CN107978205A - A kind of measuring equipment load simulator - Google Patents
A kind of measuring equipment load simulator Download PDFInfo
- Publication number
- CN107978205A CN107978205A CN201710038978.0A CN201710038978A CN107978205A CN 107978205 A CN107978205 A CN 107978205A CN 201710038978 A CN201710038978 A CN 201710038978A CN 107978205 A CN107978205 A CN 107978205A
- Authority
- CN
- China
- Prior art keywords
- equipment
- branch
- measuring equipment
- current
- load simulator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004088 simulation Methods 0.000 claims abstract description 12
- 238000004445 quantitative analysis Methods 0.000 claims description 3
- 238000004880 explosion Methods 0.000 abstract description 7
- 238000010586 diagram Methods 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000014509 gene expression Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000000819 phase cycle Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G09—EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
- G09B—EDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
- G09B23/00—Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes
- G09B23/06—Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics
- G09B23/18—Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism
- G09B23/187—Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism for measuring instruments
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/50—Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
Abstract
The invention discloses a kind of measuring equipment load simulator, including the emulation circuit being made of current simulations branch and voltage dummy branch parallel connection, emulate the 380V exchange inputs of a termination three-phase four-wire system in circuit, other end reception checks equipment, current simulations branch and voltage dummy branch are capable of providing the high-tension current of equipment to be checked in actual work, phase voltage and phase current, before formal be powered, it is powered using the simulation load of network voltage outside system and simulates energization, since the simulator possesses defencive function, even if the wiring error of equipment to be checked will not cause damage of product or explosion, work efficiency can be effectively improved, preferably protect equipment and the safety of personnel, reduce because explosion causes employee to be laid off caused by wiring error the problem of.
Description
Technical field
The present invention relates to a kind of power equipment wiring testing device, particularly a kind of high-voltage electric energy measurement machine utilization emulation
Device.
Background technology
Substation is generally by switching, the composition such as high-voltage meter, transformer and low-voltage cabinet, is set when substation checks and accepts metering
When standby, general electric current, voltage transformer and electric energy meter fit together after individually examining and determine, due to kilowatt-hour meter and transformer interface
Line is at least 7-12, wiring error often occur phase fault or it is alternate over the ground etc., plus wiring caused by secondary lead wires
Up to 28 kinds of mistake, in addition since measuring room personnel are unstable or operated by casual labour, more and more kilowatt-hour meters and mutual inductor
The frequent wrong of connection, such as pressure-wire phase sequence mistake, voltage and current line dislocation, PT multiple groundings, in some units 1 year
Occurs misconnection problem for several times, the batch meter of a 10kV or 35kV is ten hundreds of due to being lost caused by wiring error, due to connecing
Phenomena such as line mistake causes PT explosions, damages is also commonplace, and each side then mutually shifts responsibility onto others for the ownership of responsibility, often responsibility
Construction team or equipment production firm are pushed to, the safety of stability and personnel to electric system also results in great threat.Study carefully it
Reason, is because when new user accesses, does not have load in high-tension line, also without corresponding phase voltage and phase current, moreover, mesh
Preceding many metrology and measurement equipment are all high with low school, it is impossible to reflect actual conditions.
The content of the invention
For overcome the deficiencies in the prior art, the present invention, which provides one kind, can realize that height emulates, and protect equipment and personnel
The measuring equipment load simulator of safety.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of measuring equipment load simulator, including imitated by what current simulations branch and voltage dummy branch parallel connection were formed
True circuit, the 380V exchange inputs of a termination three-phase four-wire system in the emulation circuit, other end reception check equipment.
The current simulations branch includes sequentially connected pressure regulator T1 and high pressure current lifting device T2, the pressure regulator T1 settings
There is GSS Gear Select Switch.
The voltage dummy branch includes sequentially connected circuit breaker Q F, drop/pressure regulator T3 and booster T4.
The emulation circuit is connected with A.C. contactor CJ between input is exchanged with the 380V.
The equipment to be checked includes measuring equipment, electric energy meter and electric energy meter quantitative analysis instrument.
The beneficial effects of the invention are as follows:The current simulations branch and voltage dummy branch of the present invention is capable of providing to be checked set
Standby high-tension current, phase voltage and phase current in actual work, before formal be powered, is carried out using the simulation load of network voltage
Energization is simulated outside electric power system, since the simulator possesses defencive function, even if the wiring error of equipment to be checked will not
Damage of product or explosion are caused, work efficiency can be effectively improved, preferably protect equipment and the safety of personnel, is reduced because wiring is wrong
The problem of causing explosion to cause employee to be laid off by mistake.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is one of embodiments of the present invention schematic diagram;
Fig. 2 is two schematic diagrams of embodiments of the present invention.
Embodiment
Reference Fig. 1, Fig. 2, a kind of measuring equipment load simulator, including by current simulations branch and voltage dummy branch
The emulation circuit that parallel connection is formed, the 380V exchange inputs of a termination three-phase four-wire system in the emulation circuit, other end reception inspection
Look into equipment such as measuring equipment, electric energy meter and electric energy meter quantitative analysis instrument etc..The current simulations branch includes sequentially connected tune
Depressor T1 and high pressure current lifting device T2, the pressure regulator T1 are provided with GSS Gear Select Switch such as 10KV, 20KV, 35KV.The voltage
Dummy branch includes sequentially connected circuit breaker Q F, drop/pressure regulator T3 and booster T4.Handed over the 380V in the emulation circuit
A.C. contactor CJ is connected between stream input.
In the present embodiment, booster T4 output voltages such as 10kV, 20kV, 35kV, high pressure current lifting device T2 output current are such as
10th, 50,75,100A, phase voltage, phase current are exactly corresponding emulation capacity such as 10kV × 1.73 × 100A=1732kVA.This hair
Bright simulator emulation capacity be O.1-60000kVA, voltage 10kV, 10/ √ 3kV (expressions of √ 3 radical sign 3), 20kV,
20/ √ 3kV, 35kV, 35/ √ 3kV etc., monophase current before formal be powered, utilize the simulation of network voltage in below 1000A
Load is powered outside system and simulates energization, since the simulator possesses defencive function, even if the wiring of equipment to be checked is wrong
Mistake will not cause damage of product or explosion, can effectively improve work efficiency, preferably protect equipment and the safety of personnel, reduce
Because explosion causes employee to be laid off caused by wiring error the problem of.
Claims (5)
1. a kind of measuring equipment load simulator, it is characterised in that it is included by current simulations branch and voltage dummy branch simultaneously
Join the emulation circuit formed, the 380V exchange inputs of a termination three-phase four-wire system in the emulation circuit, other end reception checks
Equipment M.
2. measuring equipment load simulator according to claim 1, it is characterised in that the current simulations branch includes
Sequentially connected pressure regulator T1 and high pressure current lifting device T2, the pressure regulator T1 are provided with GSS Gear Select Switch.
3. measuring equipment load simulator according to claim 1, it is characterised in that the voltage dummy branch includes
Sequentially connected circuit breaker Q F, drop/pressure regulator T3 and booster T4, the drop/pressure regulator T3 are provided with tap changer.
4. the measuring equipment load simulator according to claim 1,2 or 3, it is characterised in that the emulation circuit and institute
State between 380V exchanges input and be connected with A.C. contactor CJ.
5. measuring equipment load simulator according to claim 1, it is characterised in that the equipment to be checked includes meter
Measure equipment, electric energy meter and electric energy meter quantitative analysis instrument.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710038978.0A CN107978205A (en) | 2017-01-19 | 2017-01-19 | A kind of measuring equipment load simulator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710038978.0A CN107978205A (en) | 2017-01-19 | 2017-01-19 | A kind of measuring equipment load simulator |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107978205A true CN107978205A (en) | 2018-05-01 |
Family
ID=62004215
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710038978.0A Pending CN107978205A (en) | 2017-01-19 | 2017-01-19 | A kind of measuring equipment load simulator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107978205A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109684661A (en) * | 2018-11-19 | 2019-04-26 | 积成电子股份有限公司 | The emulation mode of measuring instrument based on IEC62056 agreement |
CN111415559A (en) * | 2020-05-28 | 2020-07-14 | 广东电网有限责任公司培训与评价中心 | Series-type low-voltage three-phase four-wire electric energy metering simulation wiring training cabinet |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201508373U (en) * | 2009-08-27 | 2010-06-16 | 中化二建集团电仪安装工程有限公司 | Three-phase current generator |
CN101769980A (en) * | 2008-12-31 | 2010-07-07 | 新疆维吾尔自治区送变电工程公司 | Testing method simulating power transmission debugging |
CN102062829A (en) * | 2010-09-25 | 2011-05-18 | 珠海市科荟电器有限公司 | Simulation detector of power grid |
CN103236689A (en) * | 2013-04-10 | 2013-08-07 | 安徽节源节能科技有限公司 | Power quality diagnosis and management simulating device |
CN103336216A (en) * | 2013-05-30 | 2013-10-02 | 国家电网公司 | GIS equipment fault simulation test system |
CN103675751A (en) * | 2013-11-28 | 2014-03-26 | 国家电网公司 | Three-phase voltage and current analog power source for site metering device |
CN204575760U (en) * | 2015-01-29 | 2015-08-19 | 乐清市乐松自动化科技有限公司 | A kind of assembled electric cabinet pick-up unit with reactive-load compensation verification |
CN204925293U (en) * | 2015-07-21 | 2015-12-30 | 中国石油化工股份有限公司 | Power line error detection device |
-
2017
- 2017-01-19 CN CN201710038978.0A patent/CN107978205A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101769980A (en) * | 2008-12-31 | 2010-07-07 | 新疆维吾尔自治区送变电工程公司 | Testing method simulating power transmission debugging |
CN201508373U (en) * | 2009-08-27 | 2010-06-16 | 中化二建集团电仪安装工程有限公司 | Three-phase current generator |
CN102062829A (en) * | 2010-09-25 | 2011-05-18 | 珠海市科荟电器有限公司 | Simulation detector of power grid |
CN103236689A (en) * | 2013-04-10 | 2013-08-07 | 安徽节源节能科技有限公司 | Power quality diagnosis and management simulating device |
CN103336216A (en) * | 2013-05-30 | 2013-10-02 | 国家电网公司 | GIS equipment fault simulation test system |
CN103675751A (en) * | 2013-11-28 | 2014-03-26 | 国家电网公司 | Three-phase voltage and current analog power source for site metering device |
CN204575760U (en) * | 2015-01-29 | 2015-08-19 | 乐清市乐松自动化科技有限公司 | A kind of assembled electric cabinet pick-up unit with reactive-load compensation verification |
CN204925293U (en) * | 2015-07-21 | 2015-12-30 | 中国石油化工股份有限公司 | Power line error detection device |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109684661A (en) * | 2018-11-19 | 2019-04-26 | 积成电子股份有限公司 | The emulation mode of measuring instrument based on IEC62056 agreement |
CN111415559A (en) * | 2020-05-28 | 2020-07-14 | 广东电网有限责任公司培训与评价中心 | Series-type low-voltage three-phase four-wire electric energy metering simulation wiring training cabinet |
CN111415559B (en) * | 2020-05-28 | 2022-03-29 | 广东电网有限责任公司培训与评价中心 | Series-type low-voltage three-phase four-wire electric energy metering simulation wiring training cabinet |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105974348B (en) | Low-voltage current mutual inductor comprehensive detection system and its method | |
CN103440803B (en) | The authentic training system of 10kV power distribution equipment real voltage analog current closed loop | |
CN201893058U (en) | Safe simulation training system for distribution room | |
CN102097024B (en) | Distribution room safety simulation training system | |
CN201853401U (en) | Distribution room simulation system | |
CN101739877A (en) | Simulation training system of 10KV typical customer distribution room | |
CN205620485U (en) | A intelligent integrated detection device for low pressure current transformer integrates | |
CN107356830B (en) | Simulation transformer training device | |
CN104376767A (en) | Practical training platform device for handling typical low-voltage faults | |
CN103267917A (en) | Method and device for full-load test of high-capacity reactive compensation device without direct utilization of power grid | |
CN107978205A (en) | A kind of measuring equipment load simulator | |
CN206583994U (en) | A kind of intelligent distribution network terminal installation testing stand | |
CN108919016A (en) | A kind of voltage dip generator and voltage dip pilot system | |
CN205450042U (en) | Experimental switching operation platform of power transformer | |
CN108152779A (en) | Electronic current mutual inductor check system and method | |
CN102565614B (en) | Alternating voltage loop test method | |
CN204117459U (en) | Typical low pressure fault handling training platform device | |
CN208027622U (en) | A kind of measuring equipment load simulator | |
CN210142411U (en) | Universal power supply station practical training operating system and anti-electricity-stealing practical training circuit thereof | |
CN104698335A (en) | Method for debugging high-voltage transformer substation in systematization mode by using low tension electricity | |
CN204758750U (en) | Anti short circuit ability dynamic evaluation simulation model device of current transformer | |
CN216013543U (en) | Relay protection device batch test system | |
CN203432994U (en) | Phase sequence conversion device of three-phase alternating current tester | |
CN215599288U (en) | Distribution intelligent terminal grounding performance testing device | |
CN102707117A (en) | Relaying multifunctional tester |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |