CN104294808A - Application of hydraulic settlement system in deck floor refitting process - Google Patents

Application of hydraulic settlement system in deck floor refitting process Download PDF

Info

Publication number
CN104294808A
CN104294808A CN201410399293.5A CN201410399293A CN104294808A CN 104294808 A CN104294808 A CN 104294808A CN 201410399293 A CN201410399293 A CN 201410399293A CN 104294808 A CN104294808 A CN 104294808A
Authority
CN
China
Prior art keywords
hydraulic jack
antiskid
cutting
hydraulic
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410399293.5A
Other languages
Chinese (zh)
Other versions
CN104294808B (en
Inventor
许凤雪
王守成
魏涛
张宝利
张品庆
刘孟家
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Haisheng Ocean Engineering Group Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410399293.5A priority Critical patent/CN104294808B/en
Publication of CN104294808A publication Critical patent/CN104294808A/en
Application granted granted Critical
Publication of CN104294808B publication Critical patent/CN104294808B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0034Maintenance, repair or inspection of offshore constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses application of a hydraulic settlement system in the deck floor refitting process. The application includes the steps of cutting supporting stand columns, cutting antiskid stand columns and installing hydraulic jacks. In the steps of cutting the supporting stand columns and cutting the antiskid stand columns, parts 0.9 m to 1.0 m long are cut away from the fifteen supporting stand columns and the six antiskid stand columns where the hydraulic jacks need to be installed in the upward direction from a settlement box, and parts 0.45 m to 0.55 m long are cut away from the supporting columns and the antiskid stand columns where the hydraulic jacks are not installed, and a whole upper deck falls to the 4.5 m height position of the edge distance base line of the upper deck to be welded and fixed again; in the step of installing the hydraulic cylinders, all pipe systems of the upper portions of the supporting stand columns and the antiskid stand columns on the upper deck are cut off, then the hydraulic jacks are installed according to the triangle stability characteristic and through the crisscross and interval matrix distribution method, and the hydraulic jacks are controlled through a control cabinet. The hydraulic settlement system has the advantages of being reasonable in design, convenient, reliable and safe to operate, low in cost and good in economical efficiency, being little influenced by sea conditions and weather, and being beneficial to large-span deck falling construction and the like, and is widely applied in an offshore petroleum production project.

Description

The application of hydraulic pressure sedimenting system in Platform Deck reforming technology
Technical field:
The present invention relates to Platform Deck reforming technology in oil offshore oil exploitation, the particularly application of a kind of hydraulic pressure sedimenting system in Platform Deck reforming technology.
Background technology:
Existing offshore oil exploiting platform component landing technique, is generally crane barge lifting coordinative construction.This construction technology is that the landing of offshore platform component has played effect, but it also exists following shortcoming or deficiency simultaneously: 1. cost is high, and efficiency is low; 2. poor stability is dangerous large; 3. larger by sea situation meteorological effect; 4. the object lifting construction difficulty that span is large is large.
Summary of the invention:
The object of this invention is to provide the application of a kind of hydraulic pressure sedimenting system in Platform Deck reforming technology, adopt cutting column, according to triangle stability characteristic (quality), matrix distribution mode every a top one installs hydraulic jack, the unified technology mode falling to installing of final Platform Deck entirety, effectively overcomes or avoids the shortcoming that exists in above-mentioned prior art or deficiency.
The application of hydraulic pressure sedimenting system of the present invention in Platform Deck reforming technology, comprises cutting support post and cutting antiskid column, installs hydraulic jack.Described cutting support column and antiskid column, 15 support posts and 6 antiskid columns that hydraulic jack need be installed, 0.9-1.0 rice is up sliced off from mat case, support column and the antiskid column cutting 0.45-0.55 rice of hydraulic jack will be installed, upper deck entire lowering is welded and fixed again to the At The Height of upper deck back gauge baseline 4.5m; Described installation hydraulic jack, be first all pipings of the support post of upper deck and antiskid column top are cut off, then utilize triangle stability characteristic (quality), take to intersect in length and breadth, matrix distribution mode every a top one installs hydraulic jack, and hydraulic jack controlled by switch board.
Wherein, described installation hydraulic jack is provided with pallet, hydraulic jack and reinforcement support in turn in the support post after cutting.Described installation hydraulic jack, be provided with hanging basket in the antiskid column after cutting, be provided with pad and hydraulic jack in turn in hanging basket, hanging basket is provided with clips outside top.Described pallet top is channel-section steel, the bottom of cross welding is round table-like welded unit.After described 21 hydraulic jack install, operation hydraulic jack, safety switches the cutting of each support column steadily.By remaining 15 support posts and antiskid column, up slice off 0.45-0.55 rice, then operate hydraulic jack from mat box top, slowly transfer and fall on mat case to support column, it is firm again to be welded.Construct according to this step successively, at the bottom of upper deck, withdraw from hydraulic jack during distance 2.4 meters, mat box top, to the support column after the every root cutting declined, correspond on original position and carry out full weld, the entirety completing upper deck falls.
The present invention compared with prior art tool has the following advantages:
1, reasonable in design, easy to operate, reliable and secure.
2, cost is low, good economy performance.
3, less by sea situation meteorological effect.
4, for the deck-landing convenient construction that span is larger.
Accompanying drawing explanation
Fig. 1 is a kind of example structure schematic diagram of the present invention;
Fig. 2 for by the A-A shown in Fig. 1 to structural representation:
Fig. 3 for by the hydraulic jack shown in Fig. 1 with strengthen support and pallet connecting installation structure schematic diagram:
Fig. 4 is hanging basket of the present invention and hydraulic jack mounting structure schematic diagram:
Fig. 5 is for by the hanging basket plan structure schematic diagram shown in Fig. 4:
Fig. 6 is for by the improved structural representation of Platform Deck entire lowering shown in Fig. 1.
Detailed description of the invention
Consult Fig. 1-Fig. 6, the application of a kind of hydraulic pressure sedimenting system in Platform Deck reforming technology, comprise cutting support post 3 and cutting antiskid column 4, hydraulic jack is installed.Cutting support column 3 and antiskid column 4, by laterally 4 rows of support platform upper deck 1 overall weight, longitudinally 9 rows totally 36 root posts, 15 support posts 3 and 6 antiskid columns 4 of hydraulic jack 7 need be installed, 0.9-1.0 rice is up sliced off from mat case 2, the support post 3 and antiskid column 4 of not installing hydraulic jack 7 are cut 0.45-0.55 rice, upper deck 1 entire lowering is welded and fixed again to the At The Height of upper deck 1 back gauge baseline 4.5m; Hydraulic jack 7 is installed, be first all pipings of the support post 3 of upper deck 1 and antiskid column 4 top are cut off, then utilize triangle stability characteristic (quality), take to intersect in length and breadth, matrix distribution mode every a top one installs hydraulic jack 7, and hydraulic jack 7 controlled by switch board 5.
Installing hydraulic jack 7, is be provided with pallet 8 hydraulic jack 7 in the support post 3 after cutting in turn and strengthen support 6.Install hydraulic jack 7, be provided with hanging basket 10 in the antiskid column 4 after cutting, be provided with pad 11 and hydraulic jack 7 in hanging basket 10 in turn, hanging basket 10 is provided with clips 9 outside top.Pallet 8 top is channel-section steel, the bottom of cross welding is round table-like welded unit.After 21 hydraulic jack 7 install, operation hydraulic jack 7, safety switches the cutting of each support column steadily, by remaining 15 support columns 3 and antiskid column 4, up slices off 0.45-0.55 rice from mat case 2 top.Then operate hydraulic jack, slowly transfer and fall on mat case 2 to support post 3 and antiskid column 4, it is firm again to be welded.Construct according to this step successively, at the bottom of upper deck during distance 2.4 meters, mat box top, the support post 3 on hydraulic jack 7 top hangs up properly jack, and other end hangs up properly jack, hydraulic jack 7 is pulled out and transports on the bank.To the support post 3 after the every root cutting declined and antiskid column 4, correspond on original position and carry out full weld, the entirety completing upper deck 1 falls.
In operation, hanging basket plays support hydraulic jack 7.As shown in Figure 2, a support post at its center is provided with two hydraulic jack 7 for 3 times, to strengthen its holding power and balance.Hydraulic jack 7 reaches control cabinet 5 on the bank by withstand voltage manifold, carries out unifying lock control, and unification is transferred, and unification is closed down.By operating personnel's operating control handle, slowly transfer hydraulic jack 7 to support post 3 and antiskid column 4 fall mat case 2 welds firm.

Claims (7)

1. the application of hydraulic pressure sedimenting system in Platform Deck reforming technology, comprise cutting support post and cutting antiskid column and hydraulic jack is installed, it is characterized in that described cutting support column and antiskid column, 15 support posts and 6 antiskid columns that hydraulic jack need be installed, 0.9-1.0 rice is up sliced off from mat case, support column and the antiskid column cutting 0.45-0.55 rice of hydraulic jack will be installed, upper deck entire lowering is welded and fixed again to the At The Height of upper deck back gauge baseline 4.5m; Described installation hydraulic jack, be first all pipings of the support post of upper deck and antiskid column top are cut off, then utilize triangle stability characteristic (quality), take to intersect in length and breadth, matrix distribution mode every a top one installs hydraulic jack, and hydraulic jack controlled by switch board.
2. the application of hydraulic pressure sedimenting system according to claim 1 in Platform Deck reforming technology, is characterized in that described installation hydraulic jack, is to be provided with pallet, hydraulic jack and reinforcement support in turn in the support post after cutting.
3. the application of hydraulic pressure sedimenting system according to claim 1 and 2 in Platform Deck reforming technology, it is characterized in that described installation hydraulic jack,, in the antiskid column after cutting, hanging basket is installed, be provided with pad and hydraulic jack in turn in hanging basket, hanging basket is provided with clips outside top.
4. the application of hydraulic pressure sedimenting system according to claim 1 in Platform Deck reforming technology, is characterized in that described pallet top be channel-section steel, the bottom of cross welding is round table-like welded unit.
5. the application of hydraulic pressure sedimenting system according to claim 1 in Platform Deck reforming technology, after it is characterized in that described 21 hydraulic jack install, operation hydraulic jack, safety switches the cutting of each support post and antiskid column steadily, by remaining 15 support posts and antiskid column, up slice off 0.45-0.55 rice from mat box top.
6. the application of hydraulic pressure sedimenting system in Platform Deck reforming technology according to claim 1 or 5, it is characterized in that described by remaining 15 support posts and antiskid column, 0.45-0.55 rice is up sliced off from mat box top, then hydraulic jack is operated, slowly transfer and fall on mat case to support column, it is firm again to be welded.
7. the application of hydraulic pressure sedimenting system in Platform Deck reforming technology according to claim 1 or 2 or 4 or 5, it is characterized in that constructing according to this step successively, hydraulic jack is withdrawn from during distance 2.4 meters, mat box top at the bottom of upper deck, to the support post after the every root cutting declined and antiskid column, correspond on original position and carry out full weld, the entirety completing upper deck falls.
CN201410399293.5A 2014-08-14 2014-08-14 The application of hydraulic pressure sedimenting system in Platform Deck reforming technology Active CN104294808B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410399293.5A CN104294808B (en) 2014-08-14 2014-08-14 The application of hydraulic pressure sedimenting system in Platform Deck reforming technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410399293.5A CN104294808B (en) 2014-08-14 2014-08-14 The application of hydraulic pressure sedimenting system in Platform Deck reforming technology

Publications (2)

Publication Number Publication Date
CN104294808A true CN104294808A (en) 2015-01-21
CN104294808B CN104294808B (en) 2016-04-06

Family

ID=52314738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410399293.5A Active CN104294808B (en) 2014-08-14 2014-08-14 The application of hydraulic pressure sedimenting system in Platform Deck reforming technology

Country Status (1)

Country Link
CN (1) CN104294808B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208563A (en) * 2017-07-06 2019-01-15 烟台中集来福士海洋工程有限公司 The method for maintaining of self-elevating drilling platform

