towards vertical cutting along tunnel);
Fig. 2 is generalized section (moving towards vertical cutting along tunnel) after utilizing obturation process roof fall.
In figure: 1 for roof fall region, 2 for temporary lining, 3 be complete tunnel section, 4 for filling tube, 5 for overall solid-state charges, 6 be bastard coal.
Detailed description of the invention
Embodiment 1: as shown in Figure 1-2, this method utilizing expanded material obturation to connect top process coal mine roadway roof collapse comprises the steps:
1.. outside roof fall region 1, set up temporary lining 2, guarantee personnel's operating environment safety;
2.. in the middle of the section 3 of complete tunnel and side direction roof fall region, tunnel two 1 is each makes a call to a material hole, the elongated central line of above-mentioned material hole and horizontal plane angle are 15 ~ 25 ° of angles, deflect in the elongated central alignment tunnel of the material hole of both sides, tunnel, and be 15 ~ 20 ° of angles with the vertical bisector plane angle in tunnel, middle material hole and both sides, tunnel material hole are carried in a row, or emit a region large, can beat and arrange material hole more, array pitch 3 meters, hole depth is as the criterion to penetrate coal rock layer top board
3.. in material hole, install Grouting Pipe, by note rifle to foam-injection type packing fluid in Grouting Pipe, when pressure is increased to 6Mpa in hole, should stop immediately, change hole pressure injection, must not excessive pressure injection, in order to avoid note bad coal body;
4.. in Grouting Pipe 4 lower end, sealer (not shown) is installed, hole packer insertion depth 1.5 ~ 5m, broken eye or coal dust in boring must be blown off before lower hole packer, prevent from extruding between hole packer and rib sternly not causing spillage,
5.. form overall solid-state charges 5 after foaming, obtain solid top board; Inbreak bastard coal 6 below cleaning roof fall region 1, and carry out shed shoring.
Temporary lining 2 near the normal tunnel section erection in roof fall region 1 is monomer temporary lining, requires that array pitch can not be greater than 800mm.
Described filling tube 4 is no less than two groups, exposes 100-400mm, guarantees that empty top zone can be filled with.
Described expansion type packing fluid can adopt coal mine filling enclosed material (Sai Fute SF-2) or other rigid foam expanded materials, and its foaming ratio is not less than 1:15, and namely before and after foaming, volume ratio is 1:15.

Claims (4)

1. utilize expanded material obturation to connect a method for top process coal mine roadway roof collapse, comprise the steps:
1.. in roof fall region (1) outside erection temporary lining (2), guarantee personnel's operating environment safety;
2.. in the middle of complete tunnel section (3) and side direction roof fall region, tunnel two (1) is each makes a call to a material hole, the elongated central line of above-mentioned material hole and horizontal plane angle are 15 ~ 25 ° of angles, deflect in the elongated central alignment tunnel of the material hole of both sides, tunnel, and be 15 ~ 20 ° of angles with the vertical bisector plane angle in tunnel, middle material hole and both sides, tunnel material hole are carried in a row, or emit a region large, can beat and arrange material hole more, array pitch 3 meters, hole depth is as the criterion to penetrate coal rock layer top board
3.. in material hole, install Grouting Pipe, by note rifle in Grouting Pipe, foam-injection type packing fluid, when pressure is increased to 6Mpa in hole, should stop immediately, change hole pressure injection, must not excessive pressure injection, in order to avoid note bad coal body;
4.. in Grouting Pipe lower end, sealer is installed, hole packer insertion depth 1.5 ~ 5m, broken eye or coal dust in boring must be blown off before lower hole packer, prevent from extruding between hole packer and rib sternly not causing spillage,
5.. form overall solid-state charges (5) after foaming, obtain solid top board; Cleaning roof fall region (1) below inbreak bastard coal (6), and carry out shed shoring.
2. utilize expanded material obturation to connect the method for top process coal mine roadway roof collapse as claimed in claim 1, it is characterized in that: the temporary lining (2) near the normal tunnel section erection in roof fall region (1) is monomer temporary lining, requires that array pitch can not be greater than 800mm.
3. utilize expanded material obturation to connect the method for top process coal mine roadway roof collapse as claimed in claim 1, it is characterized in that: described filling tube (4) is no less than two rows, exposes 100-400mm, guarantee that empty top zone can be filled with.
4. utilize expanded material obturation to connect the method for top process coal mine roadway roof collapse as claimed in claim 1, it is characterized in that: expansion type packing fluid foaming ratio is not less than 1:20.
CN201410691048.1A 2014-11-25 2014-11-25 Method for treating coal-mine roadway roof caving by roof filling through foam-material filler Pending CN104500090A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410691048.1A CN104500090A (en) 2014-11-25 2014-11-25 Method for treating coal-mine roadway roof caving by roof filling through foam-material filler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410691048.1A CN104500090A (en) 2014-11-25 2014-11-25 Method for treating coal-mine roadway roof caving by roof filling through foam-material filler

Publications (1)

Publication Number Publication Date
CN104500090A true CN104500090A (en) 2015-04-08

Family

ID=52941529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410691048.1A Pending CN104500090A (en) 2014-11-25 2014-11-25 Method for treating coal-mine roadway roof caving by roof filling through foam-material filler

Country Status (1)

Country Link
CN (1) CN104500090A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888708A (en) * 2016-06-28 2016-08-24 金英子 Roadway roof-fall zone detection and processing method based on radar detection technique
CN105909285A (en) * 2016-06-28 2016-08-31 冯飞燕 Roof fall judgment and penetration method based on surrounding rock quality designations
CN106089246A (en) * 2016-06-28 2016-11-09 孙姗姗 A kind of fall of ground disaster restorative procedure based on grouted anchor bar
CN106121679A (en) * 2016-06-28 2016-11-16 孙姗姗 A kind of processing method of underworkings roof fall
CN107654238A (en) * 2017-09-15 2018-02-02 中国矿业大学 A kind of processing method for having dug fall of ground
CN109446659A (en) * 2018-10-31 2019-03-08 华北科技学院 A kind of method that integrated forecasting heading emits heights of roofs and hidden danger classification

