CN104110033B - Cavity long spire thin wall filling pile pipe casing - Google Patents
Cavity long spire thin wall filling pile pipe casing Download PDFInfo
- Publication number
- CN104110033B CN104110033B CN201410365214.9A CN201410365214A CN104110033B CN 104110033 B CN104110033 B CN 104110033B CN 201410365214 A CN201410365214 A CN 201410365214A CN 104110033 B CN104110033 B CN 104110033B
- Authority
- CN
- China
- Prior art keywords
- wall
- card article
- tube wall
- outer tube
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The invention discloses a kind of cavity long spire thin wall filling pile pipe casing, the first body comprising both ends open and the second body be socketed in it; First body comprises inner and outer tubes, outer tube outer wall establishes spiral fan, outer tube wall and outer wall of inner tube are equipped with groove, evenly arrange on opposite along outer tube and interior pipe circumference respectively, ball is placed between two grooves, inner tube wall is elongated along its length arranges many card articles, and every root card article front is evenly provided with guide wheel, and outer tube and interior ligament bottom are closed by fixing sheet rubber on inner pipe; The described second tube wall draw-in groove that elongated setting is identical with card article radical along its length, inner tube wall card article inserts this pocket matches.This structural cavities long spire thin wall filling pile pipe casing has feature lower than existing long-spiral drilling machine power demand, can significantly improve bearing capacity under identical concrete amount, is suitable for formation volumes wide, fetches earth simple efficient, construction safety.
Description
Technical field
The present invention relates to grout pile sleeve pipe, be specifically related to cavity long spire thin wall filling pile pipe casing.
Background technology
In pile foundation engineering, long auger guncreting pile machine is the stake machine being widely used in building site construction usage, the long spire flabellum that drill bit under power orders about effect under main drilling rod and main drilling rod are arranged disposablely can get out stake holes, again by hollow main drilling rod to concrete perfusion in stake holes pile, it is high that long screw auger drilling deposited pile has bearing capacity, be suitable for the long advantage such as can freely to change of the wide and stake of formation volumes, be widely used, but the application of long-spiral drilling machine in large-section in-situ concrete pile is but restricted, generally can only be used for the situation that castinplace pile diameter is less than 800mm, reason is that large-section in-situ concrete pile will overcome very large soil compaction and shear soil resistance when drilling construction, long-spiral drilling machine cannot meet the demands on power.
In basic pile foundation engineering construction, the construction of super large, the stake of ultra-deep pile foundation engineering is comparatively general, for large-section in-situ concrete pile type, at present, more advanced technique adopts large diameter thin wall bored concrete pile technology, this is a kind of employing immersed tube, fetch earth, die-filling, clear hole, lay reinforcing cage, concrete perfusion, tube drawing, form removal, backfill, the construction technology of pile, this construction technology has under equal requirement for bearing capacity, can reduce concrete amount, reduce costs or under equal concrete amount, significantly can improve the advantage of pile body flexural strength; Exist defect be: generally adopt tunneling boring manually to cut the earth for large diameter thin wall pouring pile hole or machinery cut the earth mode fetch earth, this construction method is taked not only to lavish labor on, and constructor needs to arrive bottom stake holes when installation form, work progress has certain danger.
Summary of the invention
The object of this invention is to provide a kind of lower to long-spiral drilling machine power demand, bearing capacity can be significantly improved under identical concrete amount, be suitable for that formation volumes is wide, the cavity llong helix bored piles pipe casing of simple efficient, the construction safety that fetches earth.
For realizing above object, the first body that cavity long spire thin wall filling pile pipe casing of the present invention comprises inner hollow both ends open and the second body be socketed in the first body; First body is made up of inner and outer tubes again, outer tube outer wall is provided with spiral fan, this spiral fan lower end exceeds outer tube bottom, outer tube wall and outer wall of inner tube are equipped with groove, arrange respectively, place ball between two grooves along outer tube and the even opposite of interior pipe circumferencial direction, inner tube wall along the circumferential direction arranges many card articles, described card article is elongated, and every root card article front is evenly provided with guide wheel, and outer tube and interior ligament bottom are closed by fixing sheet rubber on inner pipe; The draw-in groove that the along the circumferential direction elongated setting of described second tube wall is identical with described card article radical quantity, the inner tube wall card article of band guide wheel inserts this pocket matches.
