CN104180077B - Pipeline runs through concrete floor waterproof construction - Google Patents

Pipeline runs through concrete floor waterproof construction Download PDF

Info

Publication number
CN104180077B
CN104180077B CN201410390324.0A CN201410390324A CN104180077B CN 104180077 B CN104180077 B CN 104180077B CN 201410390324 A CN201410390324 A CN 201410390324A CN 104180077 B CN104180077 B CN 104180077B
Authority
CN
China
Prior art keywords
hole
conical bore
waterproof construction
concrete floor
technique hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410390324.0A
Other languages
Chinese (zh)
Other versions
CN104180077A (en
Inventor
唐金来
陈皓
唐飞
刘凯伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yu Hui Housing Industry Co., Ltd.
Original Assignee
Jincheng Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jincheng Group Co Ltd filed Critical Jincheng Group Co Ltd
Priority to CN201410390324.0A priority Critical patent/CN104180077B/en
Publication of CN104180077A publication Critical patent/CN104180077A/en
Application granted granted Critical
Publication of CN104180077B publication Critical patent/CN104180077B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Road Paving Structures (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses one and run through concrete floor waterproof construction, it comprises technique hole reserved on flooring, and the pea gravel concreten tamping after pipe laying in technique hole. Described technique hole is not waited by least two joint sizes and coaxial conical bore part is socketed to form, the perpendicular conical bore of putting is up big and down small structure, the large end of conical bore of next joint stretches in a pitch circle taper hole, and two conical bore suit places link into an integrated entity by low inside and high outside incline bench. The present invention is after pipe laying in technique hole is fixing, can between technique hole and pipeline, tamp pea gravel concreten, pea gravel concreten solidifies the built-in incline bench of rear formation, can stop the radial and axial contraction of thin concrete, also form labyrinth type water sealing structure, guarantee that flooring is non-leakage. The present invention both can be used as the waterproof construction that water supply pipeline runs through concrete floor, was also suitable as and wore the waterproof construction that other pipeline such as wireway, air channel runs through concrete floor.

Description

Pipeline runs through concrete floor waterproof construction
Technical field
The present invention relates to a kind of house floor gap waterproof construction, specifically, the present invention relates to a kind of pipeline and run through concrete floor waterproof construction.
Background technology
In architectural engineering, when casting concrete flooring, keep supplying the technique hole that sewer pipe passes by design attitude is reserved, after upper and lower conduit road is in place, tamp with pea gravel concreten the technique hole that fills vacancy more afterwards. Technique hole majority reserved in architectural engineering is cylindrical hole, also accidental up big and down small cone-shaped hole, and the technique hole of these shapes is simple in structure, make easily, after tamping, can accomplish the vacancy between effective plugging technology hole and pipeline. But, the technique hole of prior art is because lacking radially position limiting structure and axially waterproof construction, so on the flooring of residential building, reserved technique hole is tamped rear majority and is had seepage problem in reality, its reason is accessible contraction when tamping the pea gravel concreten that fills the later stage and solidifying, cause pea gravel concreten and concrete floor and pipeline junction to have micro-gap, once flooring ponding, water is seeped into downstairs along micro-gap, and excessive infiltration must cause neighbourhood's dispute.
Summary of the invention
There is seepage problem mainly for prior art in the present invention, proposes a kind of pipeline simple in structure, that construction is easy, leakage-proof effect is good and run through concrete floor waterproof construction.
The present invention is achieved through the following technical solutions technical goal.
Pipeline runs through concrete floor waterproof construction, and it comprises technique hole reserved on flooring, and the pea gravel concreten tamping after pipe laying in technique hole. Its improvements are: described technique hole is not waited by least two joint sizes and coaxial conical bore part is socketed to form, the perpendicular conical bore of putting is up big and down small structure, the large end of conical bore of next joint stretches in a pitch circle taper hole, two conical bore suit places are positioned at middle part, and both link into an integrated entity by low inside and high outside incline bench.
In said structure, cone angle alpha=30 in technique hole0~600. On technique hole, the large end radius of next pitch circle taper hole of small end radius ratio of a pitch circle taper hole is large, both semidiameter B=10mm~30mm, and the large end of next pitch circle taper hole stretches in a pitch circle taper hole small end, coincidence amount h=15mm~25mm.
The present invention compared with prior art, has following good effect:
1, technique hole is connected to form by the good luck axle of conical bore one of different size, and simple in structure, the demoulding is easy, does not increase difficulty of construction;
2, pea gravel concreten tamps between technique hole and pipeline, and the incline bench that solidifies rear formation plays and stops the radial and axial contraction of pea gravel concreten, significantly reduces the gap of flooring really, between pipeline and pea gravel concreten, is conducive to antiseep;
3, save up and down between the conical bore of fit and connect by incline bench, form labyrinth type water sealing structure after the pea gravel concreten tamping solidifies, antiseep is effective.
Brief description of the drawings
Fig. 1 is structural profile schematic diagram figure of the present invention, and this figure shows the embodiment that is made up of flooring waterproof construction upper and lower two pitch circle taper holes.
Fig. 2 is the generalized section of reserving technique hole in Fig. 1 on flooring.
Fig. 3 is incline bench structure enlarged diagram in Fig. 2.
Fig. 4 is structural profile schematic diagram of the present invention, and this figure shows the embodiment that is made up of flooring waterproof construction 4 joint phase fit conical bores.
Detailed description of the invention
Below with reference to the accompanying drawings and in conjunction with the embodiments, the invention will be further described.
Embodiment 1
Pipeline shown in Fig. 1 runs through mixed Tulou face waterproof construction, and it comprises technique hole 1.1 reserved on flooring 1, and the pea gravel concreten 2 tamping after mounting pipe 3 in technique hole 1.1. The present embodiment runs through the waterproof construction of concrete floor, supporting pipeline 3 external diameter 32mm for residence building water supply pipeline. In the time building flooring 1, by the hole of reserved technique shown in Fig. 2 1.1, because flooring 1 thickness is 120mm, belong to conventional thickness. These technique hole 1.1 use two joint sizes do not wait and coaxial conical bore part is socketed to form, and the perpendicular two pitch circle taper holes of putting are up big and down small structure. Be in the long 60mm of conical bore of next joint, coning angle 400, small end radius 25mm, holds greatly the about 46.8mm of radius. Be in the long 75mm of conical bore of a joint, coning angle 450, the large end radius of conical bore of next joint of small end radius ratio of going up as shown in Figure 3 a pitch circle taper hole is large, both semidiameter B=10mm. The large end of conical bore of next joint extend in a pitch circle taper hole, coincidence amount h=15mm, and two conical bore suit places are positioned at middle part, and both link into an integrated entity by low inside and high outside incline bench. Technique hole 1.1 in the present invention is basic components, and it is connected to form by the good luck axle of conical bore one of different size, and it is easy that flooring 1 is built the rear demoulding, do not increase difficulty of construction. After the pipeline 3 of installing in technique hole 1.1 is fixing, can between technique hole 1.1 and pipeline, tamp pea gravel concreten 2, pea gravel concreten 2 solidifies the built-in incline bench of rear formation, play and stop the 2 radial and axial contractions of the solidifying soil of microlith mud, significantly reduce the gap between flooring 1 and pea gravel concreten 2, be conducive to antiseep. Be to connect by incline bench between the conical bore of upper and lower fit on the other hand, after the pea gravel concreten tamping solidifies, form labyrinth type water sealing structure, guarantee non-leakage.
Embodiment 2
Fig. 4 is the embodiment of the present invention 2 structural representations, shows that fabrication hole 1.1 is not waited by 4 joint sizes and coaxial conical bore part is socketed to form in figure, and this embodiment is for the thicker occasion of flooring 1. The present embodiment, because junction between technique hole 1.1 and concrete is provided with 3 incline benches, that is to say and be provided with 3 road labyrinth type water sealing structures, and its water leakage performance is further strengthened. In addition other good effect is identical with embodiment 1.

Claims (3)

1. pipeline runs through a concrete floor waterproof construction, and it comprises the upper reserved technique hole (1.1) of flooring (1), and the pea gravel concreten (2) tamping after pipe laying (3) in technique hole (1.1); It is characterized in that: described technique hole (1.1) is not waited by least two joint sizes and coaxial conical bore part is socketed to form, the perpendicular conical bore of putting is up big and down small structure, the large end of conical bore of next joint stretches in a pitch circle taper hole, two conical bore suit places are positioned at middle part, and both link into an integrated entity by low inside and high outside incline bench.
2. pipeline according to claim 1 runs through concrete floor waterproof construction, it is characterized in that: cone angle alpha=30 in described technique hole (1.1)0~600
3. pipeline according to claim 1 runs through concrete floor waterproof construction, it is characterized in that: the large end radius of next pitch circle taper hole of small end radius ratio of the upper pitch circle taper hole in described technique hole (1.1) is large, both semidiameter B=10mm~30mm, the large end of next pitch circle taper hole stretches in a pitch circle taper hole small end, coincidence amount h=15mm~25mm.
CN201410390324.0A 2014-08-11 2014-08-11 Pipeline runs through concrete floor waterproof construction Active CN104180077B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410390324.0A CN104180077B (en) 2014-08-11 2014-08-11 Pipeline runs through concrete floor waterproof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410390324.0A CN104180077B (en) 2014-08-11 2014-08-11 Pipeline runs through concrete floor waterproof construction

Publications (2)

Publication Number Publication Date
CN104180077A CN104180077A (en) 2014-12-03
CN104180077B true CN104180077B (en) 2016-05-18

Family

ID=51961321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410390324.0A Active CN104180077B (en) 2014-08-11 2014-08-11 Pipeline runs through concrete floor waterproof construction

Country Status (1)

Country Link
CN (1) CN104180077B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464224A (en) * 2015-12-31 2016-04-06 四川航天建筑工程有限公司 Anti-seepage structure for reserved hole in kitchen and toilet and construction method
CN110387887A (en) * 2019-06-28 2019-10-29 同济大学建筑设计研究院(集团)有限公司 It is oriented to the construction method of partition wall and its construction method and foundation pit enclosure structure
CN111473165A (en) * 2020-05-18 2020-07-31 江苏筑森建筑设计有限公司 Waterproof structure of superimposed sheet and PVC water piping connection department
CN112283458B (en) * 2020-09-11 2022-02-15 潍坊市晨鸣新型防水材料有限公司 Leakage stoppage flexible waterproof piece capable of quickly stopping leakage

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2117589A1 (en) * 1994-08-29 1996-03-01 Michael Sakno Water imprevious intumescent firestop- ii
CN201547402U (en) * 2009-10-29 2010-08-11 河南省第二建筑工程有限责任公司 Bathroom tube-through-floor waterproof structure
CN202532026U (en) * 2012-04-22 2012-11-14 项谱成 Floor board pipeline waterproof structure
CN203258205U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Anti-leakage structure of floor-penetrating pipeline without sleeve
CN204083520U (en) * 2014-08-11 2015-01-07 锦宸集团有限公司 Pipeline runs through concrete floor waterproof construction

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3923745B2 (en) * 2001-03-16 2007-06-06 株式会社クボタ Silent drain pipe

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2117589A1 (en) * 1994-08-29 1996-03-01 Michael Sakno Water imprevious intumescent firestop- ii
CN201547402U (en) * 2009-10-29 2010-08-11 河南省第二建筑工程有限责任公司 Bathroom tube-through-floor waterproof structure
CN202532026U (en) * 2012-04-22 2012-11-14 项谱成 Floor board pipeline waterproof structure
CN203258205U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Anti-leakage structure of floor-penetrating pipeline without sleeve
CN204083520U (en) * 2014-08-11 2015-01-07 锦宸集团有限公司 Pipeline runs through concrete floor waterproof construction

Also Published As

Publication number Publication date
CN104180077A (en) 2014-12-03

Similar Documents

Publication Publication Date Title
CN104180077B (en) Pipeline runs through concrete floor waterproof construction
CN202023204U (en) Water stop device for opening of circular open caisson
WO2017071113A1 (en) Cement-soil mixing pile protected underground pipe gallery
CN202660067U (en) Waterproof sleeve preventing wall body leakage
CN103422868A (en) Structure and method for dissipating excess pore water pressure and reinforcing shield tunnel soil body
CN204083520U (en) Pipeline runs through concrete floor waterproof construction
CN201835370U (en) Pre-buried anti-leakage floor drain
CN104110265A (en) Thixotropic slurry grouting system for large-section rectangular pipe-jacking pipeline
CN101906810A (en) Pre-embedded type anti-seepage floor drain
CN201535392U (en) Top pipe slurry injection structure
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN203284803U (en) Combined type multifunctional comprehensive inspection well chamber
CN104373694A (en) Wall bushing
CN208136954U (en) Precast splice type Pipe rack
CN203757176U (en) Non-excavation-type pipeline replacement device
CN203475580U (en) Multi-functional combined rainwater plastic inspection well
CN203796281U (en) Grouting pipe structure embedded in composite pipe piece
CN205369917U (en) Bathroom antiseep built -in fitting
CN110195599B (en) Rigid anti-deflection rectangular jacking pipe connecting system and method thereof
CN203927102U (en) Polyester concrete Pressure pipe and assembly thereof
CN204175312U (en) The thixotropic slurry filling system of big cross section rectangular top pipe pipeline
CN202055256U (en) Concentrated water diversion and drainage device for large-area water seepage slope surface
CN206174970U (en) Cable tunnel push pipe tube coupling and waterproof connection structure of work well
CN204531409U (en) A kind of floor pre-buried type soil stack connector
CN209891335U (en) Novel floor downcomer embedded sleeve

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170515

Address after: 225500 No. 1118 Huaihai West Road, Jiangyan Economic Development Zone, Jiangyan District, Jiangsu, Taizhou

Patentee after: Jiangsu Yu Hui Housing Industry Co., Ltd.

Address before: 225500 No. 7 North Renmin Road, Jiangyan District, Jiangsu, Taizhou

Patentee before: Jinchen Group Co., Ltd.

TR01 Transfer of patent right