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001053609A1 (en) * 2000-01-17 2001-07-26 Saipem U.K. Limited Removal of decks from offshore structures
RU2312185C1 (en) * 2006-04-11 2007-12-10 Виктор Михайлович Комов Marine complex for in-situ hydrocarbon fuel production of oil and gas condensate (variants)
US20080247827A1 (en) * 2007-03-30 2008-10-09 Remedial (Cyprus) Pcl Work-over rig assembly and methods thereof
CN102409650A (en) * 2011-09-23 2012-04-11 中国海洋石油总公司 Method for mounting shallow water ocean jacket platform
CN102979069A (en) * 2012-12-13 2013-03-20 中铁上海工程局第二工程有限公司 Bored pile platform construction method on covering-free steep bare rock in deepwater and rapid stream
CN103452088A (en) * 2013-09-12 2013-12-18 中国海洋石油总公司 Jacking device for offshore platform
CN103469777A (en) * 2013-08-29 2013-12-25 中国海洋石油总公司 Offshore platform hydraulic self-lifting device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001053609A1 (en) * 2000-01-17 2001-07-26 Saipem U.K. Limited Removal of decks from offshore structures
RU2312185C1 (en) * 2006-04-11 2007-12-10 Виктор Михайлович Комов Marine complex for in-situ hydrocarbon fuel production of oil and gas condensate (variants)
US20080247827A1 (en) * 2007-03-30 2008-10-09 Remedial (Cyprus) Pcl Work-over rig assembly and methods thereof
CN102409650A (en) * 2011-09-23 2012-04-11 中国海洋石油总公司 Method for mounting shallow water ocean jacket platform
CN102979069A (en) * 2012-12-13 2013-03-20 中铁上海工程局第二工程有限公司 Bored pile platform construction method on covering-free steep bare rock in deepwater and rapid stream
CN103469777A (en) * 2013-08-29 2013-12-25 中国海洋石油总公司 Offshore platform hydraulic self-lifting device
CN103452088A (en) * 2013-09-12 2013-12-18 中国海洋石油总公司 Jacking device for offshore platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208563A (en) * 2017-07-06 2019-01-15 烟台中集来福士海洋工程有限公司 The method for maintaining of self-elevating drilling platform
CN109208563B (en) * 2017-07-06 2021-01-26 烟台中集来福士海洋工程有限公司 Maintenance method of self-elevating drilling platform

Also Published As

Publication number Publication date
CN104294808B (en) 2016-04-06

Similar Documents

Publication Publication Date Title
CN201268937Y (en) Double-layer hanging cradle for working aloft
CN102786004B (en) Integrally moving on-load hydraulic lifting system without mooring rope and lifting method
CN103452126B (en) Light combined hanging box with recyclable baseplate steels and construction technology thereof
CN101892636A (en) Integral lifting reconstruction method for high-span overweight continuous box girder
CN103730231B (en) A kind of head cover of transformer lowering or hoisting gear
CN103572763B (en) Large-span steel supports pattern foundation pit supporting structure Demolition Construction method
CN204626411U (en) A kind of pile foundation steel bar cage erecting device
CN104294808B (en) The application of hydraulic pressure sedimenting system in Platform Deck reforming technology
CN110893520A (en) Storage tank inversion method
KR101319019B1 (en) Method of establishing wind power generator and apparatus thereof
CN103193162A (en) Crane heightening device and method
CN204938800U (en) Tower crane rood beam basis
CN201877729U (en) Mobile type quick dismantlement spanning frame
CN106120880A (en) A kind of offshore wind farm single-pile foundation Compressive Bearing Capacity assay device
CN102101629B (en) Hierarchical synchronous hydraulic jacking process for large-tonnage ocean engineering structure
CN203127430U (en) Steel bar support frame
CN203939014U (en) A kind of tubular offshore boosting station
CN203746609U (en) Transformer top cover lifting device
CN201553529U (en) Steel pipe combined type caisson mold plate lifting frame
CN202880730U (en) Integral lifting device for outside of storage tank
CN202849925U (en) Steel trestle erected in rivers influenced by tides
KR101322917B1 (en) Method of establishing wind power generator and apparatus thereof
CN203947455U (en) A kind of Deep Water Steel structure bridging constructional device
CN104060845A (en) Temporary fixing structure for steel column and construction method thereof
CN217000178U (en) Hydraulic jacking device for integrally lifting large steel structure at high altitude

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200717

Address after: 257237, No. 3, Heilongjiang Road, Fairy River town, Hekou District, Shandong, Dongying

Patentee after: SHANDONG HAISHENG OCEAN ENGINEERING GROUP Co.,Ltd.

Address before: 257237, No. 3, Heilongjiang Road, Fairy River town, Hekou District, Shandong, Dongying

Co-patentee before: Wang Shoucheng

Patentee before: Xu Fengxue

Co-patentee before: Wei Tao