CN104191239A - Instrument board assembling production line - Google Patents

Instrument board assembling production line Download PDF

Info

Publication number
CN104191239A
CN104191239A CN201410422180.2A CN201410422180A CN104191239A CN 104191239 A CN104191239 A CN 104191239A CN 201410422180 A CN201410422180 A CN 201410422180A CN 104191239 A CN104191239 A CN 104191239A
Authority
CN
China
Prior art keywords
instrument board
vehicle frame
supporting leg
gas
agc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410422180.2A
Other languages
Chinese (zh)
Other versions
CN104191239B (en
Inventor
韩国跃
王秀峰
王潇潇
高坡
金英子
白洲通
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Haosen Auto Parts Co.,Ltd.
Original Assignee
Jinxing Automotive Interior Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinxing Automotive Interior Decoration Co Ltd filed Critical Jinxing Automotive Interior Decoration Co Ltd
Priority to CN201410422180.2A priority Critical patent/CN104191239B/en
Priority claimed from CN201410422180.2A external-priority patent/CN104191239B/en
Publication of CN104191239A publication Critical patent/CN104191239A/en
Application granted granted Critical
Publication of CN104191239B publication Critical patent/CN104191239B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P21/00Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control
    • B23P21/004Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control the units passing two or more work-stations whilst being composed
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • B25B11/02Assembly jigs

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Automobile Manufacture Line, Endless Track Vehicle, Trailer (AREA)

Abstract

The invention discloses an instrument board assembling production line, and relates to a production line for assembling instrument boards. The instrument board assembling production line is mainly designed to solve the problem that the assembling speed of instrument boards is low at present. The instrument board assembling production line comprises an AGC trolley and an AGV trolley. An annular magnetic stripe rail, a straight line magnetic stripe rail, a guide rail, air source top outlet supports and stopper cylinder supports are arranged on the ground. A conveying rail and instrument board assembling operation trolleys are further included. A conveying belt of the conveying rail is provided with protruding blocks, the air source top outlet supports are provided with air source top outlets, and the stopper cylinder supports are provided with stopper cylinders. Frames of each instrument board assembling operation trolley are fixed on a left supporting leg and a right supporting leg, and traveling wheels are arranged at the bottom of each left supporting leg and the bottom of the corresponding right supporting leg. AGC trolley stand column inserting grooves and AGC trolley guide sheets are arranged on the lower portions of the frames. Axles at the two ends of each overturning support are mounted in two mounted bearings respectively, a chuck is fixed on the axle at one end of each overturning support, and the frames are provided with ejection cylinders. Each overturning support is provided with clamping mechanisms. The frames are further provided with air source docking ports, barrier plates and stopping rods. The instrument board assembling production line has the advantage that production efficiency is high.

Description

Instrument board assembly line
Technical field:
The present invention relates to automotive trim production field, specifically relate to a kind of production line of assembling instrument board.
Background technology:
At present at automotive trim production field, the assembling process of instrument board is: several workmans stand in the both sides of microscler workbench, to the upper parts such as instrument board, air channel of installing of Guan Liang, after each parts installation, workman needs lifting Workpiece transfer to next station, carries out the installation of next parts.Its weak point is that instrument board weight is large, needs two workmans to lift, and recruitment is many, and production efficiency is low, and labour intensity is large.Defective work piece very easily in handover process, affects workpiece quality in addition.
Summary of the invention:
Technical problem to be solved by this invention is to provide a kind of instrument board assembly line, and its recruitment is few, and production efficiency is high, can defective work piece.
Above-mentioned purpose is achieved in that it comprises AGC dolly and AGV dolly, lays on the ground the annular magnetic stripe track matching with AGC dolly, also has the straight line magnetic stripe track matching with AGV dolly, and straight line magnetic stripe track is positioned at the centre of annular magnetic stripe track; Also comprise delivery track, some the instrument board assembly operation cars that structure is identical; Described delivery track comprises carriage and conveyer belt, the conveyer belt of delivery track is provided with several projections, the ground of delivery track one side is provided with guide rail, on the ground of delivery track opposite side, being fixed with several sources of the gas ejects mouthful support and several and stops air cylinder support, source of the gas ejects a mouthful support and is provided with source of the gas and ejects mouth, source of the gas ejects mouthful has tracheae to be connected with source of the gas, stops that air cylinder support is provided with to stop cylinder;
Described instrument board assembly operation car comprises vehicle frame, and vehicle frame is fixed on left branch leg and right supporting leg, and road wheel is arranged at the bottom of left branch leg and right supporting leg; Bottom one side of vehicle frame is provided with AGC stay slot, and the bottom opposite side of vehicle frame is provided with AGC car prerotation vane; Also comprise turnover bracket, on the vehicle frame of the vehicle frame of left branch leg top and right supporting leg top, rolling bearing units are all housed, the axle at turnover bracket two ends is arranged on respectively in two rolling bearing units, chuck is fixed on the axle of turnover bracket one end, on vehicle frame, be equipped with and eject cylinder, while ejecting cylinder operation, its cylinder bar can extend in the hole of chuck, and turnover bracket is positioned; Turnover bracket is provided with three clamp mechanism that structure is identical, and these three clamp mechanism are respectively lower clamp mechanism, left clamp mechanism, right clamp mechanism; Described clamp mechanism comprises clamping cylinder, the cylinder body of clamping cylinder is fixed on turnover bracket, on the cylinder bar of clamping cylinder, be connected with Y shape connector, the other end of Y shape connector is connected by pin with the rear end of compressor arm, the front end of compressor arm is equipped with pressure head, back-up block is located on the turnover bracket between Y shape connector and pressure head, and brace lower end is connected with back-up block by little axle, and the upper end of brace is connected with compressor arm by little axle; During work, workpiece is placed on turnover bracket, the clamping cylinder work of each clamp mechanism, and each hold-down head, by Work-sheet pressing, is convenient to workman and is installed;
On vehicle frame, be also provided with source of the gas docking port, barrier plate, lever;
Described source of the gas docking port comprises holder, intermediate disc is fixed on holder, in splicer, establish air flue, suction nozzle is connected by splicer with outlet nozzle, outlet nozzle stretches out from the hole of holder, between outlet nozzle and the hole wall of holder, leave gap, dome and intermediate disc are fixed together, splicer is arranged in the cavity between dome and intermediate disc, suction nozzle stretches out from dome, on intermediate disc, there are several holes, in each hole, the decorative pearl on top of an official cap is housed, the bulb of the decorative pearl on top of an official cap withstands on splicer, splicer can move freely among a small circle in dome, make suction nozzle and source of the gas eject a mouthful rapid abutting joint.
Between the outlet nozzle of described source of the gas docking port and each cylinder, by tracheae, be connected.
The place ahead of each road wheel is provided with magnet, and described each magnet respectively support by is separately contained on supporting leg.
Advantage of the present invention is: by AGC dolly, drive instrument board assembly operation car to move, the column that is the little roof of AGC stretches out, be inserted in the column slot of instrument board assembly operation car, AGC dolly, along annular magnetic stripe rail moving, drives instrument board assembly operation car to move.When it drives to delivery track front end, the column of the little roof of AGC is retracted, and from the bottom of instrument board assembly operation car, moves on, and when walking to delivery track rear end, the column at its top stretches out, and the instrument board assembly operation car being positioned at is herein taken away.In conveyer belt running, its surperficial projection contacts with the barrier plate being positioned on the instrument board assembly operation car of delivery track front end, this described instrument board assembly operation car moves backward under the drive of conveyer belt, when walking to source of the gas and eject mouthful support place, stop cylinder operation, cylinder bar stretches out shelves at the lever rear of instrument board assembly operation car, instrument board assembly operation car stops mobile, now conveyer belt stop motion, source of the gas ejects mouth and the docking of source of the gas docking port, meanwhile, AGV dolly is along straight line magnetic stripe rail moving, the workpiece cassette of depositing workpiece being placed on it is delivered to instrument board assembly operation roof, manually Guan Liang is placed on turnover bracket, adjust turnover bracket angle, then by chuck, locate.The clamping cylinder work of each clamp mechanism, by Workpiece clamping, complete after the installation of Guan Liang, stop the cylinder bar playback of cylinder, conveyer belt works on, instrument board assembly operation car continues reach, readjusts the angle of turnover bracket, carries out the installation of next parts, until all parts installations, instrument board assembly operation car is taken away delivery track by AGC dolly, and last workman unloads mounted instrument board, so circulation.Advantage is that recruitment is few, and production efficiency is high, can defective work piece, and labour intensity is low.Because the place ahead at each road wheel is provided with magnet, so can for example, by the iron article that fall to the ground (iron nail) sucking-off.
Accompanying drawing explanation:
Fig. 1 is overall structure schematic diagram of the present invention;
Fig. 2 is the Facad structure schematic diagram of instrument board assembly operation car in the present invention who amplifies;
Fig. 3 is the structure schematic diagram of instrument board assembly operation car in the present invention who amplifies;
Fig. 4 is the structural representation of the clamp mechanism on instrument board assembly operation car in the present invention who amplifies;
Fig. 5 is the structural representation of the source of the gas docking port on instrument board assembly operation car in the present invention who amplifies.
The specific embodiment:
With reference to Fig. 1-Fig. 3,, it comprises AGC dolly 1 and AGV dolly 2, lays on the ground the annular magnetic stripe track 3 matching with AGC dolly, also has the straight line magnetic stripe track 4 matching with AGV dolly, straight line magnetic stripe track is positioned at the centre of annular magnetic stripe track; Also comprise delivery track 5, some the instrument board assembly operation cars 6 that structure is identical; Described delivery track comprises carriage 5-1 and conveyer belt 5-2, the conveyer belt of delivery track is provided with several projections 5-3, the ground of delivery track one side is provided with guide rail 7, on the ground of delivery track opposite side, be fixed with that several sources of the gas eject mouthful support 8 and several stop air cylinder support 9, source of the gas ejects a mouthful support and is provided with source of the gas and ejects mouthfuls 10, source of the gas ejects mouthful has tracheae to be connected with source of the gas, stops that air cylinder support is provided with to stop cylinder 11;
Described instrument board assembly operation car comprises vehicle frame 6-1, and vehicle frame is fixed on left branch leg 6-2 and right supporting leg 6-3, and road wheel 6-4 is arranged at the bottom of left branch leg and right supporting leg; Bottom one side of vehicle frame is provided with AGC stay slot 6-6, and the bottom opposite side of vehicle frame is provided with AGC car prerotation vane 6-7; Also comprise turnover bracket 6-8, on the vehicle frame of the vehicle frame of left branch leg top and right supporting leg top, rolling bearing units are all housed, the axle at turnover bracket two ends is arranged on respectively in two rolling bearing units, chuck 6-9 is fixed on the axle of turnover bracket one end, on vehicle frame, be equipped with and eject cylinder 6-10, while ejecting cylinder operation, its cylinder bar can extend in the hole of chuck, and turnover bracket is positioned; Turnover bracket is provided with three clamp mechanism 6-11 that structure is identical, and these three clamp mechanism are respectively lower clamp mechanism, left clamp mechanism, right clamp mechanism;
With reference to Fig. 4, described clamp mechanism comprises clamping cylinder 6-11-1, the cylinder body of clamping cylinder is fixed on turnover bracket, on the cylinder bar of clamping cylinder, be connected with Y shape connector 6-11-2, the other end of Y shape connector is connected by pin with the rear end of compressor arm 6-11-3, the front end of compressor arm is equipped with pressure head 6-11-4, back-up block 6-11-5 is located on the turnover bracket between Y shape connector and pressure head, brace 6-11-6 lower ends are connected with back-up block by little axle, and the upper end of brace is connected with compressor arm by little axle; During work, workpiece is placed on turnover bracket, the clamping cylinder work of each clamp mechanism, and each hold-down head, by Work-sheet pressing, is convenient to workman and is installed;
On vehicle frame, be also provided with source of the gas docking port 6-12, barrier plate 6-13, lever 6-14;
With reference to Fig. 5, described source of the gas docking port comprises holder 6-12-1, intermediate disc 6-12-2 is fixed on holder, in splicer 6-12-3, establish air flue 6-12-4, suction nozzle 6-12-5 is connected by splicer with outlet nozzle 6-12-6, outlet nozzle stretches out from the hole of holder, between outlet nozzle and the hole wall of holder, leave gap, dome 6-12-7 is fixed together with intermediate disc, splicer is arranged in the cavity between dome and intermediate disc, suction nozzle stretches out from dome, on intermediate disc, there are several holes, in each hole, the decorative pearl on top of an official cap 6-12-8 is housed, the bulb of the decorative pearl on top of an official cap withstands on splicer, splicer can move freely among a small circle in dome, make suction nozzle and source of the gas eject a mouthful rapid abutting joint.
Between the outlet nozzle of described source of the gas docking port and each cylinder, by tracheae, be connected.
The place ahead of each road wheel is provided with magnet 6-5, and described each magnet respectively support by is separately contained on supporting leg.

Claims (2)

1. instrument board assembly line, it is characterized in that: comprise AGC dolly (1) and AGV dolly (2), lay on the ground the annular magnetic stripe track (3) matching with AGC dolly, also have the straight line magnetic stripe track (4) matching with AGV dolly, straight line magnetic stripe track is positioned at the centre of annular magnetic stripe track; Also comprise delivery track (5), some the instrument board assembly operation cars (6) that structure is identical; Described delivery track comprises carriage (5-1) and conveyer belt (5-2), the conveyer belt of delivery track is provided with several projections (5-3), the ground of delivery track one side is provided with guide rail (7), on the ground of delivery track opposite side, be fixed with that several sources of the gas eject a mouthful support (8) and several stop air cylinder support (9), source of the gas ejects a mouthful support and is provided with source of the gas and ejects mouthful (10), source of the gas ejects mouthful has tracheae to be connected with source of the gas, stops that air cylinder support is provided with to stop cylinder (11);
Described instrument board assembly operation car comprises vehicle frame (6-1), and vehicle frame is fixed on left branch leg (6-2) and right supporting leg (6-3) is upper, and road wheel (6-4) is arranged at the bottom of left branch leg and right supporting leg; Bottom one side of vehicle frame is provided with AGC stay slot (6-6), and the bottom opposite side of vehicle frame is provided with AGC car prerotation vane (6-7); Also comprise turnover bracket (6-8), on the vehicle frame of the vehicle frame of left branch leg top and right supporting leg top, rolling bearing units are all housed, the axle at turnover bracket two ends is arranged on respectively in two rolling bearing units, chuck (6-9) is fixed on the axle of turnover bracket one end, is equipped with and ejects cylinder (6-10) on vehicle frame; Turnover bracket is provided with three clamp mechanism (6-11) that structure is identical, and these three clamp mechanism are respectively lower clamp mechanism, left clamp mechanism, right clamp mechanism;
Described clamp mechanism comprises clamping cylinder (6-11-1), the cylinder body of clamping cylinder is fixed on turnover bracket, on the cylinder bar of clamping cylinder, be connected with Y shape connector (6-11-2), the other end of Y shape connector is connected by pin with the rear end of compressor arm (6-11-3), the front end of compressor arm is equipped with pressure head (6-11-4), back-up block (6-11-5) is located on the turnover bracket between Y shape connector and pressure head, brace (6-11-6) lower end is connected with back-up block by little axle, and the upper end of brace is connected with compressor arm by little axle;
On vehicle frame, be also provided with source of the gas docking port (6-12), barrier plate (6-13), lever (6-14);
Described source of the gas docking port comprises holder (6-12-1), intermediate disc (6-12-2) is fixed on holder, in splicer (6-12-3), establish air flue (6-12-4), suction nozzle (6-12-5) is connected by splicer with outlet nozzle (6-12-6), outlet nozzle stretches out from the hole of holder, between outlet nozzle and the hole wall of holder, leave gap, dome (6-12-7) is fixed together with intermediate disc, splicer is arranged in the cavity between dome and intermediate disc, suction nozzle stretches out from dome, on intermediate disc, there are several holes, the decorative pearl on top of an official cap (6-12-8) is housed in each hole, the bulb of the decorative pearl on top of an official cap withstands on splicer, splicer can move freely among a small circle in dome.
2. according to instrument board assembly line claimed in claim 1, it is characterized in that: the place ahead of each road wheel is provided with magnet (6-5), described each magnet respectively support by is separately contained on supporting leg.
CN201410422180.2A 2014-08-26 Instrument board assembly line Active CN104191239B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410422180.2A CN104191239B (en) 2014-08-26 Instrument board assembly line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410422180.2A CN104191239B (en) 2014-08-26 Instrument board assembly line

Publications (2)

Publication Number Publication Date
CN104191239A true CN104191239A (en) 2014-12-10
CN104191239B CN104191239B (en) 2016-11-30

Family

ID=

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105676826A (en) * 2016-03-07 2016-06-15 成都亨通兆业精密机械有限公司 Instrument board production line system
CN106078208A (en) * 2016-07-28 2016-11-09 平湖拓伟思自动化设备有限公司 A kind of intelligent manufacturing system based on industrial robot
CN106493579A (en) * 2016-10-31 2017-03-15 上海发那科机器人有限公司 A kind of panel beating system and its workflow
CN107649425A (en) * 2017-10-31 2018-02-02 天津市凯源新能电气有限公司 A kind of electronic instrument automatic flushing device

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2652890Y (en) * 2003-10-13 2004-11-03 上海通用东岳汽车有限公司 Assembling transport producing line
CN101987415A (en) * 2010-05-28 2011-03-23 徐州圣邦机械有限公司 Assembling production line for assembling hoist roller speed reducer assembly
CN102390677A (en) * 2011-08-03 2012-03-28 江苏天奇物流系统工程股份有限公司 Sliding plate conveying system with accompanied lifting function
EP2460620A1 (en) * 2010-12-03 2012-06-06 ThyssenKrupp System Engineering GmbH Transport system
CN103286559A (en) * 2013-06-21 2013-09-11 江苏三志电器有限公司 Production line tool of engineering machinery instrument desk
CN103640644A (en) * 2013-11-22 2014-03-19 广东邦普循环科技有限公司 Scraped automobile preprocessing method and production line thereof
CN103879738A (en) * 2014-03-31 2014-06-25 长城汽车股份有限公司 Automatic material line-following conveying system
EP2745982A2 (en) * 2012-12-08 2014-06-25 Identytec GmbH & Co. KG Production system
CN204053471U (en) * 2014-08-26 2014-12-31 金兴汽车内饰股份有限公司 Instrument board assembly line

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2652890Y (en) * 2003-10-13 2004-11-03 上海通用东岳汽车有限公司 Assembling transport producing line
CN101987415A (en) * 2010-05-28 2011-03-23 徐州圣邦机械有限公司 Assembling production line for assembling hoist roller speed reducer assembly
EP2460620A1 (en) * 2010-12-03 2012-06-06 ThyssenKrupp System Engineering GmbH Transport system
CN102390677A (en) * 2011-08-03 2012-03-28 江苏天奇物流系统工程股份有限公司 Sliding plate conveying system with accompanied lifting function
EP2745982A2 (en) * 2012-12-08 2014-06-25 Identytec GmbH & Co. KG Production system
CN103286559A (en) * 2013-06-21 2013-09-11 江苏三志电器有限公司 Production line tool of engineering machinery instrument desk
CN103640644A (en) * 2013-11-22 2014-03-19 广东邦普循环科技有限公司 Scraped automobile preprocessing method and production line thereof
CN103879738A (en) * 2014-03-31 2014-06-25 长城汽车股份有限公司 Automatic material line-following conveying system
CN204053471U (en) * 2014-08-26 2014-12-31 金兴汽车内饰股份有限公司 Instrument board assembly line

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105676826A (en) * 2016-03-07 2016-06-15 成都亨通兆业精密机械有限公司 Instrument board production line system
CN106078208A (en) * 2016-07-28 2016-11-09 平湖拓伟思自动化设备有限公司 A kind of intelligent manufacturing system based on industrial robot
CN106493579A (en) * 2016-10-31 2017-03-15 上海发那科机器人有限公司 A kind of panel beating system and its workflow
CN107649425A (en) * 2017-10-31 2018-02-02 天津市凯源新能电气有限公司 A kind of electronic instrument automatic flushing device

Similar Documents

Publication Publication Date Title
CN103317248B (en) Production device and machining method for U-shaped longitudinal beam and lining beam automatic positioning beam combining spot welding
JP6025334B2 (en) Plywood patching device
CN104108589A (en) Squirrel-cage turnover device
CN106315207A (en) Conveying and lifting mechanism for laser-cut steel plates
CN201343366Y (en) Switch device of a rail for a carrier to convey workpieces
CN103935694A (en) Heavy type suspension hinge conveying machine and conveying system
CN204053471U (en) Instrument board assembly line
CN213969700U (en) Car body side wall fixture tool and flexible assembling system
CN106976627B (en) A kind of shared bicycle transport special intelligent fixed equipment
CN103736738A (en) Roll changing device for cold rolling mill working rolls
CN105329338B (en) Synchronization system based on tire Assembling bogie
CN203268951U (en) Conveying trolley for fast switching forming die and clamp
WO2007110723A3 (en) Device for moving cars in multistorey car parks with system for centring the car
CN104191239A (en) Instrument board assembling production line
CN102305726A (en) Automatic grain sampler
CN105109535B (en) A kind of power construction transfer car(buggy) lockwheel brake
CN112355623A (en) Brake block duplex position lock screw machine
CN102887342A (en) Positioning and opening system of louver vehicle
CN104191239B (en) Instrument board assembly line
CN206415850U (en) Motor rotating disk is installed, dismounting dual-purpose integrated machine
CN104070321A (en) Assembly welding conversion device for locomotive end part beam
CN204847318U (en) High -speed platform truck is carried and is rolled bed
CN110525906B (en) Steel pipe transport vehicle and application method thereof
CN105438850B (en) A kind of operating method of vehicle guidance positioning system
CN207645714U (en) Ball valve telescopic joint fast removal trolley

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Huang Renxing

Inventor after: Wang Xiufeng

Inventor after: Gao Po

Inventor before: Han Guoyue

Inventor before: Wang Xiufeng

Inventor before: Wang Xiaoxiao

Inventor before: Gao Po

Inventor before: Jin Yingzi

Inventor before: Bai Zhoutong

CB03 Change of inventor or designer information
CP01 Change in the name or title of a patent holder

Address after: 111000 Liaoyang City, Liaoning province Taizihe District revitalization Road No. 158

Patentee after: Liaoning Jinxing automobile interior decoration Co., Ltd.

Address before: 111000 Liaoyang City, Liaoning province Taizihe District revitalization Road No. 158

Patentee before: Jinxing Automotive Interior Decoration Co., Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20210930

Address after: 111000 Zhenxing Road 158, Taizihe District, Liaoyang City, Liaoning Province

Patentee after: Liaoning Haosen Auto Parts Co.,Ltd.

Address before: 111000 Zhenxing Road 158, Taizihe District, Liaoyang City, Liaoning Province

Patentee before: LIAONING JINXING AUTOMOTIVE INTERIOR DECORATION Co.,Ltd.

TR01 Transfer of patent right