CN104376767A - Practical training platform device for handling typical low-voltage faults - Google Patents

Practical training platform device for handling typical low-voltage faults Download PDF

Info

Publication number
CN104376767A
CN104376767A CN201410668857.0A CN201410668857A CN104376767A CN 104376767 A CN104376767 A CN 104376767A CN 201410668857 A CN201410668857 A CN 201410668857A CN 104376767 A CN104376767 A CN 104376767A
Authority
CN
China
Prior art keywords
connection terminal
outlet
watt
phase
hour meter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410668857.0A
Other languages
Chinese (zh)
Inventor
吴宗兵
董如春
郝韩兵
戴芳
刘洋洋
高书勇
吴岚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Chuzhou Power Supply Co of State Grid Anhui Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Chuzhou Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Chuzhou Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410668857.0A priority Critical patent/CN104376767A/en
Publication of CN104376767A publication Critical patent/CN104376767A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B23/00Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes
    • G09B23/06Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics
    • G09B23/18Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism
    • G09B23/188Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism for motors; for generators; for power supplies; for power distribution

Landscapes

  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Algebra (AREA)
  • Power Engineering (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Physics (AREA)
  • Pure & Applied Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Educational Administration (AREA)
  • Educational Technology (AREA)
  • Theoretical Computer Science (AREA)
  • Emergency Protection Circuit Devices (AREA)

Abstract

The invention discloses a practical training platform device suitable for training staff to check and rapidly handle kinds of typical low-voltage faults for the electric power department. The practical training platform device comprises a power supply unit, an electric equipment control unit, a metering unit and an electric equipment wiring terminal unit. The practical training platform device fills up the blank of skill training at the low voltage below 1000 V in the State Grid Corporation. By simulating the scene of the typical low-voltage faults through the practical training platform device, repeated, complete and targeted exercise can be done to handle the typical low-voltage faults, the working method is improved, the ability of analyzing and solving problems of repairing staff is improved, the personal safety of the on-site repairing staff is guaranteed, manpower and material input is reduced, the traditional method that a master trains apprentices for a long time is improved, the repairing efficiency is improved, and the service quality is improved for customers.

Description

Typical low pressure fault handling training platform device
Technical field:
The present invention relates to a kind of typical low pressure fault handling training platform device, be mainly used in power department typical low pressure malfunction elimination and fast processing training.
Background technology:
Distribution low voltage failure type complexity is various, and low voltage failure has sudden with uncertainty, after low-voltage distribution repairing staff arrives fault in-situ, may run into and occur various wiring error and fault, repair personnel wants to identify fast, investigate, handling failure, and restores electricity.Dissimilar fault handling means are different, and this just requires that repair personnel will possess sturdy theory and level of skill, can rapidly removing faults.Due to the insecurity at low voltage failure scene and the rapidity of process, determine can not carry out repeatedly at fault in-situ, complete, have for exercise.
Summary of the invention:
For overcoming the defect of prior art, the object of the present invention is to provide a kind of typical low pressure fault handling training platform device, can carry out repeatedly typical fault, complete, have for exercise, improve operational method, improve repair personnel's analyze and solve problem ability, ensure the personal safety of scene rush to repair personnel.
Technical solution problem of the present invention adopts following technical scheme:
Typical low pressure fault handling training platform device:
Arranging front and back is uncovered monoblock type cabinet, the support of multiple layering is provided with in described cabinet, support in described cabinet is disposed with main breaker, the first watt-hour meter be arranged side by side, the second watt-hour meter and single-phase watt-hour meter, three-phase and four-line associating connection terminal, three current transformers, the first isolating switch be arranged side by side, the second isolating switch and safety box, the first group of connection terminal be arranged side by side, second group of connection terminal and the 3rd group of connection terminal;
Three-phase and four-line incoming power accesses described main breaker, and the outlet of main breaker is divided into three times, and main breaker first outlet is through described first isolating switch of described three current transformers access, and the outlet of the first isolating switch accesses described first group of connection terminal; Main breaker second outlet accesses the second watt-hour meter, and the second watt-hour meter outlet accesses the second isolating switch, and the second breaker outgoing line accesses second group of connection terminal; Main breaker the 3rd outlet accesses described single-phase watt-hour meter, and the outlet of single-phase watt-hour meter accesses described safety box, the described 3rd group of connection terminal of safety box outlet access.
Main breaker first outlet is through three current transformers, and Current Transformer Secondary line accesses the current segment of described three-phase and four-line associating connection terminal; On first isolating switch, pile crown connects three-phase and four-line associating terminal voltage part; The outlet of three-phase and four-line associating connection terminal connects described first watt-hour meter, the described first group of connection terminal of outlet access of the first isolating switch.
The invention provides a kind of training platform device being applicable to all kinds of low pressure typical fault investigation of power department and fast processing training, this training platform device comprises power supply unit, consumer control module, metering units, consumer binding post unit.This stage apparatus fills up the blank of Liao Guowang company below 1000V (low pressure) skills practice training, simulation typical low pressure fault in-situ is carried out by this training platform device, can carry out repeatedly typical fault, complete, have for exercise, improve operational method, improve repair personnel's analyze and solve problem ability, ensure the personal safety of scene rush to repair personnel, decrease the input of manpower and materials, improve traditional master worker and be with empty method (master worker grows the time of training an apprentice), improve first-aid repair efficiency, improve the service quality of client.
Compared with the prior art, beneficial effect of the present invention is embodied in:
1, typical low pressure fault handling training platform has filled up the blank of state's net skills practice training, the large portion of state's net skills training is 10kV and above, below 1kV electric pressure skills training part is less, but with residential customers closely bound up electric fault of living is by chance the fault of below 1kV electric pressure, therefore fast finding, judgement and process low voltage failure, resident's satisfaction can be improved, improve the social responsibility of power supply enterprise, by the real training of platform, the level of skill of power distribution rush-repair personnel can be improved.
2, typical low pressure fault handling training platform carries out repetition training to complicated and diversified distribution low voltage failure, improve field failure first-aid repair efficiency, reduce the wasting of resources caused because fault-time is long simultaneously, (fault can be searched as early as possible, process as early as possible, some consumers such as blowdown, noise reduction can use in time), effectively can reduce environmental pollution.
3, typical low pressure fault handling training platform adds perfect protective device, can charged or have a power failure carry out real training, during real training, platform safety has more controllability.
4, carry out in-site modeling by training platform, single or comprehensive real training can be carried out to all kinds of typical fault, by repeatedly, complete, have for exercise, improve operational method, improve repair personnel analyze and solve problem ability.
5, typical low pressure fault handling training platform combines all kinds of low pressure typical fault, on-the-spot by platform simulation, decreases the input of manpower and materials, improves traditional master worker and be with empty method.
Accompanying drawing illustrates:
Fig. 1 is typical low pressure fault handling training platform apparatus structure schematic diagram of the present invention; Fig. 2 is typical low pressure fault handling training platform electrical schematics of the present invention.
Number in the figure: 1 main breaker, 2 first isolating switchs, 3 second isolating switchs, 4 safety boxs, 5 first watt-hour meter, 6 second watt-hour meter, 7 single-phase watt-hour meters, 8 three-phase and four-line associating connection terminals, 9 first groups of connection terminals, 10 second groups of connection terminals, 11 the 3rd groups of connection terminals, 12 current transformers, 13 monoblock type cabinets.
Below by way of embodiment, and the invention will be further described by reference to the accompanying drawings.
Embodiment:
Embodiment: the typical low pressure fault handling training platform device of the present embodiment is as Fig. 1, shown in 2, in specifically arranging, main breaker 1 is DZ20-160 plastic casing breaker, first isolating switch 2 is DZ20-100 plastic casing breaker, second isolating switch 3 is DZ20-100 plastic casing breaker, safety box 4 is the insurance of RC-100A ceramic pluging type, first watt-hour meter 5 is DTS 3 × 1.5 (6) three-phase and four-line multi-function watt-hour meter, second watt-hour meter 6 is DTS 3 × 10 (60) type three-phase four-wire watt-hour meter, single-phase watt-hour meter 7 is DDS 5 (20) single-phase watt-hour meter, current transformer 12 is three LMZ J1-0.66kV-300/5 current transformers, monoblock type cabinet 1 is a whole cabinet device of GGD, single unit system is rectangular cabinet, height 1.4 meters, wide 1 meter, dark 0.4 meter, the 1.2 millimeters of steel plates in cabinet two side and top are closed, the whole plastic-blasting of device steel plate used, prevents corrosion.Device inside comprises power supply unit, consumer control module, metering units, consumer binding post unit.Cabinet is divided into upper and lower two parts, positive and negative two doors in top, height 50 centimetres, positive and negative two the door height 90 centimetres in bottom.GGD inner side surface of cabinet support is provided with five, makes of (∠ 30 × 3) angle steel; In cabinet, level is provided with two, support, makes of (∠ 50 × 5) angle steel; Horizontal stand two ends are erected in side supports, for installing each electric equipment, are also fixed with 30 × 3 copper bar insulators in cabinet.Bottom of cabinet bulk fixes φ 10 screw, screw is used BV-25 multiple grounding.
Device inside comprises power supply unit, consumer control module, metering units, consumer binding post unit.Power supply unit incoming power is three-phase four-wire power, accesses DZ20-160 shape shell main breaker 1, for controlling training platform device general supply by VV22-3 × 35+1 × 25.Electricity device control cell is with the general supply of main breaker 1 parametric controller.Described metering units, comprises LMZ J 1-0.66kV-300/5 current transformer three; Three-phase and four-line associating connecting terminal box one; DDS 5 (20) type single-phase watt-hour meter one piece; DTS 3 × 10 (60) type three-phase four-wire watt-hour meter one piece; DTS 3 × 1.5 (6) three-phase and four-line multi-function watt-hour meter one piece.Described consumer binding post unit, comprises first group to the 3rd group connection terminal.
Monoblock type cabinet 13 front and back is uncovered, the support of layering in cabinet is provided with main breaker 1, the first watt-hour meter 5, second watt-hour meter 6 and the single-phase watt-hour meter 7 be arranged side by side, three-phase and four-line associating connection terminal 8, be arranged side by side three current transformers 12, the first isolating switch 2, second isolating switch 3 and the safety box 4 be arranged side by side, the first group of connection terminal be arranged side by side, 9, second group of connection terminal 10 and the 3rd group of connection terminal 11.Zero line is connected with copper bar by wire.
Three-phase and four-line incoming power accesses main breaker 1 by VV22-3 × 35+1 × 25, the outlet of main breaker 1 is divided into three times, main breaker first outlet is moulded by BV-50 the outlet that copper cash accesses the first isolating switch 2, first isolating switch 2 through three current transformers and is moulded copper wire access first group of connection terminal 9 by BV-50; Main breaker second outlet access is moulded copper cash second watt-hour meter 6, second watt-hour meter outlet by BV-50 and is moulded the outlet of copper wire access second isolating switch 3, second isolating switch 3 by BV-50 and mould copper wire access second group of connection terminal 10 by BV-50; Main breaker the 3rd outlet moulds copper wire access single-phase watt-hour meter 7 by BV-25, and the outlet access safety box 4 of single-phase watt-hour meter, safety box outlet moulds copper wire access the 3rd group of connection terminal by BV-25.
