CN104358573B - 厚大矿体的阶段空场与阶段崩落联合采矿法 - Google Patents
厚大矿体的阶段空场与阶段崩落联合采矿法 Download PDFInfo
- Publication number
- CN104358573B CN104358573B CN201410462812.8A CN201410462812A CN104358573B CN 104358573 B CN104358573 B CN 104358573B CN 201410462812 A CN201410462812 A CN 201410462812A CN 104358573 B CN104358573 B CN 104358573B
- Authority
- CN
- China
- Prior art keywords
- lane
- ore
- nugget
- ore removal
- mineral building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 19
- 238000005065 mining Methods 0.000 title claims abstract description 11
- 238000004519 manufacturing process Methods 0.000 claims abstract description 10
- 238000005553 drilling Methods 0.000 claims description 17
- 229910052500 inorganic mineral Inorganic materials 0.000 claims description 17
- 239000011707 mineral Substances 0.000 claims description 17
- 239000011435 rock Substances 0.000 claims description 13
- 238000005520 cutting process Methods 0.000 claims description 10
- 238000004880 explosion Methods 0.000 claims description 10
- 230000011218 segmentation Effects 0.000 claims description 5
- 238000000605 extraction Methods 0.000 claims description 3
- 238000009826 distribution Methods 0.000 claims description 2
- 238000010790 dilution Methods 0.000 abstract description 6
- 239000012895 dilution Substances 0.000 abstract description 6
- 238000011084 recovery Methods 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 2
- 239000004744 fabric Substances 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000010348 incorporation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F13/00—Transport specially adapted to underground conditions
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Remote Sensing (AREA)
- Mechanical Engineering (AREA)
- Road Repair (AREA)
- Traffic Control Systems (AREA)
Abstract
厚大矿体的阶段空场与阶段崩落联合采矿法,其主要技术特征和基本做法是:先采用阶段空场法回收60‑70%的无贫化原矿,再用崩落法回采剩余矿柱,通过两种方法结合,提高矿石回采率,降低贫化率。
Description
技术领域
本发明属矿山技术领域
背景技术
目前技术状态:传统的地下采矿方法有空场法、崩落法、充填法三大类;空场法由于在矿体中采装,低贫化优势明显,但矿柱不易回收,损失率较高;崩落法的优点是无矿柱压矿损失,但废石混入率较高,采出矿石贫化严重;本发明的目的是:对厚大矿体,先采用阶段空场法回收60-70%的无贫化原矿,再用崩落法回采剩余矿柱,通过两种方法结合,实现扬长避短,既能有效采出大部分高品位矿石,又能使总体损失率和贫化率降低。
发明内容
本发明的主要做法是:(一)开采布局:矿块沿中段运输巷布置,其轴向大致垂直于中段运输巷;中段运输巷上部设置分段联络巷联接各矿块的分段凿岩巷;措施天井沟通中段运输巷和分段联络巷;(二)矿块结构:矿块由矿房、间柱、顶柱和桃形底柱组成;矿房中布置底部凿岩巷、分段凿岩巷和切割井、切割槽,底部凿岩巷的底板与出矿短巷的顶板持平;间柱宽度一般取矿块宽度的15%左右,由间柱抗压强度和矿体埋深确定;顶柱在回采爆破时应形成弧形拱稳定断面,拱顶厚度适宜;桃形底柱中布置矿块运输巷和出矿短巷,形成平底出矿结构,矿块运输巷贯通中段运输巷和回风巷,出矿短巷贯通矿房;(三)切割:由矿房端部切割井拉开切割槽,形成补偿空间;(四)矿房回采:利用底部凿岩巷和分段凿岩巷穿凿中深孔,爆破落矿;底部凿岩巷底板下的残留矿柱应同时爆破;每次爆破后,局部出矿,其余留矿作为临时支撑,待矿房全部回采结束后,再集中出矿;(五)间柱和顶柱的回采:矿房集中出矿结束后,爆破崩落间柱,顶柱靠自然崩落,仍利用桃形底柱的出矿结构进行出矿;(六)桃形底柱的回采:按无底柱分段崩落法工艺,桃形底柱作为一条采矿进路,由端部向中段运输巷退采;(七)采场出矿:无轨运输时,矿块运输巷和出矿短巷的断面要满足装运设备的作业条件,汽车直接进入矿房运输巷受矿;出矿短巷的端部排矿口一般要降低高度,以防止涌入过多矿石占用空间;有轨运输时,巷道断面适当缩小,出矿短巷适当加长,出矿短巷中设置移动式耙装机,该耙装机前端耙矿,后端向矿车卸载,矿车组进入矿房运输巷受矿。
说明书附图说明:
图1中:A——A图是采场横剖立面面图,B——B图是水平剖面图;图2中:C——C是纵剖立面图,(D)图是图例说明;图中标注符号意义如下:
①——矿块运输巷,②——出矿短巷,③——桃形底柱,
④——顶柱,⑤——矿房 ⑥——间柱,,
⑦——分段凿岩巷,⑧——底部凿岩巷,⑨——回风巷,
⑩——中段运输巷,(11)——底部凿岩巷出口斜坡,
(12)——措施天井,(13)——矿房切割井与切割槽, (14)——分段联络巷,
(15)——中深孔标示符,(16)——矿体标示符,(17)——崩落矿石标示符,
(18)——围岩标示符,(19)——崩落废石标示符。
Claims (1)
1.厚大矿体的阶段空场与阶段崩落联合采矿法,其基本做法如下:(一)开采布局:矿块沿中段运输巷布置,其轴向大致垂直于中段运输巷;中段运输巷上部设置分段联络巷联接各矿块的分段凿岩巷;措施天井沟通中段运输巷和分段联络巷;(二)矿块结构:矿块由矿房、间柱、顶柱和桃形底柱组成;矿房中布置底部凿岩巷、分段凿岩巷和切割井、切割槽,底部凿岩巷的底板与出矿短巷的顶板持平;间柱宽度取矿块宽度的15%左右,由间柱抗压强度和矿体埋深确定;顶柱在回采爆破时应形成弧形拱稳定断面,拱顶厚度适宜;桃形底柱中布置矿块运输巷和出矿短巷,形成平底出矿结构,矿块运输巷贯通中段运输巷和回风巷,出矿短巷贯通矿房;(三)切割:由矿房端部切割井拉开切割槽,形成补偿空间;(四)矿房回采:利用底部凿岩巷和分段凿岩巷穿凿中深孔,爆破落矿;底部凿岩巷底板下的残留矿柱应同时爆破;每次爆破后,局部出矿,其余留矿作为临时支撑,待矿房全部回采结束后,再集中出矿;(五)间柱和顶柱的回采:矿房集中出矿结束后,爆破崩落间柱,顶柱靠自然崩落,仍利用桃形底柱的出矿结构进行出矿;(六)桃形底柱的回采:按无底柱分段崩落法工艺,桃形底柱作为一条采矿进路,由端部向中段运输巷退采;(七)采场出矿:无轨运输时,矿块运输巷和出矿短巷的断面要满足装运设备的作业条件,汽车直接进入矿块运输巷受矿;出矿短巷的端部排矿口一般要降低高度,以防止涌入过多矿石占用空间;有轨运输时,巷道断面适当缩小,出矿短巷适当加长,出矿短巷中设置移动式耙装机,该耙装机前端耙矿,后端向矿车卸载,矿车组进入矿块运输巷受矿。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410462812.8A CN104358573B (zh) | 2014-09-04 | 2014-09-04 | 厚大矿体的阶段空场与阶段崩落联合采矿法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410462812.8A CN104358573B (zh) | 2014-09-04 | 2014-09-04 | 厚大矿体的阶段空场与阶段崩落联合采矿法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104358573A CN104358573A (zh) | 2015-02-18 |
CN104358573B true CN104358573B (zh) | 2016-08-31 |
Family
ID=52525870
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410462812.8A Active CN104358573B (zh) | 2014-09-04 | 2014-09-04 | 厚大矿体的阶段空场与阶段崩落联合采矿法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104358573B (zh) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104847355B (zh) * | 2015-05-15 | 2017-05-17 | 西北矿冶研究院 | 中厚急倾斜矿体空场连续开采方法 |
CN105386767B (zh) * | 2015-12-10 | 2017-09-15 | 华北理工大学 | 一种空场崩落混合开采挂帮的采矿方法 |
CN106437716A (zh) * | 2016-09-23 | 2017-02-22 | 北京矿冶研究总院 | 一种地下破碎磷矿体采矿的方法 |
CN107131805B (zh) * | 2017-05-23 | 2019-04-19 | 西北矿冶研究院 | 一种用于提高井下崩落法采场出矿品位的采矿方法 |
CN108397194A (zh) * | 2018-02-23 | 2018-08-14 | 河北钢铁集团矿业有限公司 | 无底柱分段崩落法最后中段矿体采矿平稳过渡方法 |
CN111577284A (zh) * | 2020-05-25 | 2020-08-25 | 赣州有色冶金研究所 | 一种由空场法转崩落法的方法 |
CN113047835B (zh) * | 2021-02-24 | 2022-04-15 | 中南大学 | 集空、崩、充一体的深井厚大矿体采矿方法 |
CN113803071B (zh) * | 2021-10-26 | 2022-06-17 | 中南大学 | 基于远程智能掘进机的薄矿体采矿法 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SE364339B (zh) * | 1972-06-28 | 1974-02-18 | Luossavaara Kiirunavaara Ab | |
RU2123597C1 (ru) * | 1997-06-06 | 1998-12-20 | Институт горного дела СО РАН | Способ отработки крутых пластов |
CN102128033B (zh) * | 2011-04-29 | 2013-01-30 | 北京矿冶研究总院 | 一种连续崩落采矿方法 |
CN103527197B (zh) * | 2013-10-28 | 2016-01-06 | 中国矿业大学 | 一种特厚煤层固体胶结充填巷式开采方法 |
CN103628877B (zh) * | 2013-11-26 | 2015-09-02 | 武汉科技大学 | 一种多层缓倾斜薄-中厚矿床充填采矿方法 |
-
2014
- 2014-09-04 CN CN201410462812.8A patent/CN104358573B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN104358573A (zh) | 2015-02-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104358573B (zh) | 厚大矿体的阶段空场与阶段崩落联合采矿法 | |
CN107339104B (zh) | 保安隔离矿柱回收方法 | |
CN103089266B (zh) | 露天转地下过渡期无底柱分段空场崩落采矿方法 | |
CN103628877B (zh) | 一种多层缓倾斜薄-中厚矿床充填采矿方法 | |
CN104727820B (zh) | 一种两步骤分段空场嗣后充填采矿方法 | |
CN103147761B (zh) | 一种缓倾斜松软顶板薄矿床充填采矿方法 | |
CN101725352B (zh) | 一种固体充填综采回收房式煤柱方法 | |
CN102493838A (zh) | 一种急倾斜煤层综采连续充填采煤方法 | |
CN101302931B (zh) | 一种仓房采煤后的复采和边角煤回采的方法 | |
CN101737052A (zh) | 一种分段充填采矿方法 | |
CN101881169A (zh) | 一种分段留矿崩落阶段空场嗣后充填采矿法 | |
CN103696771A (zh) | 一种跳采式旺格维利采场支巷充填采煤方法 | |
CN103557002A (zh) | 一种盘区机械化集中溜井上向水平分层充填采矿法 | |
US20180195386A1 (en) | Parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence | |
CN102704934A (zh) | 地下矿山大产能、低成本嗣后充填采矿方法 | |
CN102392642A (zh) | 一种无煤柱回采工作面的巷道布置方法 | |
CN102635392A (zh) | 超前留巷施工抽采工程的无煤柱煤与瓦斯共采方法 | |
CN107687341A (zh) | 一种极厚大不稳固矿体的上向分层点柱式充填采矿方法 | |
CN101126316A (zh) | 一种长壁综采回收房式开采煤柱的方法 | |
CN108825237B (zh) | 一种特厚煤连采机与充填相结合的分层分采工艺 | |
WO2015103861A1 (zh) | 沿空留巷y型通风高位回风巷钻孔抽采瓦斯方法 | |
CN104088662B (zh) | 一种固体充填采煤沿空留巷支护墙体的施工方法 | |
CN102086765A (zh) | 一种极薄铜矿体高分段多分层采矿法 | |
CN105736009A (zh) | 用于急倾斜薄矿体的留矿堆浸嗣后充填采矿方法 | |
CN103147759B (zh) | 一种倾斜小矿体探矿—浅孔留矿采矿方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |