Heating floor and heating floor assembly Download PDF

Info

Publication number
CN104067058B
CN104067058B CN201280066488.7A CN201280066488A CN104067058B CN 104067058 B CN104067058 B CN 104067058B CN 201280066488 A CN201280066488 A CN 201280066488A CN 104067058 B CN104067058 B CN 104067058B
Authority
CN
China
Prior art keywords
water pipe
floor
pipe
water
branched
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201280066488.7A
Other languages
Chinese (zh)
Other versions
CN104067058A (en
Inventor
黄永镐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kjrd Of Co Ltd
Original Assignee
Kjrd Of Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kjrd Of Co Ltd filed Critical Kjrd Of Co Ltd
Publication of CN104067058A publication Critical patent/CN104067058A/en
Application granted granted Critical
Publication of CN104067058B publication Critical patent/CN104067058B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/146Tubes specially adapted for underfloor heating
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/122Details
    • F24D3/125Hydraulic pipe connections
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/141Tube mountings specially adapted therefor
    • F24D3/142Tube mountings specially adapted therefor integrated in prefab construction elements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D2220/00Components of central heating installations excluding heat sources
    • F24D2220/20Heat consumers
    • F24D2220/2081Floor or wall heating panels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]

Abstract

The present invention relates to a kind of heating floor, it is the heating floor with quadrangular plan, including:Multiple water pipe configured slots, the side along tetragon extends;Branched pipe configured slot, connects two water pipe configured slots;And corner, it is arranged at the part that a water pipe configured slot and another water pipe configured slot contact, described corner includes four corner open portions, wherein, two corner open portions configure channel opening towards described water pipe, two other corner open portion towards the outer openings on floor, can be arranged in parallel two water pipes in described water pipe configured slot.

Description

Heating floor and heating floor assembly
Technical field
The present invention relates to a kind of heating floor and heating floor assembly.
Background technology
The ground heating system of existing utilization hot water, mainly makes with the following method, in embedded underground metal or synthetic resin material Comb, produce thermal source come heating water by being arranged at the boiler of indoor or outdoors, and heated hot water discharged by comb, Need the indoor transmission heat energy such as bedroom or parlor of intensification the most backward.
As the comb method to set up for described existing floor heating, have and bury pvc pipe on floor, construct on the tube mixed Solidifying soil, thus by way of the concrete on hot water heating floor.
But, described mode occur leak when it is not easy to find out correct leakage point, even if find out leakage point not allowing yet Easily place under repair, and operating expenses is also high.
For solving described problem, as shown in figure 1, proposing to arrange multiple heating floors on floor, arranging in ground intralaminar part and supplying The method to warm oneself for the comb of hot water flowing.
But, when being constructed using the floor shown in Fig. 1, need jumbo boiler and water pump, therefore, power consumption Greatly, and heating effect is undesirable.
Therefore, existing floor heating has needs uniformly heating Integral floor, and improves the problem of energy efficiency.
And, there is convenient construction to save the problem of operating expenses.
Content of the invention
The present invention proposes for solving described problem, it is intended that providing heating floor and heating floor assembly, Simply constructed by normalized floor and operating expenses can be saved, and can uniformly be heated Integral floor.
Other objects of the present invention are, provide heating floor and heating floor assembly, also can be obtained with the boiler of low capacity Obtain high-energy, and heating fee can be saved.
It is the heating floor with quadrangular plan according to the heating floor of one embodiment of the invention, including:Multiple water Pipe configured slot, the side along tetragon extends;Branched pipe configured slot, connects two water pipe configured slots;And corner, it is arranged at The part that one water pipe configured slot contacts with another water pipe configured slot, described corner includes four corner open portions, its In, two corner open portions configure channel opening towards described water pipe, two other corner open portion towards the outer openings on floor, Can be arranged in parallel two water pipes in described water pipe configured slot.
The present invention can further include midfeather, projects toward upper in the central authorities of described water pipe configured slot, thus will be described Water pipe configured slot is divided into two regions extending towards length direction.
Can project toward upper from bottom in the central authorities of described corner and be formed with central pin.
In the middle of the above-below direction of floor corner, local can be cut open.
According to the heating floor assembly of one embodiment of the invention, including:Multiple heating floors, including floor, along institute State the edge water pipe configured slot extending on floor and the branch being configured at rightabout two water pipe configured slots for connection Pipe configured slot;Water pipe, is configured at described water pipe configured slot;And branched pipe, it is configured at described branched pipe configured slot, in described water The local of pipe configured slot is arranged with two water pipes in parallel, and described water pipe includes:Flow into pipe, be connected to described branched pipe, to setting The floor having described water pipe flows into hot water;Delivery pipe, is connected to described branched pipe, from the floor array heat release being provided with described water pipe Water;And dispatch tube, it is not connected to described branched pipe, described dispatch tube abreast can be set with described inflow pipe or described delivery pipe It is placed in a water pipe configured slot.
Described heating floor includes the first floor, the second floor, the 3rd floor and the 4th floor, described first floor bag Include:First water pipe, for passing through from the outside hot water flowing into;Second water pipe, for passing through from the outside hot water flowing into, and is fed to institute State the 3rd floor side;3rd water pipe, is configured at the opposite of described first water pipe, to described second floor side hot-water supply;First Branched pipe, connects described first water pipe and described 3rd water pipe, is flowed into quilt after hot water circuit first floor side of the first water pipe It is fed to the 3rd water pipe;And the 4th water pipe, it is set to parallel with described second water pipe, and to outside drain hot water, described Two floors include:5th water pipe, is subject to hot water from described first water pipe side joint;6th water pipe, is arranged at the phase of described 5th water pipe Toss about;And second branched pipe, connect described 5th water pipe and the 6th water pipe, be flowed into the hot water circuit the of described 5th water pipe It is supplied to described 6th water pipe behind the inner side on two floors, be formed with described 3rd floor:7th water pipe, from described second water Tube side hot-water supply;8th water pipe, is arranged at the opposition side of described 7th water pipe;Three branched pipe, connects described 7th water pipe With described 8th water pipe, behind the 3rd floor described in hot water circuit being flowed into described 7th water pipe, it is supplied to described 8th water Pipe;9th water pipe, towards described 4th water pipe side discharge hot water;And the tenth water pipe, it is set to parallel with described 8th water pipe, and Towards described 9th water pipe discharge hot water, described 4th floor includes:11st water pipe, from described 7th water pipe side hot-water supply; 12nd water pipe, is arranged at the opposition side of described 11st water pipe, and is connected to the 8th water pipe;4th branched pipe, connects described 11st water pipe and described 12nd water pipe, are supplied behind the 4th floor described in hot water circuit being flowed into described 11st water pipe To described 12nd water pipe;13rd water pipe, from described 6th water pipe side inflow hot water;And the 14th water pipe, from described 12 water pipes and described 13rd water pipe flow into hot water, and are discharged into described tenth water pipe side.
Pluggable possess two water pipes and a branched pipe one between described first floor and described second floor Above floor, described two water pipes are located between described first water pipe and the 5th water pipe and the 3rd water pipe and the 6th water pipe respectively Between, described branched pipe connects between described two water pipes.
Can be inserted into more than one floor between described 3rd floor and described 4th floor, described floor possesses:Two Individual water pipe, is located between described 7th water pipe 208 and the 11st water pipe 212 and the 8th water pipe 209 and the 12nd water pipe 213 respectively Between;Branched pipe, connects between described two water pipes;And water pipe, positioned at described 14th water pipe 215 and the tenth water pipe 211 Between.
Can be inserted into more than one floor between described first floor and described 3rd floor, described floor possesses:Two Individual water pipe, the hot water by described second water pipe for the supply;Branched pipe, one end is connected to one of described two water pipes;And Water pipe, is connected with the other end of described branched pipe.
According to the present invention, form floor heating by using normalized multiple floors, thus construction is simple, and can save Operating expenses.
In accordance with the invention it is possible to uniformly heat whole floor such that it is able to improve heating effect.
According to the present invention, hot water can rapidly be circulated in multiple branched pipes, be additionally, since the heat by each branched pipe Water moves identical distance, and therefore, hot water is balancedly circulated, and the boiler of even low capacity also can improve heating effect Really, thus improving energy efficiency and saving heat cost.
Brief description
Fig. 1 is provided with the generalized schematic of the situation of existing heating floor.
Fig. 2 is the schematic top plan view of the heating floor according to one embodiment of the invention.
Fig. 3 is the sectional perspective schematic diagram of the heating floor according to one embodiment of the invention.
Fig. 4 is the schematic perspective view amplifying the corner shown in Fig. 3.
Fig. 5 is the approximate vertical view of the heating floor assembly according to one embodiment of the invention.
Fig. 6 is the schematic perspective view of heating floor assembly according to other embodiments of the invention.
Fig. 7 is the outline of " T " the font connecting elements being used in the heating floor assembly according to one embodiment of the invention Schematic diagram.
Fig. 8 is the outline of " L " the font connecting elements being used in the heating floor assembly according to one embodiment of the invention Schematic diagram.
Fig. 9 is the combined structure being used for illustrating between floor in the heating floor assembly according to one embodiment of the invention Schematic diagram.
Specific embodiment
Hereinafter, with reference to the accompanying drawings of the heating floor according to one embodiment of the invention and the ground that includes this heating floor Thermally board component.
Fig. 2 is the top view of the heating floor 100 according to one embodiment of the invention, and Fig. 3 is axonometric chart, and Fig. 4 is to amplify The schematic diagram of the corner 170 shown in Fig. 3.
Look down and include during the heating floor 100 according to the present embodiment being in substantially the floor 110 of tetragon, on described floor 110 top is provided with comb configured slot 150,160.
Described comb configured slot 150,160 includes water pipe configured slot 150 and branched pipe configured slot 160, can be described Plate 110 is recessed downward and is formed, and also can form a pair of protuberance projecting upward from floor 110, and use described protuberance Between space formed comb configured slot, be also applicable to described two situations.
In the present embodiment, the top on described floor 110 is formed with protuberance, between a pair of protuberance of parallel elongate Space formed comb configured slot 150,160.
Specifically, the edge on floor 110 projects toward upper and is formed with outer wall 120, and described outer wall is along quadrangularly Four sides of plate 110 extend, and inwards abreast extend with described outer wall 120 and are formed with inwall 130, inwall and described outer wall 120 It is spaced and formed.
Space between described outer wall 120 and described inwall 130 forms water pipe configured slot 150.In described outer wall 120 and interior It is formed with midfeather 140, described midfeather is set to and described outer wall 120 and described inwall 130 parallel elongate between wall 130. Therefore, can be arranged in parallel two water pipes across midfeather 140, water pipe configured slot 150 be divided into outside water pipe configured slot 150a and Inner side water pipe configured slot 150b.
It is formed with corner 170 at the both ends of described outer wall 120 and described inwall 130.
Described corner 170, including:Four corner open portions, towards four direction opening;Bending section, opens in each corner It is shaped generally as the circular arc of 1/4 circle between oral area;And central pin 173, centrally located.Herein, described corner open portion leads to Cross midfeather 140 and be divided into two regions.
Two ends being connected to described water pipe configured slot 150 in described four corner open portions, and towards described water Pipe configured slot 150 opening, two other corner open portion local of described outer wall 120 is cut open, and towards outer openings.
When arranging multiple heating floor 100 as the present embodiment, it is arranged to towards the corner open portion of outer openings Corresponding with the corner open portion on adjacent floor, thus the water pipe on two floors that can be interconnected by corner 170 Configured slot 150.
The central authorities of described corner 170 are provided with central pin 173.Described central pin 173 divides multiple for intersect The path that water pipe passes through, when applying external force from top to corner, described central pin stops described external force from being delivered to water pipe.
The outside of corner, that is, the outside of the end of the corner on floor face up lower section to cut specific thickness and formed In conjunction with cut 180.Described combination cut 180 is cut open 1/4 disc for having specific thickness, cuts in described combination The top in portion 180 is formed with the screw combined hole 190 penetrating up and down.
It is inserted with reference to auxiliary part 610 (shown in Fig. 9) in described combination cut 180 and screw combined hole 190, thus In conjunction with fixing a floor and the floor adjacent with this floor.For the side with reference to a floor and the floor adjacent with this floor Method, is described in detail when method to set up is described.
By four described water pipe configured slots 150 around the inner side in region be formed with branched pipe configured slot 160.Described point Manifold configurations groove 160 be towards floor 110 top project a pair of protuberance between space, including:Multiple line parts 161, It is the straight line being parallel to each other;And curve part 162, it is in substantially "U" shaped, and be incorporated into the end of described line part 161.Institute State one end that line part 161 combines in the both ends of "U" shaped of described curve part 162, thus overall is in repeatedly " S " font Curved shape.
Now, in the point of intersection of described water pipe configured slot 150 and branched pipe configured slot 160, the local of inwall 130 is cut open And form connection cut 131.Relative two water pipe configured slot 150 on a floor 100 is respectively formed with described in one Connect cut 131, described two connection cut 131 abut to form in corner 170 towards diagonal.
Described line part 161 and described curve part 162 may be integrally formed as a component.
When multiple floor with described construction is set, become form as shown in Figure 5.The top that Fig. 5 is shown in floor sets The heating floor assembly put comb and formed.
One embodiment of the heating floor assembly according to the present invention is described with reference to Fig. 5.
In shown in Fig. 5 four floor, the floor positioned at right side upper end is the first floor 100, positioned at left side upper end Floor is the second floor 100a, is the 3rd floor 100b positioned at the floor of right side lower end, is the 4th positioned at the floor of left side lower end Floor 100c.
In the present embodiment, the water pipe being configured at water pipe configured slot is divided into inflow pipe, delivery pipe and dispatch tube Three kinds of forms, flowing into pipe is to become to make the hot water of outside be flowed into inside and be sent to the water pipe of the passage of branched pipe, delivery pipe It is the water pipe of the passage of the hot water becoming discharge cycle in branched pipe, dispatch tube is not attached to branched pipe and supplying hot water passes through Water pipe.
First, the first floor 100 is provided with 202,203,204,205 and branched pipe 301 of four water pipes.
The outside corner 170 on the first floor for the pipe 201 that flows into being connected with boiler (omit diagram) etc. is connected to first Water pipe 202 and the second water pipe 203.Now, described first water pipe 202 is the inflow that the hot water for circulation the first floor 100 flows into Pipe, the second water pipe 203 is the dispatch tube transmitting hot water to the 3rd floor 100b.
It has been provided opposite to the 3rd water pipe 204 in described first water pipe 202.Described 3rd water pipe 204 is for towards outside The delivery pipe of the hot water on discharge cycle the first floor 100.
Now, described first water pipe 202, the second water pipe 203 and the 3rd water pipe 204 are configured at inner side water pipe configured slot 150a.
Described 4th water pipe 205 is abreast arranged at a water pipe configured slot with described second water pipe 203.Therefore, one In individual water pipe configured slot 150, in inner side, water pipe configured slot 150b is provided with the second water pipe 203, in outside water pipe configured slot 150a It is provided with the 4th water pipe 205.
Branched pipe configured slot 160 between described first water pipe 202 and described 3rd water pipe 203 is provided with the first branch Pipe 301.
Described first branched pipe 301 includes:Multiple line parts 161, corresponding to the shape of described branched pipe configured slot 160; And curve part 162, it is in substantially "U" shaped, and be formed at the end of described line part, a side end of described first branched pipe It is incorporated into the first water pipe 202 near the corner of left side upper end, end side combines on its cornerwise rightabout In the 3rd water pipe 204.In the present embodiment, described branched pipe 162 is by described line part 161 and described curve part 162 1 bodily form One-tenth forms, and is to be formed by a flexible flexible pipe.
Now, water pipe 202,203 and branched pipe are combined by " T " font connecting elements 400.As shown in fig. 7, described " T " Font connecting elements 400 is " T " font hollow member, for connecting two water pipes and branched pipe, is formed with saw in outboard end The fixed part 401 of profile of tooth such that it is able to fixedly secure combined comb make its without departing from.
Second floor 100a is provided with 206,207 and branched pipe 302 of two water pipes.
First, the water pipe configured slot in upside is provided with the 5th water pipe 206.Described 5th water pipe 206 is connected to described One water pipe 202, and become the surplus hot water's inflow not passing through the first branched pipe 301 in the hot water supplying to be flowed into the first water pipe 202 Inflow pipe.
The opposition side of described 5th water pipe 206 is provided with the 6th water pipe 207, in described 5th water pipe 206 and described It is provided with second branched pipe 302 between six water pipes 207.Described 6th water pipe 207 has been the delivery pipe of channeling, for flowing Enter externally discharged behind second branched pipe 302 circulating floor inside to the hot water of described 5th water pipe 206.
3rd floor is provided with 208,209,210,211 and branched pipe 303 of four water pipes.
7th water pipe 208 is incorporated into described second water pipe 203, is arranged at the water pipe configuration of upside on the 3rd floor 100b Groove.Described 7th water pipe 208 is that the hot water being flowed into and through the second water pipe 203 by outside inflow entrance 201 is flowed into the 3rd The inflow pipe of floor 100b.
The opposition side of described 7th water pipe 208 is provided with the 8th water pipe 209, in described 7th water pipe 208 and described Branched pipe configured slot 160 between eight water pipes 209 is provided with Three branched pipe 303.Now, described 8th water pipe 209 becomes row Put pipe.Described 7th water pipe 208 and described 8th water pipe 209 are all arranged at inner side water pipe configured slot 150b.
Right side water pipe configured slot on described 3rd floor 100b is provided with the 9th water pipe 210.Described 9th water pipe 210 It is the dispatch tube of described 4th water pipe 205 that one end is connected to described first floor 100, be arranged at outside water pipe configured slot 150a.
The other end of described 9th water pipe 210 is incorporated into the tenth water pipe 211.Described tenth water pipe 211 and described 8th water Pipe 209 is abreast arranged at a water pipe configured slot 150.Now, in a water pipe configured slot 150, in the configuration of inner side water pipe Groove 150b is provided with described 8th water pipe 209, and in outside, water pipe configured slot 150a is provided with described tenth water pipe 211.
Now, described 9th water pipe 210 and described tenth water pipe 211 are all dispatch tube.
Described 4th floor 100c is provided with 212,213,214,215 and branched pipe 304 of four water pipes.
First, the 11st water pipe 212 being arranged at the so-called inflow pipe of upside water pipe configured slot is connected to described 3rd ground The hot water that 7th water pipe 208 of plate 100b and making circulates in the 4th floor 100c flows into.Contrary in described 11st water pipe 212 Side is provided with the 12nd water pipe 213 of so-called delivery pipe, is provided between described 11st water pipe and described 12nd water pipe 4th branched pipe 304.
The left side water pipe configured slot of described 4th floor 100c is provided with the 13rd water pipe 214, is provided with described The water pipe configured slot of 12 water pipes 213 and described 12nd water pipe 213 are abreast provided with the 14th water pipe 215.Described tenth Three water pipes 214 are the 6th water pipes 207 that one end is connected to described second floor, and the other end is connected to the biography of the 14th water pipe 215 Send pipe, described 14th water pipe is that one end is connected to described 13rd water pipe 214, and the other end is connected to described 3rd floor 100b The tenth water pipe 211 dispatch tube.
In the composition of heating floor assembly as described above, for smooth circulation hot water, the internal diameter of water pipe is more than branched pipe Internal diameter.When the section of described water pipe and branched pipe is not circle, the sectional area inside water pipe is more than the sectional area of branched pipe.
On two adjacent floors, interconnective two water pipes are formed one, for example, described 4th water Pipe 205 and described 9th water pipe 210 may be integrally formed as a component, now, the boundary of the 4th water pipe 205 and the 9th water pipe 210 Depending on limit is according to the position on residing floor.That is, the part on the first floor 100 becomes the 4th water pipe 203, positioned at the 3rd Part on the 100b of floor becomes the 9th water pipe 210.
Hereinafter, illustrate hot water circuit in having the process in heating floor assembly configured as above.
First, when boiler (omitting diagram) etc. runs, hot water is flowed into pipe 201 and is flowed into by outside needs heat up to crouch Room or parlor etc..
Be flowed in the hot water on the first floor 100 by the outside pipe 201 that flows into, a part be flowed into the first water pipe 202 and Remainder is flowed into the second water pipe 203.
Now, it is flowed in the hot water of the first water pipe 202, after part circulation the first branched pipe 301, pass through the 3rd water pipe 203 outsides being discharged into the first floor 100, then pass sequentially through the 6th water pipe 207, the 13rd water pipe 214, the 12nd water pipe 213rd, the tenth water pipe 211, the 9th water pipe 210 and the 4th water pipe 205 are discharged into the outside in bedroom or parlor.
Through, in the hot water that the first water pipe 202 flows into, the 5th water pipe not being flowed into by the surplus hot water of the first branched pipe 301 205, and the second floor 100a is heated by second branched pipe 302, then the second floor is discharged into by the 6th water pipe 207 The outside of 100a, and pass sequentially through the 13rd water pipe 214, the 12nd water pipe 213, the tenth water pipe 211, the 9th water pipe 210 and 4th water pipe 205 is discharged into the outside in bedroom or parlor.
7th water pipe 208 is flowed into by the hot water that outside inflow pipe 201 is flowed into described second water pipe 203, through stream In the hot water entering, after part circulation Three branched pipe 303 uniformly heating the 3rd floor 100b, pass sequentially through the 8th water pipe 209th, the 12nd water pipe 213, the 14th water pipe 215, the tenth water pipe 211, the 9th water pipe 210 and the 4th water pipe 205 are discharged Outside to bedroom or parlor.
It is flowed in the hot water of the 7th water pipe 208 through the second water pipe 203, do not pass through the surplus hot water of Three branched pipe 303 After being flowed into the 11st water pipe 212, circulation the 4th branched pipe 304 after uniformly heating the 4th floor 100c, pass sequentially through the 12 water pipes 213, the 14th water pipe 215, the tenth water pipe 211, the 9th water pipe 210 and the 4th water pipe 205 are discharged into bedroom Or the outside in parlor.
By being constructed using as above, the mobile route of hot water is circulated more areas by diversification, uniformly heats While Integral floor, circulation rate is accelerated, thus the boiler of even low capacity also can produce high energy efficiency.Especially, follow The displacement of the hot water of each branched pipe of ring is all identical, does not therefore produce the interval that the flowing of hot water is stalled or slows down, So as to efficient heating effect is reached by the boiler of low capacity.
Due to by the first branched pipe 301, second branched pipe 302, Three branched pipe 303 and the 4th branched pipe 304 The displacement of hot water is all identical, therefore, it is readily appreciated that as above situation.
When for three pipe intersecting situations, can be combined when vertical using " T " font connecting elements 400 as shown in Figure 7 During two pipes, can be using " L " font connecting elements 500 as shown in Figure 8.It is also formed with the outside of described " L " character form component Zigzag fixed part 501.
As shown in fig. 6, expansible heating floor assembly as shown in Figure 5.
That is, can be between described first floor 100 and described second floor 100a and described 3rd floor 100b and described The more than one floor of horizontally set between 4th floor.
Can be between described first floor 100 and described 3rd floor 100b with described second floor 100a and described Vertically arranged more than one floor between four floor 100c.
The floor being arranged between the first floor 100 and the second floor 100a is provided with so-called the 15th water flowing into pipe 16th water pipe 217 of pipe 216, quintafurcation pipe 305 and so-called delivery pipe, thus pass through so-called stream from the first floor 100 Pass through the 16th water pipe 217 of so-called delivery pipe after the hot water circuit quintafurcation pipe 306 of the 15th water pipe 216 inflow entering pipe It is discharged into the second floor 100a side.Now, one end of so-called the 15th water pipe 216 flowing into pipe is incorporated into described first floor 100 the first water pipe 202, the other end is incorporated into the 5th water pipe 206 of described second floor 100a, and the 16th of so-called delivery pipe the One end of water pipe 217 is incorporated into the 3rd water pipe 204 on described first floor 100, and the other end is incorporated into the of described second floor Six water pipes 207.
The floor being arranged between the 3rd floor 100b and the 4th floor 100c is provided with one and flows into pipe 218, branch Pipe 306, delivery pipe 219 and dispatch tube 220, thus pass through so-called the 17th water pipe 218 flowing into pipe from the 3rd floor 100b After hot water circuit the 6th branched pipe 306 flowing into, the 4th floor is discharged into by the 18 water pipe 219 of so-called delivery pipe 100c.
So-called dispatch tube is passed through by the hot water of the 14th water pipe 215 transmission of the so-called dispatch tube of the 4th floor 100c 19th water pipe 220 is sent to the tenth water pipe 211 of the so-called dispatch tube of the 3rd floor 100b.
Now, one end of so-called the 17th water pipe 218 flowing into pipe is incorporated into the 7th water pipe of described 3rd floor 100b 208, the other end is incorporated into the 11st water pipe 212 of described 4th floor 100c, and the one of the 18 water pipe 219 of so-called delivery pipe End is incorporated into the 8th water pipe 209 on described 3rd floor, and the other end is incorporated into the 12nd water pipe of described 4th floor 100c 213, one end of the 19th water pipe 220 of so-called dispatch tube is incorporated into the 14th water pipe 215 of described 4th floor 100c, another End is incorporated into described tenth water pipe 211.
Therefore, floor lateral magnification can be configured in the essential structure of Fig. 5 by above method.
When the floor panel assembly of vertical expansion Fig. 5, be arranged at described first floor 100 and described 3rd floor 100b it Between floor four water pipes and a branched pipe are set, the basic arrangement of comb is identical with the first floor.
In floor setting three water pipes and being arranged between described second floor 100a and described 4th floor 100c Individual branched pipe, removes the 14th water pipe 215 of so-called dispatch tube on the 4th floor, then become identical comb arrangement.
Therefore, by being configured as above, on the basis of the comb arrangement of Fig. 5, can be on the first floor and the 3rd floor Between and between the second floor and the 4th floor, more than one floor is set.
That is, the heating floor assembly of Fig. 5 can expand configuration anyhow, and, even if carrying out expansion configuration, due to by each The displacement of the hot water of branched pipe is identical, therefore, it is possible to persistently keep good effect by the present invention.
Hereinafter, the method to set up with heating floor configured as above and heating floor assembly is described.
First, constructor arranges multiple heating floors according to the present invention on ground.Then, in conjunction with a floor and with this The adjacent floor in floor.Now, combined between floor by the combination auxiliary part 610 shown in Fig. 9.
As shown in figure 9, being formed by the component in circular flat with specific thickness with reference to auxiliary part 610.
Described combination auxiliary part 610 has the disc with the almost identical thickness of combination cut 180 on described floor, Formed by having the materials such as resilient rubber.
Therefore, as shown in figure 9, when with reference to four floors, in the combination cut 180 of the corner being formed at four floors After inserting discoidal combination auxiliary part 610, in the screw combined hole 190 insertion spiral shell wearing on the corner top on floor Silk, thus screw passes through with reference to auxiliary part 610.By described process, fixedly secure adjacent four floor.
When with reference to two floors, using the combination auxiliary part that specific thickness is had on semicircular plane, thus Adjacent two floor can be fixedly secured.
By method as defined above, behind floor, comb is set.Be connected with each other between water pipe and water pipe, water pipe and point Between arm, each comb is connected by connection auxiliary part as shown in Figures 7 and 8.
Now, the central pin 173 projecting toward upper in the central authorities of corner is used for dividing the passage through each comb.
After setting comprises water pipe and the comb of branched pipe on floor, pour the accumulation of heats such as loess or mortar in the inner side of inwall Component is dried.
Then, the top on described floor covers lid and is fixed.Described lid is by tabular component flat above Become.A heatable brick bed plate etc. can be spread on the lid to use, according to the characteristic in construction area, insulated floor can be set further.
When the present invention is described, comb be connected to other comb include situation that two combs are directly connected to and The situation that two combs are attached by other combs or other components.
Described comb is the term comprising water pipe and branched pipe, should be interpreted that and comprises by the softness material such as rubber or synthetic resin The concepts such as the flexible pipe of material, pipe.

Claims (9)

1. a kind of heating floor, it is that have the heating floor of quadrangular plan it is characterised in that including:
Multiple water pipe configured slots, the side along tetragon extends;
Branched pipe configured slot, connects two water pipe configured slots;And
Corner, is arranged at the part that a water pipe configured slot and another water pipe configured slot contact,
Described corner includes four corner open portions,
Two corner open portions configure channel opening towards described water pipe,
Two other corner open portion towards the outer openings on floor,
Can be arranged in parallel two water pipes in described water pipe configured slot.
2. heating floor according to claim 1, it is characterised in that further including midfeather, configures in described water pipe The central authorities of groove project toward upper, thus described water pipe configured slot is divided into two regions extending towards length direction.
3. heating floor according to claim 1 is it is characterised in that dash forward toward upper from bottom in the central authorities of described corner Go out to be formed with central pin.
4. heating floor according to claim 1 is it is characterised in that the middle local of the above-below direction of floor corner is cut Open.
5. a kind of heating floor assembly is it is characterised in that include:
Multiple heating floors, including floor, along described floor edge extend water pipe configured slot and for connect configuration Branched pipe configured slot in rightabout two water pipe configured slots;
Water pipe, is configured at described water pipe configured slot;And
Branched pipe, is configured at described branched pipe configured slot,
It is arranged with two water pipes in the local of described water pipe configured slot in parallel,
Described water pipe includes:
Flow into pipe, be connected to described branched pipe, flow into hot water to the floor being provided with described water pipe;
Delivery pipe, is connected to described branched pipe, puts hot water from the floor array being provided with described water pipe;And
Dispatch tube, is not connected to described branched pipe,
Described dispatch tube is abreast arranged at a water pipe configured slot with described inflow pipe or described delivery pipe.
6. heating floor assembly according to claim 5 it is characterised in that described heating floor include the first floor, Two floors, the 3rd floor and the 4th floor,
Described first floor includes:
First water pipe, for passing through from the outside hot water flowing into;
Second water pipe, for passing through from the outside hot water flowing into, and is fed to described 3rd floor side;
3rd water pipe, is configured at the opposite of described first water pipe, to described second floor side hot-water supply;
First branched pipe, connects described first water pipe and described 3rd water pipe, is flowed into hot water circuit first ground of the first water pipe It is supplied to the 3rd water pipe behind plate side;And
4th water pipe, is set to parallel with described second water pipe, and to outside drain hot water,
Described second floor includes:
5th water pipe, is subject to hot water from described first water pipe side joint;
6th water pipe, is arranged at the opposition side of described 5th water pipe;And
Second branched pipe, connects described 5th water pipe and the 6th water pipe, is flowed into hot water circuit second ground of described 5th water pipe It is supplied to described 6th water pipe behind the inner side of plate,
Described 3rd floor includes:
7th water pipe, from described second water pipe side hot-water supply;
8th water pipe, is arranged at the opposition side of described 7th water pipe;
Three branched pipe, connects described 7th water pipe and described 8th water pipe, is flowed into the hot water circuit institute of described 7th water pipe It is supplied to described 8th water pipe after stating the 3rd floor;
9th water pipe, towards described 4th water pipe side discharge hot water;And
Tenth water pipe, is set to parallel with described 8th water pipe, and towards described 9th water pipe discharge hot water,
Described 4th floor includes:
11st water pipe, from described 7th water pipe side hot-water supply;
12nd water pipe, is arranged at the opposition side of described 11st water pipe, and is connected to the 8th water pipe;
4th branched pipe, connects described 11st water pipe and described 12nd water pipe, is flowed into the hot water of described 11st water pipe It is supplied to described 12nd water pipe after circulating described 4th floor;
13rd water pipe, from described 6th water pipe side inflow hot water;And
14th water pipe, flows into hot water from described 12nd water pipe and described 13rd water pipe, and is discharged into described tenth water pipe Side.
7. heating floor assembly according to claim 6 is it is characterised in that on described first floor and described second floor Between can be inserted into more than one floor, described floor includes:
Two water pipes, respectively be located between described first water pipe and the 5th water pipe and the 3rd water pipe and the 6th water pipe between;And
One branched pipe, connects between described two water pipes.
8. heating floor assembly according to claim 7 is it is characterised in that on described 3rd floor and described 4th floor Between can be inserted into more than one floor, described floor includes:
Two water pipes, respectively be located between described 7th water pipe and the 11st water pipe and the 8th water pipe and the 12nd water pipe between;
Branched pipe, connects between described two water pipes;And
Water pipe, positioned between described 14th water pipe and the tenth water pipe.
9. heating floor assembly according to claim 6 is it is characterised in that on described first floor and described 3rd floor Between can be inserted into more than one floor, described floor includes:
Two water pipes, the hot water by described second water pipe for the supply;
Branched pipe, one end is connected to one of described two water pipes;And
Water pipe, is connected with the other end of described branched pipe.
CN201280066488.7A 2012-01-09 2012-12-04 Heating floor and heating floor assembly Active CN104067058B (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR10-2012-0002286 2012-01-09
KR1020120002286A KR101192550B1 (en) 2012-01-09 2012-01-09 Floor heating pannel and pannel assembly for floor heating
PCT/KR2012/010441 WO2013105736A1 (en) 2012-01-09 2012-12-04 Floor heating panel and floor heating panel assembly

Publications (2)

Publication Number Publication Date
CN104067058A CN104067058A (en) 2014-09-24
CN104067058B true CN104067058B (en) 2017-03-01

Family

ID=47288250

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201280066488.7A Active CN104067058B (en) 2012-01-09 2012-12-04 Heating floor and heating floor assembly

Country Status (5)

Country Link
US (1) US20150159884A1 (en)
JP (1) JP6072828B2 (en)
KR (1) KR101192550B1 (en)
CN (1) CN104067058B (en)
WO (1) WO2013105736A1 (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101268410B1 (en) 2012-08-22 2013-07-01 케이제이알디 (주) Heating line for floor and method for constructing the same
CN104727517A (en) * 2013-12-18 2015-06-24 王世华 Heated floor
KR20160019343A (en) * 2014-08-11 2016-02-19 윤영환 Heating system
KR101636627B1 (en) 2014-12-31 2016-07-07 이신춘 The assembly underfloor heating yellow soil panel of lightweight and high-strength
KR101649544B1 (en) 2015-05-27 2016-08-19 주식회사 히팅플러스 Hot water heating prefabricated panel structure
EP3112549A1 (en) * 2015-07-01 2017-01-04 KEOKI Company SA Construction panel intended for building heating and/or cooling walls of buildings
EP3378134B1 (en) 2015-11-19 2023-01-18 NLIGHT, Inc. Laser fault tolerance and self-calibration system
US11025034B2 (en) 2016-08-31 2021-06-01 Nlight, Inc. Laser cooling system
US10574020B2 (en) 2016-12-15 2020-02-25 Nlight, Inc. Fiber laser packaging
US20180298611A1 (en) * 2017-04-17 2018-10-18 David R. Hall Configurable Hydronic Structural Panel
KR102046630B1 (en) * 2018-02-13 2019-11-19 (주)제이앤씨트레이딩 Self-assembly hot water mat
WO2019178003A1 (en) 2018-03-12 2019-09-19 Nlight, Inc. Fiber laser having variably wound optical fiber
EP3841261B1 (en) * 2018-08-22 2024-01-03 EliTilE AG Covering, functional element for a covering, and method for producing a covering
KR102604858B1 (en) * 2022-11-03 2023-11-22 김은주 Hot water panel system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2074431U (en) * 1990-08-10 1991-04-03 高明日 Combined `kang'-heating panel
JPH10246451A (en) * 1997-03-07 1998-09-14 Tokyo Gas Co Ltd Panel unit for floor heating and panel for floor heating using the same
JPH11193622A (en) * 1997-12-31 1999-07-21 Tokyo Gas Co Ltd Fixing mechanism of backer laminated plate on floor heating panel
CN1380958A (en) * 2000-04-03 2002-11-20 三菱化学产资株式会社 Foldable floor heating panel
CN1465920A (en) * 2002-07-03 2004-01-07 顾世章 Low temp. floor radiation heating device and mfg. method thereof
JP2005337638A (en) * 2004-05-28 2005-12-08 Harman Pro:Kk Floor heating panel
KR20090006092U (en) * 2007-12-17 2009-06-22 오택화 Insulation hypocaust panel

Family Cites Families (32)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5225442A (en) * 1975-08-20 1977-02-25 Matsushita Electric Ind Co Ltd Unit type radiator
JPS5569624U (en) * 1978-11-07 1980-05-13
JPS5572024U (en) * 1978-11-14 1980-05-17
JPS5580698U (en) * 1978-11-30 1980-06-03
JPS5862441A (en) * 1981-10-09 1983-04-13 Asahi Chem Ind Co Ltd Floor-heating panel
JPS5941723A (en) * 1982-09-01 1984-03-08 Takagi Sangyo Kk Floor heating panel
US4817707A (en) * 1986-09-26 1989-04-04 Ryowa Corporation Heating soft floor mat
ATE223020T1 (en) * 1994-03-15 2002-09-15 Terry Wayne Alsberg UNDERFLOOR HEATING SYSTEM
JPH08128657A (en) * 1994-10-28 1996-05-21 Kurita Kogyo:Kk Heat insulating panel for floor heating, and method for burying seamless pipe
US5788152A (en) * 1995-03-15 1998-08-04 Alsberg; Terry Wayne W. Floor heating system
FR2746426B1 (en) * 1996-03-21 1998-06-05 Isobox Technologies THERMALLY INSULATING MOLDED SLAB AND MANUFACTURING METHOD THEREOF
JPH1096521A (en) * 1996-09-24 1998-04-14 Matsushita Electric Works Ltd Hot water floor-heating system
ATE220191T1 (en) * 1998-11-23 2002-07-15 Plan Holding Gmbh SELF-SUPPORTING MODULAR PREFABRICATED RADIATION PANEL, METHOD FOR PRODUCTION AND RADIATION SURFACE PRODUCED THEREFROM
JP2001241683A (en) * 2000-02-24 2001-09-07 Hirokku Tekunika:Kk Electric heater
AU2002218285A1 (en) * 2000-11-06 2002-05-15 SST-Rolltec-Gmbh and Co.KG. Modular panel for laying in underfloor and wall heating systems and thermoconductive sheets for the same
KR200248945Y1 (en) * 2001-05-14 2001-10-19 정태원 Electric panel for heating
EP1382915A1 (en) * 2002-07-15 2004-01-21 SULZER, Hans Dietrich Heat exchanging element and method for fabricating and method for mounting such elements
US6676027B1 (en) * 2002-12-30 2004-01-13 Schmidt Aircraft Products, Inc. Heater for aircraft cockpit
DE10307686B4 (en) * 2003-02-21 2014-11-20 Kermi Gmbh area heating system
KR200315204Y1 (en) * 2003-02-27 2003-06-02 조훈희 Detachable structure for fixing korean under panels
US8028742B2 (en) * 2005-01-05 2011-10-04 Joachim Fiedrich Radiant heating/cooling tubing substrate with in plane bus
ITBO20060185A1 (en) * 2006-03-15 2007-09-16 Global Eco Service S R L HEATING SYSTEM WITH CARPET OR FLOOR, PARTICULARLY FOR ARTISTIC, CULTURAL AND / OR MONUMENTAL AREAS AND FOR MOBILE APPLICATIONS IN GENERAL.
KR200432475Y1 (en) * 2006-09-20 2006-12-04 두 년 김 Side panel for heating room
US9010060B2 (en) * 2007-05-09 2015-04-21 Antonio Rapaz Construction panel
USH2231H1 (en) * 2007-08-27 2009-08-04 Siang Teik Teoh Tubular heating-pipe solar water-heating-system with integral tank
US20090230113A1 (en) * 2008-02-29 2009-09-17 Batori Imre Heated floor support structure and method of installing
KR100896655B1 (en) * 2008-09-22 2009-05-11 이희곤 Knockdown keeping warm panel having the warm water mobile course of couple
EP2169317B8 (en) * 2008-09-25 2016-08-31 Roth Werke GmbH Multi-layer board
KR100901132B1 (en) * 2008-12-30 2009-06-04 김창대 Frefabricated heating panel
IT1393538B1 (en) * 2009-03-27 2012-04-27 Messana MODULAR PREFABRICATED RADIANT PANEL WITH BUILT-IN COLLECTORS.
KR101089506B1 (en) * 2009-05-21 2011-12-05 (주)화성에너지 A panel structure with warm water pipe
WO2011155663A1 (en) * 2010-06-11 2011-12-15 Lee Jong Doo Silicate mineral-based, eco-friendly construction method for saving construction and heating costs, shortening construction period, eliminating cement poison and sick house syndrome, and reducing inter-floor height of high-rise building

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2074431U (en) * 1990-08-10 1991-04-03 高明日 Combined `kang'-heating panel
JPH10246451A (en) * 1997-03-07 1998-09-14 Tokyo Gas Co Ltd Panel unit for floor heating and panel for floor heating using the same
JPH11193622A (en) * 1997-12-31 1999-07-21 Tokyo Gas Co Ltd Fixing mechanism of backer laminated plate on floor heating panel
CN1380958A (en) * 2000-04-03 2002-11-20 三菱化学产资株式会社 Foldable floor heating panel
CN1465920A (en) * 2002-07-03 2004-01-07 顾世章 Low temp. floor radiation heating device and mfg. method thereof
JP2005337638A (en) * 2004-05-28 2005-12-08 Harman Pro:Kk Floor heating panel
KR20090006092U (en) * 2007-12-17 2009-06-22 오택화 Insulation hypocaust panel

Also Published As

Publication number Publication date
WO2013105736A1 (en) 2013-07-18
JP6072828B2 (en) 2017-02-01
KR101192550B1 (en) 2012-10-17
CN104067058A (en) 2014-09-24
US20150159884A1 (en) 2015-06-11
JP2015520348A (en) 2015-07-16

Similar Documents

Publication Publication Date Title
CN104067058B (en) Heating floor and heating floor assembly
KR101168604B1 (en) Hot water mat with water way of a high frequency welding
CN109449329A (en) Battery bracket for Vehicular battery module
EP3279599A1 (en) Heat exchanger and multi-split system having same
KR101104013B1 (en) Air pocket type hot water flooring panel
CN104048468A (en) Refrigerator
CN103968700A (en) Efficient heat exchange water pipe and heat pipe radiant heating/refrigerating system
CN210217019U (en) Installation structure of decoration engineering indoor panel
EP1629235A1 (en) Heating system with heat transmission fluid distributed in finished floor boards
CN104207697A (en) Energy-saving shower system utilizing shower waste water heat to regulate shower water temperature
KR20130128564A (en) Heating mat having radiator
KR101271714B1 (en) Electric boiler
CN218683489U (en) Temperature control blanket double-area temperature-adjusting water path structure
KR200267535Y1 (en) Radiator for “ONDOL”heating system using heat agent
CN101699186B (en) High-efficiency water tank for heat pump water heater
KR101137104B1 (en) warm water heating system having a low energy consumption
CN205878398U (en) Leak protection wind mounting structure of condenser and sideboard in concurrent flow off -premises station
KR101311348B1 (en) Hot water mat
JP4217830B2 (en) Natural circulation promotion device
CN219222747U (en) Air circulation device of air film building
CN213746992U (en) Heat circulation pipeline connecting device of electric water heating system
CN205878329U (en) Breaker and two water course water heating radiator
CN203940553U (en) Ground buried pipe of ground source heat pump enhanced heat exchange pipe laying structure
CN210051185U (en) Hybrid heat exchanger
CN205448327U (en) Water heater inner bag and air -source heat bump water heater

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant