CN104268700A - Intelligent early warning and control system for major network project cost investment - Google Patents

Intelligent early warning and control system for major network project cost investment Download PDF

Info

Publication number
CN104268700A
CN104268700A CN201410511301.0A CN201410511301A CN104268700A CN 104268700 A CN104268700 A CN 104268700A CN 201410511301 A CN201410511301 A CN 201410511301A CN 104268700 A CN104268700 A CN 104268700A
Authority
CN
China
Prior art keywords
cost
major network
key index
early warning
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410511301.0A
Other languages
Chinese (zh)
Inventor
方昱璋
张琦
付兵彬
杨晶
包权宗
林东敏
丁政中
马林
王海璐
孙永彦
魏勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGXI BOWEI NEW TECHNOLOGY CO LTD
State Grid Corp of China SGCC
State Grid Gansu Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Gansu Electric Power Co Ltd
Original Assignee
JIANGXI BOWEI NEW TECHNOLOGY CO LTD
State Grid Corp of China SGCC
State Grid Gansu Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Gansu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGXI BOWEI NEW TECHNOLOGY CO LTD, State Grid Corp of China SGCC, State Grid Gansu Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Gansu Electric Power Co Ltd filed Critical JIANGXI BOWEI NEW TECHNOLOGY CO LTD
Priority to CN201410511301.0A priority Critical patent/CN104268700A/en
Publication of CN104268700A publication Critical patent/CN104268700A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • G06Q10/06375Prediction of business process outcome or impact based on a proposed change
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to an intelligent early warning and control system for major network project cost investment. An intelligent early warning and control method includes the steps that the requirements and the standards of cost data collection in the processes of project estimate, rough calculation, budget and settlement are unified, and cost and technical data within 3-5 years in a region range are collected to form a major network project typical cost database; various bid invitations in collected typical cost are researched and analyzed, and data with large influence are extracted as key index data to form a key index comparison model; based on the typical cost database and the key index comparison model, a key parameter selecting rule, a key index matching rule and a comparison and early warning rule are made to achieve intelligent early warning and control over a major network project. The indexes of major network project cost are collected and analyzed, the key index parameters affecting the cost investment are researched and set, an intelligent means is provided for evaluating the major network project design, and the cost abnormal conditions are detected intelligently and marked out.

Description

A kind of major network construction costs investment intelligent early-warning control system
Technical field
The present invention relates to a kind of major network construction costs investment intelligent early-warning control system, belong to electric system Project Cost Field.
Background technology
Under current Engineering Cost Management pattern, construction costs evaluation method is confined to investment estimate or budget estimate of preliminary design, and can not contain comprehensively and serve construction costs, budgetary estimate, each stage horizontal management of clearing, construction costs overall process cannot be met, the needs of dynamic management, affect project investment control.And in evaluation procedure, expert is general evaluates according to management expectancy and experience, lacks a set of science, reasonable, effectively evaluating module, thus can not specification cost evaluate well.
Summary of the invention
The object of the invention is for the deficiencies in the prior art, provide a kind of major network construction costs to invest intelligent early-warning control system.
Object of the present invention is achieved through the following technical solutions:
1, consolidated project estimation, budgetary estimate, budget, clearing each process cost data collection requirements and specification, and collect 3-5 cost and technical data in geographic coverage, form major network engineering typical cost database;
2, all kinds of bids of collecting in typical cost are studied, analyzed, extract the larger data of impact as key index data, form key index contrast model;
3, based on typical cost storehouse and key index model, formulate key parameter selection rule, key index matched rule, contrast early warning rule, realize major network engineering intelligent forewarn.
Beneficial effect of the present invention: by carrying out Collection and analysis to the index of major network construction costs, research setting affects the key index parameter of cost investment, intelligent means are provided, Intelligent Measurement and identify its cost abnormal conditions for carrying out evaluation to major network engineering design.
Embodiment
Object of the present invention is achieved through the following technical solutions:
1, consolidated project estimation, budgetary estimate, budget, clearing each process cost data collection requirements and specification, and collect 3-5 cost and technical data in geographic coverage, form major network engineering typical cost database;
2, all kinds of bids of collecting in typical cost are studied, analyzed, extract the larger data of impact as key index data, form key index contrast model;
3, based on typical cost storehouse and key index model, formulate key parameter selection rule, key index matched rule, contrast early warning rule, realize major network engineering intelligent forewarn.

Claims (1)

1. a major network construction costs investment intelligent early-warning control system, is characterized in that:
The estimation of A, consolidated project, budgetary estimate, budget, clearing each process cost data collection requirements and specification, and collect 3-5 cost and technical data in geographic coverage, form major network engineering typical cost database;
B, all kinds of bids of collecting in typical cost are studied, analyzed, extract the larger data of impact as key index data, form key index contrast model;
C, based on typical cost storehouse and key index model, formulate key parameter selection rule, key index matched rule, contrast early warning rule, realize major network engineering intelligent forewarn.
CN201410511301.0A 2014-09-29 2014-09-29 Intelligent early warning and control system for major network project cost investment Pending CN104268700A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410511301.0A CN104268700A (en) 2014-09-29 2014-09-29 Intelligent early warning and control system for major network project cost investment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410511301.0A CN104268700A (en) 2014-09-29 2014-09-29 Intelligent early warning and control system for major network project cost investment

Publications (1)

Publication Number Publication Date
CN104268700A true CN104268700A (en) 2015-01-07

Family

ID=52160220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410511301.0A Pending CN104268700A (en) 2014-09-29 2014-09-29 Intelligent early warning and control system for major network project cost investment

Country Status (1)

Country Link
CN (1) CN104268700A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105373885A (en) * 2015-11-10 2016-03-02 国网福建省电力有限公司 Electric power engineering design review and technical economic evaluation information system
CN112396336A (en) * 2020-11-27 2021-02-23 国网天津市电力公司 Intelligent evaluation system and evaluation method for power transmission and transformation project cost

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105373885A (en) * 2015-11-10 2016-03-02 国网福建省电力有限公司 Electric power engineering design review and technical economic evaluation information system
CN112396336A (en) * 2020-11-27 2021-02-23 国网天津市电力公司 Intelligent evaluation system and evaluation method for power transmission and transformation project cost

Similar Documents

Publication Publication Date Title
WO2013006302A3 (en) Automatic identification of operating parameters for power plants
EP2520994A3 (en) Automated system and method for implementing statistical comparison of power plant operations
MX2017016552A (en) Method of detecting home appliance bus control system.
CN104410163B (en) A kind of safety in production based on electric energy management system and power-economizing method
CN105574642A (en) Smart grid big data-based electricity price execution checking method
CN105631598A (en) Electrical equipment defect analysis method based on cluster defects
CN103310294A (en) Energy performance contracting system
CN101465544A (en) Real time collection and monitoring system for electrification side control performance standard check
CN104992381A (en) Power grid project quantity list evaluation application software platform establishing method
CN106777005A (en) User power utilization behavior analysis method based on big data technological improvement clustering algorithm
CN103793756A (en) Transformer economic operation characteristic analyzing method
Chowdhury et al. Non-intrusive load monitoring using ensemble empirical mode decomposition and random forest classifier
CN104268700A (en) Intelligent early warning and control system for major network project cost investment
CN104156888A (en) Power system operation risk monitoring method based on comprehensive risk evaluation model
CN102323975B (en) Message correctness judging method of IEC61850-based model file
CN104299167A (en) Energy consumption analysis method for user power data of intelligent energy consumption system
CN103217590A (en) Method automatically acquiring atmospheric electric field thunder and lightning early-warning characteristic parameter threshold values
CN110413622B (en) Data processing method based on electric power big data platform
CN104143160A (en) Method for evaluating power grid dispatching capacity on basis of computer implementation
CN102968060A (en) Intelligent identification method for turbine adjustment system parameters
CN108198090B (en) Typhoon monitoring and point distribution method for power grid power transmission and distribution facility
CN113725919B (en) Energy-saving power system for new energy grid-connected power generation and dynamic energy-saving scheduling method
CN104598457A (en) Method for predicting surface noise situation by multi-point noise value through interpolation algorithm
CN111181172B (en) Power grid frequency disturbance source positioning method for scheduling master station
CN104036433A (en) Method for evaluating running management level of power distribution network

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150107

WD01 Invention patent application deemed withdrawn after publication