Fast alignment method and device for blast furnace top ring Download PDFInfo
- Publication number
- CN104357608A CN104357608A CN201410539825.0A CN201410539825A CN104357608A CN 104357608 A CN104357608 A CN 104357608A CN 201410539825 A CN201410539825 A CN 201410539825A CN 104357608 A CN104357608 A CN 104357608A
- Authority
- CN
- China
- Prior art keywords
- blast furnace
- furnace shell
- shell seal
- top ring
- ring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21B—MANUFACTURE OF IRON OR STEEL
- C21B7/00—Blast furnaces
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Manufacturing & Machinery (AREA)
- Materials Engineering (AREA)
- Metallurgy (AREA)
- Organic Chemistry (AREA)
- Blast Furnaces (AREA)
Abstract
The invention provides a fast alignment method for a blast furnace top ring. The specific technical scheme is that the method comprises the following steps: step one, adjusting nuts are welded; step two, the top ring is hoisted to a furnace shell seal cover, and a cross center mark of the top ring corresponds to vertical and horizontal center lines of the furnace shell seal cover; and step three, the levelness of the ring is adjusted, measuring sliding staff is placed on an upper plane of the ring, and the levelness of the top ring is adjusted through bolts according to the height difference of an eyeball of a level gauge. A fast alignment device for the blast furnace top ring comprises four sets of nuts and bolts, the four sets of nuts are fixedly arranged on the cross center lines on the inner side of the upper port of the blast furnace shell seal cover and are symmetrically arranged with the circle center of the upper port of the blast furnace shell seal cover as the center, and the four sets of bolts are in threaded connection with the nuts. The fast alignment method and device for the blast furnace top ring have the advantages that not only the alignment precision is high, but also the alignment time of the blast furnace top ring is shortened, and the cost is reduced.
Description
Technical field
The present invention relates to equipment field engineering field, particularly a kind of fast aligning method of blast furnace roof steel ring, is particularly useful for the fast aligning of blast furnace roof steel ring.
Background technology
In existing metallurgy construction, the aligning method that blast furnace roof steel ring is installed welds baffle plate on furnace shell and steel ring, and then regulate with screw block, time-consuming, be awkward, efficiency is low, affects the installation period of furnace top equipment.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of fast aligning method and device of blast furnace roof steel ring, and not only centering precision is high, and shortens the alignment time of blast furnace roof steel ring, reduces cost.
For achieving the above object, the fast aligning method of a kind of blast furnace roof steel ring that the present invention proposes, its concrete technical scheme is:
The first step, welding setting nut, is welded on the cross centre line of last furnace shell seal closure inner side suitable for reading by the plain nut that four covers are installed respectively;
Second step, lifting lip ring, is lifted into lip ring on furnace shell seal closure, and the cross searching of lip ring is marked, and medullary ray is corresponding in length and breadth with furnace shell seal closure;
3rd step, regulates steel ring levelness, is placed in the upper plane of steel ring, according to the discrepancy in elevation of spirit-leveling instrument eyeball, is regulated the levelness of lip ring by bolt by measurement Sopwith staff.
A kind of fast calibrating device of blast furnace roof steel ring, it comprises four cover nuts and bolts, the cross centre line that described four cover nuts are fixedly installed on last furnace shell seal closure inner side suitable for reading is symmetrical arranged centered by the last furnace shell seal closure center of circle suitable for reading, and four described cover bolts and nuts are threaded connection.
The fast aligning method of a kind of blast furnace roof steel ring proposed by the invention and device, not only centering precision is high, and shortens the alignment time of blast furnace roof steel ring, reduces cost.
Accompanying drawing explanation
Fig. 1 is that the fast aligning method of a kind of blast furnace roof steel ring proposed by the invention arranges schematic diagram.
Fig. 2 is A-A sectional view in Fig. 1.
Embodiment
See accompanying drawing, a kind of fast aligning method of blast furnace roof steel ring, its concrete technical scheme is:
The first step, welding setting nut 1, is welded on the cross centre line of last furnace shell seal closure 5 inner side suitable for reading by the plain nut that four covers are installed respectively;
Second step, lifting lip ring 3, is lifted into lip ring on furnace shell seal closure, and the cross searching of lip ring is marked, and medullary ray is corresponding in length and breadth with furnace shell seal closure;
3rd step, regulates steel ring levelness, is placed in the upper plane of steel ring, according to the discrepancy in elevation of spirit-leveling instrument eyeball, is regulated the levelness of lip ring by bolt 2 by measurement Sopwith staff 4.
A kind of fast calibrating device of blast furnace roof steel ring, it comprises four cover nuts 1 and bolt 2, the cross centre line that described four cover nuts are fixedly installed on last furnace shell seal closure inner side suitable for reading is symmetrical arranged centered by the last furnace shell seal closure center of circle suitable for reading, and four described cover bolts and nuts are threaded connection.
The fast aligning method of a kind of blast furnace roof steel ring proposed by the invention and device, not only centering precision is high, and shortens the alignment time of blast furnace roof steel ring, reduces cost.
Claims (2)
1. a fast aligning method for blast furnace roof steel ring, its concrete technical scheme is:
The first step, welding setting nut, is welded on the cross centre line of last furnace shell seal closure inner side suitable for reading by the plain nut that four covers are installed respectively;
Second step, lifting lip ring, is lifted into lip ring on furnace shell seal closure, and the cross searching of lip ring is marked, and medullary ray is corresponding in length and breadth with furnace shell seal closure;
3rd step, regulates steel ring levelness, is placed in the upper plane of steel ring, according to the discrepancy in elevation of spirit-leveling instrument eyeball, is regulated the levelness of lip ring by bolt by measurement Sopwith staff.
2. the fast calibrating device of a blast furnace roof steel ring, it comprises four cover nuts and bolts, it is characterized in that on the cross centre line that described four cover nuts are fixedly installed on last furnace shell seal closure inner side suitable for reading and to be symmetrical arranged centered by the last furnace shell seal closure center of circle suitable for reading, four described cover bolts and nuts are threaded connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410539825.0A CN104357608A (en) | 2014-10-14 | 2014-10-14 | Fast alignment method and device for blast furnace top ring |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410539825.0A CN104357608A (en) | 2014-10-14 | 2014-10-14 | Fast alignment method and device for blast furnace top ring |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104357608A true CN104357608A (en) | 2015-02-18 |
Family
ID=52524914
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410539825.0A Pending CN104357608A (en) | 2014-10-14 | 2014-10-14 | Fast alignment method and device for blast furnace top ring |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104357608A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113736946A (en) * | 2021-09-22 | 2021-12-03 | 武汉精鼎科技股份有限公司 | Construction process for KR desulfurization tank bottom permanent layer |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102634616A (en) * | 2012-04-26 | 2012-08-15 | 中国十七冶集团有限公司 | Blast furnace top flange jackscrew aligning method |
-
2014
- 2014-10-14 CN CN201410539825.0A patent/CN104357608A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102634616A (en) * | 2012-04-26 | 2012-08-15 | 中国十七冶集团有限公司 | Blast furnace top flange jackscrew aligning method |
Non-Patent Citations (1)
Title |
---|
房政等: "高炉无料钟炉顶钢圈安装施工技术", 《安徽建筑》, no. 1, 29 February 2012 (2012-02-29), pages 122 - 108 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113736946A (en) * | 2021-09-22 | 2021-12-03 | 武汉精鼎科技股份有限公司 | Construction process for KR desulfurization tank bottom permanent layer |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202298628U (en) | Automatic steel pipe column perpendicularity adjusting device using reverse construction method | |
CN104499485B (en) | One pile for one column fully automatic hydraulic verticality-regulating system and vertical adjustment method | |
CN102434003B (en) | Heavy battened steel column construction process | |
CN203604930U (en) | Tunnel detection radar scanning support | |
CN204495337U (en) | A kind of self-level(l)ing device for laser forming | |
CN102580820B (en) | Roller type vertical mill installation method | |
CN104020055A (en) | Multifunctional direct shear and consolidation device of coarse-grained soil | |
CN102634616A (en) | Blast furnace top flange jackscrew aligning method | |
CN103967284B (en) | The steel column installation method of reserved stigma docking | |
CN103243746A (en) | Wind generator foundation ring precision calibrating system and construction method thereof | |
CN104357608A (en) | Fast alignment method and device for blast furnace top ring | |
CN203531027U (en) | Precise leveling system of fan foundation ring with dedicated jacks for supporting and positioning | |
CN101838986A (en) | Disassembling tool type lattice column and construction method thereof | |
CN103451338A (en) | Method for installing ascending tubes and five-way balls of blast furnace gas systems | |
CN205000354U (en) | Rim of a cup basis steel column installation elevation control structure | |
CN103644891B (en) | The measuring method of top of ultrahigh column absolute altitude | |
CN103624537A (en) | Leveling method and leveling device for equipment installation | |
CN203599840U (en) | Leveling device for installing equipment | |
CN105569351A (en) | Mounting construction technology of steel structure steel column | |
CN104863259A (en) | Upside-down construction method for large-span ultra-high signal-layer cylindrical architectural steel structure | |
CN205476528U (en) | Precast pile device of taking one's place fast | |
CN204944456U (en) | Wall column formwork verticality laser detecting apparatus | |
CN204199170U (en) | Bridge steel support installation pinner | |
CN205276334U (en) | A spherical load box for self -balancing peg method | |
CN204235102U (en) | Alignment device in a kind of large-scale drive apparatus axle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150218 |