CN104184058B - A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof - Google Patents

A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof Download PDF

Info

Publication number
CN104184058B
CN104184058B CN201410479356.8A CN201410479356A CN104184058B CN 104184058 B CN104184058 B CN 104184058B CN 201410479356 A CN201410479356 A CN 201410479356A CN 104184058 B CN104184058 B CN 104184058B
Authority
CN
China
Prior art keywords
busbar
kink
low
cabinet
voltage cabinet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410479356.8A
Other languages
Chinese (zh)
Other versions
CN104184058A (en
Inventor
束龙胜
陈周
彭家斌
张辉煌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Zhongdian Xingfa and Xinlong Technology Co Ltd
Original Assignee
Anhui Zhongdian Xingfa and Xinlong Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Zhongdian Xingfa and Xinlong Technology Co Ltd filed Critical Anhui Zhongdian Xingfa and Xinlong Technology Co Ltd
Priority to CN201410479356.8A priority Critical patent/CN104184058B/en
Publication of CN104184058A publication Critical patent/CN104184058A/en
Application granted granted Critical
Publication of CN104184058B publication Critical patent/CN104184058B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Gas-Insulated Switchgears (AREA)
  • Patch Boards (AREA)

Abstract

The invention discloses a kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof, including straight-bar portion (1), straight-bar portion (1) one end is provided with handle (4), the other end is provided with the first kink (2), first kink (2) one end is provided with the second kink (3), first kink (2) is provided with chute (21), and the second kink (3) is provided with draw-in groove (31);Also include the pivot pin that can slide in draw-in groove (31), utilize lever push type to install, easy for installation efficiently.

Description

A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof
Technical field
The invention belongs to low-tension switch cabinet technical field, particularly relate to a kind of low-voltage cabinet busbar installation tool and The method installing low-voltage cabinet busbar.
Background technology
Low pressure BLOKSET switch cabinet equipment is the switch cubicle of joint brand, is the most all France's Schneider Company designs and develops, and domestic production factory is all to rely on its technology bulk transfers to carry out factorial praluction.But because of The principle of its design and integrally-built restriction, in big current system is used, the busbar on its cabinet top arranges row Row have to arrange that two rows could meet the requirement of system busbar electric current vertically.Because its big electric current busbar is Two arrangements vertically are put, thus cause switchgear when also cabinet busbar connects, and vertically arranged lower floor is female Connect complex between row's cabinet, even cannot connect, thus cause on-site customer and installation unit to be complained even Refusal is installed, and complete factory to send someone in-site installation, even if but complete factory be also difficult to in-site installation operate, Even first to remove upper strata busbar to install and connect copper bar between the cabinet of lower floor's busbar, this considerably increases existing The services amount of field, increases production cost, leaves negative effect the most also to client and installation unit.
Summary of the invention
The technical problem to be solved is to provide a kind of also cabinet busbar making double layer mother board and installs more square Just, simpler low-voltage cabinet busbar installation tool and the method for installation low-voltage cabinet busbar thereof.
In order to solve above-mentioned technical problem, the technical solution adopted in the present invention is: a kind of low-voltage cabinet busbar peace Holding tool, including straight-bar portion, described straight one end of the rod is provided with handle, and the other end is provided with the first kink, institute Stating first kink one end and be provided with the second kink, described first kink is provided with chute, described second curved Folding part is provided with draw-in groove;Also include the bearing pin that can slide in described chute.
Described handle is cylindrical, and handle welds with straight-bar portion.
Described straight-bar portion, the first kink and the second kink are integral type structure.
A kind of method installing low-voltage cabinet busbar of above-mentioned low-voltage cabinet busbar installation tool, comprises the steps:
1), when busbar being taken out in cabinet, choose two installation tools and be individually positioned in the both sides of busbar, First kink of installation tool is towards outside cabinet, and the draw-in groove of the second kink is installed on cross rail outer;Pin Axle passes installing hole and the chute of two installation tools of busbar;Outwards pull handle, with draw-in groove as fulcrum, Busbar is taken out under the drive of bearing pin;
2) when busbar being loaded cabinet, choose two installation tools and be individually positioned in the both sides of busbar, install First kink of instrument is towards inside cabinet, and the draw-in groove of the second kink is installed on cross rail inner;Bearing pin is worn Cross installing hole and the chute of two installation tools of busbar;Inwardly pull handle, with draw-in groove as fulcrum, at pin Under the drive of axle, busbar is pushed cabinet.
Described bearing pin passes through nut locking in chute.
A technical scheme in technique scheme has the advantage that or beneficial effect, will be previously required to tear open Dress double layer mother board upper end busbar just can carry out busbar and connect the connection of copper bar, or by barbarous and original and poor efficiency The complicated installation of rate is transformed into the high-efficient simple installation that lever is pusher.It is easy to in-site installation, it is to avoid scene Secondary is done over again, and has stopped the workload of factory's Site Service simultaneously, has reduced operating cost.
Accompanying drawing explanation
The structural representation of the Fig. 1 low-voltage cabinet busbar installation tool for providing in the embodiment of the present invention;
Fig. 2 is Fig. 1 busbar installation tool working state figure when being taken out in cabinet by busbar;
Labelling in above-mentioned figure is: 1, straight-bar portion, the 2, first kink, and 21, chute, 3, second Kink, 31, draw-in groove, 4, handle, 5, cabinet, 6, bearing pin, 7, busbar, 71, installing hole, 8, Crossbeam.
Detailed description of the invention
For making the object, technical solutions and advantages of the present invention clearer, below in conjunction with accompanying drawing to the present invention Embodiment is described in further detail.
Seeing Fig. 1, a kind of low-voltage cabinet busbar installation tool, including straight-bar portion 1, one end, straight-bar portion 1 is provided with hands Handle 4, the other end is provided with the first kink 2, and first kink 2 one end is provided with the second kink 3, and first is curved Folding part 2 is provided with chute 21, and the second kink 3 is provided with draw-in groove 31;Also include to slide in chute 21 Dynamic bearing pin 6.
Handle 4 is cylindrical, and handle 4 welds with straight-bar portion 1.
Straight-bar portion the 1, first kink 2 and the second kink 3 are integral type structure.
A kind of method installing low-voltage cabinet busbar of above-mentioned low-voltage cabinet busbar installation tool, comprises the steps:
1), when busbar 7 being taken out in cabinet 5, choose two installation tools and be individually positioned in the two of busbar 7 Side, the first kink 2 of installation tool is towards outside cabinet 5, and the draw-in groove 31 of the second kink 3 is installed on Outside crossbeam 8;Bearing pin 6 passes installing hole 71 and the chute 21 of two installation tools of busbar 7;Outwards pull Fixed handle 4, with draw-in groove 31 as fulcrum, takes out busbar 7 under the drive of bearing pin 6;As shown in Figure 2.
2), when busbar 7 being loaded cabinet 5, choose two installation tools and be individually positioned in the both sides of busbar 7, First kink 2 of installation tool is towards inside cabinet 5, and the draw-in groove 31 of the second kink 3 is installed on crossbeam Inside 8;Bearing pin 6 passes installing hole 71 and the chute 21 of two installation tools of busbar 7;Inwardly pull hands Handle 4, with draw-in groove 31 as fulcrum, pushes cabinet 5 by busbar 7 under the drive of bearing pin 6.Will be in Fig. 2 Installation tool reverses direction.
Bearing pin 6 passes through nut locking in chute 21.
By the fulcrum using a crossbeam 8 in low pressure BLOKSET switch cabinet equipment as propelling, simultaneously The installing hole 71 utilizing busbar to connect on copper bar is positioning towed, busbar connects copper bar and pushes adjacent switch cubicle Equipment.
After using above-mentioned structure, will be previously required to dismount double layer mother board upper end busbar and just can carry out busbar connection The connection of copper bar, or it is transformed into the efficient of lever push type by barbarous and original and inefficient complicated installation Simple installation.It is easy to in-site installation, it is to avoid on-the-spot secondary is done over again, and has stopped factory's Site Service simultaneously Workload, reduce operating cost.
Above in conjunction with accompanying drawing, the present invention is exemplarily described, it is clear that the present invention implements not by upper State the restriction of mode, if the various unsubstantialities that the method design that have employed the present invention is carried out with technical scheme Improvement, or the most improved design by the present invention and technical scheme directly apply to other occasion, all exists Within protection scope of the present invention.

Claims (5)

1. a low-voltage cabinet busbar installation tool, it is characterised in that erector has two, installation toolkit Including straight-bar portion (1), described straight-bar portion (1) one end is provided with handle (4), and the other end is provided with the first kink (2), Described first kink (2) one end is provided with the second kink (3), and described first kink (2) is provided with Chute (21), described second kink (3) is provided with draw-in groove (31);Also including can be in described chute (21) The bearing pin (6) of interior slip.
2. low-voltage cabinet busbar installation tool as claimed in claim 1, it is characterised in that described handle (4) For cylinder, handle (4) welds with straight-bar portion (1).
3. low-voltage cabinet busbar installation tool as claimed in claim 1 or 2, it is characterised in that described straight-bar Portion (1), the first kink (2) and the second kink (3) are integral type structure.
4. the installation low-voltage cabinet busbar of the low-voltage cabinet busbar installation tool as described in claim 1-3 is arbitrary Method, it is characterised in that comprise the steps:
1), when busbar (7) being taken out in cabinet (5), choose two installation tools and be individually positioned in busbar (7) both sides, first kink (2) of installation tool is towards cabinet (5) outside, the second kink (3) Draw-in groove (31) be installed on crossbeam (8) outside;Bearing pin (6) is through the installing hole (71) of busbar (7) Chute (21) with two installation tools;Outwards pull handle (4), with draw-in groove (31) as fulcrum, at pin Busbar (7) is taken out under the drive of axle (6);
2), when busbar (7) being loaded cabinet (5), choose two installation tools and be individually positioned in busbar (7) Both sides, first kink (2) of installation tool towards cabinet (5) inner side, the second kink (3) Draw-in groove (31) is installed on crossbeam (8) inner side;Bearing pin (6) through busbar (7) installing hole (71) and The chute (21) of two installation tools;Inwardly pull handle (4), with draw-in groove (31) as fulcrum, at bearing pin (6) under drive, busbar (7) is pushed cabinet (5).
5. the method installing low-voltage cabinet busbar of low-voltage cabinet busbar installation tool as claimed in claim 4, its Being characterised by, described bearing pin (6) passes through nut locking in chute (21).
CN201410479356.8A 2014-09-18 2014-09-18 A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof Active CN104184058B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410479356.8A CN104184058B (en) 2014-09-18 2014-09-18 A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410479356.8A CN104184058B (en) 2014-09-18 2014-09-18 A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof

Publications (2)

Publication Number Publication Date
CN104184058A CN104184058A (en) 2014-12-03
CN104184058B true CN104184058B (en) 2016-09-14

Family

ID=51964905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410479356.8A Active CN104184058B (en) 2014-09-18 2014-09-18 A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof

Country Status (1)

Country Link
CN (1) CN104184058B (en)

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2256193Y (en) * 1995-10-18 1997-06-11 牛犇 Sealed branch bus installation and inserting device
CN201797281U (en) * 2010-08-05 2011-04-13 大全电气有限公司 In-cabinet main bus bracket
CN202129316U (en) * 2011-06-13 2012-02-01 江苏金方圆数控机床有限公司 Bus bending device
CN203039313U (en) * 2013-01-22 2013-07-03 广东伊顿母线有限公司 Bus duct installation tool
CN203135352U (en) * 2013-02-04 2013-08-14 中建三局第三建设工程有限责任公司 Bridging tool for bus and copper bar
US9048598B2 (en) * 2013-04-30 2015-06-02 Norman R. Byrne Low voltage power receptacle for modular electrical systems
CN203691260U (en) * 2014-02-20 2014-07-02 南京冠亚电源设备有限公司 Photovoltaic inverter busbar fixing installation structure
CN204130967U (en) * 2014-09-18 2015-01-28 安徽鑫龙电器股份有限公司 A kind of low-voltage cabinet busbar erecting tools

Also Published As

Publication number Publication date
CN104184058A (en) 2014-12-03

Similar Documents

Publication Publication Date Title
CN204103316U (en) For the charged insulation eagle's beak pliers action bars disconnected of isolated circuit breaker
CN204088984U (en) For the charged insulating socket spanner hand-operating lever disconnected of isolated circuit breaker
CN205147181U (en) Electrified little generating line cutting means
CN204905778U (en) Plug -in cable head puller
CN203674624U (en) Sleeve-type combination tool for live-line jumper clamp fastening
CN104037662A (en) Special spanner for disassembling drainage wire clamp in electrified mode
CN104184058B (en) A kind of low-voltage cabinet busbar installation tool and the method installing low-voltage cabinet busbar thereof
CN103840277A (en) Electrification connection wire clamp of 66 kV power transmission line electricity leading wire
CN202260147U (en) Bus connector
CN203983518U (en) Substation equipment ground structure
CN204558688U (en) Earthing clamp
CN204252623U (en) A kind of easy-to-mount bracing wire sheath
CN204130967U (en) A kind of low-voltage cabinet busbar erecting tools
CN202495694U (en) Charged fastening device for substation equipment clip bolts
CN107086548B (en) A kind of transfer tributary unit of dc circuit breaker
CN203951097U (en) A kind of charged conduction wire clamp special spanner that disconnects
CN204905673U (en) A station service wiring system for thermal power factory
CN202586085U (en) A portable operation head used for cutting and delivering power of equipment in a ring main unit
CN204632959U (en) A kind of for filling, the device of dismounting ground wire
CN204304054U (en) Bus-tapping current transfer device
CN102969671B (en) Equipotential outlet trolley for double bundle conductor
CN203367920U (en) Earth potential working non-bearing-force connection wire clamp
CN106505419A (en) A kind of switch cubicle of the quick secondary connection of energy
CN207338994U (en) A kind of integrated switched bottom of cabinet seat
CN201946940U (en) Device for sealing tubing head perforation and partial cables penetrating the perforation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 241008 Anhui Province, Wuhu City Jiuhua Jiujiang District No. 118 North Park electrical components

Applicant after: ANHUI ZHONGDIAN XINGFA AND XINLONG TECHNOLOGY CO., LTD.

Address before: 241008 Anhui Province, Wuhu City Jiuhua Jiujiang District No. 118 North Park electrical components

Applicant before: Xinlong Electric-Appliance Co., Ltd., Anhui

COR Change of bibliographic data