CN104459378B - A kind of intelligent substation method for diagnosing faults - Google Patents
A kind of intelligent substation method for diagnosing faults Download PDFInfo
- Publication number
- CN104459378B CN104459378B CN201410665071.3A CN201410665071A CN104459378B CN 104459378 B CN104459378 B CN 104459378B CN 201410665071 A CN201410665071 A CN 201410665071A CN 104459378 B CN104459378 B CN 104459378B
- Authority
- CN
- China
- Prior art keywords
- information
- failure
- alarm
- hypothesis
- breaker
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
A kind of intelligent substation method for diagnosing faults, is carried out by following 10 steps:Step 1:Gather each variable of failure hypothesis vector;Step 2:Networking modeling analysis;Step 3:Sample matrix is set up to be estimated;Step 4:Calculate the corresponding target function value of failure hypothesis;Step 5:Judge whether to meet end condition;Step 6:Obtain correct failure hypothesis;Step 7:The alarm state received in practice;Step 8:Comparison information;Step 9:The alarm failing to report or report by mistake, the breaker of malfunction tripping;Step 10:Defect elimination is carried out to failure, recovers normal operation.Present invention reduces the management cost of power system, backward, outmoded artificial accident analysis and tupe are changed, the man power and material of intelligent substation operation, the production cost reduced is greatly reduced, operating efficiency is improved, is that intelligent substation construction and operation provide technical support.
Description
Technical field
The invention belongs to electricity field, more particularly to a kind of intelligent substation method for diagnosing faults.
Background technology
Intelligent substation is to use advanced, reliable, integrated and environmentally friendly smart machine, with whole station information digitalization, communication
Platform network, information sharing are standardized as basic demand, are automatically performed information gathering, measurement, control, protection, metering and examine
The basic function such as survey, meanwhile, possess support power network automatically control in real time, Intelligent adjustment, on-line analysis decision-making and collaboration interaction etc.
The transformer station of Premium Features.Intelligent substation mainly includes intelligent high-voltage equipment and transformer station's integration information platform two parts.Intelligence
Energy high-tension apparatus mainly includes intelligent transformer, Intelligent high voltage switch device, electronic mutual inductor etc..Intelligent transformer and control
System is connected by telecommunication optical fiber, and transformer state parameter and service data can be grasped in time.When the method for operation changes,
Voltage, power situation of the equipment according to system, decide whether to adjust tap;When equipment goes wrong, early warning can be sent simultaneously
State parameter etc. is provided, operational management cost is reduced to a certain extent, hidden danger is reduced, transformer station high-voltage side bus reliability is improved.Intelligence
Energy high-tension switch gear is switchgear and control device with superior performance, equipped with electronic equipment, sensor and actuator,
With monitoring and diagnostic function.Electronic mutual inductor refers to pure optical fiber mutual inductor, magneto-optic glass transformer etc., can effectively overcome biography
The shortcoming of system electromagnetic transformer.Transformer station's integration information platform function has two, and one is the horizontal information sharing of system, main table
Now information acquisition is unitized for various upper layer applications in management system;Two be the standardization of the longitudinal information of system, main table
The transparence now supported for each layer to its upper layer application.
Intelligent substation contacts hinge as control centre and transformer station, directly facing the O&M of system operation and equipment
Management, integrate commander, scheduling, monitoring, operate, its operation and intelligent decision-making level to raising power system self-healing ability
And the reliability of power supply plays an important role.But the research of current alarm processing, fault diagnosis and accident treatment is mostly concentrated on
Electric power system dispatching center or transformer station, the research of the power system alarm processing such as based on analytic modell analytical model, based on artificial god
Research through metanetwork power system failure diagnostic, the research of Stackelberg Decision for Power System Restoration based on many agent.On
State research and certain breakthrough is obtained in terms of theoretical research, some are even applied in systems in practice.And base
Extremely lack in the method for diagnosing faults and the theory of accident treatment of intelligent substation and its application study.
On the other hand, when occurring accident, intelligent substation will often receive alarm up to hundreds of, person on duty in tens seconds
Found by the Substation Bus Arrangement of monitoring system and determine accident impact scope, it is determined that and recording the breaker disconnected and protecting dynamic
Make information, and be distributed to all departments, reporting scheduling, while carrying out crash analysis;Teams and groups operations staff, according on all messages
Information is passed, tripping operation, protection act situation rule of thumb analyze cause of accident substantially, urgent referral patrols fibrillar center personnel on site
Check.Because quantities of messages is excessive, accident treatment needs to complete within short a few minutes again, and the electric power that monitoring personnel relies on is known
Know and experience is difficult timely and effective failure correctly to be judged.
The content of the invention
In order to solve the above problems, the present invention provides a kind of intelligent substation method for diagnosing faults, the invention is characterised in that,
Carried out by following 10 steps:
Step 1:Gather each variable of failure hypothesis vector;
Correlation logic between relay protection, breaker actuation, various warning messages is gathered, intelligent substation is mainly just gathered
The breaker actuation alarm inside relay protection information and real time data Data2 inside internal stationary data Data1;
Step 2:Networking modeling analysis;
The information classification that step 1 is collected is 4 classes:Crucial warning information, relay protection information, reason event and outlet
Breaker information;
Step 3:Sample matrix is set up to be estimated;
It is to screen and reject the weak information of correlation to set up the purpose that sample matrix is estimated, and improves the standard of collection information
True property and importance;
Assuming that having n+m information in intelligent substation, n is relay protection information (B1~B6), and m is outlet breaker information
(D1~D6), the business reasons hits within the period is k (C1~C5);Set up sample matrix:
Wherein vector ViRegard a sample group of SPACE V as, then sample group quantity is n in V, and dimension is k;
Assuming that sample group is divided into c class, i.e., a c group of planes.If clustering number of times is t (t >=1, t ∈ N), when initial
T=1 is made, any selection c (1≤c≤n) individual sample groups are used as c class G from all sample groupsp(p=1,2 ..., c) initial
Cluster centre
Then any one sample group ViEuclidean distance to c cluster centre is
For any one sample group Vi, alwaysOne(p=1,2 ..., c) makeMinimum is reached, then
By ViIt is divided into class GpIn;
All sample groups have been traveled through, 1 clustering is completed.Define the square error summation of cluster:
As the index for assessing similitude in class, by E(t)> 1 data are all rejected.Following steps only calculate E(t)≤1
Data;
Step 4:Calculate the corresponding target function value of failure hypothesis.
Initial signal for accident is acted with live tank circuit breakers separating brake;Whether powered analyzed by topological structure of breaker is carried out
Once power supply interrupted district identification accident occurs, all possible reason event composition event of warning information searching after intelligently filters is utilized
Hinder hypothesis collection, thus failure cause Solve problems are expressed as without constraint Zero-one integer programming problem;
IfTo actually receive the letter of the critical alert after intelligent alarm processing
Breath collection, wherein aiWithFor breaker actuation information and time of origin, bmWithProtection act information and time of origin.To expect the critical alert information collection received.Failure hypothesis collection H is institute
Possible reason event sets;
Object function Fobj (Hi) be used to weigh certain failure hypothesis H in failure hypothesis collection HiReasonability, object function is:
Fobj(Hi)=min (w1|▽M(Hi)|+w2|T(Hi)|+w3|Hi|)
Wherein, alarm coverage index ▽ M (Hi) it is K dimensional vectors (K is warning information sum);|▽M(Hi) | reflect event
Hinder hypothesis HiCorrespondence expects that alarm can not cover the number of actual alarm information;I.e. failure assumes HiThe live coverage with alarm,
Its value is smaller, it is meant that a covering of the failure hypothesis closer to failure virtual condition;Failure hypothesis diversity factor index T (Hi)
For K dimensional vectors, | T (Hi) | reflection actual alarm information and failure assume HiCorresponding expectation alarm aggregation M*(H) diversity factor, |
T(Hi) | it is smaller, it is meant that faulty equipment, malfunction or the protection of tripping and fewer, the failure hypothesis H of breaker sumiConfidence level
It is higher;
Step 5:Judge whether to meet end condition;
Optimizing solution is carried out to the object function without constraint Zero-one integer programming problem of above-mentioned formation, finally given optimal
Solve Hbest, confidence level highest failure hypothesis, function Fobj (H can be obtainedi) there is optimal solution to meet end condition, meet condition
Go to step 6;If function Fobj (Hi) 3 are then gone to step without optimal solution, proceed to set up fault sample matrix and be estimated, reject
Gross error;
Step 6:Obtain correct failure hypothesis;
Correct failure hypothesis is now obtained, i.e., correct failure hypothesis correspondingly expects each alarm state received
Step 7:The alarm state received in practice;
The real protection actionable alarms provided inside intelligent substation inside real time data Data2 are provided.
Step 8:Comparison information;
The information of step 6 and step 7 is compared, diagnostic result is exported.
Step 9:The alarm failing to report or report by mistake, the breaker of malfunction tripping;
According to resulting diagnostic result, you can judge to fail to report and report by mistake, malfunction, tripping breaker;Its judgment principle is:
Have in expecting and actually do not occur as failing to report or breaker tripping;And do not actually occurred in expecting as wrong report or breaker malfunction;
Step 10:Defect elimination is carried out to failure, recovers normal operation;
After accident diagnosis result comes out, according to the result of step 9, defect elimination is carried out to failure, intelligence rapidly carries out accident
Processing, recovers normal operation.
The present invention compared with the existing technology, with advantages below and beneficial effect:The present invention proposes the event of intelligent substation
Architecture feature of the barrier processing diagnostic method according to intelligent substation, two-dimentional classification is carried out emphatically to warning information, is set up
Fault sample matrix is estimated, reject weak relevant information, intelligently filters alarm processing, the flow framework of fault diagnosis algorithm and
Principle is described in detail, and demonstrates validity of the present invention and feasibility by embodiment.Present invention reduces power system
Management cost, change fall behind, outmoded artificial accident analysis and tupe, greatly reduce intelligent substation operation
Man power and material, the production cost reduced, improves operating efficiency, is national " 13 " intelligent substation construction and operation
There is provided technical support.
Brief description of the drawings
Fig. 1 is a kind of step flow chart of intelligent substation method for diagnosing faults of the invention;
Fig. 2 is the topology diagram of step 3 networking modeling analysis of the present invention;
Fig. 3 is the electrical structure diagram of embodiment of the present invention.
Embodiment
Below in conjunction with accompanying drawing, technical scheme is clearly and completely described.
As shown in figure 1, a kind of intelligent substation method for diagnosing faults, the invention is characterised in that, enter by following 10 steps
OK:
Step 1:Gather each variable of failure hypothesis vector;
Correlation logic between relay protection, breaker actuation, various warning messages is gathered, intelligent substation is mainly just gathered
The breaker actuation alarm inside relay protection information and real time data Data2 inside internal stationary data Data1;
Step 2:Networking modeling analysis;
The information classification that step 1 is collected is 4 classes:Crucial warning information, relay protection information, reason event and outlet
Breaker information;
Step 3:Sample matrix is set up to be estimated;
It is to screen and reject the weak information of correlation to set up the purpose that sample matrix is estimated, and improves the standard of collection information
True property and importance;
Assuming that having n+m information in intelligent substation, n is relay protection information (B1~B6), and m is outlet breaker information
(D1~D6), the business reasons hits within the period is k (C1~C5);Set up sample matrix:
Wherein vector ViRegard a sample group of SPACE V as, then sample group quantity is n in V, and dimension is k;
Assuming that sample group is divided into c class, i.e., a c group of planes.If clustering number of times is t (t >=1, t ∈ N), when initial
T=1 is made, any selection c (1≤c≤n) individual sample groups are used as c class G from all sample groupsp(p=1,2 ..., c) initial
Cluster centre
Then the Euclidean distance of any one sample group Vi to c cluster centres is
For any one sample group Vi, alwaysOne(p=1,2 ..., c) makeMinimum is reached, then
By ViIt is divided into class GpIn;
All sample groups have been traveled through, 1 clustering is completed.Define the square error summation of cluster:
As the index for assessing similitude in class, by E(t)> 1 data are all rejected.Following steps only calculate E(t)≤1
Data;
Step 4:Calculate the corresponding target function value of failure hypothesis.
Initial signal for accident is acted with live tank circuit breakers separating brake;Whether powered analyzed by topological structure of breaker is carried out
Once power supply interrupted district identification accident occurs, all possible reason event composition event of warning information searching after intelligently filters is utilized
Hinder hypothesis collection, thus failure cause Solve problems are expressed as without constraint Zero-one integer programming problem;
IfTo actually receive the letter of the critical alert after intelligent alarm processing
Breath collection, wherein aiWithFor breaker actuation information and time of origin, bmWithProtection act information and time of origin.To expect the critical alert information collection received;Failure hypothesis collection H is institute
Possible reason event sets;
Object function Fobj (Hi) be used to weigh certain failure hypothesis H in failure hypothesis collection HiReasonability, object function is:
Fobj(Hi)=min (w1|▽M(Hi)|+w2|T(Hi)|+w3|Hi|)
Wherein, alarm coverage index ▽ M (Hi) it is K dimensional vectors (K is warning information sum);|▽M(Hi) | reflect event
Barrier hypothesis Hi correspondences expect that alarm can not cover the number of actual alarm information;I.e. failure assumes HiThe live covering with alarm
Degree, its value is smaller, it is meant that a covering of the failure hypothesis closer to failure virtual condition;Failure hypothesis diversity factor index T
(Hi) it is K dimensional vectors, | T (Hi) | reflection actual alarm information and failure assume HiCorresponding expectation alarm aggregation M*(H) difference
Degree, | T (Hi) | it is smaller, it is meant that faulty equipment, malfunction or the protection of tripping and fewer, the failure hypothesis H of breaker sumiCan
Reliability is higher;
Step 5:Judge whether to meet end condition;
Optimizing solution is carried out to the object function without constraint Zero-one integer programming problem of above-mentioned formation, finally given optimal
Solve Hbest, confidence level highest failure hypothesis, function Fobj (H can be obtainedi) there is optimal solution to meet end condition, meet condition
Go to step 6;If function Fobj (Hi) 3 are then gone to step without optimal solution, proceed to set up fault sample matrix and be estimated, reject
Gross error;
Step 6:Obtain correct failure hypothesis;
Correct failure hypothesis is now obtained, i.e., correct failure hypothesis correspondingly expects each alarm state received
Step 7:The alarm state received in practice;
The real protection actionable alarms provided inside intelligent substation inside real time data Data2 are provided.
Step 8:Comparison information;
The information of step 6 and step 7 is compared, diagnostic result is exported.
Step 9:The alarm failing to report or report by mistake, the breaker of malfunction tripping;
According to resulting diagnostic result, you can judge to fail to report and report by mistake, malfunction, tripping breaker;Its judgment principle is:
Have in expecting and actually do not occur as failing to report or breaker tripping;And do not actually occurred in expecting as wrong report or breaker malfunction;
Step 10:Defect elimination is carried out to failure, recovers normal operation;
After accident diagnosis result comes out, according to the result of step 9, defect elimination is carried out to failure, intelligence rapidly carries out accident
Processing, recovers normal operation.
For the clearly explanation above method, analyzed with the following Examples.
Embodiment:Certain 220kV transformer stations 1M buses physical fault is case, verifies fault diagnosis side proposed by the invention
Method.The running status of power network is as shown in Figure 3 before failure.
Original message 110 was received within 60 seconds, using method proposed by the present invention to warning information compress filtering and
After merging treatment, nearly ten are reduced to, obtained critical alarms information is as shown in table 1, the corresponding networking modeling analysis such as institute of table 2
Show, as shown in table 3, related breaker and numbering are as shown in table 4 for event code the reason for related, analysis institute's relative breaker and
Message coding is as shown in table 5.
Table 1:The critical alarms information received
Table 2:Corresponding networking modeling analysis
Sequence number | Protect name | Reason event | Outlet breaker |
A1 | B1 | C11 | D1~D5 |
A2 | B1 | C11 | D1~D5 |
A3 | B2 | C1~C14 | D6 |
A3 | B3 | C1~C14 | D6 |
A4 | B2 | C1~C14 | D5 |
A4 | B3 | C1~C14 | D5 |
A5 | B2 | C1~C6, C11~C14 | D4 |
A5 | B3 | C1~C6, C11~C14 | D4 |
A1 | B1 | C12 | D5~D7, D8~D10 |
A2 | B2 | C12 | D5~D7, D8~D10 |
Wherein each symbol is so representative and its implication are as follows:
B1 zero-sequencedirectional protection B2 overcurrent protection B3 bus differential protections
Table 3:Related the reason for event code
Table 4:Related breaker and numbering
Numbering | Breaker name | Numbering | Breaker name |
D1 | 4736 breakers | D2 | 4738 breakers |
D3 | 4740 breakers | D4 | 2012 breakers |
D5 | 2015 breakers | D6 | 2026 breakers |
The related crucial alarm of analysis and its outlet breaker
Table 5:Analyze institute's relative breaker and message coding
Failure hypothesis vector:H=[c1, c2, c3, c4, c5, c6, c7, c8, c9, c10, c11, c12, c13, c14] is represented
Whether each reason event really occurs, and there occurs then ci=1, does not occur to be then 0.The alarm aggregation actually received:Relay protection
Action message A1~A5 and breaker D1~D6 action message:A6~A11.
Expect alarm aggregation:Corresponding to the different values of each failure hypothesis, different expectation alarms are had, are occurred with c12
Exemplified by, illustrate the calculating process of the target function value of failure hypothesis.Each coefficient, w in object function calculation formula1, w2, w3Respectively
For 10000,10,1.If c12=1, remaining ci=0 (i ≠ 12) is 0, calculates its corresponding expectation.C12 is in mixing rule net
Obtain the protection correspondence of all crucial warning information, outlet breaker, its triggering of its corresponding " 220kV 2M bus-bar faults "
Message, collectively constitute C11 it is corresponding expectation, including:A1, A2, A3, A4, A5, A9, A10, A11, A12, A13, A14, A15.
Expectation state and virtual condition are substituted into formula and calculate ▽ M (H)=30000, T (H)=70, | H |=1, Fobj (Hi)=
30071。
The result of other failure hypothesis also can class this calculating, program analysis after, the result for obtaining optimization is:C11=
1, ci=0 (i ≠ 11), i.e. 220kV 1M bus-bar faults, during the object function corresponding to it is asked for, expect alarm and reality
Alarm is completely superposed, and the number that the failure hypothesis vector reason event after coincidence occurs is 1, is optimal solution.
Analysis process in the case of information is imperfect:Assuming that having leaked certain two message in the alarm received:A2220kV1M-
The BP-2B of 2M bus differential protections two;The breaker actuation of A6220kV Yunnan Shandong III lines 4736.Its analysis method is consistent with above procedure, by
Table 2 understands that element contained by its failure hypothesis H is constant;Object function is calculated, in upper section case consistent with the method normally calculated
Optimal solution c11=1, remaining ci=0 (i ≠ 11) is 0, due to not receiving A2, and A6, and the object function that correspondence is obtained can become
Greatly, its desired value can be tried to achieve:Coverage is 0, and diversity factor is 2 × 10=20, obtains Fobj (Hi)=21, and pass through sequential operation knot
Fruit understands that this is minimum value, and fault diagnosis result is still 220kV 1M bus-bar faults, meets the end condition of the step 5, turns
Step 6, that is, correct failure hypothesis is obtained.
Draw after result above, according to analysis principle program may recognize that A2 is misses alarm, and A6 is to breaker just
For the breaker of tripping.
According to fault diagnosis result:The eastern regions of the Yunnan Province intelligent station 220kV 1M bus-bar faults, search the eastern regions of the Yunnan Province intelligent station bus automatically
The accident treatment prediction scheme of failure, technical staff starts out at once carry out troubleshooting.
Present invention employs advanced reliable, safe diagnostic method, be conducive to strengthen marketing, transformer station operation and
Aggregate level is lifted, is that power supply enterprise and company explore and save a large amount of human and material resources, makes intelligent substation operating cost saving
More than 60%.
Claims (1)
1. a kind of intelligent substation method for diagnosing faults, it is characterised in that carried out by following 10 steps:
Step 1:Gather each variable of failure hypothesis vector;
Correlation logic between relay protection, breaker actuation, various warning messages is gathered, intelligent substation internal stationary number is gathered
According to the breaker actuation warning information inside the relay protection information inside Data1 and real time data Data2;
Step 2:Networking modeling analysis;
The information classification that step 1 is collected is 4 classes:Crucial warning information, relay protection classification information, reason event and outlet
Breaker information;
Step 3:Sample matrix is set up to be estimated;
It is to screen and reject the weak information of correlation to set up the purpose that sample matrix is estimated, and improves the accuracy of collection information
And importance;
Assuming that having jbn+jbm information in intelligent substation, jbn is relay protection classification information (B1~B6), and jbm is disconnected for outlet
Road device information (D1~D6), in the information and real time data Data2 inside collection intelligent substation internal stationary data Data1
The reason for information time section in face, event hits was n × k (C1~C5);Set up sample matrix:
Wherein vector ViRegard a sample group of SPACE V as, then sample group quantity is n in V, and dimension is k;
Assuming that sample group is divided into c class, i.e., a c group of planes;If clustering number of times is t, t >=1, t ∈ N, initial season t=
1, arbitrarily c sample group of selection is used as c class G from all sample groupsp, in 1≤c≤n, p=1,2 ..., c initial clustering
The heart
Then any one sample group ViEuclidean distance to c cluster centre is
For any one sample group Vi, alwaysP=1,2 ..., c, makesMinimum is reached, then by Vi
It is divided into class GpIn;
All sample groups have been traveled through, 1 clustering is completed;Define the square error summation of cluster:
As the index for assessing similitude in class, by E(t)> 1 data are all rejected;Following steps only calculate E(t)≤ 1 number
According to;
Step 4:Calculate the corresponding target function value of failure hypothesis;
Initial signal for accident is acted with live tank circuit breakers separating brake;Once accident occurs, check whether breaker is powered, and by
Analysis of Topological Structure recognizes power supply interrupted district;Utilize all possible reason event composition event of warning information searching after intelligently filters
Hinder hypothesis collection, thus failure cause Solve problems are expressed as without constraint Zero-one integer programming problem;
IfTo actually receive the critical alert information collection after intelligent alarm processing,
Wherein aprWithFor breaker actuation information and time of origin, bqWithProtection act information and time of origin;To expect the critical alert information collection received;Failure hypothesis collection H is institute
Possible reason event sets;
Object function Fobj (Hif) be used to weigh certain failure hypothesis H in failure hypothesis collection HifReasonability, object function is:
Wherein, alarm coverage indexFor K dimensional vectors, K is warning information sum;Reflect failure hypothesis HifIt is right
It should it is expected that alarm can not cover the number of actual alarm information, i.e. failure hypothesis HifThe live coverage with alarm, its value is smaller,