Main breaker first outlet is through three current transformers, and Current Transformer Secondary line moulds the current segment of copper wire access three-phase and four-line associating connection terminal 8 by BV-4; On first isolating switch 2, pile crown is moulded copper cash by BV-2.5 and is connect three-phase and four-line associating connection terminal 8 voltage segment; The outlet that the outlet of three-phase and four-line associating connection terminal 8 connects the first watt-hour meter 5, first isolating switch 2 moulds copper wire access first group of connection terminal 9 by BV-50.
Real training mode is as follows:
1, table meter fault.
Typical low pressure fault handling training platform is by loosening single-phase watt-hour meter connection terminal, and the table meter live wire inlet wire that simulated field causes because of consumer overload blows fault.When student processes this fault, extracting RCIA 100A 380V type and insert fuse (simulation disconnect user internal electric source inlet wire master switch), whether having exception, ammeter whether to have registration by observing ammeter line terminals outward appearance; If there is registration, and to measure this ammeter 2,4 voltage between terminals with multimeter be 220V (or having electricity with electroscope measurement), be then user's internal fault.If without registration, and to measure this ammeter 1,3 voltage between terminals with multimeter be 220V, and to measure this ammeter 2,4 voltage between terminals with multimeter be 0V (or measuring without electricity with electroscope), be then table meter fault.Treating method, for using acceptable safety protective articles, is again made joint and is accessed this table meter, if voltage is 220V and table meter recovers normal between this table meter 2,4 terminal, can recover power transmission after errorless on inspection; After if again do, joint accesses this ammeter, between 2,4 terminals, voltage is still 0, be then table meter internal fault, disconnected by ammeter mains side, change ammeter for subsequent use.If there is no ammeter for subsequent use, can temporarily by ammeter 1,3 terminal, 2,4 terminal short circuits, recover power transmission temporarily, and then change ammeter.
Three-phase and four-line direct active watt-hour meter fault handling method is with similar above.The fault handling of three-phase and four-line multifunctional electric energy meter is divided into primary fault and secondary failure, if wire, a primary side current mutual inductor burn out, (will simulate disconnect user internal electric source inlet wire master switch), restringing, mutual inductor, then restore electricity.Secondary wiring fault, three-phase and four-line is combined connection terminal current return short circuit, voltage circuit is opened, and changes secondary line, then restores electricity.
2, insurance fault is inserted
Typical low pressure fault handling training platform takes out by inserting insurance internal fuse, the slotting insurance fuse opening fault that simulated field causes because crossing consumer.When student processes this fault, disconnect RCIA 100A 380V type and insert insurance (user's internal electric source inlet wire master switch), by field condition, it is normal that insurance inlet wire side voltage is inserted in the measurement of application multimeter, outgoing line side voltage is 0V, can judge to insure fuse opening.Treating method is use by the insulation instrument of handle and the working cloth of comprehensive coat-sleeve, and insulated shoes worn by tape insulation gloves, extracts and inserts insurance, changes the fuse of dimension, inserts and inserts insurance, recovers power transmission.If RCIA 100A380V type is inserted insurance and burnt out, cannot fuse being changed, when ensureing safety temporarily with 4mm2 aluminum steel short circuit, then more can insert insurance.
Goat's horn insurance fault handling method with insert insure similar.
3, low-pressure plastic shell circuit breaker fault
Typical low pressure fault handling training platform loosens by moulding pile crown splicing ear on shell main breaker 1, the low tension switch fault that simulated field causes because of consumer overload.When student processes this fault, shell main breaker (user's internal electric source inlet wire master switch) is moulded in disconnection, and by field condition, it is normal that breaker of plastic casing inlet wire side voltage measured by application multimeter, outgoing line side voltage is 0V, can tentatively judge to mould the tripping operation of shell main breaker.To mould shell main breaker reset button to reset, switch is sent in examination, normally can power transmission.If abnormal, mains side, for using acceptable safety protective articles, disconnects by treating method, after changing fault breaker of plastic casing, and power transmission.For subsequent usely mould shell main breaker if do not have, consider that repairing recovers power transmission, will can mould shell main breaker about 1 terminal respectively with the interim short circuit of fuse temporarily, recovery power transmission, and then change isolating switch.
4, consumer binding post unit fault
Typical low pressure fault handling training platform passes through consumer binding post unit loosened screw, simulated field consumer inlet wire fault, first visual examination.It is normal that consumer connection terminal line voltage measured by application multimeter, consumer inlet wire side voltage is 0V, can be judged as that consumer connection terminal outgoing line side is to consumer inlet wire side fault, disconnect consumer, disconnect binding post unit gauge tap, check that after changing fault wire, power transmission is normal.Measure consumer connection terminal primary voltage with multimeter normal, outgoing line side voltage is 0V, can be judged as consumer connection terminal fault, disconnects binding post unit gauge tap, and check and change connection terminal, power transmission is normal.

Claims (2)

1. typical low pressure fault handling training platform device, is characterized in that:
Arranging front and back is uncovered monoblock type cabinet (13), the support of multiple layering is provided with in described cabinet, support in described cabinet is disposed with main breaker (1), the first watt-hour meter (5) be arranged side by side, second watt-hour meter (6) and single-phase watt-hour meter (7), three-phase and four-line associating connection terminal (8), three current transformers (12), the first isolating switch (2) be arranged side by side, second isolating switch (3) and safety box (4), the first group of connection terminal (9) be arranged side by side, second group of connection terminal (10) and the 3rd group of connection terminal (11),
Three-phase and four-line incoming power accesses described main breaker (1), the outlet of main breaker (1) is divided into three times, main breaker first outlet is through described first isolating switch (2) of described three current transformers access, and the outlet of the first isolating switch (2) accesses described first group of connection terminal (9); Main breaker second outlet accesses the second watt-hour meter (6), and the second watt-hour meter outlet accesses the second isolating switch (3), and the second isolating switch (3) outlet accesses second group of connection terminal (10); Main breaker the 3rd outlet accesses described single-phase watt-hour meter (7), and the outlet of single-phase watt-hour meter accesses described safety box (4), the described 3rd group of connection terminal of safety box outlet access.
2. typical low pressure fault handling training platform device according to claim 1, it is characterized in that, main breaker first outlet is through three current transformers, and Current Transformer Secondary line accesses the current segment of described three-phase and four-line associating connection terminal (8); The upper pile crown of first isolating switch (2) connects three-phase and four-line associating connection terminal (8) voltage segment; Three-phase and four-line associating connection terminal (8) outlet connects described first watt-hour meter (5), the described first group of connection terminal (9) of outlet access of the first isolating switch (2).
CN201410668857.0A 2014-11-20 2014-11-20 Practical training platform device for handling typical low-voltage faults Pending CN104376767A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410668857.0A CN104376767A (en) 2014-11-20 2014-11-20 Practical training platform device for handling typical low-voltage faults

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410668857.0A CN104376767A (en) 2014-11-20 2014-11-20 Practical training platform device for handling typical low-voltage faults

Publications (1)

Publication Number Publication Date
CN104376767A true CN104376767A (en) 2015-02-25

Family

ID=52555650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410668857.0A Pending CN104376767A (en) 2014-11-20 2014-11-20 Practical training platform device for handling typical low-voltage faults

Country Status (1)

Country Link
CN (1) CN104376767A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104794968A (en) * 2015-05-20 2015-07-22 国家电网公司 Low-voltage electric energy measuring, mounting and connection analyzing comprehensive practical training device
CN106960619A (en) * 2016-12-30 2017-07-18 绍兴电力设备成套公司 Integrate electrical practice training and the training set and application method of low-voltage collecting meter reading failure
CN108548947A (en) * 2018-03-30 2018-09-18 上海电力学院 A kind of guillotine type electric energy metering combined wiring box
CN109994013A (en) * 2019-04-12 2019-07-09 广西电网有限责任公司桂林供电局 Low-voltage collecting meter reading failure safe hidden troubles removing emulation training device
CN112578319A (en) * 2021-01-12 2021-03-30 国网山东省电力公司成武县供电公司 Low-voltage distribution cabinet equipment line connection point monitoring alarm device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006149026A (en) * 2004-11-17 2006-06-08 Chugoku Electric Power Co Inc:The Apparatus, method and program for power interruption and for generating instantaneous voltage drop area diagram information and area displaying system
CN201508645U (en) * 2009-08-27 2010-06-16 北京市电力公司 Low-voltage comprehensive fault simulation device
CN203300112U (en) * 2013-06-19 2013-11-20 陕西省彬县职业教育中心 Electricity measurement and electricity distribution demonstration board
CN203366568U (en) * 2013-07-04 2013-12-25 北京北研兴电力仪表有限责任公司 Low-voltage fault-clearing program-controlled simulation device
CN204117459U (en) * 2014-11-20 2015-01-21 国家电网公司 Typical low pressure fault handling training platform device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006149026A (en) * 2004-11-17 2006-06-08 Chugoku Electric Power Co Inc:The Apparatus, method and program for power interruption and for generating instantaneous voltage drop area diagram information and area displaying system
CN201508645U (en) * 2009-08-27 2010-06-16 北京市电力公司 Low-voltage comprehensive fault simulation device
CN203300112U (en) * 2013-06-19 2013-11-20 陕西省彬县职业教育中心 Electricity measurement and electricity distribution demonstration board
CN203366568U (en) * 2013-07-04 2013-12-25 北京北研兴电力仪表有限责任公司 Low-voltage fault-clearing program-controlled simulation device
CN204117459U (en) * 2014-11-20 2015-01-21 国家电网公司 Typical low pressure fault handling training platform device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104794968A (en) * 2015-05-20 2015-07-22 国家电网公司 Low-voltage electric energy measuring, mounting and connection analyzing comprehensive practical training device
CN104794968B (en) * 2015-05-20 2018-03-13 国家电网公司 Low-voltage electric energy metering is installed and wiring analysis comprehensive training device
CN106960619A (en) * 2016-12-30 2017-07-18 绍兴电力设备成套公司 Integrate electrical practice training and the training set and application method of low-voltage collecting meter reading failure
CN108548947A (en) * 2018-03-30 2018-09-18 上海电力学院 A kind of guillotine type electric energy metering combined wiring box
CN109994013A (en) * 2019-04-12 2019-07-09 广西电网有限责任公司桂林供电局 Low-voltage collecting meter reading failure safe hidden troubles removing emulation training device
CN109994013B (en) * 2019-04-12 2024-05-14 广西电网有限责任公司桂林供电局 Low-voltage centralized meter reading fault potential safety hazard investigation simulation training device
CN112578319A (en) * 2021-01-12 2021-03-30 国网山东省电力公司成武县供电公司 Low-voltage distribution cabinet equipment line connection point monitoring alarm device

Similar Documents

Publication Publication Date Title
CN106935089B (en) Power information acquisition terminal installation training system and method
CN104376767A (en) Practical training platform device for handling typical low-voltage faults
CN106094571B (en) Multifunctional anti-electricity-theft simulation experiment platform
CN107945608A (en) Almightiness type power supply station Training in Comprehensive Skills device
CN108847078B (en) Dress table meets electric training system
CN103840438B (en) The detecting system of the intellectualized switchgear ground protection function of distribution network systems
CN101867225A (en) Debugging method for integrated automation of transformer substation and integration of relaying protection system
CN101769980A (en) Testing method simulating power transmission debugging
CN106383308A (en) Charge control circuit breaker automatic breaking/closing test device
CN105319466B (en) A kind of middle pressure electric equipment simulation live testing test method
CN204117459U (en) Typical low pressure fault handling training platform device
CN108597291A (en) A kind of matching net wire loss simulation training system
CN104794968B (en) Low-voltage electric energy metering is installed and wiring analysis comprehensive training device
CN204720059U (en) A kind of high-voltage electric-energy meter is installed and test training device
CN102024363A (en) Simulated training system of load breaker
CN108152779A (en) Electronic current mutual inductor check system and method
CN206097639U (en) Low -pressure measurement trains equipment
CN107978205A (en) A kind of measuring equipment load simulator
Tatcho et al. A real time digital test bed for a smart grid using RTDS
CN112396906A (en) Comprehensive simulation system for professional post skills and examination of electricity inspection for actual operation
CN102024364A (en) Simulated training system
CN106023748A (en) Low-voltage metering training device
CN208271415U (en) Almightiness type power supply station Training in Comprehensive Skills device
CN205809573U (en) Multi-function electricity fraudulent using-proof Simulation Experimental Platform
CN102707117A (en) Relaying multifunctional tester

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150225

WD01 Invention patent application deemed withdrawn after publication