The bottom end face of described every root card article is provided with downward-sloping clear native sheet, leaves gap between clear native sheet base and the second body.
The inner tube wall card article radical of described second tube wall draw-in groove and band guide wheel is three and is evenly arranged in 120 °.
The groove of outer tube and interior pipe described in said structure cavity long spire thin wall filling pile pipe casing is arranged along outer tube and the even opposite of interior pipe circumferencial direction respectively, and its beneficial effect is for ball provides rotation space; The beneficial effect of described card article is the draw-in groove of insertion second body thus realizes the connection with pipe in the first body; Described clear its beneficial effect of native sheet is the soil body in cleaning second body draw-in groove; The described ball be arranged between inner and outer pipes two groove is solid sphere, and its beneficial effect rotates mutually for ease of the first body inner and outer pipes; Described its beneficial effect of guide wheel evenly arranged along card article facade length direction is reduce the friction between card article and draw-in groove; Described sheet rubber one end is fixedly connected on interior pipe bottom along interior pipe circumferencial direction, and the other end is close to outer tube bottom, but does not hinder outer tube to rotate, and its beneficial effect enters between inner and outer pipes for preventing the soil body; Described second tube length direction is elongated arranges draw-in groove, and its beneficial effect inserts for ease of pipe clamp bar in the first body, and the first body and the second body are combined, and prevents from occurring between pipe and the second body in the first body mutually to rotate.
Cavity long spire thin wall filling pile pipe casing of the present invention main operational steps when constructing is as follows: 1. place cleaning; 2. vibration sinks to above-mentioned second body to design elevation, and reserved certain length body, outside the soil body, facilitates the first body to insert; 3. after in the first body, pipe clamp bar inserts the reserved length section of the second body along the second body draw-in groove, first body outer tube is rotated along interior pipe by roller under dynamic action, the soil body constantly takes out by the spiral fan being welded on outer tube outer wall, the clear native sheet being contained in pipe clamp bar bottom in the first body clears up the soil body in the second body draw-in groove, makes the first body constantly decline until arrive design elevation along the second body draw-in groove smoothly; 4. extract the first body along the second body draw-in groove, form annular stake holes; 5. sediment at the bottom of cleaning eye; 6. reinforcing cage is placed, concreting; 7. the second body is extracted on concreting limit in limit, and utilizes the second body tamped concrete; 8. pile.
Cavity long spire thin wall filling pile pipe casing of the present invention, combine the advantage of large diameter thin wall bored concrete pile technology and long screw auger drilling deposited pile, power demand can be reduced and can form annular thin wall castinplace pile again, can construct in soft, hardpan, be suitable for formation volumes wide, there is following beneficial effect:
Compared with existing long screw auger drilling deposited pile, on the one hand under equal requirement for bearing capacity, can concrete amount be reduced, reduce costs, or under equal concrete amount, can significantly improve pile body flexural strength; On the other hand, can not also the inner soil body of disturbance, can not only power demand be reduced, solve prior art because of the problem making diameter be restricted more than the application in the large-section in-situ concrete pile of 800mm that long screw auger mechanomotive force cannot meet the demands; And solve the annular difficult problem fetched earth of castinplace pile, also avoid employing manually die-filling, constructor is protected safely.
Accompanying drawing explanation
Fig. 1 is first, second body vertical section schematic diagram of cavity long spire thin wall filling pile pipe casing of the present invention;
Fig. 2 is A-A generalized section in Fig. 1;
Fig. 3 is the positive elevational schematic view of draw-in groove of cavity long spire thin wall filling pile pipe casing second body of the present invention;
Fig. 4 is the draw-in groove side elevation schematic diagram of cavity long spire thin wall filling pile pipe casing second body of the present invention;
Fig. 5 is cavity long spire thin wall filling pile pipe casing inner tube wall card article of the present invention and the positive elevational schematic view of guide wheel;
Fig. 6 is cavity long spire thin wall filling pile pipe casing inner tube wall card article of the present invention and guide wheel side elevation schematic diagram;
Fig. 7 is the sheet rubber scheme of installation of cavity long spire thin wall filling pile pipe casing of the present invention;
Fig. 8 is detail drawing 1 groove and ball assembly structure schematic diagram in Fig. 1;
Fig. 9 is detail drawing 2 card article and draw-in groove assembly structure schematic diagram in Fig. 2;
Figure 10 is the clear native sheet scheme of installation of detail drawing 3 in Fig. 1.
Reference numeral: the groove 6 of the first body 1, second body 2, interior pipe 3, outer tube 4, spiral fan 5, outer tube wall, the groove 7 of outer wall of inner tube, the card article 8 of inner tube wall, clear native sheet 9, ball 10, guide wheel 11, draw-in groove 12, weld seam 13, bolt 14 and sheet rubber 15.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, cavity long spire thin wall filling pile pipe casing of the present invention is described in further detail.
As shown in Fig. 1 ~ Figure 10, the first body 1 that cavity long spire thin wall filling pile pipe casing of the present invention comprises inner hollow both ends open and the second body 2 be socketed in the first body; First body 1 is made up of interior pipe 3 and outer tube 4 again, outer tube outer wall is provided with spiral fan 5, this spiral fan lower end exceeds outer tube bottom, outer tube wall and outer wall of inner tube are equipped with groove 6,7, arrange along outer tube 4 and the even opposite of interior pipe 3 circumferencial direction respectively, ball 10 is placed between two grooves, inner tube wall along the circumferential direction arranges three card articles 8 and is evenly arranged in 120 °, described card article is elongated, every root card article front is evenly provided with guide wheel 11, and outer tube 4 and bottom, interior pipe 3 gap are by closing with the fixing sheet rubber 15 on inner pipe of bolt 14; The draw-in groove 12 that the along the circumferential direction elongated setting of described second tube wall is identical with described card article radical quantity, the inner tube wall card article 8 of band guide wheel 11 inserts this pocket matches; The bottom end face of every root card article 8 is provided with downward-sloping clear native sheet 9, leaves gap between clear native sheet base and the second body 2.
During construction, first by high-frequency vibratory hammer, the second body 2 is vibrated the insertion soil body, and reserved certain length body is outside the soil body, after pipe clamp bar 8 in the first body inserts the reserved length section of the second body along draw-in groove 12, first body outer tube 4 is rotated along interior pipe 3 by roller 10 under dynamic action, and the soil body takes out by the spiral fan 5 of outer tube outer wall welding; Due to Action of Gravity Field, along with the continuous taking-up of the soil body, the clear native sheet 9 of the first its bottom can clear up the soil body of in draw-in groove 12, and the first body constantly declines until the stake holes soil body all takes out along the second body draw-in groove.Arrive after design elevation until the first body, first body is extracted along draw-in groove 12, just an annular stake holes is defined thus, utilize clear hole device to be cleaned out by sediment at the bottom of hole, then, transfer reinforcing cage, concreting, treat that certain height is arrived in concreting, while extract interior tube edge to return slotting tamped concrete, just define required thin wall filling pile.
Claims (3)
1. a cavity long spire thin wall filling pile pipe casing, the first body comprising inner hollow both ends open and the second body be socketed in the first body, the first tube wall is provided with spiral fan, and this spiral fan lower end exceeds outer tube bottom; It is characterized in that: described first body is made up of inner and outer tubes again, outer tube wall and outer wall of inner tube are equipped with groove, arrange along outer tube and the even opposite of interior pipe circumferencial direction respectively, ball is placed between two grooves, inner tube wall along the circumferential direction arranges many card articles, described card article is elongated, and every root card article front is evenly provided with guide wheel, and outer tube and interior ligament bottom are closed by fixing sheet rubber on inner pipe; The draw-in groove that the along the circumferential direction elongated setting of described second tube wall is identical with described card article radical quantity, the inner tube wall card article of band guide wheel inserts this pocket matches.
2. cavity long spire thin wall filling pile pipe casing according to claim 1, is characterized in that: the bottom end face of described every root card article is provided with downward-sloping clear native sheet, leaves gap between clear native sheet base and the second body.
3. cavity long spire thin wall filling pile pipe casing according to claim 1, is characterized in that: the inner tube wall card article radical of described second tube wall draw-in groove and band guide wheel is three and is evenly arranged in 120 °.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410365214.9A CN104110033B (en) | 2014-07-29 | 2014-07-29 | Cavity long spire thin wall filling pile pipe casing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410365214.9A CN104110033B (en) | 2014-07-29 | 2014-07-29 | Cavity long spire thin wall filling pile pipe casing |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104110033A CN104110033A (en) | 2014-10-22 |
CN104110033B true CN104110033B (en) | 2016-04-20 |
Family
ID=51707011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410365214.9A Active CN104110033B (en) | 2014-07-29 | 2014-07-29 | Cavity long spire thin wall filling pile pipe casing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104110033B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112695757B (en) * | 2020-12-21 | 2022-05-10 | 建始县节龙工贸有限责任公司 | Super slow setting concrete secant pile casing drill sleeve |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2108166U (en) * | 1991-07-27 | 1992-06-24 | 广东省鹤山县建筑设计院 | Dual pipe drilling tools with single acting local reverse recycle |
CN102182404A (en) * | 2011-03-10 | 2011-09-14 | 李征 | Cast-in-situ tubular pile rotary drilling rig capable of forming annular hole and piling method |
CN202265822U (en) * | 2011-10-17 | 2012-06-06 | 福建工程学院 | Pile forming device for cast-in-situ concrete thin-wall piles |
CN204023565U (en) * | 2014-07-29 | 2014-12-17 | 福建永强岩土股份有限公司 | The long spiral thin wall filling pile of cavity pipe casing |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62296009A (en) * | 1986-06-12 | 1987-12-23 | Seiji Tsuji | Piling work |
-
2014
- 2014-07-29 CN CN201410365214.9A patent/CN104110033B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2108166U (en) * | 1991-07-27 | 1992-06-24 | 广东省鹤山县建筑设计院 | Dual pipe drilling tools with single acting local reverse recycle |
CN102182404A (en) * | 2011-03-10 | 2011-09-14 | 李征 | Cast-in-situ tubular pile rotary drilling rig capable of forming annular hole and piling method |
CN202265822U (en) * | 2011-10-17 | 2012-06-06 | 福建工程学院 | Pile forming device for cast-in-situ concrete thin-wall piles |
CN204023565U (en) * | 2014-07-29 | 2014-12-17 | 福建永强岩土股份有限公司 | The long spiral thin wall filling pile of cavity pipe casing |
Also Published As
Publication number | Publication date |
---|---|
CN104110033A (en) | 2014-10-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104018792B (en) | Reducing screw displacement pile drilling tool and construction method thereof | |
CN105780763B (en) | Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile | |
CN104452749B (en) | The constructional method of a kind of reinforced concrete cast-in-situ pile tube | |
CN103122632A (en) | Construction method for drilling hole and casting pile in plastic flow stratum or karst cave stratum | |
CN202509533U (en) | Single reinforcement pulling force type anti-floating anchor rod | |
CN203569561U (en) | Novel pile forming device of steel pipe protection wall cast-in-place piles following up drill | |
CN104110032B (en) | Major diameter cavity long spire thin wall filling pile pipe casing | |
CN104110033B (en) | Cavity long spire thin wall filling pile pipe casing | |
CN207260151U (en) | Drill bit is pulled out in a kind of rotation of the long casing of rotary drilling rig pulling bored concrete pile | |
CN206752454U (en) | One kind perfusion embedded pile | |
CN204023565U (en) | The long spiral thin wall filling pile of cavity pipe casing | |
CN101858196A (en) | Low gravity center three-axle spiral drilling machine and drilling method thereof | |
CN104846820B (en) | Hold type screw-type Squeezing Soil Pile pile-forming equipment and bore forming method in a kind of end | |
CN203904990U (en) | Long spiral thin-walled grouting pile pipe casing with large-diameter cavity | |
CN204023564U (en) | The long spiral thin wall filling pile of major diameter cavity pipe casing | |
CN103572756B (en) | Cast-in-place pile sleeve and construction method thereof | |
CN206768796U (en) | A kind of concrete-pile external spiral combines hole-forming device with inside spin | |
CN104005409B (en) | Major diameter cavity long spiral thin wall filling pile pipe casing and bore forming method | |
CN209324259U (en) | A kind of drilling tool for the compacted pore-creating filling pile of long spire | |
CN201148615Y (en) | Steel tube pile foundation built by inseminate steel bar | |
CN204282348U (en) | A kind of reinforced concrete cast-in-situ pile tube | |
CN210598826U (en) | Mechanical pile forming device for bottom-expanding cast-in-place foundation pile | |
CN206418494U (en) | Steel reinforcement cage plants pile foundation structure | |
CN103882859B (en) | A kind of original state of Shi Hanzhang fetches earth cast-with-pressure concrete pile and construction method thereof | |
CN106836228A (en) | Filling type stake hollow drill |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |