CN104438476B - A kind of building steel tube apparatus for correcting - Google Patents

A kind of building steel tube apparatus for correcting Download PDF

Info

Publication number
CN104438476B
CN104438476B CN201410570860.9A CN201410570860A CN104438476B CN 104438476 B CN104438476 B CN 104438476B CN 201410570860 A CN201410570860 A CN 201410570860A CN 104438476 B CN104438476 B CN 104438476B
Authority
CN
China
Prior art keywords
block
fixed
standing groove
dsah
underframe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410570860.9A
Other languages
Chinese (zh)
Other versions
CN104438476A (en
Inventor
梁旭
陈伟
杨云章
杨云龙
吴俊�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MESKA GROUP CONSTRUCTION CO Ltd
Original Assignee
MESKA GROUP CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MESKA GROUP CONSTRUCTION CO Ltd filed Critical MESKA GROUP CONSTRUCTION CO Ltd
Priority to CN201410570860.9A priority Critical patent/CN104438476B/en
Publication of CN104438476A publication Critical patent/CN104438476A/en
Application granted granted Critical
Publication of CN104438476B publication Critical patent/CN104438476B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D3/00Straightening or restoring form of metal rods, metal tubes, metal profiles, or specific articles made therefrom, whether or not in combination with sheet metal parts
    • B21D3/10Straightening or restoring form of metal rods, metal tubes, metal profiles, or specific articles made therefrom, whether or not in combination with sheet metal parts between rams and anvils or abutments

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of building steel tube apparatus for correcting, including underframe, it is fixed with steel pipe on described underframe and places block, steel pipe is placed in block and is provided with standing groove, support column it is fixed with on underframe, servomotor and two bracers it are fixed with on support column, the two ends of screw mandrel are hinged on two bracers, the upper end of screw mandrel is stretched out upper support block and is connected by shaft coupling is fixing with the output shaft of servomotor, contiguous block is screwed onto in screw mandrel, upper holder block it is fixed with on contiguous block, the bottom surface of upper holder block has indent, the width of upper holder block is less than the width of standing groove, indent is the most corresponding with standing groove, the end face of indent is arcwall face, the bottom surface of standing groove is arcwall face.It is without manually correcting, and it can be with automatic straightening, and rectification effect is good, and efficiency is high.

Description

A kind of building steel tube apparatus for correcting
Technical field:
The present invention relates to Architectural Equipment technical field, a kind of building steel tube is rectified Equipment.
Background technology:
In construction site, be required to use some tubing, have solid or hollow, its In carrying more or less have bending produce, some tubing bending ratios are more serious, its general nothing Method reuses, and can only cast out, and some slight bending pipe fitting can be carried out by rectification again Secondary use, existing antidote one uses and is fixed at the two ends of bending tube, by briquetting pair Middle part bending part carries out bending rectification, and general employing manual rotation's screw rod, by the pressure on screw rod Block is corrected, and its efficiency is low, and artificial bending expends bodily strength, and labour intensity is big.
Summary of the invention:
It is an object of the invention to overcome the deficiencies in the prior art, it is provided that a kind of building steel tube corrects dress Putting, it is without manually correcting, and it can be with automatic straightening, and rectification effect is good, and efficiency is high.
The present invention solves the scheme of described technical problem:
A kind of building steel tube apparatus for correcting, including underframe, described underframe is fixed with steel pipe and places Block, steel pipe is placed in block and is provided with standing groove, underframe is fixed with support column, fixing on support column Having servomotor and two bracers, the two ends of screw mandrel are hinged on two bracers, screw mandrel Upper end is stretched out upper support block and is connected, even by shaft coupling is fixing with the output shaft of servomotor Connecing block to be screwed onto in screw mandrel, contiguous block is fixed with upper holder block, the bottom surface of upper holder block has indent, The width of upper holder block is less than the width of standing groove, and indent is the most corresponding with standing groove, the top of indent Face is arcwall face, and the bottom surface of standing groove is arcwall face;
Being fixed with two fixed blocks on underframe, two fixed blocks place the two ends of block at steel pipe, Gu Determining to be fixed with on block dsah-pot, spring sleeve is in dsah-pot, and the top of dsah-pot is fixed with even Connecing end cap, the connection dish block sleeve of the bottom of connection post is in dsah-pot, and described connection post includes The middle part that the forward end that the connection dish block of bottom and the middle part of connection dish block form extends connects Cylinder, connection dish block is pressed against on spring, connects the middle part of post through connecting end cap and being fixed on On position-limited rack, position-limited rack being fixed with limited block, two limited block sleeves respectively are in standing groove Two ends, middle part connect cylinder through connect end cap through hole, the diameter of through hole be less than connection dish The diameter of block.
Forming inserting column on described fixed block, inserting column sleeve is in dsah-pot, after spring End sleeve is in inserting column.
The prominent effect of the present invention is:
Compared with prior art, it is without manually correcting, and it can be corrected with automatic straightening Effective, efficiency is high.
Accompanying drawing illustrates:
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the partial side view of the present invention.
Detailed description of the invention:
The present invention will be described in detail with concrete preferred embodiment below in conjunction with the accompanying drawings, so that Advantages and features of the invention can be easier to be readily appreciated by one skilled in the art, and these embodiments are only It is only the purpose illustrated, it is no intended to the scope of the present invention is defined.
Embodiment, as shown in such as Fig. 1 to 2, a kind of building steel tube apparatus for correcting, including underframe 1, described underframe 1 is fixed with steel pipe and places block 2, steel pipe is placed in block 2 and is provided with standing groove 21, underframe 1 is fixed with support column 3, support column 3 is fixed with servomotor 4 and two Propping up bracer 41, the two ends of screw mandrel 42 are hinged on two bracers 41, the upper end of screw mandrel 42 Stretch out upper support block 41 and be connected by shaft coupling is fixing with the output shaft of servomotor 4, Contiguous block 5 is screwed onto in screw mandrel 42, and contiguous block 5 is fixed with upper holder block 51, upper holder block 51 Bottom surface there is indent 52, the width of upper holder block 51 is less than the width of standing groove 21, indent 52 is corresponding with standing groove about 21, and the end face of indent 52 is arcwall face, the end of standing groove 21 Face is arcwall face;
Being fixed with two fixed blocks 11 on underframe 1, two fixed blocks 11 place block 2 at steel pipe Two ends, fixed block 11 is fixed with dsah-pot 12, spring 13 sleeve in dsah-pot 12, The top of dsah-pot 12 is fixed with connection end cap 14, connects the connection dish block of the bottom of post 15 16 sleeves are in dsah-pot 12, and connection dish block 16 is pressed against on spring 13, connect post 15 Middle part through connecting end cap 14 being fixed on position-limited rack 17, position-limited rack 17 is fixed with Limited block 18, two limited block 18 sleeve two ends in standing groove 21 respectively.
Described connection post 15 includes that the connection dish block 16 of bottom becomes with the middle part of connection dish block 16 The middle part that the forward end that type has extends connects cylinder 151, and middle part connects cylinder 151 through connecting The through hole 141 of end cap 14, the diameter of through hole 141 is less than the diameter of connection dish block 16.
Forming inserting column 111 on described fixed block 11, inserting column 111 sleeve is at dsah-pot In 12, the rear end sleeve of spring 13 is in inserting column 111.
Operation principle: be placed on by steel pipe in standing groove 21, is then carried by servomotor 4 Movable wire bar 42 rotates so that upper holder block is pressed for 51 times, and sleeve is in standing groove 21 so that The top sleeve of steel pipe, in indent 52, is gradually reduced so that steel pipe pressure by indent 52 Directly, wherein, the two ends of steel pipe are to be carried out at the limited block 18 at standing groove 21 two ends by sleeve Spacing, along with steel pipe straightening elongated time, by the retraction of spring 13 so that limited block 18 exists Ensure to be clamped on the premise of steel pipe and retreat, it is ensured that the effect of rectification.
Embodiment of above is merely to illustrate the present invention, and not limitation of the present invention, relevant The those of ordinary skill of technical field, without departing from the spirit and scope of the present invention, Can also make a variety of changes and modification, the technical scheme of the most all equivalents falls within the present invention Category, the scope of patent protection of the present invention should be defined by the claims.

Claims (1)

1. a building steel tube apparatus for correcting, including underframe (1), it is characterised in that: described Being fixed with steel pipe on underframe (1) and place block (2), steel pipe is placed in block (2) and is provided with standing groove (21), underframe (1) being fixed with support column (3), support column is fixed with servo on (3) Motor (4) and two bracers (41), the two ends of screw mandrel (42) are hinged on two bracers (41) on, the upper end of screw mandrel (42) stretch out upper support block (41) and by shaft coupling with The output shaft of servomotor (4) is fixing to be connected, and contiguous block (5) is screwed onto in screw mandrel (42), Being fixed with upper holder block (51) on contiguous block (5), the bottom surface of upper holder block (51) has indent (52), The width of upper holder block (51) is less than the width of standing groove (21), indent (52) and standing groove (21) corresponding up and down, the end face of indent (52) is arcwall face, the bottom surface of standing groove (21) For arcwall face;
Being fixed with two fixed blocks (11) on underframe (1), two fixed blocks (11) are at steel pipe Place the two ends of block (2), fixed block (11) is fixed with dsah-pot (12), spring (13) Sleeve is in dsah-pot (12), and the top of dsah-pot (12) is fixed with connection end cap (14), Connection dish block (16) sleeve of the bottom of connection post (15) is in dsah-pot (12), described Connect post (15) and include that connection dish block (16) of bottom becomes with the middle part of connection dish block (16) The middle part that the forward end that type has extends connects cylinder (151), and connection dish block (16) is pressed against bullet On spring (13), connect the middle part of post (15) through connecting end cap (14) and being fixed on spacing On frame (17), position-limited rack (17) is fixed with limited block (18), two limited blocks (18) Sleeve two ends in standing groove (21) respectively, middle part connects cylinder (151) through connecting The through hole (141) of end cap (14), the diameter of through hole (141) is less than connection dish block (16) Diameter;
Inserting column (111), inserting column (111) sleeve is formed on described fixed block (11) In dsah-pot (12), the rear end sleeve of spring (13) is in inserting column (111).
CN201410570860.9A 2014-10-23 2014-10-23 A kind of building steel tube apparatus for correcting Expired - Fee Related CN104438476B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410570860.9A CN104438476B (en) 2014-10-23 2014-10-23 A kind of building steel tube apparatus for correcting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410570860.9A CN104438476B (en) 2014-10-23 2014-10-23 A kind of building steel tube apparatus for correcting

Publications (2)

Publication Number Publication Date
CN104438476A CN104438476A (en) 2015-03-25
CN104438476B true CN104438476B (en) 2016-08-24

Family

ID=52885669

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410570860.9A Expired - Fee Related CN104438476B (en) 2014-10-23 2014-10-23 A kind of building steel tube apparatus for correcting

Country Status (1)

Country Link
CN (1) CN104438476B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105268782B (en) * 2015-11-13 2017-06-16 舟山长宏国际船舶修造有限公司 A kind of railing apparatus for correcting
CN105946040B (en) * 2016-05-25 2018-05-08 惠安网信通技术开发有限公司 A kind of plastic cylinder body fixes perforating mechanism
CN105946034B (en) * 2016-05-25 2018-06-05 吉林大学 A kind of plastic cylinder body fixed mechanism with interfix
CN115780579B (en) * 2023-01-05 2023-04-18 唐山奥达机械制造有限公司 Automatic straightening equipment for cold-drawn steel

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204182723U (en) * 2014-10-23 2015-03-04 美信佳集团建设有限公司 A kind of building steel tube apparatus for correcting

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11179465A (en) * 1997-12-17 1999-07-06 Showa Alum Corp Manufacturing device for heat-exchanger and manufacture thereof
US6234000B1 (en) * 1999-09-20 2001-05-22 Wiley L. Bowling Ball-bat repairing method
US7310987B1 (en) * 2006-07-17 2007-12-25 Eitel Presses, Inc. Bend-straightening machine with vertically movable table
CN201603778U (en) * 2010-01-05 2010-10-13 深圳市新沧海机械有限公司 Automatic detecting and straightening machine for rod piece
CN202725688U (en) * 2012-06-13 2013-02-13 上海天阳钢管有限公司 Lifting type steel pipe straightening machine
CN203330188U (en) * 2013-06-29 2013-12-11 江西锐特实业有限公司 Shaft part straightening clamp

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204182723U (en) * 2014-10-23 2015-03-04 美信佳集团建设有限公司 A kind of building steel tube apparatus for correcting

Also Published As

Publication number Publication date
CN104438476A (en) 2015-03-25

Similar Documents

Publication Publication Date Title
CN104438476B (en) A kind of building steel tube apparatus for correcting
CN201978974U (en) Shriveled pipe restorer
CN204431095U (en) Mechanical type oil pipe pressure test fixture
CN204182723U (en) A kind of building steel tube apparatus for correcting
CN204182722U (en) A kind of hollow steel pipe means for correcting for building
CN103994932B (en) Reinforcing steel bar bending tester
CN204381125U (en) A kind of tubing straightening and bending device
CN206873887U (en) A kind of adjustable construction scaffold
CN104708190A (en) Suspension type siphon horizontal drainage pipe welding correcting support
CN105221042A (en) The structure of the protection grid of size adjustable
CN204974835U (en) Steel pipe bar straightener is used in municipal administration
CN204332907U (en) One is high puts bulb-changing device
CN204449614U (en) A kind of suspension type siphon drainage transverse tube welding correcting bracket
CN104014950A (en) Reinforcement steel framework seam welder with steel bar penetrating assisting plate and use method thereof
CN204002452U (en) The structure of the protection grid that size is adjustable
CN209124640U (en) A kind of small-caliber steel pipe means for correcting
CN207724877U (en) Heavy caliber solid wall pipe tube head supporting rack
CN204194489U (en) Steel pipe brace
CN205382700U (en) Embedded nut formula is wall spare even
CN201940933U (en) Tool special for detaching expansion sleeve of trimmed roller way
CN205600216U (en) Welding jig suitable for steel pipe
CN205743777U (en) Power tongs for drill rod
CN205763074U (en) A kind of steel tube straightener
CN204475862U (en) Length-adjustable construction formwork is to drawing device
CN105584024A (en) Extrusion type die taking jig

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: No. 358, Zijing Road, Huzhou Economic and Technological Development Zone, Huzhou City, Zhejiang Province, 313000

Patentee after: MESKA GROUP CONSTRUCTION Co.,Ltd.

Address before: No. 589, Waihuan East Road, Huzhou City, Zhejiang Province, 313000

Patentee before: MESKA GROUP CONSTRUCTION Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160824

Termination date: 20211023