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101487392A (en) * 2008-01-16 2009-07-22 中国神华能源股份有限公司 House pillar type coal mining method
CN101864970A (en) * 2010-01-29 2010-10-20 中国科学院武汉岩土力学研究所 Method for supporting and protecting soft, collapsible and super thick coal seam tunnel based on filling behind support and device thereof
CN102702675A (en) * 2012-01-05 2012-10-03 北京东方雨虹防水技术股份有限公司 Chemical grouting filling seal material for coal mine, and preparation method and application method thereof
CN103061788A (en) * 2013-01-11 2013-04-24 江苏建筑职业技术学院 Loose broken tunnel top plate reinforcing and supporting method
CN103321654A (en) * 2013-07-04 2013-09-25 中国矿业大学 Method for managing roof collapse of coal mine roadway by aid of flexible air bags

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101487392A (en) * 2008-01-16 2009-07-22 中国神华能源股份有限公司 House pillar type coal mining method
CN101864970A (en) * 2010-01-29 2010-10-20 中国科学院武汉岩土力学研究所 Method for supporting and protecting soft, collapsible and super thick coal seam tunnel based on filling behind support and device thereof
CN102702675A (en) * 2012-01-05 2012-10-03 北京东方雨虹防水技术股份有限公司 Chemical grouting filling seal material for coal mine, and preparation method and application method thereof
CN103061788A (en) * 2013-01-11 2013-04-24 江苏建筑职业技术学院 Loose broken tunnel top plate reinforcing and supporting method
CN103321654A (en) * 2013-07-04 2013-09-25 中国矿业大学 Method for managing roof collapse of coal mine roadway by aid of flexible air bags

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刘钧: "煤矿巷道冒顶区的加固充填技术", 《内蒙古煤炭经济》 *
卞正荣等: "用罗克休、马丽散充填加固技术处理巷道冒顶", 《煤炭科技》 *
张洪涛: "瑞米充填加固技术处理巷道冒顶", 《科技信息》 *
谢劲峰: "马丽散加固充填技术在处理冒顶中的应用", 《煤炭技术》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888708A (en) * 2016-06-28 2016-08-24 金英子 Roadway roof-fall zone detection and processing method based on radar detection technique
CN105909285A (en) * 2016-06-28 2016-08-31 冯飞燕 Roof fall judgment and penetration method based on surrounding rock quality designations
CN106089246A (en) * 2016-06-28 2016-11-09 孙姗姗 A kind of fall of ground disaster restorative procedure based on grouted anchor bar
CN106121679A (en) * 2016-06-28 2016-11-16 孙姗姗 A kind of processing method of underworkings roof fall
CN107654238A (en) * 2017-09-15 2018-02-02 中国矿业大学 A kind of processing method for having dug fall of ground
CN109446659A (en) * 2018-10-31 2019-03-08 华北科技学院 A kind of method that integrated forecasting heading emits heights of roofs and hidden danger classification

Similar Documents

Publication Publication Date Title
CN104500090A (en) Method for treating coal-mine roadway roof caving by roof filling through foam-material filler
CN102536239B (en) Long-wall working face coal pillar-free mining method
CN109763822A (en) Face in steep thick coal seam Multi sectional is without coal column placement method between coal column staggered floor Hu Xiang and section
CN103775084B (en) High inclination-angle, mining height workface equipment cross geological structure crushed zone construction technology
CN109763861B (en) Roof fall processing method for fault fracture zone in incision
CN104632219A (en) Large mining height gob-side entry retaining method for thick coal seams
CN207073410U (en) The anti-reflection system of injection hot water and liquid nitrogen is circulated to coal seam
CN107120137B (en) A kind of coal roadway tunneling is along seat earth Deephole pre-splitting blasting pumping method
CN110130978B (en) Method for plugging broken coal side of thick coal seam in broken area of filling and re-mining small kiln
CN104100271B (en) Pre-pick is led cave filling artificial side secondary multiplexing roadside support and is become lane method
CN103835723A (en) Comprehensive pretreatment method for shaft penetration in mined-out area stratum
CN105863639A (en) Coal-mining method of loose coal seam
CN105804786A (en) Method for layer penetrating, drilling, pressing punching and permeability improving of soft coal seam floor
Li et al. Trial of small gateroad pillar in top coal caving longwall mining of large mining height
CN104727847B (en) Filled wall is from the gob-side entry retaining method without coal column eliminated
CN103089277A (en) Space reinforcing construction technology of sand layer roadway
CN108442953B (en) Using the coal mine roadway roof collapse area processing method of the radar exploration technique and grouted anchor bar
CN110566236A (en) Pipe shed and steel support combined supporting device and supporting method
CN110566238A (en) Mud rock roof small coal pillar gob-side roadway supporting structure and method thereof
CN106150522A (en) A kind of top board utilizing inspection instrument for borehole detection Collapsed zone subsides administering method
CN111022050B (en) Fully-closed blasting pressure relief and self-retained roadway method for grouting reconstruction of composite roof
CN106761841A (en) Working face tailgate fractured coal grouting reinforcement method
CN110552731A (en) top coal caving stoping roadway grouting anchor cable supporting structure and advanced supporting method thereof
CN106121678B (en) A kind of detection of top plate empty top zone and roadway repair method based on the radar exploration technique
CN210622819U (en) Pipe shed and steel support combined supporting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150408

RJ01 Rejection of invention patent application after publication