CN104314589A - Mounting method for longitudinal waste stop belt of tunnel side wall foundation - Google Patents
Mounting method for longitudinal waste stop belt of tunnel side wall foundation Download PDFInfo
- Publication number
- CN104314589A CN104314589A CN201410420832.9A CN201410420832A CN104314589A CN 104314589 A CN104314589 A CN 104314589A CN 201410420832 A CN201410420832 A CN 201410420832A CN 104314589 A CN104314589 A CN 104314589A
- Authority
- CN
- China
- Prior art keywords
- steel
- stop belt
- side wall
- water stop
- waterstop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 16
- 239000002699 waste material Substances 0.000 title abstract 2
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 23
- 239000010959 steel Substances 0.000 claims abstract description 23
- 239000002184 metal Substances 0.000 claims abstract description 15
- 229910052751 metal Inorganic materials 0.000 claims abstract description 15
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims abstract description 8
- 229910052742 iron Inorganic materials 0.000 claims abstract description 4
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract 7
- 238000005553 drilling Methods 0.000 abstract 1
- 238000004321 preservation Methods 0.000 abstract 1
- 230000002746 orthostatic effect Effects 0.000 description 4
- 238000010276 construction Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
- E21D11/381—Setting apparatus or devices
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention discloses a mounting method for a longitudinal waste stop belt of a tunnel side wall foundation. The mounting method comprises the following steps: firstly, straightening the elongated steel-edged water stop belt and enabling the straightened steel-edged water stop belt to penetrate out of an end mold preservation slot of the side wall foundation to be cast; secondly, clamping the tail end of the steel-edged water stop belt from two sides of the steel-edged water stop belt by using two hard metal bars, and respectively tightening the upper end and the lower end of the metal bars by using iron wires; thirdly, drilling an anchor in the rear wall of the side wall foundation to be cast, wherein the upper end of the anchor tilts backwards, and the anchor and the steel-edged water stop belt are positioned on the same longitudinal plane; fourthly, connecting the tail end of a wire gripper with the upper end of the anchor by a steel wire rope, connecting the front end of the wire gripper with the middles of the two metal bars by the steel wire ropes, wrenching a wrench on the wire gripper, and tightening and straightening the steel-edged water stop belt by driving the steel wire rope. The problem that the longitudinal water stop belt in the tunnel side wall foundation is poorer in longitudinal mounting linearity and vertical mounting verticality is fundamentally solved; besides, the mounting method is simple in operation and has a broad popularization value.
Description
Technical field
The present invention relates to method for tunnel construction technical field, be specifically related to the mounting method of longitudinal waterstop in tunnel side wall basis.
Background technology
Longitudinal waterstop on tunnel side wall basis easily need keep straight line to install, but easily occurs not straight, tipping phenomenon etc. in practice of construction process, has a strong impact on engineering guarded drainage quality.Now current, generally adopts and steel clip is installed on steel pipe lives waterstop, or adopt two angle steel to clamp waterstop, or employing spacer bars skeleton clamps waterstop, or employing is set up bar dowel and clamped the methods such as waterstop and fixed.This several method all needs by waterstop at elongated scope internal fixtion, and the part that waterstop is embedded in concrete is very easily disturbed when concreting, its longitudinal linearity and vertical orthostatic poor.
Summary of the invention
The present invention aims to provide one conveniently longitudinal waterstop mounting method, fundamentally improves longitudinal waterstop in tunnel side wall basis and installs longitudinal linearity and the poor problem of vertical orthostatic.
For this reason, the technical solution adopted in the present invention is: a kind of longitudinal waterstop mounting method of tunnel side wall basis, comprises the following steps:
Step one: longitudinally made in order by the steel limit waterstop after spreading, then passes from the end mould preformed groove on abutment wall basis to be built;
Step 2: from the both sides of steel limit waterstop, the end of steel limit waterstop is clamped with two hard metal rods, then tighten respectively with the two ends up and down of iron wire by metal bar;
Step 3: squeeze into holdfast on the rear wall on abutment wall basis to be built, the upper end of holdfast is towards rear-inclined, and holdfast and steel limit waterstop are positioned on same fore-and-aft plane;
Step 4: be connected by wire rope with the upper end of holdfast by turnbuckle tail end, turnbuckle front end is connected by wire rope with the middle part of two metal bars, then pulls the spanner on turnbuckle, makes the waterstop tension of steel limit exceptionally straight by driving wire rope.
Preferred as such scheme, described metal bar and holdfast all can adopt the reinforcement fabrication of job site, draw materials conveniently.
The invention has the beneficial effects as follows: when installing for longitudinal waterstop, common turnbuckle, wire rope, reinforcing bar is only utilized to complete, and fundamentally improve longitudinal waterstop in tunnel side wall basis longitudinal linearity and the poor problem of vertical orthostatic are installed, and simple to operate, there is promotional value widely.
Accompanying drawing explanation
Fig. 1 is the Construction State figure of invention.
Detailed description of the invention
Below in conjunction with drawings and Examples, the invention will be further described.
As shown in Figure 1, a kind of longitudinal waterstop mounting method of tunnel side wall basis, comprises the following steps:
Step one: longitudinally made in order by the steel limit waterstop 1 after spreading, then passes from the end mould preformed groove 2a on abutment wall basis 2 to be built, and this step is identical with the first step that existing current longitudinal waterstop is installed.
Step 2: with the both sides of two hard metal rods 3 from steel limit waterstop 1, the end of steel limit waterstop 1 is clamped, then tighten respectively with the two ends up and down of iron wire 4 by metal bar 3, thus ensure steel limit waterstop 1 stress balance in the exceptionally straight process of tension.
Step 3: squeeze into holdfast 5 on the rear wall on abutment wall basis 2 to be built, the upper end of holdfast 5 towards rear-inclined at an angle, and holdfast 5 and steel limit waterstop 1 are positioned on same fore-and-aft plane, be to ensure the longitudinal linearity after waterstop 1 installation of steel limit and vertical orthostatic equally; Directly utilize abutment wall basis 2 to be built to install fixing holdfast 5 simultaneously.
Step 4: be connected by wire rope with the upper end of holdfast 5 by turnbuckle 6 tail end, turnbuckle 6 front end is connected by wire rope with the middle part of two metal bars 3, then pulls the spanner on turnbuckle 6, exceptionally straight by driving wire rope to make steel limit waterstop 1 strain.Turnbuckle 6, from strap wrenches, is common turnbuckle, can commercially buys.
Wherein, metal bar 3 and holdfast 5 all can adopt the reinforcement fabrication of job site.
Claims (2)
1. longitudinal waterstop mounting method on tunnel side wall basis, is characterized in that, comprise the following steps:
Step one: longitudinally made in order on steel limit waterstop (1) after spreading, then passes from the end mould preformed groove (2a) of abutment wall basis (2) to be built;
Step 2: with the both sides of two hard metal rods (3) from steel limit waterstop (1), the end on steel limit waterstop (1) is clamped, then use iron wire (4) to be tightened respectively at the two ends up and down of metal bar (3);
Step 3: squeeze into holdfast (5) on the rear wall of abutment wall basis (2) to be built, the upper end of holdfast (5) is towards rear-inclined, and holdfast (5) and steel limit waterstop (1) are positioned on same fore-and-aft plane;
Step 4: the upper end of turnbuckle (6) tail end with holdfast (5) is connected by wire rope, turnbuckle (6) front end is connected by wire rope with the middle part of two metal bars (3), then pulling the spanner on turnbuckle (6), making steel limit waterstop (1) strain exceptionally straight by driving wire rope.
2. according to longitudinal waterstop mounting method on tunnel side wall basis according to claim 1, it is characterized in that: described metal bar (3) and holdfast (5) all can adopt the reinforcement fabrication of job site.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410420832.9A CN104314589B (en) | 2014-08-25 | 2014-08-25 | Longitudinal waterstop mounting method on tunnel side wall basis |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410420832.9A CN104314589B (en) | 2014-08-25 | 2014-08-25 | Longitudinal waterstop mounting method on tunnel side wall basis |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104314589A true CN104314589A (en) | 2015-01-28 |
CN104314589B CN104314589B (en) | 2016-03-30 |
Family
ID=52369884
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410420832.9A Active CN104314589B (en) | 2014-08-25 | 2014-08-25 | Longitudinal waterstop mounting method on tunnel side wall basis |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104314589B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106168137A (en) * | 2016-08-30 | 2016-11-30 | 中铁十九局集团第七工程有限公司 | Tunnel buried water stop belt installation device and construction method thereof |
CN107143360A (en) * | 2017-07-20 | 2017-09-08 | 中铁二局集团有限公司 | A kind of short abutment wall waterstop fixing means in tunnel |
CN108150197A (en) * | 2018-02-05 | 2018-06-12 | 中铁隧道集团处有限公司 | Radially overturning inverted arch trestle and its installation position method for demoulding to arc formwork |
CN112240215A (en) * | 2020-10-23 | 2021-01-19 | 中铁工程装备集团有限公司 | Waterproof structure between water-stop strip and prefabricated component and construction method of waterproof structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4822947B2 (en) * | 2006-06-19 | 2011-11-24 | 東日本旅客鉄道株式会社 | Impermeable wall construction method and liquefaction suppression method |
CN202578718U (en) * | 2012-05-18 | 2012-12-05 | 中铁十二局集团第七工程有限公司 | Locating system for embedded part at construction joint between tunnel invert and secondary lining |
CN102996143A (en) * | 2012-11-19 | 2013-03-27 | 中铁十二局集团有限公司 | Construction method of fully pouring tunnel invert |
CN203603935U (en) * | 2013-12-19 | 2014-05-21 | 中铁十局集团有限公司 | Positioning device of steel edge water-stop strip of tunnel longitudinal construction joint |
CN203730016U (en) * | 2013-12-09 | 2014-07-23 | 中铁五局(集团)有限公司 | Mounting tool for tunnel buried vertical rubber waterstop |
-
2014
- 2014-08-25 CN CN201410420832.9A patent/CN104314589B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4822947B2 (en) * | 2006-06-19 | 2011-11-24 | 東日本旅客鉄道株式会社 | Impermeable wall construction method and liquefaction suppression method |
CN202578718U (en) * | 2012-05-18 | 2012-12-05 | 中铁十二局集团第七工程有限公司 | Locating system for embedded part at construction joint between tunnel invert and secondary lining |
CN102996143A (en) * | 2012-11-19 | 2013-03-27 | 中铁十二局集团有限公司 | Construction method of fully pouring tunnel invert |
CN203730016U (en) * | 2013-12-09 | 2014-07-23 | 中铁五局(集团)有限公司 | Mounting tool for tunnel buried vertical rubber waterstop |
CN203603935U (en) * | 2013-12-19 | 2014-05-21 | 中铁十局集团有限公司 | Positioning device of steel edge water-stop strip of tunnel longitudinal construction joint |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106168137A (en) * | 2016-08-30 | 2016-11-30 | 中铁十九局集团第七工程有限公司 | Tunnel buried water stop belt installation device and construction method thereof |
CN107143360A (en) * | 2017-07-20 | 2017-09-08 | 中铁二局集团有限公司 | A kind of short abutment wall waterstop fixing means in tunnel |
CN108150197A (en) * | 2018-02-05 | 2018-06-12 | 中铁隧道集团处有限公司 | Radially overturning inverted arch trestle and its installation position method for demoulding to arc formwork |
CN108150197B (en) * | 2018-02-05 | 2024-04-05 | 中铁隧道集团一处有限公司 | Radial overturning inverted arch trestle of arc-shaped template and mounting, positioning and demolding method thereof |
CN112240215A (en) * | 2020-10-23 | 2021-01-19 | 中铁工程装备集团有限公司 | Waterproof structure between water-stop strip and prefabricated component and construction method of waterproof structure |
Also Published As
Publication number | Publication date |
---|---|
CN104314589B (en) | 2016-03-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104314589B (en) | Longitudinal waterstop mounting method on tunnel side wall basis | |
CN203905481U (en) | Rectangular column mould hoop | |
CN204491425U (en) | A kind of external prestressing strengthening structure of T-shaped bridge diaphragm | |
CN103122692A (en) | Reinforcing device of shear wall end socket formwork | |
CN104631820B (en) | A kind of steel strand are to the device drawing fixing concrete template | |
CN106401196A (en) | Steel strand tensioning device for pre-stressed anchorage device | |
CN204960953U (en) | Vertical waterstop of formula of burying device of flare -outing in tunnel | |
CN101745983A (en) | A kind of tubular pile pre-stress stretching device | |
CN202461363U (en) | Disc steel bar straightening machine for building | |
CN106758663B (en) | Buried rubber fastening band installs positioning construction method in one kind | |
CN204431470U (en) | A kind of concrete pipe pile tensioning system | |
CN203230178U (en) | Column formwork and column hoop | |
CN204754210U (en) | Instrument is consolidated to beam mold board | |
CN204875782U (en) | Device that carries out stretch -draw and locking to prestressed anchorage pole of muscle of giving first place to with reinforcing bar | |
CN204282551U (en) | A kind of rubber fastening band installation and positioning structure | |
CN204299162U (en) | To encorbelment steel I-beam anchor structure | |
CN204152551U (en) | A kind of reusable mine down-hole filling barricade | |
CN207794600U (en) | A kind of oblique bracing means of building form | |
CN106948339B (en) | Steel reinforcement cage pipe penetrating guide and steel reinforcement cage pipe penetrating method | |
CN215948902U (en) | Cast in situ concrete post template fixing clamp | |
CN207092104U (en) | A kind of steel-pipe pile attachment structure | |
CN204311731U (en) | Putlock fastening devices | |
CN204311725U (en) | Putlock Combined fixing device | |
CN203034796U (en) | Reinforced device of shear wall end formwork | |
CN103195235A (en) | Design and calculation for detachable steel plate type steel fixture |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |