Summary of the invention
In view of the above, the present invention is necessary to provide a kind of desalted water production system, can be by control automatically
Process units processed, it is achieved unmanned, producing water ratio is high.
The present invention provides a kind of desalted water production system, and desalted water production system, including raw water box, middle water
Case, reuse water tank, raw water pump, filter, middle water pump, counter-infiltration system, reuse water pump, flocculant
Case, flocculant filter pump and control centre, raw water box is provided with water intaking valve and the first liquidometer, Yuan Shui
The outlet of case is connected to raw water pump, and raw water pump connects filter, and flocculant case is by flocculant filter pump even
Being connected to filter, filter is connected to the water inlet of intermediate water tank, and intermediate water tank is provided with the second liquidometer,
The outlet of intermediate water tank connects middle water pump, and middle water pump is connected to counter-infiltration system, and counter-infiltration system is even
Being connected to the water inlet of reuse water tank, reuse water tank is provided with the 3rd liquidometer, the outlet of reuse water tank is even
It is connected to liquidometer and each water pump that reuse water pump, control centre connect on each water tank respectively, controls each water pump
Being turned on and off, described desalted water production system also includes that a purging system, described purging system include punching
The section of washing, brushing stage, hydro-peening section, cyclic water tank, the first circulating pump, the second circulating pump and effluent outfall,
Purge zone, brushing stage, hydro-peening section sequentially set gradually, and purge zone is provided with flusher and squeeze roll, brush
The section of washing is provided with scrubs unit and squeeze roll, and hydro-peening section is provided with hydro-peening unit and squeeze roll, in cyclic water tank
Being provided with filter screen separator, the hydro-peening unit of hydro-peening section connects described reuse water pump, so that hydro-peening unit is supplied water,
Second circulating pump connects hydro-peening section and hydro-peening unit, to carry out repeats itself spray, hydro-peening Duan Lian in hydro-peening section
Connect cyclic water tank to follow with the water to cyclic water tank supply hydro-peening unit hydro-peening backflow, some first circulating pumps connections
Ring water tank scrubs unit to flusher, brushing stage respectively, to be supplied respectively by the water after cyclic water tank inner filtration
Scrub unit, brushing stage and hydro-peening section be respectively connecting to cyclic water tank to flusher, brushing stage, with
For scrubbing or water after hydro-peening flows into cyclic water tank to filter, purge zone and cyclic water tank are respectively connecting to dirt
Water discharge spout, is expelled to effluent outfall with the water of overfill in the water after rinsing or cyclic water tank.
Further, described filter includes medium filter, active carbon filter, demineralizer, security personnel
Filter.
Further, described purging system also includes squeezing acid section, squeezes acid section and is arranged on a upper station of purge zone,
First passing through for steel band and enter to purge zone after squeezing acid section, squeezing acid section has acid squeezing roller.
Further, two filter screen separator are set in described cyclic water tank, be correspondingly formed the first filter box,
Second filter box and the third filter box, the first filter box appearance connects brushing stage and the water of hydro-peening section backflow, the third filter box
Supply water respectively to purge zone, brushing stage.
It addition, the present invention is necessary to provide the control method of a kind of desalted water production system.
A kind of control method of described desalted water production system, its control method is as follows:
The water level of each water tank is set, water level 2m is high water level, water level is middle between 0.5 to 2m
Water level, < 0.5m is low water level to water level;
The water level of the first liquidometer detection raw water box, the water level of the second liquidometer detection intermediate water tank, the 3rd liquid
The water level of position meter detection reuse water tank;Control centre exports control signal control accordingly according to the signal of detection
Water intaking valve, raw water pump, middle water pump and the opening and closing of reuse water pump, specifically,
The action executing of water intaking valve judges:
When the liquid level of raw water box is in low water level and middle water level, and water intaking valve opens moisturizing, when the liquid level of raw water box
Being in high water level, water intaking valve is closed and is stopped moisturizing;
The action executing of raw water pump judges:
Being in high water level when the liquid level of raw water box is in the liquid level of low water level or intermediate water tank, raw water pump stops
Draw water;It is in middle low water level when the liquid level of raw water box is in the liquid level of middle water level and high water level and intermediate water tank,
Raw water pump is opened and is drawn water;And when raw water pump is opened when, control centre controls flocculant filter pump simultaneously
To pipeline for flocculant, raw water pump pumps water to filter, and filter delivers to intermediate water tank after having filtered,
It is in middle high water level, former water when the liquid level of intermediate water tank is in the liquid level of low water level and middle water level and raw water box
Moisturizing opened by pump, is in low water level when the liquid level of intermediate water tank is in the liquid level of high water level or raw water box, former
Water pump cuts out and stops moisturizing;
The action executing of middle water pump judges:
It is in high water level, middle water pump when the liquid level of intermediate water tank is in the liquid level of low water level or reuse water tank
Stop pumping;Low water in the liquid level of intermediate water tank is in middle water level and high water level and reuse high water tank is in
Position, middle water pump is opened and is drawn water;
The action executing of reuse water pump judges:
When the liquid level of reuse water tank is in middle high water level, production line is supplied water by reuse water pump;When reuse water tank
Liquid level when being in low, reuse water pump stops supplying water.
Compared to prior art, the desalted water production system that the present invention is automatically controlled by design, it is achieved automatically
Producing water, unmanned, production efficiency is high, reduces hand labor intensity.By using at the after-stage scrubbed
Desalted water cleans, and both having ensured finally to clean is to use desalted water to clean, it is ensured that steel band quality, saves again
Desalted water cost and consumption.The residual chemicals of steel strip surface can thoroughly be removed by purging system, it is ensured that
The cleaning quality of steel band, and by the clean water of back segment is recycled to the scrubbing unit of leading portion, thus
Save water resource, especially save desalted water cost and consumption.
The preferred embodiments of the invention and beneficial effect thereof, will in conjunction with detailed description of the invention the most specifically
Bright.
Detailed description of the invention
Below in conjunction with accompanying drawing, the detailed description of the invention of the present invention is described in detail.It should be appreciated that this
Detailed description of the invention described by place is merely to illustrate and explains the present invention, is not limited to the present invention.
Refer to Fig. 1, the desalted water production system shown in the present invention, including raw water box 1, intermediate water tank 2, return
With water tank 3, raw water pump 11, filter 12, middle water pump 21, counter-infiltration system 22, reuse water pump 31, wadding
Solidifying agent case 4, flocculant filter pump 41 and control centre's (not shown).
It is provided with water intaking valve 13 on raw water box 1 and the first liquidometer 14, the outlet of raw water box 1 are connected to former water
Pump 11, raw water pump 11 connects filter 12.Flocculant case 4 is connected to filter 12 by flocculant filter pump 41,
Filter 12 is connected to the water inlet of intermediate water tank 2, and intermediate water tank 2 is provided with the second liquidometer 23, middle
The outlet of water tank 2 connects middle water pump 21, and middle water pump 21 is connected to counter-infiltration system 22, counter-infiltration system
22 water inlets being connected to reuse water tank 3, reuse water tank 3 is provided with the 3rd liquidometer 32, reuse water tank 31
Outlet be connected to liquidometer that reuse water pump 31, control centre connect on each water tank respectively and each water pump,
Control being turned on and off of each water pump.In the present embodiment, control centre uses PLC.
Water intaking valve 13 controls the water inlet of raw water box 1, and water intaking valve 13 can use Pneumatic butterfly valve or electromagnetic valve control
System, controls the unlatching of water intaking valve 13 by PLC output control signal.First liquidometer 14, the second liquidometer 23
And the 3rd liquidometer 32 be attached separately to raw water box 1, intermediate water tank 2, the top of reuse water tank 3.Liquidometer (14,
23,32) use ultrasonic level gage, the height of water level in water tank can be detected, output analogue signal to PLC,
PLC combines Liquid level water intaking valve 13 and the opening and closing of each water pump (11,21,31,41).Raw water pump
The water of raw water box 1 is pumped to intermediate water tank 2 by 11 through filter 12.Filter 12 includes medium filter,
Active carbon filter, demineralizer, cartridge filter etc., it is used for filtering the impurity in former water.Flocculant filters
The pipeline being connected to raw water pump 11 pumped with filter 12 by flocculant in flocculant case 4 by pump 41, and flocculant is assisted
Filter 12 is helped to filter more thorough, totally.The water of intermediate water tank 2 is pumped to reverse osmosis system by middle water pump 21
System 22 delivers to reuse water tank 3 after carrying out depth-type filtration.The water of reuse water tank 3 can be delivered to raw by reuse water pump 31
Product line uses.
When controlling desalted water production system, control method is as follows:
Control water intaking valve 13 by PLC output control signal to open, to raw water box 1 moisturizing, the first liquidometer 14
The water level of detection raw water box 1.PLC is according to the startup of the water lev el control raw water pump 11 of raw water box 1 and intermediate water tank 2
With stopping.Water level is set, works as water level 2m is high water level, water level is middle water between 0.5 to 2m
Position, < 0.5m is low water level to water level.When the liquid level of raw water box 1 is in low water level and middle water level (water level < 2m),
Water intaking valve 13 opens moisturizing, and when the liquid level of raw water box 1 is in high water level (water level > 2m), water intaking valve 13 is closed and stopped
Only moisturizing;When the liquid level of raw water box 1 is in low water level (water level < 0.5m) or the liquid level of intermediate water tank 2 is in
High water level (water level > 2m), raw water pump 11 stops pumping;When the liquid level of raw water box 1 is in middle water level and high water level
The liquid level of (water level>0.5m) and intermediate water tank 2 is in middle low water level (water level<2m), and raw water pump 11 is opened and taken out
Water.When raw water pump 11 is opened when, PLC controls flocculant filter pump 41 to pipeline for flocculant simultaneously.Former
Water pump 11 pumps former water to filter 12, and intermediate water tank 2 delivered to by filter 12 after having filtered.
When the liquid level of intermediate water tank 2 is at low water level and middle water level (water level < 2m) and the liquid level of raw water box 1
In middle high water level (water level > 0.5m), supplying water condition opened by raw water pump 11, when the liquid level of intermediate water tank 2 is in height
The liquid level of water level (water level>2m) or raw water box 1 is in low water level (water level<0.5m), and raw water pump 11 cuts out
Stop moisturizing;When the liquid level of intermediate water tank 2 is in low water level (water level < 0.5m) or the liquid level of reuse water tank 3
Being in high water level (water level > 2m), middle water pump 21 stops pumping;When the liquid level of intermediate water tank 2 is in middle water level
It is in middle low water level (water level<2m), middle water pump with high water level (water level>0.5m) and reuse water tank 3 liquid level
21 unlatchings are drawn water.
When the liquid level of reuse water tank 3 is in middle high water level (water level > 0.3m), production line is supplied by reuse water pump 31
Water;When the liquid level of reuse water tank 3 is in low (water level < 0.3m), reuse water pump 31 stops supplying water.
Desalted water production system of the present invention farther includes the cleaning system used by the desalted water produced
System.
Refer to Fig. 2, described purging system include squeeze acid section 51, purge zone 52, brushing stage 53, hydro-peening section 54,
Cyclic water tank 55, some first circulating pumps 56, some second circulating pumps 57 and effluent outfall 58.Squeeze acid
Section 51, purge zone 52, brushing stage 53, hydro-peening section 54 are set gradually by the direction of advance of a steel band 70.
Squeezing acid section 51 and be provided with acid squeezing roller 511, acid squeezing roller 511 is made up of some acid-proof rubber rolls, motor drives.
Acid squeezing roller 511 mainly removes a large amount of acid solutions that steel strip surface band from descaling bath does not comes, and squeezes the acid solution gone and directly stays
Return acid tank, acid cost can be saved, it also avoid the trouble that follow-up sewage disposal acid band is come simultaneously.
Purge zone 52 is provided with flusher 521 and squeeze roll 522.Steel band after acid squeezing roller 511, first warp
Cross purge zone 52, be rinsed steel strip surface now by substantial amounts of water, owing to steel strip surface exists number acid
Property material, so the value that the water after Chong Xiing does not recycles, is flowed directly to effluent outfall 58, passes through
Sewage discharge water pipe 58 is emitted into Sewage Disposal.After having rinsed steel band, remove steel band by squeeze roll 522
The water of the flushing of remained on surface, enters brushing stage.
Brushing stage 53 is provided with scrubs unit 531 and squeeze roll 532, scrubs unit 531 and includes some brush roll
(figure is not marked), squeeze roll 532 is arranged on the both sides of brush roll.Brush roll is in order to brush further to steel strip surface
Washing, squeeze roll 532 mainly removes steel strip surface from having the moisture of a small amount of acid solution, squeezes the moisture gone and directly stays back
Brushing stage.The steel strip surface of this section the most more cleans, and the more steel strip surface residual chemicals toward back segment is the fewest,
Water after scrubbing can be delivered to cyclic water tank 55, cyclic water tank 55 filter after give leading portion purge zone 52,
And brushing stage 53 repeats itself utilizes, thus save water resource.
Hydro-peening section 54 is provided with some hydro-peening units 541 and some squeeze rolls 542, and hydro-peening unit 541 is in order to steel
Band sprays, and squeeze roll 542 once sprays the moisture of remnants before mainly removing steel strip surface, squeezes the moisture gone
Directly stay back hydro-peening section.In the present embodiment, hydro-peening section 54 itself is internal uses secondary cycle spray to design, and two
Platform the second circulating pump 57 connects hydro-peening section and corresponding hydro-peening unit 541 respectively, carries out repeats itself spray, can
To utilize water resource to ensure steel band quality to greatest extent simultaneously.
Hydro-peening section 54 connects water inlet pipe 543, and the desalted water produced for desalted water production system flows into, to spray
Washing machine group 541 supplies water.Hydro-peening unit 541 uses desalted water to be carried out, because hydro-peening section 54 determines steel band table
The quality in face, so using desalted water, the chloride ion content of desalted water is low, it is possible to reduce to steel strip surface matter
The impact of amount.Owing to the production cost of desalted water is higher, so purge zone 52, brushing stage 53 use hydro-peening section
The desalted water of 54 hydro-peening backflows and the industry water brush of supply are scrubbed.The most both final hydro-peening section 54 had been ensured
It is to use desalted water to clean, it is ensured that steel band quality, saves again desalted water cost and consumption.Concrete scheme
It is back to cyclic water tank 55 for the current complete by hydro-peening section 54 hydro-peening.Cyclic water tank 55 is back to supplying after water filtration
Purge zone 52, brushing stage 53.
It is provided with some filter screen separator 551 in cyclic water tank 55, is correspondingly formed some grades of filter boxs.The present embodiment
In, it is provided with two filter screen separator 551 in cyclic water tank 55, is correspondingly formed the first filter box 552, second
Filter box 553, the third filter box 554.First filter box 552 receives the water refluxed from brushing stage 53 and hydro-peening section 54,
Then filter to the second filter box 553, then filter to the third filter box 554 from the second filter box 553.After filtration
Two filter boxs 553, the water of the third filter box 554 can be supplied to purge zone 52, brushing stage 53.The water of the third filter box 554
Be filter after clean water, the first filter box 552 is simultaneously connected with effluent outfall 58, can discharge as required
The sewage of cyclic water tank 55 or in cyclic water tank 55 water of overfill.
First circulating pump 56 connects cyclic water tank 55 and scrubs unit 531 to flusher 521, brushing stage respectively,
So that the water after cyclic water tank 55 inner filtration is respectively fed to flusher 521, scrubs unit 531.It is connected to
It is provided with valve 61 on the pipeline of circulating pump, can open as required.Brushing stage 53 and hydro-peening section 54 points
Be not connected to cyclic water tank 55, so, by the first circulating pump 56 to flusher 521, scrub unit 531
Periodical feeding, the backwater of brushing stage 53 and hydro-peening section 54 flows back to cyclic water tank 55 simultaneously.
If the liquid level of cyclic water tank 55 is relatively low, then carry out moisturizing by an industry filling pipe 60, it is ensured that circulation
The liquid level of water tank 55.
During cleaning, steel band, after the acid squeezing roller 511 of crowded acid section 51, first passes around purge zone 52 and rinses, rinse
After complete steel band, removed the water of the flushing of steel strip surface residual by squeeze roll 542, then in turn through brushing stage
Scrubbing, and all have squeeze roll to extract steel strip surface before and after scrubbing each time, after scrubbing, steel band enters
Hydro-peening section 54, sprays through secondary cycle in hydro-peening section 54, sends after extracting, so can be thoroughly by steel band table
The residual chemicals in face is removed, it is ensured that the cleaning quality of steel band, and by by the clean water of back segment
Recycle to the scrubbing unit of leading portion, thus save water resource, especially save desalted water cost and consumption.
In cleaning process, hydro-peening section 54 flows into desalted water through water inlet pipe 543 and is carried out, and desalted water
Circulated sprinkling under the effect of the second circulating pump 57, the desalted water after simultaneously cleaning flows into cyclic water tank 55
Second filter box 553 and the third filter box 554 is flowed into after first filter box 552, and filtration.First circulating pump 56 is made
Flow into the flusher 521 of purge zone 52 with lower second filter box 553 and the third filter box 554, scrub unit 531,
The water that purge zone 52 has been rinsed flows into sewage discharge water pipe 58, and the water that brushing stage 53 is scrubbed is back to recirculated water
First filter box 552 of case 55.Additionally, when the liquid level of cyclic water tank 55 is relatively low, entered by industry filling pipe 60
Row moisturizing.
To sum up, the desalted water production system that the present invention is automatically controlled by design, it is achieved automatic water production, unmanned
On duty, production efficiency is high, reduces hand labor intensity.By using desalted water to clean at the after-stage scrubbed,
Both ensured finally to clean is use desalted water clean, it is ensured that steel band quality, save again desalted water cost and
Consume.The residual chemicals of steel strip surface can thoroughly be removed by purging system, it is ensured that the cleaning matter of steel band
Amount, and by the clean water of back segment is recycled to the scrubbing unit of leading portion, thus save water resource,
Especially save desalted water cost and consumption.
Without departing from the thought of the invention, the various different embodiments of the present invention are carried out combination in any,
All should be considered as present disclosure;In the technology concept of the present invention, technical scheme is carried out
The combination in any of the thought without prejudice to the invention that multiple simple modification and different embodiment are carried out, all
Should be within protection scope of the present invention.