CN104452597A - Supporting system for construction of super-long water pier prestressed cap beam - Google Patents

Supporting system for construction of super-long water pier prestressed cap beam Download PDF

Info

Publication number
CN104452597A
CN104452597A CN201410687410.8A CN201410687410A CN104452597A CN 104452597 A CN104452597 A CN 104452597A CN 201410687410 A CN201410687410 A CN 201410687410A CN 104452597 A CN104452597 A CN 104452597A
Authority
CN
China
Prior art keywords
steel
support
pier
steel plate
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410687410.8A
Other languages
Chinese (zh)
Other versions
CN104452597B (en
Inventor
郭颖
余流
李永红
徐楚
窦卫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co ltd Of China Construction Sixth Engineering Bureau
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201410687410.8A priority Critical patent/CN104452597B/en
Publication of CN104452597A publication Critical patent/CN104452597A/en
Application granted granted Critical
Publication of CN104452597B publication Critical patent/CN104452597B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种水中墩超长预应力盖梁施工支撑体系,该支撑体系包括支架,支架包括设置在相邻两根水中墩柱之间的两个呈八字形布置的钢斜撑以及布设在每根水中墩柱周围的四根钢管立柱;在每个撑杆的底端连接有销铰及其支座,钢斜撑底端的销铰支座通过预埋钢板Ⅱ与相应水中墩柱的承台连接;撑杆的顶端和钢管立柱的顶端均设有水平支撑盖板,水平支撑盖板上固定有一纵向支撑梁;在纵向支撑梁的两端各设有一沙箱,砂箱支撑横向承重梁,在横向承重梁上固定多根纵向分配梁,所有纵向分配梁形成体系的水平支撑面。本发明承载能力强,稳定性高,能够适用长度超过40m、安装高度大于8m,墩身间净距大于18m的超长水中墩盖梁施工。

The invention discloses a construction supporting system for super-long prestressed cover beams of underwater piers. Four steel pipe columns around each underwater pier; a pin hinge and its support are connected at the bottom of each strut, and the pin hinge support at the bottom of the steel diagonal brace passes through the pre-embedded steel plate II and the corresponding underwater pier The cap is connected; the top of the strut and the top of the steel pipe column are equipped with a horizontal support cover, and a longitudinal support beam is fixed on the horizontal support cover; a sandbox is provided at each end of the longitudinal support beam, and the sandbox supports the horizontal load. Beams, multiple longitudinal distribution beams are fixed on the horizontal load-bearing beams, and all the longitudinal distribution beams form the horizontal support surface of the system. The invention has strong bearing capacity and high stability, and can be applied to the construction of ultra-long underwater pier cap beams with a length of more than 40m, an installation height of more than 8m, and a clear distance between pier bodies of more than 18m.

Description

水中墩超长预应力盖梁施工支撑体系Construction support system of ultra-long prestressed cover beam for pier in water

技术领域technical field

本发明涉及一种盖梁施工支撑体系,特别是一种水中墩超长预应力盖梁施工支撑体系。The invention relates to a construction support system of a cover beam, in particular to a construction support system of an ultra-long prestressed cover beam for an underwater pier.

背景技术Background technique

目前,国内大型市政、公路桥梁设计多为双向六车道或八车道,单向三车道或四车道,墩柱盖梁的长度多数在40m以下,少数长度在40m以上,盖梁施工普遍采用支架法和无支架法两种方式。支架法对地基的承载力要求高,地基处理费用高,工期受限,施工稍有不慎,即可造成支架整体下沉,严重影响盖梁的施工质量,且对于水中桥墩不适用;无支架法施工常见的有:预埋法、横穿法和抱箍法,虽然适用于高墩盖梁和水中盖梁,但三种方法各有利弊,每种方法的优点均不能兼顾保证盖梁支撑体系对施工进度、质量及成本等多方面的整体控制要求。At present, domestic large-scale municipal and highway bridges are mostly designed with six or eight lanes in two directions, and three or four lanes in one direction. and the non-stent method. The support method has high requirements on the bearing capacity of the foundation, the cost of foundation treatment is high, and the construction period is limited. A little carelessness in construction can cause the overall support of the support to sink, seriously affecting the construction quality of the cap beam, and it is not suitable for piers in water; no support The common methods of construction are: pre-embedded method, crossing method and hoop method. Although they are suitable for high pier cap beams and underwater cap beams, the three methods have their own advantages and disadvantages, and the advantages of each method cannot ensure the support of the cap beam. The system has overall control requirements for construction progress, quality and cost.

苏州市中环快速路工业园区段工程吴淞江大桥,为单跨双幅简支钢桁架桥,总重约4410t,跨径119m,单幅宽22.8m,属国内单幅宽度之最、苏州市及江苏省跨径之最,盖梁:长54.2m,宽3.6m,高2.5m,亦为国内同类型桥梁长度之最,单个盖梁总重可达1300t,盖梁下墩柱与墩柱之间净距为20.2m,且位于水上施工,吴淞江南岸存在超过20m深的淤泥质土层,传统的支架法施工和无支架法施工均不适用于此工程。同时这个工程对支架的承载能力、稳定性提出的要求非常高。并且,在上述盖梁的施工中,为了避免砼收缩变形及徐变对墩身产生的应力造成局部节点混凝土开裂,需要采用预顶工艺,通常情况下需要搭设临时支架,在水上进行地基处理和支撑架体搭设,施工难度大,工期长,成本高。The Wusong River Bridge in the Suzhou Zhonghuan Expressway Industrial Park Section Project is a single-span double-width simply supported steel truss bridge with a total weight of about 4410t, a span of 119m, and a single width of 22.8m. It is the largest single width in China, Suzhou and Jiangsu The longest span in the province, the cover beam: 54.2m in length, 3.6m in width, and 2.5m in height, also the length of the bridge of the same type in China, the total weight of a single cover beam can reach 1300t, between the pier columns under the cover beam The net distance is 20.2m, and the construction is located on the water. There is a muddy soil layer more than 20m deep on the south bank of the Wusong River. Neither the traditional support method nor the non-support method construction is suitable for this project. At the same time, this project has very high requirements on the bearing capacity and stability of the bracket. Moreover, in the construction of the above-mentioned cover beams, in order to avoid cracking of local node concrete caused by concrete shrinkage deformation and creep stress on the pier body, it is necessary to adopt a pre-topping process. Usually, it is necessary to erect temporary supports and carry out foundation treatment and The construction of the support frame is difficult, the construction period is long, and the cost is high.

发明内容Contents of the invention

本发明为解决公知技术中存在的技术问题而提供一种水中墩超长预应力盖梁施工支撑体系,该支撑体系承载能力强,稳定性高,能够适用长度超过40m、安装高度大于8m,墩身间净距大于18m的超长水中墩盖梁施工。In order to solve the technical problems existing in the known technology, the present invention provides a super-long prestressed cover beam construction support system for piers in water. The support system has strong bearing capacity and high stability. Construction of ultra-long underwater piers and cap beams with a net distance of more than 18m.

本发明为解决公知技术中存在的技术问题所采取的技术方案是:一种水中墩超长预应力盖梁施工支撑体系,所述盖梁下部设有至少两根水中墩柱,该支撑体系包括支架,所述支架包括设置在相邻两根水中墩柱之间的两个呈八字形布置的钢斜撑以及布设在每根所述水中墩柱周围的四根钢管立柱;对应每一根所述水中墩柱的四根所述钢管立柱的底端通过预埋钢板Ⅰ固定在该水中墩柱的承台的四个角部;每个所述钢斜撑设有两根撑杆,每个所述钢斜撑的两根所述撑杆在该支架横向立面上的投影重合,且纵向间距与纵向相邻的两根钢管立柱1的间距相同,每个所述钢斜撑的两根所述撑杆通过钢结构连接在一起,在每个所述撑杆的底端连接有销铰及其支座,所述钢斜撑底端的销铰支座通过预埋钢板Ⅱ与相应所述水中墩柱的承台连接,所述预埋钢板Ⅱ位于与其靠近的所述预埋钢板Ⅰ的外侧;呈八字形布置的两个所述钢斜撑的顶部通过横向连接梁连接;每根所述撑杆的顶端和每根所述钢管立柱的顶端均设有等标高的水平支撑盖板,在纵向相对的每两个所述水平支撑盖板上固定有一纵向支撑梁;所有所述钢管立柱和所有所述钢斜撑通过水平连接构件Ⅰ连接在一起;The technical solution adopted by the present invention to solve the technical problems existing in the known technology is: a support system for the construction of super-long prestressed cover beams in water piers, the lower part of the cover beams is provided with at least two underwater pier columns, and the support system includes Support, the support includes two steel diagonal braces arranged in a figure-eight shape between two adjacent water piers and four steel pipe columns arranged around each of the water piers; corresponding to each of the water piers The bottom ends of the four steel pipe columns of the above-mentioned water pier columns are fixed on the four corners of the caps of the water pier columns through pre-embedded steel plates I; each of the steel diagonal braces is provided with two struts, each The projections of the two struts of the steel diagonal brace on the horizontal elevation of the bracket coincide, and the longitudinal distance is the same as the distance between the two vertically adjacent steel pipe columns 1, and the two steel diagonal braces of each The struts are connected together through a steel structure, and a pin hinge and its support are connected at the bottom end of each strut, and the pin hinge support at the bottom end of the steel diagonal brace is connected with the corresponding said strut through the embedded steel plate II. The caps of pier columns in water are connected, the pre-embedded steel plate II is located on the outside of the pre-embedded steel plate I close to it; the tops of the two steel braces arranged in a figure-eight shape are connected by transverse connecting beams; each of the The tops of the struts and the tops of each of the steel pipe columns are provided with horizontal support covers of equal elevation, and a longitudinal support beam is fixed on each of the two vertically opposite horizontal support covers; all of the steel pipe columns and all the steel braces are connected together through the horizontal connecting member I;

在多根所述纵向支撑梁的两端各设有一砂箱,所述纵向支撑梁两端的砂箱分别支撑两根横向承重梁,在两根所述横向承重梁上固定多根并排布置的纵向分配梁,所有所述纵向分配梁形成体系的水平支撑面。A sand box is respectively provided at both ends of the plurality of longitudinal support beams, and the sand boxes at the two ends of the longitudinal support beams support two transverse load-bearing beams respectively, and a plurality of vertical load-bearing beams arranged side by side are fixed on the two transverse load-bearing beams. Distribution beams, all of said longitudinal distribution beams form the horizontal support surface of the system.

在所述支架上安装预顶机构,所述预顶机构包括相对的预顶钢板Ⅰ和预顶钢板Ⅱ,所述预顶钢板Ⅰ和所述预顶钢板Ⅱ分别预埋在相邻的两根水中墩柱的外侧表面上,在所述预顶钢板Ⅰ和所述预顶钢板Ⅱ之间自所述预顶钢板Ⅰ开始设有依次水平连接的预顶钢管、千斤顶和承压座,所述预顶钢管与所述预顶钢板Ⅰ连接;所述预顶钢管由限位卡板支撑,所述限位卡板固定在所述纵向支撑梁的中部顶面上。The pre-jacking mechanism is installed on the bracket, and the pre-jacking mechanism includes the relative pre-jacking steel plate I and the pre-jacking steel plate II, and the pre-jacking steel plate I and the pre-jacking steel plate II are respectively pre-embedded in two adjacent On the outer surface of the pier column in the water, between the pre-jacking steel plate I and the pre-jacking steel plate II, there are pre-jacking steel pipes, jacks and pressure seats connected horizontally in sequence from the pre-jacking steel plate I. The pre-jacking steel pipe is connected to the pre-jacking steel plate I; the pre-jacking steel pipe is supported by a limit clamp, and the limit clamp is fixed on the middle top surface of the longitudinal support beam.

在所述预埋钢板Ⅰ和所述预埋钢板Ⅱ的下面焊接有倒U形锚固钢筋和水平加强钢筋网,所述水平加强钢筋网与所述倒U形锚固钢筋连接。Under the pre-embedded steel plate I and the pre-embedded steel plate II, an inverted U-shaped anchoring steel bar and a horizontal reinforcement mesh are welded, and the horizontal reinforcement mesh is connected to the inverted U-shaped anchoring steel bar.

所述砂箱由与所述纵向支撑梁固接的下砂桶和上活塞支墩组成;在所述下砂桶内盛装有细砂体;所述上活塞支墩设有一倒置的桶体,在所述倒置的桶体内满筑有混凝土结构;所述倒置的桶体插装在所述下砂桶内,所述上活塞支墩由所述细砂体支撑,在所述下砂桶的下端侧壁上设有放砂口,在所述放砂口上安装有封堵门。The sand box is composed of a lower sand barrel fixedly connected with the longitudinal support beam and an upper piston buttress; fine sand bodies are contained in the lower sand barrel; the upper piston buttress is provided with an inverted barrel, The inverted barrel is filled with concrete structures; the inverted barrel is inserted into the lower sand barrel, the upper piston abutment is supported by the fine sand body, and the lower sand barrel is A sand outlet is provided on the side wall of the lower end, and a plugging door is installed on the sand outlet.

所述放砂口是由螺纹孔形成的,所述封堵门是由螺栓形成的。The sand discharge port is formed by threaded holes, and the plugging door is formed by bolts.

所述倒置的桶体设有外缘伸出在该桶体之外的底部,形成支墩顶部支撑盖板;所述下砂桶的底部外缘伸出在所述下砂桶的桶体之外,形成砂箱的底部支撑托板。The inverted barrel is provided with a bottom with an outer edge protruding outside the barrel to form a buttress top support cover; the outer edge of the bottom of the lower sand barrel is stretched out between the barrel of the lower sand barrel Outside, form the bottom supporting pallet of the sand box.

所述预埋钢板Ⅱ和与其靠近的所述预埋钢板Ⅰ是一整块钢板。The embedded steel plate II and the embedded steel plate I adjacent to it are a whole steel plate.

所述横向连接梁、所述纵向支撑梁、所述钢斜撑的构件、所述横向承重梁和所述纵向分配梁均采用双拼工字钢结构。The transverse connection beam, the longitudinal support beam, the members of the steel diagonal bracing, the transverse load-bearing beam and the longitudinal distribution beam all adopt double I-shaped steel structure.

对应每一根所述水中墩柱的四根所述钢管立柱的底部通过水平连接构件Ⅱ形成一体。The bottoms of the four steel pipe columns corresponding to each of the underwater piers are integrated through the horizontal connecting member II.

所述钢斜撑底端的销铰支座与靠近该销铰支座的所述钢管立柱的底部采用水平钢板连接。The pin-hinge support at the bottom end of the steel diagonal brace is connected to the bottom of the steel pipe column near the pin-hinge support by a horizontal steel plate.

本发明具有的优点和积极效果是:The advantages and positive effects that the present invention has are:

1)支架采用墩柱的承台作为着力点,将结构承受荷载传递至永久结构,打破了目前国内市政及公路桥梁领域内超长水中墩盖梁支架法和无支架法施工的限制。在水中墩柱承台施工期间预埋钢板,待水中墩柱施工完成后,将钢斜撑和钢管立柱连接在预埋钢板上,拔除用于墩柱及承台施工的拉森桩,将钢斜撑转到设定倾角,即可进行下一步的施工,能够缩短盖梁支撑体系的安装工期,节省成本。原因在于:利用销铰结构,使钢斜撑可以进行角度调整。由于墩柱施工用的围堰拉森桩与支架的钢斜撑是交叉的,安装支架时必须先拔出交叉部位的拉森桩。如果采用钢斜撑与承台预埋钢板直接焊接的架设方式,施工难度大,承台离江岸较远、又有水下障碍物,故改为在钢斜撑的底脚处增加一个铰接结构与承台预埋钢板连接,使用该铰接结构可以不受现场环境条件和拉森桩交叉的影响,钢斜撑与承台预埋钢板连接后,采用手拉葫芦牵住穿过钢斜撑上部耳板的钢丝绳与墩柱临时固定,使钢斜撑垂直于承台,待拉森桩拔除后再按照斜向角度进行安装。如不设置销铰可转动结构,则需整体打设拉森桩围堰,将所有墩柱承台形成封闭的整体。设置销铰节点,可提前拔除部分承台施工用拉森桩,同时减少了整体打设拉森桩的成本和工期,缩短了支架安装时间,节省了拉森桩的租赁费用。本发明利用已有的墩柱承台作为结构的基础,减少了地基处理的工艺环节,并且结构所用钢构件还可以循环利用,能够节约大量成本。与传统的支架法和无支架法相比,本发明避免了支架法施工需对地基进行处理或打设钢管桩、承载力和稳定性不足的缺点,并且采用型钢支承,刚度大,承载能力强,相对无支架法施工盖梁而言,避免了预埋法、横穿法、抱箍法的各项缺陷,对永久结构墩身质量及外观无影响,能够适用长度超过40m、安装高度大于8m,墩身间净距大于18m的水中墩超长盖梁施工,并且能够适用于非圆柱形墩柱的盖梁施工。1) The support adopts the cap of the pier column as the focus point, and transfers the load of the structure to the permanent structure, breaking the current domestic municipal and highway bridge field. Pre-embed the steel plate during the construction of the pier column cap in the water. After the construction of the pier column in the water is completed, connect the steel diagonal brace and the steel pipe column to the pre-embedded steel plate, pull out the Larsen pile used for the construction of the pier column and the cap, and place the steel When the diagonal brace is turned to the set inclination angle, the next step of construction can be carried out, which can shorten the installation period of the cover beam support system and save costs. The reason is that the angle of the steel diagonal brace can be adjusted by using the pin-hinge structure. Since the cofferdam Larsen piles used for pier column construction are intersected with the steel diagonal braces of the support, the Larsen piles at the intersection must be pulled out first when the support is installed. If the erection method of direct welding of the steel diagonal brace and the pre-embedded steel plate of the cap is adopted, the construction is difficult, the cap is far away from the river bank, and there are underwater obstacles, so a hinged structure is added at the foot of the steel diagonal brace It is connected with the pre-embedded steel plate of the cap, and the use of this hinged structure can not be affected by the site environmental conditions and the crossing of Larsen piles. After the steel diagonal brace is connected with the pre-embedded steel plate of the cap, a chain hoist is used to hold and pass through the upper part of the steel diagonal brace The steel wire rope of the ear plate is temporarily fixed to the pier column, so that the steel diagonal brace is perpendicular to the cap, and the Larsen pile is pulled out and then installed according to the oblique angle. If there is no pin-hinge rotatable structure, Larsen pile cofferdam needs to be erected as a whole to form a closed whole of all pier caps. The setting of pin-hinge joints can remove some Larsen piles used for platform cap construction in advance, and at the same time reduce the cost and construction period of the overall setting of Larsen piles, shorten the installation time of supports, and save the rental cost of Larsen piles. The present invention utilizes the existing pier caps as the foundation of the structure, reduces the technical links of foundation treatment, and the steel components used in the structure can also be recycled, which can save a lot of cost. Compared with the traditional support method and no support method, the present invention avoids the disadvantages of the need to deal with the foundation or install steel pipe piles in the construction of the support method, and the shortcomings of insufficient bearing capacity and stability, and adopts section steel support, which has high rigidity and strong bearing capacity , compared with the construction of cap beams without support method, it avoids the defects of pre-embedding method, crossing method and hoop method, and has no effect on the quality and appearance of the permanent structure pier body. It is suitable for the construction of ultra-long cover beams for underwater piers with a net distance of more than 18m, and can be applied to the construction of cover beams for non-cylindrical pier columns.

2)体系支架为墩柱的预推装置提供了临时支撑,减少了搭设临时支架的地基处理及支撑架体搭设等工艺环节,进一步缩短了工期、降低了人工费及材料成本。2) The system support provides temporary support for the pre-push device of the pier column, which reduces the process links such as foundation treatment and support frame erection for erecting the temporary support, further shortens the construction period, reduces labor costs and material costs.

3)利用砂箱作为横向承重梁的支撑,使体系的支撑标高可以微调,提高了安装精度,并且能够使拆模施工方便。砂箱结构简单、加工方便、承载力高,可以有效提高施工效率,尤其在墩身为高墩时,利用砂箱作为可调支座的结构,能够有效地的降低施工难度,提高安全系数。砂箱的主要加工材料为钢管及细砂,砂箱体积小,能够节省材料,降低施工成本,且在施工结束后箱体及细砂均可再次使用,现场无废料残留,在节约成本的同时,还能有效地减少对环境的污染。3) The sand box is used as the support of the horizontal load-bearing beam, so that the support elevation of the system can be fine-tuned, the installation accuracy is improved, and the formwork removal and construction can be facilitated. The sand box has simple structure, convenient processing and high bearing capacity, which can effectively improve the construction efficiency. Especially when the pier is a high pier, using the sand box as an adjustable support structure can effectively reduce the construction difficulty and improve the safety factor. The main processing materials of the sand box are steel pipe and fine sand. The sand box is small in size, which can save materials and reduce construction costs. After the construction is completed, the box body and fine sand can be used again, and there is no waste left on site. , and can effectively reduce environmental pollution.

综上所述,本发明刚度大,承载能力强,能够缩短工期、降低人工费及材料成本,并且安装精度高,是一个可循环利用的多功能支撑结构体系。To sum up, the present invention has high rigidity, strong bearing capacity, can shorten the construction period, reduce labor costs and material costs, and has high installation precision. It is a recyclable multifunctional support structure system.

附图说明Description of drawings

图1为本发明的立面图;Fig. 1 is the elevation view of the present invention;

图2为图1的俯视图;Fig. 2 is the top view of Fig. 1;

图3-1为图1的Ⅰ-Ⅰ剖视图;Figure 3-1 is a sectional view of I-I in Figure 1;

图3-2为图1的Ⅱ-Ⅱ剖视图;Figure 3-2 is a sectional view of II-II in Figure 1;

图3-3为图1的Ⅲ-Ⅲ剖视图;Figure 3-3 is a sectional view of III-III in Figure 1;

图3-4为图1的A-A剖视图;Fig. 3-4 is A-A sectional view of Fig. 1;

图4为本发明的承台预埋钢板Ⅰ和承台预埋钢板Ⅱ的立面图;Fig. 4 is the elevation view of the pre-embedded steel plate I and the pre-embedded steel plate II of the present invention;

图5为本发明的承台预埋钢板Ⅰ和承台预埋钢板Ⅱ的锚固钢筋结构示意图;Fig. 5 is a schematic diagram of the anchoring reinforcement structure of the pre-embedded steel plate I of the cap and the pre-embedded steel plate II of the present invention;

图6为本发明的墩柱预埋钢板的结构示意图;Fig. 6 is the structural schematic diagram of pier column pre-embedded steel plate of the present invention;

图7为本发明的预顶机构安装示意图;Figure 7 is a schematic diagram of the installation of the pre-jacking mechanism of the present invention;

图8为图7的俯视图;Figure 8 is a top view of Figure 7;

图9为本发明的砂箱正面图。Fig. 9 is a front view of the sand box of the present invention.

图中:1、钢管立柱;2、水中墩柱;3-1、撑杆;3-2、钢结构;4、横向连接梁;5、纵向支撑梁;6、水平连接构件Ⅰ;7、预埋钢板Ⅰ;8、预埋钢板Ⅱ;9、水平连接构件Ⅱ;10、销铰;11、销铰支座;12、承台;13、水平支撑盖板;14、拉森桩;15、承台顶层钢筋;16、水平加强钢筋网;17、倒U形锚固钢筋;18、预顶钢板Ⅰ;19、限位卡板;20、预顶钢管;21、千斤顶;22、承压座;23、预顶钢板Ⅱ;24、U形锚固钢筋;25、传力竖向钢板;26、轴向限位挡板;27、砂箱;27-1、下砂桶;27-1-1、砂箱的底部支撑托板;27-1-2、细砂体;27-1-3、封堵门;27-2、上活塞支墩;27-2-1、支墩顶部支撑盖板;27-2-2、混凝土结构;28、横向承重梁;29、纵向分配梁;30、盖梁;31、护栏;32、底模。In the figure: 1. Steel pipe column; 2. Pier column in water; 3-1. Strut; 3-2. Steel structure; Buried steel plate Ⅰ; 8. Embedded steel plate Ⅱ; 9. Horizontal connecting member Ⅱ; 10. Pin hinge; 11. Pin hinge support; 16. Horizontal reinforcing steel mesh; 17. Inverted U-shaped anchoring steel bar; 18. Pre-jacking steel plate I; 19. Limit clamping plate; 20. Pre-jacking steel pipe; 21. Jack; 22. Pressure seat; 23. Pre-top steel plate II; 24. U-shaped anchoring steel bar; 25. Vertical steel plate for force transmission; 26. Axial limit baffle; 27. Sand box; 27-1. Lower sand barrel; 27-1-1. The bottom supporting plate of the sand box; 27-1-2, fine sand body; 27-1-3, the plugging door; 27-2, the upper piston pier; 27-2-1, the supporting cover plate at the top of the pier; 27-2-2. Concrete structure; 28. Horizontal load-bearing beam; 29. Vertical distribution beam; 30. Cover beam; 31. Guardrail; 32. Bottom form.

具体实施方式Detailed ways

为能进一步了解本发明的发明内容、特点及功效,兹例举以下实施例,并配合附图详细说明如下:In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:

请参阅附图,一种水中墩超长预应力盖梁施工支撑体系,所述盖梁30下部设有至少两根水中墩柱2,该支撑体系包括支架及其上部支撑结构。Please refer to the accompanying drawings, a super-long prestressed cover beam construction support system for submerged pier, at least two submerged pier columns 2 are arranged at the lower part of the cover beam 30, and the support system includes a bracket and its upper supporting structure.

所述支架包括设置在相邻两根水中墩柱2之间的两个呈八字形布置的钢斜撑以及布设在每根水中墩柱周围的四根钢管立柱1;对应每一根所述水中墩柱2的四根所述钢管立柱1的底端通过预埋钢板Ⅰ7固定在该水中墩柱2的承台12的四个角部;每个所述钢斜撑设有两根撑杆3-1,每个所述钢斜撑的两根所述撑杆3-1在该支架横向立面上的投影重合,且纵向间距与纵向相邻的两根钢管立柱1的间距相同,每个所述钢斜撑的两根所述撑杆3-1通过钢结构3-2连接在一起,在每个撑杆3-1的底端连接有销铰10及其支座11,所述钢斜撑底端的销铰支座11通过预埋钢板Ⅱ8与相应所述水中墩柱2的承台12连接,所述预埋钢板Ⅱ8位于与其靠近的所述预埋钢板Ⅰ1的外侧,所述撑杆3-1的底端和所述钢斜撑底端的销铰支座11通过销铰10连接,在所述销铰10的尾部设有环槽,在所述环槽内插装有轴向限位挡板26,所述轴向限位挡板26固定在所述钢斜撑底端的销铰支座11上;呈八字形布置的两个所述钢斜撑的顶部通过横向连接梁4连接;每根所述撑杆3-1的顶端和每根所述钢管立柱2的顶端均设有等标高的水平支撑盖板13,在纵向相对的每两个所述水平支撑盖板13上固定有一纵向支撑梁5;作为预顶钢管20及砂箱27放置的平台;所有所述钢管立柱1和所有所述钢斜撑通过水平连接构件Ⅰ6连接在一起。The support includes two steel diagonal braces arranged in a figure-eight shape between two adjacent water piers 2 and four steel pipe columns 1 arranged around each water piers; corresponding to each of the water piers The bottom ends of the four steel pipe columns 1 of the pier column 2 are fixed to the four corners of the cap 12 of the pier column 2 in the water through the embedded steel plate I7; each of the steel diagonal braces is provided with two struts 3 -1, the projections of the two struts 3-1 of each of the steel diagonal braces on the horizontal elevation of the bracket coincide, and the longitudinal spacing is the same as that of the two vertically adjacent steel pipe columns 1, each The two struts 3-1 of the steel diagonal brace are connected together by a steel structure 3-2, and a pin hinge 10 and its support 11 are connected to the bottom end of each strut 3-1. The pin-hinge support 11 at the bottom of the diagonal brace is connected to the cap 12 of the corresponding underwater pier 2 through the embedded steel plate II8, the embedded steel plate II8 is located on the outside of the embedded steel plate I1 close to it, and the brace The bottom end of the rod 3-1 is connected with the pin hinge support 11 at the bottom end of the steel brace through a pin hinge 10, and an annular groove is arranged at the tail of the pin hinge 10, and an axial shaft is inserted in the annular groove. The limit baffle 26, the axial limit baffle 26 is fixed on the pin-hinge support 11 at the bottom end of the steel brace; Connection; the top of each of the struts 3-1 and the top of each of the steel pipe columns 2 are provided with a horizontal support cover 13 of equal elevation, on each of the two vertically opposite horizontal support covers 13 A longitudinal support beam 5 is fixed; it is used as a platform for placing the pre-jack steel pipe 20 and the sand box 27; all the steel pipe columns 1 and all the steel diagonal braces are connected together through horizontal connecting members I6.

在多根所述纵向支撑梁5的两端各设有一砂箱27,所述纵向支撑梁5两端的砂箱27分别支撑两根横向承重梁28,在两根所述横向承重梁28上固定多根并排布置的纵向分配梁29,所有所述纵向分配梁29形成体系的水平支撑面。用于安装盖梁的底模32和护栏31等。A sand box 27 is respectively provided at two ends of the plurality of longitudinal support beams 5, and the sand boxes 27 at the two ends of the longitudinal support beam 5 support two transverse load-bearing beams 28 respectively, and are fixed on the two transverse load-bearing beams 28. A plurality of longitudinal distribution beams 29 arranged side by side, all of which form the horizontal support surface of the system. Bottom form 32 and guardrail 31 etc. that are used to install cover beam.

所述砂箱27由与所述纵向支撑梁5固接的下砂桶27-1和上活塞支墩27-2组成;在所述下砂桶27-1内盛装有细砂体27-1-1;所述上活塞支墩27-2设有一倒置的桶体,在所述倒置的桶体内满筑有混凝土结构27-2-2;所述倒置的桶体插装在所述下砂桶27-1内,所述上活塞支墩27-2由所述细砂体27-1-1支撑,在所述下砂桶27-1的下端侧壁上设有放砂口,在所述放砂口上安装有封堵门。The sand box 27 is composed of a lower sand barrel 27-1 fixedly connected with the longitudinal support beam 5 and an upper piston pier 27-2; the lower sand barrel 27-1 is filled with a fine sand body 27-1 -1; the upper piston abutment 27-2 is provided with an inverted barrel, and a concrete structure 27-2-2 is built in the inverted barrel; the inverted barrel is inserted into the lower sand In the barrel 27-1, the upper piston abutment 27-2 is supported by the fine sand body 27-1-1, and a sand outlet is provided on the lower end side wall of the lower sand barrel 27-1. A plugging door is installed on the sand outlet.

在本实施例中,所述放砂口是由螺纹孔形成的,所述封堵门是由螺栓27-1-3形成的。所述倒置的桶体设有外缘伸出在该桶体之外的底部,形成支墩顶部支撑盖板27-2-1;所述下砂桶27-1的底部外缘伸出在所述下砂桶的桶体之外,形成砂箱的底部支撑托板27-1-2,以便与纵向支撑梁5采用螺栓连接,使砂箱27的水平位置可调,使砂箱27能够多次重复循环利用。In this embodiment, the sand discharge opening is formed by a threaded hole, and the plugging door is formed by bolts 27-1-3. The inverted barrel body is provided with a bottom with an outer edge protruding from the barrel body to form a buttress top supporting cover plate 27-2-1; the bottom outer edge of the lower sand barrel 27-1 extends above the In addition to the barrel body of the following sand barrel, the bottom supporting plate 27-1-2 of the sand box is formed, so as to be connected with the longitudinal support beam 5 by bolts, so that the horizontal position of the sand box 27 can be adjusted, so that the sand box 27 can be multi- repeated recycling.

在本实施例中,中间的墩柱的截面为椭圆形。墩柱施工用的围堰拉森桩14桩长18m,设河床顶标高为0.00m,则水面标高是1.5m,墩柱承台顶标高为-2.8m。为了方便施工,节约成本,将预顶机构安装在上述支架上,所述预顶机构包括相对的预顶钢板Ⅰ18和预顶钢板Ⅱ23,所述预顶钢板Ⅰ18和所述预顶钢板Ⅱ23分别预埋在相邻的两根水中墩柱2的外侧表面上,在所述预顶钢板Ⅰ18和所述预顶钢板Ⅱ23之间自所述预顶钢板Ⅰ18开始设有依次水平连接的预顶钢管20、千斤顶21和承压座22,所述预顶钢管20与所述预顶钢板Ⅰ18连接,在所述预顶钢管20的另一端和所述预顶钢板Ⅱ23之间安装千斤顶21和承压座22,所述千斤顶21位于所述预顶钢管20和所述承压座22之间。在实施预顶操作前,千斤顶21和承压座22从体系的水平支撑面上吊放。所述预顶钢管20由限位卡板19支撑,所述限位卡板19固定在所述纵向支撑梁5的中部顶面上。In this embodiment, the cross-section of the middle pier is elliptical. The 14 cofferdam Larsen piles used for pier column construction are 18m long. If the elevation of the riverbed top is 0.00m, then the water surface elevation is 1.5m, and the elevation of the pier cap top is -2.8m. In order to facilitate construction and save costs, the pre-jacking mechanism is installed on the above-mentioned bracket. The pre-jacking mechanism includes the relative pre-jacking steel plate I18 and the pre-jacking steel plate II23. Buried on the outer surfaces of two adjacent piers 2 in water, between the pre-roofing steel plate I18 and the pre-roofing steel plate II23, there are pre-roofing steel pipes 20 horizontally connected sequentially from the pre-roofing steel plate I18 , a jack 21 and a pressure seat 22, the pre-jack steel pipe 20 is connected to the pre-jack steel plate I18, and the jack 21 and the pressure seat are installed between the other end of the pre-jack steel pipe 20 and the pre-jack steel plate II23 22. The jack 21 is located between the pre-jacked steel pipe 20 and the pressure seat 22. Before implementing the pre-jacking operation, the jack 21 and the pressure seat 22 are suspended from the horizontal support surface of the system. The pre-jacking steel pipe 20 is supported by a limit clamp 19 , and the limit clamp 19 is fixed on the middle top surface of the longitudinal support beam 5 .

对墩柱施加预顶力,若直接接触,千斤顶头与墩柱接触面小,受力集中,有局部开裂的可能,因此在千斤顶21的前方,设置了承压座22和预顶钢板Ⅱ23,同理,在预顶钢管20远离千斤顶21的端部外侧设置了预顶钢板Ⅰ18,所述预顶钢板Ⅰ18和所述预顶钢板Ⅱ23结构相同,均包括一块与水中墩柱2外侧表面适配的弧形钢板,在弧形钢板的背面焊接有U形锚固钢筋24,所述U形锚固钢筋24的开口方向与所述弧形钢板的开口方向相同,在所述U形锚固钢筋24的底部设有两个内翻的勾状结构。所述勾状结构的作用与胀管的作用类似。所述预顶钢板Ⅰ18和所述预顶钢板Ⅱ23通过焊接锚固筋,达到扩散集中应力的作用。所述承压座22包括传力竖向钢板25,所述传力竖向钢板25通过钢连接结构Ⅱ与所述预顶钢板Ⅱ23连接。在进行预顶施工时,为了防止对墩柱产生污染,采用土工布包裹所述预顶钢板Ⅰ18和所述预顶钢板Ⅱ23的周边区域。If the pre-jacking force is applied to the pier column, if there is direct contact, the contact surface between the jack head and the pier column is small, the force is concentrated, and there is a possibility of local cracking. The reason is that a pre-jacking steel plate I18 is set outside the end of the pre-jacking steel pipe 20 away from the jack 21. The pre-jacking steel plate I18 and the pre-jacking steel plate II23 have the same structure, and both include a piece that is adapted to the outer surface of the pier column 2 in the water. Arc-shaped steel plate, U-shaped anchoring steel bar 24 is welded on the back side of the arc-shaped steel plate, the opening direction of the U-shaped anchoring steel bar 24 is the same as the opening direction of the described arc-shaped steel plate, and the bottom of the U-shaped anchoring steel bar 24 is provided There are two inverted hook-like structures. The function of the hook structure is similar to that of the expanding tube. The pre-roofing steel plate I18 and the pre-roofing steel plate II23 achieve the function of diffusing concentrated stress by welding anchor bars. The pressure bearing seat 22 includes a force-transmitting vertical steel plate 25, and the force-transmitting vertical steel plate 25 is connected to the pre-supporting steel plate II 23 through a steel connection structure II. During the pre-roofing construction, in order to prevent pollution to the piers, geotextiles are used to wrap the surrounding areas of the pre-roofing steel plate I18 and the pre-roofing steel plate II23.

预顶装置借用盖梁支撑体系的支架作为临时支撑,安装预顶钢管、承压座,预顶钢管利用限位卡板与支架固定,减少了单独做临时支撑的地基处理及支撑架体搭设等工艺环节,能够缩短工期,降低人工费及材料成本。The pre-jacking device uses the bracket of the cover beam support system as a temporary support, and installs the pre-jacking steel pipe and the pressure seat. The pre-jacking steel pipe is fixed by the limit clamp and the bracket, which reduces the foundation treatment and the erection of the supporting frame for temporary support alone. The process link can shorten the construction period, reduce labor costs and material costs.

钢管立柱1承压,底部与承台12连接部位局部受压,钢斜撑底部铰接节点与承台12连接部位受压并抗剪,因此在预埋钢板Ⅰ7和预埋钢板Ⅱ8下面焊接倒U形锚固钢筋17与承台永久结构相连,并在预埋钢板Ⅰ7和预埋钢板Ⅱ8下面设置三层水平加强钢筋网16,所述水平加强钢筋网16位于承台顶层钢筋15的下方,与倒U形锚固钢筋17和承台内钢筋分别连接。钢筋焊接网的纵筋与横筋形成网状结构,与混凝土粘结锚固性好,承受的载荷均匀扩散分布,能够明显提高钢筋混凝土结构的抗震裂性能。能够减少混凝土的裂缝,能够提高抗剪能力和局部抗压承载力。所述钢斜撑位于与其靠近的所述钢管立柱1的外侧,所述预埋钢板Ⅱ8和与其靠近的所述预埋钢板Ⅰ7是一整块钢板,以进一步方便施工。为了加强结构的稳定性,所述钢斜撑底端的销铰支座与靠近该销铰支座的所述钢管立柱的底部采用水平钢板连接。为了在满足结构强度和刚度的情况下,减轻结构重量,所述横向连接梁4、所述纵向支撑梁5、所述钢斜撑的构件、所述横向承重梁28和所述纵向分配梁29均采用双拼工字钢结构。为了进一步增强结构刚度,对应每一根所述水中墩柱2的四根所述钢管立柱1的底部通过水平连接构件Ⅱ9形成一体。为了确保钢管立柱1和预埋钢板Ⅰ7连接可靠,在所述钢管立柱1的底部设有与所述预埋钢板Ⅰ7焊接的加劲筋板。每个所述钢斜撑的两根所述撑杆3-1通过米字形钢结构连接在一起,施工方便,结构可靠。The steel pipe column 1 is under pressure, the connection between the bottom and the cap 12 is under local pressure, and the connection between the bottom hinge node of the steel diagonal brace and the cap 12 is under pressure and resists shearing. Shaped anchoring steel bars 17 are connected to the permanent structure of the platform cap, and three layers of horizontal reinforcing steel mesh 16 are arranged under the pre-embedded steel plate I7 and pre-embedded steel plate II8. The U-shaped anchoring steel bar 17 is connected with the inner steel bar of the cap respectively. The longitudinal bars and transverse bars of the welded steel mesh form a network structure, which has good bonding and anchoring properties with concrete, and the bearing load is evenly spread and distributed, which can significantly improve the anti-seismic cracking performance of reinforced concrete structures. It can reduce the cracks of concrete and improve the shear capacity and local compressive bearing capacity. The steel brace is located on the outside of the steel pipe column 1 adjacent to it, and the embedded steel plate II8 and the embedded steel plate I7 adjacent to it are a whole steel plate to further facilitate construction. In order to strengthen the stability of the structure, the pin-hinge support at the bottom end of the steel diagonal brace is connected with the bottom of the steel pipe column near the pin-hinge support by a horizontal steel plate. In order to reduce the weight of the structure while satisfying the structural strength and rigidity, the transverse connection beam 4, the longitudinal support beam 5, the members of the steel diagonal brace, the transverse load-bearing beam 28 and the longitudinal distribution beam 29 All adopt double I-beam structure. In order to further enhance the structural rigidity, the bottoms of the four steel pipe columns 1 corresponding to each of the underwater pier columns 2 are integrated through a horizontal connecting member II9. In order to ensure a reliable connection between the steel pipe column 1 and the embedded steel plate I7, a stiffener plate welded to the embedded steel plate I7 is provided at the bottom of the steel pipe column 1 . The two struts 3-1 of each of the steel diagonal braces are connected together through a rice-shaped steel structure, which is convenient for construction and reliable in structure.

综上所述,本发明在承台施工时预埋钢板,将钢管立柱和钢斜撑铰接节点焊接在预埋钢板上,拔除承台施工用的局部拉森桩后转动钢斜撑至指定角度,采取焊接横向连接梁的结构固定钢斜撑,通过焊接水平连接构件加强水平方向的支撑连接,在纵向相对的钢管立柱和钢斜撑上分别固定纵向连接梁,在多根纵向连接梁中部固定预顶钢管的限位卡板,为墩柱的预顶装置提供临时支撑;在多根纵向连接梁的两端分别固定砂箱,用来支撑两根横向承重梁,在两根横向承重梁上固定多根纵向分配梁,形成体系的水平支撑面。本发明是一个可循环利用的多功能支撑结构体系。In summary, the present invention pre-embeds the steel plate during the construction of the cap, welds the steel pipe column and the steel diagonal bracing hinge joints on the pre-embedded steel plate, pulls out the local Larsen pile used for the construction of the cap, and then rotates the steel diagonal brace to the specified angle , take the structure of welded horizontal connecting beams to fix the steel diagonal braces, strengthen the horizontal support connection by welding the horizontal connecting members, fix the longitudinal connecting beams on the vertically opposite steel pipe columns and steel diagonal braces, and fix the middle parts of multiple longitudinal connecting beams The limit clamping plate of the pre-jacking steel pipe provides temporary support for the pre-jacking device of the pier column; the sand boxes are respectively fixed at the two ends of the multiple longitudinal connecting beams to support the two horizontal load-bearing beams. Fix multiple longitudinal distribution beams to form the horizontal support surface of the system. The invention is a recyclable multifunctional supporting structure system.

由钢管立柱及钢斜撑形成的这种结构体系承担盖梁自重及施工荷载传递下来的竖向荷载,并将作用力传递至永久结构承台基础上,对永久结构影响较小,结构受力均匀,支撑稳固。且该结构体系,能够很好地解决其它支架体系由于钢管桩承受竖向荷载并通过与河床的摩擦力作用下导致钢管桩加长、从而造成基础稳定性能不足的现象。适用于淤泥质土层比较深的,在不加长支撑高度的情况下,满足承载力的要求。另外,在钢管立柱顶端焊接水平支撑盖板,一是可以在单点起吊时用于钢丝绳悬挂围绕,二是可以增大接触面积,使从上部传递下来的作用力能够均匀通过水平支撑盖板竖直传递给钢管立柱。This structural system formed by steel pipe columns and steel diagonal braces bears the vertical load transmitted by the self-weight of the cap beam and the construction load, and transmits the force to the foundation of the permanent structural cap, which has little impact on the permanent structure and the structural force Uniform and well supported. Moreover, this structural system can well solve the problem of insufficient foundation stability due to the lengthening of the steel pipe piles caused by the vertical load of the steel pipe piles and the friction with the river bed in other support systems. It is suitable for relatively deep silty soil layers, and meets the requirements of bearing capacity without increasing the support height. In addition, the horizontal support cover plate is welded on the top of the steel pipe column. First, it can be used for hanging around the steel wire rope when lifting at a single point. Pass directly to the steel pipe column.

在支架上设置预顶钢管,通过千斤顶对墩身施加预顶力,能够避免超长大体积盖梁砼收缩变形及徐变影响对墩身产生的应力造成局部节点混凝土开裂。预顶力加载完成后在预顶钢管与预顶钢板Ⅱ之间焊接钢构件,卸载千斤顶和承压座,将预顶力转移至钢构件上,预顶力可通过预顶钢管传递,作用于墩柱顶部以下1m左右范围内,使墩身顶部承受预顶力,能够与超长盖梁大体积混凝土收缩应力对墩顶产生的拉应力相互抵消,以避免节点产生裂纹和开裂。预推钢管需等到盖梁浇筑完成达到设计强度后方可拆除。Pre-jacking steel pipes are arranged on the support, and a pre-jacking force is applied to the pier body through a jack, which can avoid local joint concrete cracking caused by the stress generated by the shrinkage deformation and creep of the ultra-large-volume cap beam concrete on the pier body. After the pre-jacking force is loaded, the steel member is welded between the pre-jacking steel pipe and the pre-jacking steel plate II, the jack and the pressure seat are unloaded, and the pre-jacking force is transferred to the steel member. The pre-jacking force can be transmitted through the pre-jacking steel pipe and acts on the In the range of about 1m below the top of the pier column, the top of the pier body can bear the pre-jacking force, which can offset the tensile stress generated by the shrinkage stress of the super-long cover beam mass concrete on the pier top, so as to avoid cracks and cracks at the joints. The pre-pushed steel pipes cannot be removed until the cover beams are poured and reach the design strength.

设置在节点位置上的砂箱作为横向承重梁的下支点,标高可调节,能够有效避免支架安装过程出现误差,此外在盖梁施工完成后,可通过砂箱的下落(10~20cm)完成横向承重梁的下放,预留出底模拆除空间,利于拆模作业。The sand box set at the node position is used as the lower fulcrum of the horizontal load-bearing beam, and the elevation can be adjusted, which can effectively avoid errors in the installation process of the bracket. In addition, after the construction of the cover beam is completed, the sand box can be dropped (10-20cm) to complete the horizontal direction. The lowering of the load-bearing beams reserves a space for the removal of the bottom form, which is beneficial to the removal of the formwork.

用于调节标高的砂箱,首先需选用性能优良的工程砂,并且晒干,砂箱需提前进行承载性能试验,按照施工过程承受的荷载进行预压,通过试验获得相关参数,确定砂用量和加载之后砂自身挤压密实造成的高度减少量,施工时需根据该项参数预留出该高度。砂箱工作原理主要通过承压对砂产生挤压力,拧紧螺栓孔后砂箱承压,卸掉螺栓孔上的螺栓,用人工掏出砂箱内的砂,达到降低标高的作用。For the sand box used to adjust the elevation, it is first necessary to select engineering sand with excellent performance and dry it in the sun. The sand box needs to be tested for bearing performance in advance, and preloaded according to the load borne during the construction process. Relevant parameters are obtained through the test to determine the amount of sand and After loading, the height reduction caused by the compaction of the sand itself should be reserved according to this parameter during construction. The working principle of the sand box is mainly to generate extrusion force on the sand under pressure. After the bolt holes are tightened, the sand box is under pressure, the bolts on the bolt holes are removed, and the sand in the sand box is manually pulled out to reduce the elevation.

可调标高砂箱,作用类似于千斤顶。一套支撑体系共计20个,为保证各砂箱受力均匀,在墩柱间(单跨范围内)砂箱间距平均按6.06m布置,根据砂箱受力情况和砂箱装满工程砂后的压缩值。确定压缩值,预留压缩高度,精确调整砂箱顶标高,达到控制盖梁底模高度的目的。拆除底模时,先卸掉螺栓,用人工掏出砂箱内的砂,达到整体下落的目的,从而留出底模拆除空间。The height-adjustable sand box acts like a jack. There are a total of 20 supporting systems. In order to ensure that the sand boxes are evenly stressed, the sand box spacing between pier columns (within a single span) is arranged at an average of 6.06m. compression value. Determine the compression value, reserve the compression height, and accurately adjust the elevation of the top of the sand box to achieve the purpose of controlling the height of the bottom mold of the cover beam. When removing the bottom mold, the bolts are removed first, and the sand in the sand box is manually pulled out to achieve the purpose of falling as a whole, thereby leaving a space for the bottom mold to be removed.

砂箱作为整个支架体系的重要传递构件和拆模落架手段,可看作是横向承重梁的支座,施工时单个砂箱承受荷载在130t以上,因此需控制平面偏差,保持多点可调砂箱安装时的平面网精确,避免改变支架受力体系,造成体系失稳。需要对安装后的20个砂箱进行拉线测量并调整,确保标高一致,中心线在同一直线上,平面偏差不超过1cm。为确保施工安全,在使用砂箱前,随机取样在150t压力机上做试验,验证砂箱受力情况和砂箱装满工程砂后的压缩值(标准砂约为1cm,工程用黄砂可达2cm)。根据试验确定的压缩值,预留压缩高度,精确调整砂箱顶标高,达到控制盖梁底模高度平整的目的。The sand box, as an important transmission component of the entire support system and a means of removing the formwork, can be regarded as the support of the transverse load-bearing beam. During construction, a single sand box bears a load of more than 130t, so it is necessary to control the plane deviation and maintain multi-point adjustable sand. When the box is installed, the plane net is accurate to avoid changing the stress system of the bracket and causing the system to be unstable. It is necessary to measure and adjust the wires of the 20 sand boxes after installation to ensure that the elevations are consistent, the center lines are on the same straight line, and the plane deviation does not exceed 1cm. In order to ensure construction safety, before using the sand box, random samples are taken for testing on a 150t press to verify the force of the sand box and the compression value after the sand box is filled with engineering sand (standard sand is about 1cm, and engineering yellow sand can reach 2cm ). According to the compression value determined by the test, the compression height is reserved, and the elevation of the top of the sand box is precisely adjusted to achieve the purpose of controlling the height of the bottom formwork of the cover beam.

尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以做出很多形式,这些均属于本发明的保护范围之内。Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, people can also make many forms without departing from the purpose of the present invention and the scope of protection of the claims, and these all belong to the protection scope of the present invention.

Claims (10)

1.一种水中墩超长预应力盖梁施工支撑体系,所述盖梁下部设有至少两根水中墩柱,其特征在于,该支撑体系包括支架,所述支架包括设置在相邻两根水中墩柱之间的两个呈八字形布置的钢斜撑以及布设在每根所述水中墩柱周围的四根钢管立柱;对应每一根所述水中墩柱的四根所述钢管立柱的底端通过预埋钢板Ⅰ固定在该水中墩柱的承台的四个角部;每个所述钢斜撑设有两根撑杆,每个所述钢斜撑的两根所述撑杆在该支架横向立面上的投影重合,且纵向间距与纵向相邻的两根钢管立柱1的间距相同,每个所述钢斜撑的两根所述撑杆通过钢结构连接在一起,在每个所述撑杆的底端连接有销铰及其支座,所述钢斜撑底端的销铰支座通过预埋钢板Ⅱ与相应所述水中墩柱的承台连接,所述预埋钢板Ⅱ位于与其靠近的所述预埋钢板Ⅰ的外侧;呈八字形布置的两个所述钢斜撑的顶部通过横向连接梁连接;每根所述撑杆的顶端和每根所述钢管立柱的顶端均设有等标高的水平支撑盖板,在纵向相对的每两个所述水平支撑盖板上固定有一纵向支撑梁;所有所述钢管立柱和所有所述钢斜撑通过水平连接构件Ⅰ连接在一起;1. A super-long prestressed cover beam construction support system for pier in water, the bottom of the cover beam is provided with at least two pier columns in water, it is characterized in that, the support system includes a support, and the support includes two adjacent Two steel diagonal braces arranged in a figure-eight shape between the piers in the water and four steel pipe columns arranged around each of the piers in the water; the four steel pipe columns corresponding to each of the piers in the water The bottom end is fixed on the four corners of the caps of the piers in the water by pre-embedded steel plates I; The projections on the horizontal elevation of the bracket coincide, and the longitudinal distance is the same as the distance between two vertically adjacent steel pipe columns 1, and the two braces of each steel diagonal brace are connected together by a steel structure. The bottom end of each strut is connected with a pin hinge and its support, and the pin hinge support at the bottom end of the steel diagonal brace is connected to the cap of the corresponding underwater pier through the embedded steel plate II. The steel plate II is located on the outside of the pre-embedded steel plate I close to it; the tops of the two steel diagonal braces arranged in a figure-eight shape are connected by a transverse connecting beam; the top of each strut and each steel pipe column Horizontal support covers of the same elevation are provided at the top of each, and a longitudinal support beam is fixed on every two horizontal support covers vertically opposite; all the steel pipe columns and all the steel diagonal braces pass through the horizontal connecting member connected together; 在多根所述纵向支撑梁的两端各设有一砂箱,所述纵向支撑梁两端的砂箱分别支撑两根横向承重梁,在两根所述横向承重梁上固定多根并排布置的纵向分配梁,所有所述纵向分配梁形成体系的水平支撑面。A sand box is respectively provided at both ends of the plurality of longitudinal support beams, and the sand boxes at the two ends of the longitudinal support beams support two transverse load-bearing beams respectively, and a plurality of vertical load-bearing beams arranged side by side are fixed on the two transverse load-bearing beams. Distribution beams, all of said longitudinal distribution beams form the horizontal support surface of the system. 2.根据权利要求1所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,在所述支架上安装预顶机构,所述预顶机构包括相对的预顶钢板Ⅰ和预顶钢板Ⅱ,所述预顶钢板Ⅰ和所述预顶钢板Ⅱ分别预埋在相邻的两根水中墩柱的外侧表面上,在所述预顶钢板Ⅰ和所述预顶钢板Ⅱ之间自所述预顶钢板Ⅰ开始设有依次水平连接的预顶钢管、千斤顶和承压座,所述预顶钢管与所述预顶钢板Ⅰ连接;所述预顶钢管由限位卡板支撑,所述限位卡板固定在所述纵向支撑梁的中部顶面上。2. The super-long prestressed cover beam construction support system for pier in water according to claim 1, characterized in that a pre-jacking mechanism is installed on the support, and the pre-jacking mechanism includes a relative pre-jacking steel plate I and a pre-jacking Steel plate II, the pre-roof steel plate I and the pre-roof steel plate II are respectively pre-embedded on the outer surfaces of two adjacent water piers, and the pre-roof steel plate I and the pre-roof steel plate II are automatically The pre-jacking steel plate I is initially equipped with a pre-jacking steel pipe, a jack and a pressure seat connected horizontally in sequence, and the pre-jacking steel pipe is connected with the pre-jacking steel plate I; the pre-jacking steel pipe is supported by a limit clamp, so The limiting clamping plate is fixed on the middle top surface of the longitudinal support beam. 3.根据权利要求1所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,在所述预埋钢板Ⅰ和所述预埋钢板Ⅱ的下面焊接有倒U形锚固钢筋和水平加强钢筋网,所述水平加强钢筋网与所述倒U形锚固钢筋连接。3. The super-long prestressed cover beam construction support system for pier in water according to claim 1, characterized in that an inverted U-shaped anchoring steel bar and a horizontal Reinforcing reinforcement mesh, the horizontal reinforcement reinforcement mesh is connected with the inverted U-shaped anchoring reinforcement. 4.根据权利要求1所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,所述砂箱由与所述纵向支撑梁固接的下砂桶和上活塞支墩组成;在所述下砂桶内盛装有细砂体;所述上活塞支墩设有一倒置的桶体,在所述倒置的桶体内满筑有混凝土结构;所述倒置的桶体插装在所述下砂桶内,所述上活塞支墩由所述细砂体支撑,在所述下砂桶的下端侧壁上设有放砂口,在所述放砂口上安装有封堵门。4. The super-long prestressed cover beam construction support system of pier in water according to claim 1, wherein the sand box is composed of a lower sand bucket and an upper piston pier affixed to the longitudinal support beam; The lower sand barrel is filled with fine sand; the upper piston abutment is provided with an inverted barrel, and a concrete structure is built in the inverted barrel; the inverted barrel is inserted into the lower In the sand bucket, the upper piston abutment is supported by the fine sand body, and a sand outlet is provided on the side wall of the lower end of the lower sand bucket, and a plugging door is installed on the sand outlet. 5.根据权利要求4所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,所述放砂口是由螺纹孔形成的,所述封堵门是由螺栓形成的。5. The super-long prestressed cover beam construction support system for submerged pier according to claim 4, characterized in that, the sand outlet is formed by threaded holes, and the plugging door is formed by bolts. 6.根据权利要求4所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,所述倒置的桶体设有外缘伸出在该桶体之外的底部,形成支墩顶部支撑盖板;所述下砂桶的底部外缘伸出在所述下砂桶的桶体之外,形成砂箱的底部支撑托板。6. The super-long prestressed cover beam construction support system for pier in water according to claim 4, characterized in that, the inverted barrel is provided with a bottom with an outer edge protruding from the barrel to form the top of the buttress The supporting cover plate; the outer edge of the bottom of the lower sand bucket protrudes outside the body of the lower sand bucket to form the bottom supporting plate of the sand box. 7.根据权利要求1所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,所述预埋钢板Ⅱ和与其靠近的所述预埋钢板Ⅰ是一整块钢板。7. The super-long prestressed cover beam construction support system for underwater pier according to claim 1, characterized in that the embedded steel plate II and the embedded steel plate I adjacent to it are a whole steel plate. 8.根据权利要求1所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,所述横向连接梁、所述纵向支撑梁、所述钢斜撑的构件、所述横向承重梁和所述纵向分配梁均采用双拼工字钢结构。8. The super-long prestressed cover beam construction support system for pier in water according to claim 1, characterized in that, the transverse connecting beam, the longitudinal support beam, the member of the steel diagonal brace, and the transverse load-bearing beam Both the longitudinal distribution beam and the longitudinal distribution beam adopt a double-span I-beam structure. 9.根据权利要求1所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,对应每一根所述水中墩柱的四根所述钢管立柱的底部通过水平连接构件Ⅱ形成一体。9. The super-long prestressed cover beam construction support system for underwater pier according to claim 1, characterized in that the bottoms of the four steel pipe columns corresponding to each of the underwater pier columns are integrated through horizontal connecting members II . 10.根据权利要求1所述的水中墩超长预应力盖梁施工支撑体系,其特征在于,所述钢斜撑底端的销铰支座与靠近该销铰支座的所述钢管立柱的底部采用水平钢板连接。10. The super-long prestressed cover beam construction support system for pier in water according to claim 1, characterized in that, the pin-hinge support at the bottom end of the steel diagonal brace and the bottom of the steel pipe column near the pin-hinge support Connected by horizontal steel plates.
CN201410687410.8A 2014-11-25 2014-11-25 Pier prestressed cap beam with extra length Construction Supporting System in water Active CN104452597B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410687410.8A CN104452597B (en) 2014-11-25 2014-11-25 Pier prestressed cap beam with extra length Construction Supporting System in water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410687410.8A CN104452597B (en) 2014-11-25 2014-11-25 Pier prestressed cap beam with extra length Construction Supporting System in water

Publications (2)

Publication Number Publication Date
CN104452597A true CN104452597A (en) 2015-03-25
CN104452597B CN104452597B (en) 2016-06-29

Family

ID=52899298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410687410.8A Active CN104452597B (en) 2014-11-25 2014-11-25 Pier prestressed cap beam with extra length Construction Supporting System in water

Country Status (1)

Country Link
CN (1) CN104452597B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223207A (en) * 2016-09-13 2016-12-14 中国建筑土木建设有限公司 Bridge bent cap does not have and falls to ground support strutting arrangement and relevant support piece
CN108589516A (en) * 2018-07-05 2018-09-28 北京市市政工程设计研究总院有限公司 A bridge elastic support system with self-supporting steel structure
CN109944165A (en) * 2019-04-24 2019-06-28 中铁二十四局集团有限公司 A kind of temporary support method of the modularization regulating posture for the installation of prefabricated bent cap
CN110004832A (en) * 2019-04-09 2019-07-12 宁波市政工程建设集团股份有限公司 Long span cantilever truss formula bent cap strutting system and construction method
CN110144829A (en) * 2019-06-20 2019-08-20 中国五冶集团有限公司 A supporting structure for supporting the main structure of a tied arch bridge
CN110820574A (en) * 2019-11-07 2020-02-21 上海建工七建集团有限公司 A kind of inclined sand box device and installation and unloading method thereof
CN111254829A (en) * 2018-12-03 2020-06-09 沈阳市政集团有限公司 Supporting system for iron jacking sand box and construction method thereof
CN113073555A (en) * 2021-03-19 2021-07-06 中铁大桥局集团第四工程有限公司 Pier top block positioning system and construction method thereof
CN113431183A (en) * 2021-06-30 2021-09-24 机械工业第六设计研究院有限公司 Installation method of gallery truss with connected structure
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam
CN114960425A (en) * 2022-03-31 2022-08-30 广西路桥工程集团有限公司 Supporting device for square pier capping beam
CN115748498A (en) * 2022-12-16 2023-03-07 中建科工集团有限公司 Temporary support for steel box girder and construction method for steel box girder bridge

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202008003536U1 (en) * 2007-04-23 2008-05-29 Döllen, Heinz von Mobile superstructure for bridges, in particular steel composite bridges
FR2966173A1 (en) * 2010-10-19 2012-04-20 Conseil Service Investissements Method for forming spacer for connecting formwork to bridge piers during construction of bridge, involves fixing formwork plate behind projecting parts extending from non-right portion of beams
CN202865752U (en) * 2012-11-15 2013-04-10 中铁八局集团第二工程有限公司 Support used for pier bent cap on-site concrete
CN203684102U (en) * 2013-12-26 2014-07-02 浙江金筑交通建设有限公司 Prefabricated girder support system erected at the junction span of the ramp bridge and the main line bridge
CN103981809A (en) * 2014-05-15 2014-08-13 宝鸡中铁宝桥天元实业发展有限公司 Support beam falling method for surfaces of middle and small bridges and special support device
CN204343168U (en) * 2014-11-25 2015-05-20 中建六局第三建筑工程有限公司 Pier prestressed cap beam with extra length Construction Supporting System in water

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202008003536U1 (en) * 2007-04-23 2008-05-29 Döllen, Heinz von Mobile superstructure for bridges, in particular steel composite bridges
FR2966173A1 (en) * 2010-10-19 2012-04-20 Conseil Service Investissements Method for forming spacer for connecting formwork to bridge piers during construction of bridge, involves fixing formwork plate behind projecting parts extending from non-right portion of beams
CN202865752U (en) * 2012-11-15 2013-04-10 中铁八局集团第二工程有限公司 Support used for pier bent cap on-site concrete
CN203684102U (en) * 2013-12-26 2014-07-02 浙江金筑交通建设有限公司 Prefabricated girder support system erected at the junction span of the ramp bridge and the main line bridge
CN103981809A (en) * 2014-05-15 2014-08-13 宝鸡中铁宝桥天元实业发展有限公司 Support beam falling method for surfaces of middle and small bridges and special support device
CN204343168U (en) * 2014-11-25 2015-05-20 中建六局第三建筑工程有限公司 Pier prestressed cap beam with extra length Construction Supporting System in water

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223207A (en) * 2016-09-13 2016-12-14 中国建筑土木建设有限公司 Bridge bent cap does not have and falls to ground support strutting arrangement and relevant support piece
CN108589516A (en) * 2018-07-05 2018-09-28 北京市市政工程设计研究总院有限公司 A bridge elastic support system with self-supporting steel structure
CN111254829A (en) * 2018-12-03 2020-06-09 沈阳市政集团有限公司 Supporting system for iron jacking sand box and construction method thereof
CN110004832A (en) * 2019-04-09 2019-07-12 宁波市政工程建设集团股份有限公司 Long span cantilever truss formula bent cap strutting system and construction method
CN110004832B (en) * 2019-04-09 2024-03-05 宁波市政工程建设集团股份有限公司 Large-span cantilever truss type bent cap bracket system and construction method
CN109944165A (en) * 2019-04-24 2019-06-28 中铁二十四局集团有限公司 A kind of temporary support method of the modularization regulating posture for the installation of prefabricated bent cap
CN110144829A (en) * 2019-06-20 2019-08-20 中国五冶集团有限公司 A supporting structure for supporting the main structure of a tied arch bridge
CN110820574A (en) * 2019-11-07 2020-02-21 上海建工七建集团有限公司 A kind of inclined sand box device and installation and unloading method thereof
CN113073555A (en) * 2021-03-19 2021-07-06 中铁大桥局集团第四工程有限公司 Pier top block positioning system and construction method thereof
CN113431183A (en) * 2021-06-30 2021-09-24 机械工业第六设计研究院有限公司 Installation method of gallery truss with connected structure
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam
CN114960425A (en) * 2022-03-31 2022-08-30 广西路桥工程集团有限公司 Supporting device for square pier capping beam
CN115748498A (en) * 2022-12-16 2023-03-07 中建科工集团有限公司 Temporary support for steel box girder and construction method for steel box girder bridge

Also Published As

Publication number Publication date
CN104452597B (en) 2016-06-29

Similar Documents

Publication Publication Date Title
CN104452597B (en) Pier prestressed cap beam with extra length Construction Supporting System in water
CN113585049B (en) Self-resetting prefabricated assembled concrete filled steel tube pier node connecting structure with replaceable plastic hinges and construction method thereof
CN103866693B (en) A kind of mounting method of steel concrete bowstring arch bridge arch rib
CN113585053B (en) Prefabricated assembled concrete-filled steel tube pier with out-of-site tension prestress and construction method thereof
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN108412128A (en) A kind of connection structure of steel core concrete column
CN104831639B (en) A kind of ultra-wide nonprismatic continuous beam 0# block consolidation and releasing construction method
CN104452598B (en) The construction method of pier prestressed cap beam with extra length Construction Supporting System in water
CN109137739B (en) Tower anchor-pier anchor combined rapid construction method of self-anchored suspension bridge
CN211228066U (en) A connection structure of prefabricated steel pier and foundation
CN108425374B (en) Overall construction method of steel suspension box cofferdam with tie-beam dumbbell-type platform under complex sea conditions
CN206486819U (en) A kind of stable support body system for ensureing continuous beam cantilever casting construction
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN103233426A (en) Bailey beam support free of buttress in soft foundation and supporting method thereof
CN110318344A (en) A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method
CN212223642U (en) A kind of lateral diagonal bracing reinforcement structure of single-column pier bridge
CN204343168U (en) Pier prestressed cap beam with extra length Construction Supporting System in water
CN214168790U (en) Concrete-filled steel tube assembled truss composite beam construction system
CN206418464U (en) A kind of Bailey bracket support system
CN105696474A (en) Deformation-resisting strengthening method for arch bridge in surface deformation area
CN104404885B (en) The device of pre-jacking force is applied for pier prestressed cap beam with extra length in water
CN209128886U (en) A tower beam thrust connection device for rapid construction of self-anchored suspension bridges
CN104404884B (en) For the support of pier prestressed cap beam with extra length Construction Supporting System in water
CN108505449B (en) A construction method for the hoisting system of the underwater support of a concrete-filled steel tube arch bridge
CN204401462U (en) For the support of pier prestressed cap beam with extra length Construction Supporting System in water

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200327

Address after: 300451 No. 72, Hangzhou Road, Binhai New Area, Tianjin

Co-patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Address before: 300456 No. 75, Xingang Road, Tanggu District, Tianjin

Co-patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION NO.3 CONSTRUCTION ENGINEERING Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: No. 72 Hangzhou Road, Tianjin Binhai New Area, 300451

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee before: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.