Mean a covering of the failure hypothesis closer to failure virtual condition;Failure hypothesis diversity factor index T (Hif) for K tie up to
Amount, | T (Hif) | reflection actual alarm information and failure hypothesis HifCorresponding expectation alarm aggregation M*(H) diversity factor, | T (Hif)
| it is smaller, it is meant that faulty equipment, malfunction or the protection of tripping and fewer, the failure hypothesis H of breaker sumifConfidence level it is higher;
Step 5:Judge whether to meet end condition;
Optimizing solution is carried out to the object function without constraint Zero-one integer programming problem of above-mentioned formation, optimal solution is finally given
Hbest, confidence level highest failure hypothesis, function Fobj (H can be obtainedif) there is optimal solution to meet end condition, meet condition and turn
Step 6;If function Fobj (Hif) 3 are then gone to step without optimal solution, continue to set up fault sample matrix being estimated, reject thick mistake
Difference;
Step 6:Obtain correct failure hypothesis;
Correct failure hypothesis is now obtained, i.e., correct failure hypothesis correspondingly expects each alarm state received;
Step 7:The alarm state received in practice;
The real protection breaker actuation warning information provided inside intelligent substation inside real time data Data2 is provided;
Step 8:Comparison information;
The information of step 6 and step 7 is compared, diagnostic result is exported;
Step 9:The alarm failing to report or report by mistake, the breaker of malfunction tripping;
According to resulting diagnostic result, you can judge to fail to report and report by mistake, malfunction, tripping breaker;Its judgment principle is:Expect
In have, it is and actual when not occurring, be judged to fail to report or breaker tripping;Do not have in expecting, and actually occur, be judged to report by mistake or break
Road device malfunction;
Step 10:Defect elimination is carried out to failure, recovers normal operation;
After accident diagnosis result comes out, according to the result of step 9, defect elimination is carried out to failure, intelligence rapidly carries out accident treatment,
Recover normal operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410665071.3A CN104459378B (en) | 2014-11-19 | 2014-11-19 | A kind of intelligent substation method for diagnosing faults |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410665071.3A CN104459378B (en) | 2014-11-19 | 2014-11-19 | A kind of intelligent substation method for diagnosing faults |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104459378A CN104459378A (en) | 2015-03-25 |
CN104459378B true CN104459378B (en) | 2017-07-28 |
Family
ID=52905748
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410665071.3A Active CN104459378B (en) | 2014-11-19 | 2014-11-19 | A kind of intelligent substation method for diagnosing faults |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104459378B (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104764979A (en) * | 2015-03-30 | 2015-07-08 | 国网河南省电力公司经济技术研究院 | Virtual information fusion power grid alarming method based on probabilistic reasoning |
CN106290709A (en) * | 2015-06-02 | 2017-01-04 | 齐鲁工业大学 | A kind of transformer station gas wireless monitor alarm control method |
CN105427043A (en) * | 2015-11-20 | 2016-03-23 | 江苏省电力公司扬州供电公司 | Improved nearest neighbor algorithm-based power grid alarm analysis method |
CN106597845B (en) * | 2016-11-09 | 2019-04-16 | 同济大学 | A kind of power transmission network method for diagnosing faults based on multiple-objection optimization |
CN110336382A (en) * | 2019-08-01 | 2019-10-15 | 广东电网有限责任公司 | A kind of confirmation method, device, equipment and the medium of electric network fault warning information |
CN111951124B (en) * | 2020-08-10 | 2024-03-19 | 国网山西省电力公司 | Power distribution automation terminal alarm defect identification method based on power supply traceability array |
CN113097981B (en) * | 2021-03-15 | 2022-03-25 | 国网江苏省电力有限公司南通供电分公司 | Method for judging missing of monitoring alarm signal of transformer substation |
CN117172796A (en) * | 2023-08-07 | 2023-12-05 | 北京智慧大王科技有限公司 | Big data electronic commerce management system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102938587A (en) * | 2012-12-10 | 2013-02-20 | 上海市电力公司 | Intelligent power grid safety and stability early-warning and control method |
CN103293421A (en) * | 2013-06-07 | 2013-09-11 | 云南电力调度控制中心 | Power grid fault diagnostic model and diagnostic method thereof |
CN103324845A (en) * | 2013-06-13 | 2013-09-25 | 国电南瑞科技股份有限公司 | Intelligent substation switch state estimation method based on uncertainty reasoning |
CN103617561A (en) * | 2013-12-02 | 2014-03-05 | 深圳供电局有限公司 | System and method for evaluating state of secondary equipment of power grid intelligent substation |
CN103630869A (en) * | 2013-11-29 | 2014-03-12 | 国网安徽省电力公司 | Clustering algorithm-based exceptional event analysis method for evaluating whole state of electric meter |
-
2014
- 2014-11-19 CN CN201410665071.3A patent/CN104459378B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102938587A (en) * | 2012-12-10 | 2013-02-20 | 上海市电力公司 | Intelligent power grid safety and stability early-warning and control method |
CN103293421A (en) * | 2013-06-07 | 2013-09-11 | 云南电力调度控制中心 | Power grid fault diagnostic model and diagnostic method thereof |
CN103324845A (en) * | 2013-06-13 | 2013-09-25 | 国电南瑞科技股份有限公司 | Intelligent substation switch state estimation method based on uncertainty reasoning |
CN103630869A (en) * | 2013-11-29 | 2014-03-12 | 国网安徽省电力公司 | Clustering algorithm-based exceptional event analysis method for evaluating whole state of electric meter |
CN103617561A (en) * | 2013-12-02 | 2014-03-05 | 深圳供电局有限公司 | System and method for evaluating state of secondary equipment of power grid intelligent substation |
Also Published As
Publication number | Publication date |
---|---|
CN104459378A (en) | 2015-03-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104459378B (en) | A kind of intelligent substation method for diagnosing faults | |
CN103454516B (en) | Intelligent transformer substation secondary equipment health state diagnostic method | |
CN103679556B (en) | The intelligent diagnosing method of distribution transformer terminals power failure alarm | |
CN106124935A (en) | Middle and low voltage network Fault Locating Method | |
CN108037415A (en) | Distribution network failure information excavating and diagnostic method based on multi-source heterogeneous data | |
CN107844880A (en) | A kind of electric network fault grade automatic identifying method based on multisource data fusion | |
CN108931972A (en) | A kind of substation secondary device condition intelligent diagnostic method based on model-driven | |
CN110380514B (en) | Intelligent substation relay protection secondary circuit fault diagnosis method | |
CN103218695A (en) | Secondary equipment intelligence state evaluation diagnostic system and method thereof | |
CN109501834A (en) | A kind of point machine failure prediction method and device | |
CN105158647B (en) | Dan Zhanduan electric network failure diagnosis and aid decision-making method based on grid monitoring system | |
CN105573283B (en) | The foundation in substation equipment function association storehouse and the filter method of event correlation information group | |
CN106712287A (en) | Intelligent alarm analysis system of intelligent transformer substation | |
CN102707199B (en) | Intelligent diagnosis method and system of dispatching warning message of power grid | |
CN102142716A (en) | Power grid online fault diagnosis method based on three-state data multidimensional cooperative processing | |
CN103227450B (en) | On-line failure recovery method and system | |
CN103956831B (en) | The intelligent diagnosing method of a kind of transmission line distribution transforming phase shortage alarm | |
CN103324128B (en) | Primary equipment fault warning comprehensive compression method in power dispatching automation system | |
CN108919044B (en) | Active identification method for unit distribution power grid faults based on mutual verification mechanism | |
CN104297616A (en) | 10kV distribution line breaking detection method based on multi-system information interaction | |
CN109001596A (en) | A kind of electric network failure diagnosis and transmission line parameter identification system | |
CN108732444A (en) | Intelligent substation protects equipment running status apparatus for evaluating and maintenance decision method | |
CN104734353B (en) | Intelligent substation hovering fault monitoring method based on network message | |
CN103208049A (en) | Quick accident analysis method and system for abnormal alarm | |
CN109298228A (en) | A kind of Intelligence Diagnosis method and system based on photovoltaic group string current anomaly |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |