CN104370407B - A kind of well work mine water underground purifies and cyclic utilization system - Google Patents

A kind of well work mine water underground purifies and cyclic utilization system Download PDF

Info

Publication number
CN104370407B
CN104370407B CN201410485558.3A CN201410485558A CN104370407B CN 104370407 B CN104370407 B CN 104370407B CN 201410485558 A CN201410485558 A CN 201410485558A CN 104370407 B CN104370407 B CN 104370407B
Authority
CN
China
Prior art keywords
water
grades
mine water
mine
pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410485558.3A
Other languages
Chinese (zh)
Other versions
CN104370407A (en
Inventor
张超
尹燕广
崔宗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Environmental Energy (Shandong) Environmental Technology Co.,Ltd.
Original Assignee
张超
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 张超 filed Critical 张超
Priority to CN201410485558.3A priority Critical patent/CN104370407B/en
Publication of CN104370407A publication Critical patent/CN104370407A/en
Application granted granted Critical
Publication of CN104370407B publication Critical patent/CN104370407B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Suspended Particles By Flocculating Agents (AREA)

Abstract

The present invention relates to a kind of well work mine water underground purify and cyclic utilization system, the water sand piece-rate system being sequentially connected with, fine particle pretreatment system, strengthen coagulation system, flco speed subsystem, sludge treating system for three grades.The present invention has simplification pump selection and maintenance, the abrasion of minimizing pipeline and burn into are easy to process with follow-up water utilize the advantages such as technique is connected.

Description

A kind of well work mine water underground purifies and cyclic utilization system
Art
The present invention relates to a kind of well work mine water underground purify and cyclic utilization system.
Background technology
Traditional mine water treatment technique is to spend huge energy consumption will to collect in sump by the Central Pump Room of mine Mine water rises to floor treatment, simultaneously as the deposition of coal dust rock dust, is usually the shape of " Cang Shui, half storehouse mud " in sump State, has had a strong impact on the dischargeable capacity of sump, for preventing water damage from there is the biggest potential safety hazard.Simultaneously as water pump lifting Be the sewage containing float, pump efficiency is severely impacted, and the pump housing and sewerage system damage are serious.Traditional handicraft accounts for Ground area is huge, operation stability is poor, operating cost is high, investment is big.And industrial water under mine, need huge at surface construction Clear water reserviors, complicated tubing is transported to underground work face, causes unnecessary waste.(1) the regular desilting of shaft sump A difficult problem: the mud of deposition in sump, needs to dig clearly in time, and this can bring many potential safety hazards, spend substantial amounts of expense of bringing down stocks; There is " messy " phenomenon in floor treatment technique, pollutant shift, and cause the secondary pollution of environment..
Along with the mine circular economy industrial that mine water resource is the most in short supply and water consumption is big is fast-developing, the money of mine water Source is worth and increasingly comes into one's own, and particularly in hydropenia mining area, mine water has become as main industry, domestic water source, And clearly write industry technical policy and design specification.Drainage sunk well in mine Mine Water Transacting Technology and Water purification at present The tightst inseparable system engineering, has become as the primary goal for the treatment of mine drainage for recycling;Mine class enterprise Floor treatment technique easily causes the unordered discharge of coal slime, wastes mine resource.
Summary of the invention
It is an object of the invention to provide a kind of in the direct treatment and purification of down-hole, first meet downhole production water, surplus Rise to the technical matters that floor synthetic utilizes.Meet mine industry energy conservation, keep the safety in production, reduce production cost, water resource combine Close the demand utilized.
The technical solution adopted for the present invention to solve the technical problems is: a kind of well work mine water underground purifies and circulation profit By system, the water sand piece-rate system being sequentially connected with, fine particle pretreatment system, strengthen coagulation systems for three grades, flco speed is divided and is System, sludge treating system;
Described water sand piece-rate system includes elevator, scrapper conveyor chute, collects mud sump and belt-type elevating conveyor, elevator, Scrapper conveyor chute is separately fixed on the two side of collection mud sump, and belt-type elevating conveyor is connected with elevator;
Described fine particle pretreatment system includes the three grades of sedimentation tanks being sequentially connected with, and belt-type elevating conveyor is by mine water Send into first order sedimentation tank, pneumatic sludge pump is set in first order sedimentation tank, stirring diving slurry is installed bottom two or three grades of ponds Pump, three grades of sedimentation tank deposits, by the sludge treating system of transport pump to rear end, go the mine water after oil removal by quiet State pipe-line mixer, one-level stirring pool;
Described three grades of reinforcement coagulation systems be sequentially connected with communicate static pipeline mixer, one-level stirring pool, two grades Stirring pool and three grades of stirring pools, static pipeline mixer;
Described flco speed subsystem sludge treating system mud magnetic separating device, is connected by multiple rare-earth magnetic discs and forms, from Three grades of stirring pools mine water out enters mud magnetic separating device, recycles after filter;
Described sludge treating system includes sludge pump and the pressure filter being sequentially connected with.
1, water sand piece-rate system:
Mine water is more than containing substantial amounts of diameter the coal petrography granule of 5mm, according to grading, counts roughly and account for float More than 70%, it is achieved water particle diameter big with this part coal petrography granule separates, and is the key of this system process technology, is also follow-up work The basis of skill.Owing to conditions down-hole limits, traditional eddy flow removes sand, gravitational settling technique cannot be applied.
Present invention employs bucket lifting+bottom 40T scraper plate chute+80 transhipment belt combined process of aperture 0.5CM.? Mine water is after central authorities' water channel collects, and the fighter first flowing into the positive negative zero in tunnel arranged below collects mud sump, and in pond setting angle 80 Degree, the continuous way bucket elevator of lift bucket dehydration aperture 0.5cm, it is achieved the separation of major part granule, connect updip after collection mud sump Pond salvaged by angle groove-like scraper plate chute, can process the particulate matter that the remaining particulate matter of lift bucket, lift bucket and chute are collected, focus on The transhipment belt of lift bucket front end, can continuously, high throughput, realize water sand efficiently and separate and the rapid transport of mud is to mine Transportation system.Mine water gravity flow after removing sand enters next processing unit.
2, fine particle pretreatment system:
Mine water after removing sand, the most a large amount of containing particle diameter, less than 5mm to the float more than 300 μm, (SS is for go further Except this partial contamination thing, this technological design three swirler circle bores sedimentation tank deeply, arranges pneumatic spoil disposal in first order sedimentation tank Pump, is delivered to the sludge treating system of rear end by the particulate matter of fast deposition, installs stirring diving slag in front end bottom two or three grades of ponds Stock pump.Current tangent line enters, and increases bulky grain suspended substance sedimentation speed and deposition, and deposit is by the dirt of transport pump to rear end Mud sump focuses on.The mine water after oil removal is gone to flow automatically entrance next unit again.
3, coagulation system is strengthened for three grades
Through the mine water of pretreatment, after by fine particle processing unit, arrange after first passing through third level preliminary sedimentation tank Inclination angle static pipeline mixer, add PAC and dense media (Fe3O4 content 95%, moisture 8%, sulfur-bearing in blender 0.1%, true density 4.5g/cm3)) carry out the coagulating first season, water outlet enters first order high-speed stirred pond, and oar blade type stirs Device, rotating speed 150r/min, after abundant coagulation stirs, in the stirring pool of the second level, add PAM(polyacrylamide), second level frame Posture stirs, and rotating speed 90r/min, the third level adds strong mixing, frame-type, rotating speed 35r/min
Add the mine water of strong mixing coagulation through three grades, define the small floccule body with dense media as core, by hanging in water Float and dense media particle flocculation to together with.Realizing the initial gross separation with water, gravity flow enters flco speed subsystem together.
4, flco speed subsystem.
Utilize magnetic force of inducting the dense media floc sedimentation float in waste water to be salvaged to separate, reach purification of water quality and suspension The purpose that thing reclaims, it is necessary to meet following relationship
Wherein:
FMagnetic---act on the magnetic force in the floc sedimentation float with dense media as core;
∑FMachine---making a concerted effort of all mechanical forces contrary with magnetic force direction.
Weight component that ∑ F machine is included in aqueous medium, microgranule are along magnetic force FMagneticAqueous medium suffered during the motion of direction glues Scold resistance and the acceleration resistance of grain orientation motion.
Only meet FMagnetic≥∑FMachineTime, dense media floc sedimentation float its is possible to adsorbed under the action of a magnetic field separation.
The usefulness law of down-hole treatment is pressed formula and is calculated:
Wherein:
N effectiveness parameters;
δ grain density;
The viscosity of μ water;
SAlwaysThe total effective area of magnetic action;
Q processes flow;
D particle diameter.
Magnetic force is the biggest, and down-hole treatment equipment effectiveness is the highest, and degree of association is first power proportional relation.
Magnetic force effective area is the biggest, and down-hole treatment equipment effectiveness is the highest, and degree of association is first power proportional relation.
This process selection rare-earth Nd-Fe-B permanent magnetic steel (intensity between Surface field intensity 3500gs adjacent magnetic field 2000gs), form the high magnetic field intensity of work space and high magnetic field gradients, make in waste water dense media microgranule and flocculation adsorption at it On namagnetic substance microgranule, under magnetic field force effect, overcome the mechanical external force such as fluid resistance and microgranule gravity, it is the most fixed to produce To motion, absorption is on rare-earth magnetic disc surface, thus the float in waste water is separated, and completes flco speed point process.Remove The mine water gravity flow of float enters next unit
5, sludge treating system:
In system 4 isolated mud flco, the dense media added containing system 3, this partial sludge initially enters mud magnetic Segregation apparatus reclaims dense media, and the response rate more than 99%, the dense media of recovery is by adding pump circulating to system 3.After de-magnetic Mud can homologous ray 2 discharge mud, be delivered to pressure filter dehydration and drying by sludge pump, mud cake passes through underground transport system Outward transport.
6, ultra-filtration system:
Containing the SS of about 10mg/l in system 4 water outlet, for ensureing follow-up comprehensive utilization water quality, system water outlet is again from flowing to Enter gravity stream accurate filter, go out aqueous suspension and ensure between 3-5mg/l.Accurate filter spoil disposal enters system 5.
7, down-hole reclaiming system:
According to down-hole productive prospecting, down-hole fire-fighting, depositing dust, rinse, backfill, the production link such as oil emulsion water distribution can make Use substantial amounts of industrial water.Conventional approach is the sewage collected by shaft sump, rises to ground by Central Pump Room, is building Sewage disposal system and pond, roughing-in, it is transported to down-hole and uses.Huge investment and energy consumption need to be spent.
The present invention uses down-hole direct reuse technique, by multistage frequency conversion constant pressure water supply system, by the water outlet of system 6, root According to mine demand, it is transported to each setting, meets fire-fighting, depositing dust use.Simultaneously according to oil emulsion water distribution demand and water quality Situation, if clean water, can direct adapted, if salinity and hardness exceed standard, the most supporting UF+RO system does advanced treating, Surplus gravity flow after reuse enters next unit.
8, sump drainage system: each mine enterprise, according to safety code and design specification, all can have shaft sump and join Set Central Pump Room drainage system, the water outlet of present system 7, gravity flow enters sump, by Central Pump Room, is promoted to ground.
9, floor synthetic utilizes system:
What system 8 was emitted into ground is treated clean water, and according to the function distribution that grass work is wide, ground sets Thribble meets the clear water reserviors of 4 hours storage time according to the water yield, is water source according to this, is available for ground fire demand water, and power plant's cooling follows Ring water, mill water, it is available for worker's bath water, Office Area reclaimed water etc. after sterilization.Meanwhile, if in system 7 breast Carburetion water distribution does not possess the condition of realization, can fetch water in pond, ground, builds small-scale terrestrial water desalting plant, with oil emulsion scientific matching After, by pipeline, static pressure is to each oil setting.Water-deficient area can be according to consumption and water quality, and supporting clean unit is as quoting Water.Through above-mentioned 9 systems, the sewage produced in production process can be recycled by mine enterprise to greatest extent, and minimizing is taken out Take underground water source or outsourcing production, domestic water.
10, electric-control system:
Whole set process realizes automatic control, remotely controls, EPA under surge well, also can upload field video signal.? Grass control room, can omnidistance remote control, monitoring process flow process overall process.
The invention has the beneficial effects as follows: 1. simplify pump selection and maintenance
Shaft sump water is risen to ground by ground treatment strategies, needs to use Pulp pump, as long as down-hole treatment scheme is then Select clarified water pump, the drainability of equivalent specifications, use clarified water pump can investment reduction 30%--50%, extend maintenance period simultaneously 3--4 times.
2. pipeline abrasion and corrosion are reduced
Coal slime in mine water and float are not only worn and torn pump part, but also heavy wear discharge pipe line, according to investigations, Under equal conditions, the service life of down-hole treatment scheme drain pipe is 2-3 times of aboveground processing scheme drain pipe service life.Special It not for acid mine water, after down-hole is neutralized process, rises to ground again, the use of water pump and pipeline can be extended Life-span more than 5 times.
3. it is easy to utilize nearby
The important utilization ways of reclamation of mine water is for down-hole depositing dust, watering and fire demand water and oil emulsion at present Preparation water.Use ground treatment strategies time, the cleaning mine water after process needs to return to down-hole, cause pipeline turn back laying, The reciprocal waste transported also increases equipment operating cost.Clear water can be delivered directly to down-hole water spot by down-hole treatment scheme, Convenient, efficient, after surplus clear water puts in storage, ground can be promoted to as comprehensive utilization water source.
4. land seizure is reduced
Mine water ground treatment strategies typically constitutes from by bigger land area, with daily handling ability 10000m3Mine water As a example by treatment plant, from preliminary sedimentation tank to clear water reserviors, need 5 to 6 grades of structures, need land area 5000-8000m2, and Underground Department Reason scheme, area of plane 300m2?;Use down-hole treatment technique, can be colliery development newly-increased ground production system displacement Soil.
5. sump dischargeable capacity efficiency is improved.Major part mine is all at downhole designs volume 2000m3Above central water Storehouse, a large amount of coal slimes in mine water, rock dust etc. quickly precipitate at sump, have impact on dischargeable capacity and suspended substance sedimentation efficiency, and one As within every 1 to 3 months, will dig clearly once.Down-hole treatment scheme can process swallet, coal slime and float directly, continuously Separated in time, it is ensured that the maximum dischargeable capacity of central water sump, substantially increased the ability of mine defending flood and water damage.
6. mechanization sump cleaning is realized
It is the hard working of high intensity that shaft sump digs clearly, is limited by down-hole site condition, work occurs in operation the most repeatedly Hinder accident.And down-hole treatment scheme uses independent sludge treating system to reclaim coal slime, dramatically reduce coal slime heavy in down-hole Form sediment, greatly reduce heavy physical work, novel mechanical can be used convenient for a small amount of coal slime of deposition in sump at a specified future date Reclaim.
7. climate change effect it is not afraid of.
Mine water Ground Processing System can be disturbed by worst case meteorological conditions such as severe cold, heavy rain, sand and dust, has a strong impact on place Reason effect, special for being northern area, need to add a cover, increase the isolation climatic effect of HVAC facility.Down-hole treatment scheme then environment bar Part is constant, favourable continuous service.
8. clear water gug, it is simple to utilize.
Mine water underground process technique can realize clear water and rise to ground, is equivalent to newly beat water source at a glance in mine Well, can supply the various uses such as production, fire-fighting, depositing dust, bathing, greening easily.
9. it is easy to process with follow-up water utilize technique to be connected.
Along with the new mining area exploitation of the deep production of Old Eastern mining area and western part, need the mine water of special handling and advanced treating More and more, the prerequisite of special handling and advanced treatment process is the former water of input cleaning, mine water underground processing scheme Effluent quality can reach special handling and advanced treatment process water inlet requirement.Major part mine is all built particularly at present Ground mine sewage treatment plant, after clear water gug, can transform spy as according to follow-up water requirement original Sewage Plant Different and advanced treating plant stand.The construction space of preciousness is provided for subsequent treatment.
10. coal recovery it is easy to.
Mine water underground processing scheme uses pressure filter to reclaim coal slime, and filter cake moisture, can be direct in down-hole about 40% Enter transport, promote system, reclaimed coal slime resource the most to greatest extent, and efficiently solved the coal slime that floor treatment is brought " messy " problem.
Accompanying drawing explanation
Fig. 1 is water sand piece-rate system structural representation.
Fig. 2 is fine particle pretreatment system structural representation.
Fig. 3 is table 7-1 schematic diagram.
Detailed description of the invention
A kind of well work mine water underground purifies and cyclic utilization system, the water sand piece-rate system being sequentially connected with, fine particle Pretreatment system, strengthens coagulation system, flco speed subsystem, sludge treating system for three grades;
Described water sand piece-rate system includes elevator 1, scrapper conveyor chute 2, collection mud sump 3 and belt-type elevating conveyor 4, promotes Machine 1, scrapper conveyor chute 2 are separately fixed on the two side of collection mud sump 3, and belt-type elevating conveyor 4 is connected with elevator 1;
Described fine particle pretreatment system includes the three grades of sedimentation tanks being sequentially connected with, and belt-type elevating conveyor 4 is by mine Water sends into first order sedimentation tank 5, arranges and be provided with stirring diving bottom 6,23 grades of ponds of pneumatic sludge pump in first order sedimentation tank 4 Pulp pump 7, three grades of sedimentation tank deposits, by the sludge treating system of transport pump to rear end, go the mine water after oil removal to lead to Cross static pipeline mixer and enter one-level stirring pool;
Described three grades of reinforcement coagulation systems be sequentially connected with communicate static pipeline mixer, one-level stirring pool, two grades Stirring pool and three grades of stirring pools, static pipeline mixer;
Described flco speed subsystem sludge treating system mud magnetic separating device, is connected by multiple rare-earth magnetic discs and forms, from Three grades of stirring pools mine water out enters mud magnetic separating device, recycles after filter;
Described sludge treating system includes sludge pump and the pressure filter being sequentially connected with.
At Xie Zhuan colliery, the solid colliery of dragon and Fu Cheng colliery three, the actual operating data of down-hole treatment purification water treatment system is divided Analysis and result of calculation collect sees Fig. 3, and Fig. 3 is shown in data comparative analysis.
As can be seen from Figure 3:
(1) amount of energy saving 0.043-0.047kWh/(t hm before and after underground coal mine treatment and purification water treatment system is implemented), the most often 1t mine water promotes 100m and can economize on electricity 0.043-0.047kWh, average economize on electricity 0.045 kWh/(t hm).
(2) fractional energy savings 8.83%-10.26% before and after underground coal mine treatment and purification water treatment system is implemented, average out to 9.50%.
(3) as follows by the displacement after the project implementation and drain height conversion year amount of electricity saving:
Colliery, the ①Xie village: 0.047kWh/(t hm) × 5465254t × 4.59hm=117.90 ten thousand kWh;
2. the solid colliery of dragon: 0.043kWh/(t hm) × 24019920t × 8.6hm=888.26 ten thousand kWh;
3. Fu Cheng colliery: 0.045kWh/(t hm) × 2117000t × 3.94hm=37.53 ten thousand kWh;
4. add up to: 117.90 ten thousand kWh+888.26 ten thousand kWh+37.53 ten thousand kWh=1043.69 ten thousand kWh.

Claims (3)

1. well work mine water underground purifies and a cyclic utilization system, and the water sand piece-rate system being sequentially connected with, fine particle is pre- Processing system, strengthens coagulation system, flco speed subsystem, sludge treating system for three grades;
Described water sand piece-rate system includes elevator, scrapper conveyor chute, collection mud sump and belt-type elevating conveyor, elevator, scraper plate Machine chute is separately fixed on the two side of collection mud sump, and belt-type elevating conveyor is connected with elevator;
Described fine particle pretreatment system includes the three grades of sedimentation tanks being sequentially connected with, mine water after removing sand gravity flow entrance the First stage precipitation tank, arranges pneumatic sludge pump in first order sedimentation tank, be provided with stirring diving slurry pump bottom two or three grades of ponds, three grades Sedimentation tank deposit, by the sludge treating system of transport pump to rear end, goes the mine water after oil removal to be mixed by static pipeline Clutch enters one-level stirring pool;
Described three grades of reinforcement coagulation systems be sequentially connected with communicate static pipeline mixer, one-level stirring pool, two grades of stirrings Pond and three grades of stirring pools;
Described flco speed subsystem is mud magnetic separating device, multiple rare-earth magnetic discs connect and form, from three grades of stirring pools out Mine water enter mud magnetic separating device, recycle after filter;
Described sludge treating system includes sludge pump and the pressure filter being sequentially connected with.
A kind of well work mine water underground the most according to claim 1 purifies and cyclic utilization system, it is characterised in that: described Rare-earth magnetic disc replace with rare-earth Nd-Fe-B permanent magnetic steel, intensity between its Surface field intensity 3500gs adjacent magnetic field 2000gs。
A kind of well work mine water underground the most according to claim 1 purifies and cyclic utilization system, it is characterised in that: also wrap Include down-hole reclaiming system, sump drainage system and floor synthetic and utilize system.
CN201410485558.3A 2014-11-12 2014-11-12 A kind of well work mine water underground purifies and cyclic utilization system Active CN104370407B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410485558.3A CN104370407B (en) 2014-11-12 2014-11-12 A kind of well work mine water underground purifies and cyclic utilization system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410485558.3A CN104370407B (en) 2014-11-12 2014-11-12 A kind of well work mine water underground purifies and cyclic utilization system

Publications (2)

Publication Number Publication Date
CN104370407A CN104370407A (en) 2015-02-25
CN104370407B true CN104370407B (en) 2016-11-23

Family

ID=52549653

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410485558.3A Active CN104370407B (en) 2014-11-12 2014-11-12 A kind of well work mine water underground purifies and cyclic utilization system

Country Status (1)

Country Link
CN (1) CN104370407B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105498310A (en) * 2015-12-31 2016-04-20 徐州天科机械制造有限公司 Water non-stop continuous cleaning method and equipment for coal mine underground central water sump
CN106219859B (en) * 2016-08-16 2018-03-16 中电建水环境治理技术有限公司 Gush water multistage purification processing system more than polluted bed mud processing in river lake
CN108911228A (en) * 2017-11-15 2018-11-30 山东融汇环境工程有限公司 A kind of high suspended matter mine water underground load purification system and technique
CN108266224B (en) * 2018-01-13 2023-06-16 山东莱芜煤矿机械有限公司 Underground coal mine sump dredging process and equipment thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103570179A (en) * 2013-11-12 2014-02-12 煤炭工业济南设计研究院有限公司 Underground mine water treatment system and method
CN203545833U (en) * 2013-11-12 2014-04-16 煤炭工业济南设计研究院有限公司 Underground mine water treatment system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9475718B2 (en) * 2013-05-06 2016-10-25 John O. Richmond Water purification system and process with water pretreatment apparatus

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103570179A (en) * 2013-11-12 2014-02-12 煤炭工业济南设计研究院有限公司 Underground mine water treatment system and method
CN203545833U (en) * 2013-11-12 2014-04-16 煤炭工业济南设计研究院有限公司 Underground mine water treatment system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
煤矿井下重介质加载磁分离水处理技术工艺及效益分析;张超等;《第十四届中国科协年会第1分会场:水资源保护与水处理技术国际学术研讨会论文集》;20121231;第1-8页第1-4节 *

Also Published As

Publication number Publication date
CN104370407A (en) 2015-02-25

Similar Documents

Publication Publication Date Title
CN103232132B (en) Magnetic separation method and apparatus for mine water underground treatment
CN105016592B (en) Slurry recycling circulation system and slurry recycling method thereof
CN102942231B (en) Purification method of coal mine distribution underground reservoir water resource
CN104370407B (en) A kind of well work mine water underground purifies and cyclic utilization system
CN102491557B (en) Underground mine water treatment method
WO2020155524A1 (en) Fully-mechanized coal-mining face mine shaft water resource utilization system and method for using same
CN104163536A (en) Magnetic coagulation mine water underground purification technology
CN105439363A (en) Magnetic coagulation and separation purification technology for mine water
CN104724876A (en) Coal mine underground water processing method
CN103570179A (en) Underground mine water treatment system and method
CN116062939A (en) System and method for treating and recycling underground coal slime water of coal mine
CN105668740A (en) Integrated sand washing waste water reuse device
CN203425567U (en) Sewage treatment device
CN104944552A (en) Flocculent precipitate water processing method adopting slag or abrasive blasting scrap as micro sand
CN205061779U (en) Novel deposit depositing reservoir
CN202390268U (en) In-situ reuse treatment system for downhole directional drilling machine medium circulation water
CN112028341B (en) Sand stone production wastewater treatment system and wastewater treatment method in hydraulic and hydroelectric engineering construction
CN104225969A (en) Method and device for concentrating molybdenum ore flotation tailing ore pulp
CN203890159U (en) Remote intelligently controlled mining wastewater purification device
CN104556526A (en) Underground sewage closed-loop purification method
CN202762147U (en) Underground coal slime water sedimentation device
CN204714625U (en) Constructing tunnel advanced sewage treatment system
CN202898135U (en) Remote intelligent self-control mine water underground purification device
CN105417660A (en) Treatment method and device for waterworks production wastewater
CN102557386A (en) Sludge disposal method for circulating water of coal gas station of alumina plant

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180614

Address after: 271200 B18 four unit, Tai'an new hi tech Zone, Shandong

Patentee after: Shandong Environmental Protection Technology Co., Ltd.

Address before: 271000 Shicun Road, Sun Village, Xinwen office, Xintai, Tai'an, Shandong, Shilong Road, 62

Patentee before: Zhang Chao

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 271200 B18 four unit, Tai'an new hi tech Zone, Shandong

Patentee after: China Construction Environmental Energy (Shandong) Environmental Technology Co.,Ltd.

Address before: 271200 B18 four unit, Tai'an new hi tech Zone, Shandong

Patentee before: SHANDONG HUANNENG ENVIRONMENTAL PROTECTION TECHNOLOGY Co.,Ltd.