A kind of tup for hammer mill
Technical field
The present invention relates to tup technical field, be specifically related to a kind of tup for hammer mill.
Background technology
The main working parts of hammer mill is the rotor with hammer.Rotor is by main shaft, disk, bearing pin
Form with hammer.Motor rotor driven high speed rotating in crusher chamber.Tup is main vulnerable part,
The quality of tup directly affects the crushing efficiency of disintegrating machine.Tup during operation, in addition to being clashed into,
Also being impacted by material, be so repeatedly used for a long, the work surface of tup will be destroyed, and makes table
Face shape changes.The most domestic hammer head of hammer crusher major part is made by potassium steel.
Material feeds in machine from top material inlet, by high-speed motion the hitting of hammer, impact, shear, grind
Act on and pulverize.In rotor bottom, it is provided with in sieve plate, comminuting matter and passes through less than the grade of screen size
Sieve plate is discharged, and continues the strike by hammer and grinding more than the coarse fraction detention of screen size on sieve plate,
Outside finally by sieve plate discharge machine.
Hammer mill is the industrial department widely used production equipment such as building materials, metallurgy, chemical fertilizer, and tup
It it is the vulnerable part that consumption is the biggest.The working surface of tup contacts with material, produces heavily stressed abrasion.
Owing to the material that is broken is usually the hard objects such as rock, metallic ore, the abrasion of part is that ratio is more serious
's.By analyzing tup surface microscopic topographic, the wear process of tup belongs to deformation and erosive wear is combined
The result of cooperation.This is running up due to tup surface, and material is carried out by the motional inertia of tup
Hit and attrition crushing.During relative motion, these materials interact with piece surface, no
Simply slide, also impact, roll, the mode such as wash away.When abrasive hardness exceedes material hardness, abrasive material
Corner angle make material generation Plastic Flow be expressed to the surrounding of pit by thrusting material surface, material deform
To a certain extent, abrasive grain is crushed.Multiple granules contact with cheating material deformed around, are allowed to again become
, there is Plastic Flow in shape, work-hardening capacity increases further.When the strain fatigue limit exceeding material
Time formed grinding come off.
In Chinese Patent Application No.: disclose a kind of tup for hammer mill in 200910001666,
It is assembled with hammer handle by hammer body.Described hammer body is billiard table shape, and billiard table centrage is provided with round open-work,
Billiard table lower end circle open-work matches with hammer handle upper hollow shaft cylindrical, and straight pin is through hammer body circle open-work, with hollow
Bar endoporus matches, and is fixed by bolt, channel nut and split pin, forms assembled billiard table shape hammehead structure.
This technical scheme is in actually used engineering, and straight pin, bolt, split pin are highly prone to damage, this skill
Art scheme haves much room for improvement.
Summary of the invention
For the problems referred to above, the invention provides a kind of tup for hammer mill, have higher resistance to
Mill property, hardness, intensity.
In order to solve the problems referred to above, the technical scheme that the present invention provides is:
A kind of tup for hammer mill, each composition and percentage by weight thereof be: C:1.2 1.4%,
Si:0.6 0.8%, Mn:18 20%, Ni:0.04 0.06%, Mo:0.2 0.4%, Cr:
4 6%, Re:1.0 1.2%, V:1.2 1.4%, P :≤0.02%, S :≤0.02%;Remaining
Amount is Fe.
Preferably, each composition and percentage by weight thereof are: C:1.25 1.4%, Si:0.65 0.8%,
Mn:18.5 20%, Ni:0.045 0.06%, Mo:0.25 0.4%, Cr:4.5 6%,
Re:1.0 1.2%, V:1.2 1.4%, P :≤0.02%, S :≤0.02%;Surplus is Fe.
Preferably, each composition and percentage by weight thereof are: C:1.3%, Si:0.68%, Mn:19%,
Ni:0.05%, Mo:0.25%, Cr:5.5%, Re:1.05%, V:1.35%, P:0.02%,
S:0.01%;Surplus is Fe.
Preferably, each composition and percentage by weight thereof are: C:1.25%, Si:0.75%, Mn:18.5%,
Ni:0.045%, Mo:0.35%, Cr:4.5%, Re:1.15%, V:1.22%, P:0.01%,
S:0.02%;Surplus is Fe.
For the production method of the tup of hammer mill, comprise the following steps:
(1) melting;Add steel scrap, the pig iron carries out melting, and each composition after melting to meet the requirements, melting
Temperature is: 1,560 1580 DEG C;
(2) add Re and carry out Metamorphism treatment: carry out in three times, add the Re of total amount 12 14% for the first time,
Granularity 1.5 2.5mm;Second time adds total amount 22 25% when steel ladle poured into by the molten iron of 45 50%
Re, granularity 0.5 0.8mm;Third time adds when bull ladle is poured into a mould, granularity 1.5 2mm;
(3) cast: temperature is 1,460 1480 DEG C;
(4) 30 35 DEG C it are cooled to;
(5) Quenching Treatment: when temperature is 300 320 DEG C, is incubated 1.8 2 hours;It is 540 in temperature
When 560 DEG C, being incubated 1.8 2 hours, when temperature is 940 960 DEG C, insulation 1.4 1.6 is little
Time, it is cooled to room temperature with the speed of 20 DEG C/h the most again;
(6) temper: when temperature is 200 220 DEG C, is incubated 1.4 1.6 hours, in temperature is
When 380 400 DEG C, it is incubated 2.0 2.2 hours, is cooled to room temperature with the speed of 15 DEG C/h the most again.
Compared with prior art, the invention have the benefit that
The tup of the present invention, by improving formula, rational Technology for Heating Processing, the intensity of the tup of raising,
Hardness, compares potassium steel tup more of the prior art, and intensity improves 20 30%, and service life carries
High 1.6 1.8 times, decrease cost, decrease waste, also reduce the number of times changing tup, alleviate
The labor intensity of workman.
Detailed description of the invention
The present invention will be further described below:
Embodiment 1:
A kind of tup for hammer mill, each composition and percentage by weight thereof be: C:1.3%, Si:
0.68%, Mn:19%, Ni:0.05%, Mo:0.25%, Cr:5.5%, Re:1.05%, V:
1.35%, P:0.02%, S:0.01%;Surplus is Fe.
For the production method of the tup of hammer mill, comprise the following steps:
(1) melting;Add steel scrap, the pig iron carries out melting, and each composition after melting to meet the requirements, melting
Temperature is: 1570 DEG C;
(2) add Re and carry out Metamorphism treatment: carry out in three times, add the Re of total amount 13%, granularity for the first time
1.8mm;Second time adds the Re of total amount 24%, granularity 0.6mm when steel ladle poured into by the molten iron of 46%;
Third time adds when bull ladle is poured into a mould, granularity 1.8mm;
(3) cast: temperature is 1475 DEG C;
(4) 32 DEG C it are cooled to;
(5) Quenching Treatment: when temperature is 310 DEG C, is incubated 1.9 hours;When temperature is 545 DEG C, protect
Temperature 1.85 hours, when temperature is 955 DEG C, is incubated 1.4 hours, the most again with the speed of 20 DEG C/h
It is cooled to room temperature;
(6) temper: when temperature is 205 DEG C, is incubated 1.55 hours, when temperature is 385 DEG C,
It is incubated 2.2 hours, is cooled to room temperature with the speed of 15 DEG C/h the most again.
Embodiment 2:
A kind of tup for hammer mill, each composition and percentage by weight thereof be: C:1.25%, Si:
0.75%, Mn:18.5%, Ni:0.045%, Mo:0.35%, Cr:4.5%, Re:1.15%,
V:1.22%, P:0.01%, S:0.02%;Surplus is Fe.
For the production method of the tup of hammer mill, comprise the following steps:
(1) melting;Add steel scrap, the pig iron carries out melting, and each composition after melting to meet the requirements, melting
Temperature is: 1565 DEG C;
(2) add Re and carry out Metamorphism treatment: carry out in three times, add the Re of total amount 12.5%, grain for the first time
Degree 2.2mm;Second time adds the Re of total amount 23%, granularity 0.7mm when steel ladle poured into by the molten iron of 48%;
Third time adds when bull ladle is poured into a mould, granularity 1.6mm;
(3) cast: temperature is 1478 DEG C;
(4) 31 DEG C it are cooled to;
(5) Quenching Treatment: when temperature is 315 DEG C, is incubated 1.9 hours;When temperature is 555 DEG C, protect
Temperature 1.85 hours, when temperature is 955 DEG C, is incubated 1.55 hours, the most again with the speed of 20 DEG C/h
It is cooled to room temperature;
(6) temper: when temperature is 200 DEG C, is incubated .6 hour, when temperature is 380 DEG C, protects
Temperature 2.2 hours, is cooled to room temperature with the speed of 15 DEG C/h the most again.
Embodiment 3:
A kind of tup for hammer mill, each composition and percentage by weight thereof be: C:1.2%, Si:
0.8%, Mn:18%, Ni:0.06%, Mo:0.2%, Cr:6%, Re:1.0%, V:1.4%,
P:0.02%, S:0.01%;Surplus is Fe.
For the production method of the tup of hammer mill, comprise the following steps:
(1) melting;Add steel scrap, the pig iron carries out melting, and each composition after melting to meet the requirements, melting
Temperature is: 1580 DEG C;
(2) add Re and carry out Metamorphism treatment: carry out in three times, add the Re of total amount 12%, granularity for the first time
2.5mm;Second time adds the Re of total amount 25%, granularity 0.5mm when steel ladle poured into by the molten iron of 45%;
Third time adds when bull ladle is poured into a mould, granularity 2mm;
(3) cast: temperature is 1460 DEG C;
(4) 35 DEG C it are cooled to;
(5) Quenching Treatment: when temperature is 300 DEG C, is incubated 2 hours;When temperature is 540 DEG C, insulation
2 hours, when temperature is 940 DEG C, it is incubated 1.6 hours, is cooled to the speed of 20 DEG C/h the most again
Room temperature;
(6) temper: when temperature is 200 DEG C, is incubated 1.6 hours, when temperature is 380 DEG C, protects
Temperature 2.2 hours, is cooled to room temperature with the speed of 15 DEG C/h the most again.
Embodiment 4:
A kind of tup for hammer mill, each composition and percentage by weight thereof be: C:1.4%, Si:
0.6%, Mn:20%, Ni:0.04%, Mo:0.4%, Cr:4%, Re:1.2%, V:1.2%,
P:0.01%, S:0.02%;Surplus is Fe.
For the production method of the tup of hammer mill, comprise the following steps:
(1) melting;Add steel scrap, the pig iron carries out melting, and each composition after melting to meet the requirements, melting
Temperature is: 1580 DEG C;
(2) add Re and carry out Metamorphism treatment: carry out in three times, add the Re of total amount 12%, granularity for the first time
2.5mm;Second time adds the Re of total amount 25%, granularity 0.5mm when steel ladle poured into by the molten iron of 45%;
Third time adds when bull ladle is poured into a mould, granularity 1.5mm;
(3) cast: temperature is 1480 DEG C;
(4) 30 DEG C it are cooled to;
(5) Quenching Treatment: when temperature is 320 DEG C, is incubated 1.8 hours;When temperature is 560 DEG C, protect
Temperature 1.8 hours, when temperature is 960 DEG C, is incubated 1.4 hours, and the speed with 20 DEG C/h is cold the most again
But to room temperature;
(6) temper: when temperature is 210 DEG C, is incubated 1.5 hours, when temperature is 385 DEG C, protects
Temperature 2.2 hours, is cooled to room temperature with the speed of 15 DEG C/h the most again.
Embodiment 5:
A kind of tup for hammer mill, each composition and percentage by weight thereof be: C:1.2%, Si:
0.6%, Mn:19%, Ni:0.06%, Mo:0.2%, Cr:4%, Re:1.2%, V:1.4%,
P:0.02%, S:0.01%;Surplus is Fe.
For the production method of the tup of hammer mill, comprise the following steps:
(1) melting;Add steel scrap, the pig iron carries out melting, and each composition after melting to meet the requirements, melting
Temperature is: 1560 DEG C;
(2) add Re and carry out Metamorphism treatment: carry out in three times, add the Re of total amount 14%, granularity for the first time
2.5mm;Second time adds the Re of total amount 22%, granularity 0.8mm when steel ladle poured into by the molten iron of 45%;
Third time adds when bull ladle is poured into a mould, granularity 1.5mm;
(3) cast: temperature is 1460 DEG C;
(4) 30 DEG C it are cooled to;
(5) Quenching Treatment: when temperature is 300 DEG C, is incubated 1.8 hours;When temperature is 560 DEG C, protect
Temperature 2 hours, when temperature is 940 DEG C, is incubated 1.4 hours, cools down with the speed of 20 DEG C/h the most again
To room temperature;
(6) temper: when temperature is 220 DEG C, is incubated 1.6 hours, when temperature is 380 DEG C, protects
Temperature 2.0 hours, is cooled to room temperature with the speed of 15 DEG C/h the most again.
The ultimate principle of the present invention, principal character and advantages of the present invention have more than been shown and described.The industry
Skilled person will appreciate that, the present invention is not restricted to the described embodiments, above-described embodiment and description
Described in the principle that the present invention is simply described, without departing from the spirit and scope of the present invention, this
Invention also has various changes and modifications, and these changes and improvements both fall within scope of the claimed invention
In.Claimed scope is defined by appending claims and equivalent thereof.