CN104052633B - 智能站61850与远动104规约集成测试方法 - Google Patents
智能站61850与远动104规约集成测试方法 Download PDFInfo
- Publication number
- CN104052633B CN104052633B CN201410232488.0A CN201410232488A CN104052633B CN 104052633 B CN104052633 B CN 104052633B CN 201410232488 A CN201410232488 A CN 201410232488A CN 104052633 B CN104052633 B CN 104052633B
- Authority
- CN
- China
- Prior art keywords
- iec61850
- systems
- stipulations
- station
- information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000010354 integration Effects 0.000 title claims abstract description 18
- 238000010998 test method Methods 0.000 title claims abstract description 12
- 238000012360 testing method Methods 0.000 claims abstract description 17
- 238000013507 mapping Methods 0.000 claims abstract description 11
- 238000004891 communication Methods 0.000 claims description 12
- 238000004088 simulation Methods 0.000 claims description 9
- 230000000052 comparative effect Effects 0.000 claims description 5
- 238000012986 modification Methods 0.000 claims description 3
- 230000004048 modification Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 9
- 238000005516 engineering process Methods 0.000 description 4
- 238000006243 chemical reaction Methods 0.000 description 3
- 230000011664 signaling Effects 0.000 description 3
- 238000005259 measurement Methods 0.000 description 2
- 238000006467 substitution reaction Methods 0.000 description 2
- 241000272814 Anser sp. Species 0.000 description 1
- 241001269238 Data Species 0.000 description 1
- 230000002159 abnormal effect Effects 0.000 description 1
- 230000005856 abnormality Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
本发明涉及智能变电站自动化系统领域中针对IEC61850与远动IEC104规约集成测试的方法,尤其是一种智能站61850与远动104规约集成测试方法。其特点是,包括如下步骤:1)IEC61850系统与104系统同时与调度主站进行通信;2)专业计算机通过镜像口监听方式分别获取IEC61850系统和104系统的通道数据;3)通过建立IEC61850信息模型,解析步骤1)监听获取的IEC61850系统的通道数据,并以树型结构详细列出变电站信息属性。本发明的方法适用于同时采用IEC61850标准协议和104规约进行通信的变电站自动化系统,可实现系统不同规约的正确映射,保证变电站自动化系统运行正常。
Description
技术领域
本发明涉及智能变电站自动化系统领域中针对IEC61850与远动IEC104规约集成测试的方法,尤其是一种智能站61850与远动104规约集成测试方法。
背景技术
随着电网智能化的推进,变电站智能化技术逐渐成为智能电网技术的关键。IEC61850标准作为当前最具权威的国际通信标准被世界各国广泛应用。智能电子设备(Intelligent Electronic Device,简称IED),通过IEC61850/MMS与监控系统、保信子站、远动机等进行数据通信,IED设备之间通过IEC61850/GOOSE来传递快速报文,实现网络跳闸和装置之间的联闭锁,完成无缝通信。
IEC61850是一个综合的标准,用于基于现代网络技术的变电站自动化系统。而目前,国内基于IEC61850的变电站自动化系统还处于起步阶段,利用IEC61850来设计的自动化变电站为数不多,变电站与调度主站的通信仍采用104或者101、102规约居多,这就需要变电站远动装置采集IED设备信息之后结果规约转换,将61850标准的信息转换成其他规约(如104规约),目前尚缺乏一种策略,能够在不影响通信的同时,检测出采集的IED设备61850标准信息属性与远动装置转换后的规约信息属性(如104规约属性)一致,导致电力调度通信的不通畅。
发明内容
本发明的目的是提供一种智能站61850与远动104规约集成测试方法,用于智能站中两种不同规约通信时的集成测试,能够保证两种规约转换后变电站信息属性一致,不影响变电站自动化系统的正常通信。
一种智能站61850与远动104规约集成测试方法,其特别之处在于,包括如下步骤:
1)IEC61850系统与104系统同时与调度主站进行通信;
2)专业计算机通过镜像口监听方式分别获取IEC61850系统和104系统的通道数据;
3)通过建立IEC61850信息模型,解析步骤1)监听获取的IEC61850系统的通道数据,并以树型结构详细列出变电站信息属性;
4)通过电力规约分析软件解析步骤1)监听获取的104系统的通道数据,并建立实时数据库保存解析后的104规约信息属性;
5)采用比对器对步骤2)解析的IEC61850系统信息模型的变电站信息属性与步骤2)解析的104系统信息属性进行比对映射,选出完全匹配与不匹配信息属性;
6)通过建立公共数据库保存步骤4)选出映射后的完全匹配的信息属性,并生成配置IED描述文件供IEC61850系统调用;
7)输出不匹配信息属性结果报告,标示为不通过;
8)以步骤7)出生的结果报告为修改依据对IEC61850系统和104系统进行修改,回到步骤1)继续进行测试,直到步骤7)输出标示为通过的结果报告,完成IEC61850与远动104规约集成测试。
步骤1)中的调度主站是模拟的调度主站,具有与真实调度主站相同的功能,并支持同参数下同时进行双通道通信,其中,IEC61850系统模拟的智能站设备直接与模拟的调度主站进行通信,104系统通过将智能站设备信息采集后以104规约转发给模拟的调度主站。
步骤2)中获取通道数据是通过镜像口监听方式来进行,实现报文复制抓包,从而不对测试中业务数据流产生任何影响。
步骤4)中所使用的电力规约分析软件支持104规约分析功能。
步骤6)中生成配置IED描述文件,将自动导入IEC61850系统,从而方便系统建模。
步骤7)输出的比对结果是作为中间修改参照表存在,步骤8)中输出的标示为通过的结果报告将作为本次测试完成的报告,供日后佐证。
本发明的方法适用于同时采用IEC61850标准协议和104规约进行通信的变电站自动化系统,可实现系统不同规约的正确映射,保证变电站自动化系统运行正常。本发明方法的有益效果还包括:1、研制出了一套IEC61850与远动104规约集成测试方法;2、将研制的集成测试方法使用到变电站自动化系统中,帮助变电站自动化系统在完成IEC104规约到IEC61850标准转化期间的完美过渡;3、采用镜像口监听方式获取通道信息,不对正在运行的自动化系统造成影响,保证系统的安全运行;4、运用比对器对映射参数进行比对,输出不匹配项,并发出告警信息便于系统检查;5、本集成测试方法具有模拟调控主站前置通信功能,与被测设备通信IEC104,并能解析遥信、遥测值并具有遥控、遥调功能;6、本集成测试方法具有IEC61850的MMS服务的客户端功能,能采集多台IED设备数据,并能解析遥测、遥信数据;7、本集成测试方法可对子站装置的通信正确性及延时性进行测试;8、本集成测试方法测试包括61850取代方法,通过替代值对仿真IED设备的遥测及遥信数据进行设值。
附图说明
附图1为本发明方法的流程图。
具体实施方式
由于两种规约的集成测试采用公共数据库方式保存变电站信息属性,建立IEC61850的信息模型,将执行104的信息属性解析后存入104规约实时数据库,IEC61850信息模型的信息属性与存入104规约实时数据库的104信息属性进行映射,映射后的变电站信息保存至公共数据库。映射过程采用参数比对器对不通过规约的信息属性进行比较,完全匹配则保存入库,不匹配则报出异常并输出异常报告供检测。
实施例1:
步骤1:IEC61850系统与104系统同时与调度主站进行通信;
步骤2:专业计算机通过镜像口监听方式分别获取IEC61850系统和104系统的通道数据;
步骤3:通过建立IEC61850信息模型,解析步骤1)监听获取的IEC61850系统的通道数据,并以树型结构详细列出变电站信息属性;
步骤4:通过电力规约分析软件解析步骤1)监听获取的104系统的通道数据,并建立实时数据库保存解析后的104规约信息属性;
步骤5:采用比对器对步骤2)解析的IEC61850系统信息模型的变电站信息属性与步骤2)解析的104系统信息属性进行比对映射,选出完全匹配与不匹配信息属性;
步骤6:通过建立公共数据库保存步骤4)选出映射后的完全匹配的信息属性,并生成配置IED描述文件供IEC61850系统调用;
步骤7:输出不匹配信息属性结果报告,标示为不通过;
步骤8:以步骤7)出生的结果报告为修改依据对IEC61850系统和104系统进行修改,回到步骤1)继续进行测试,直到步骤7)输出标示为通过的结果报告,完成IEC61850与远动104规约集成测试。
Claims (1)
1.一种智能站61850与远动104规约集成测试方法,其特征在于,包括如下步骤:
1)IEC61850系统与104系统同时与调度主站进行通信;
2)专业计算机通过镜像口监听方式分别获取IEC61850系统和104系统的通道数据;
3)通过建立IEC61850信息模型,解析步骤2)监听获取的IEC61850系统的通道数据,并以树型结构详细列出变电站信息属性;
4)通过电力规约分析软件解析步骤2)监听获取的104系统的通道数据,并建立实时数据库保存解析后的104规约信息属性;
5)采用比对器对步骤3)解析的IEC61850系统信息模型的变电站信息属性与步骤4)解析的104系统信息属性进行比对映射,选出完全匹配与不匹配信息属性;
6)通过建立公共数据库保存步骤5)选出映射后的完全匹配的信息属性,并生成配置IED描述文件供IEC61850系统调用;
7)输出不匹配信息属性结果报告,标示为不通过;
8)以步骤7)出生的结果报告为修改依据对IEC61850系统和104系统进行修改,回到步骤2)继续进行测试,直到步骤7)输出标示为通过的结果报告,完成IEC61850与远动104规约集成测试;
步骤1)中的调度主站是模拟的调度主站,具有与真实调度主站相同的功能,并支持同参数下同时进行双通道通信,其中,IEC61850系统模拟的智能站设备直接与模拟的调度主站进行通信,104系统通过将智能站设备信息采集后以104规约转发给模拟的调度主站;
步骤2)中获取通道数据是通过镜像口监听方式来进行,实现报文复制抓包,从而不对测试中业务数据流产生任何影响;
步骤4)中所使用的电力规约分析软件支持104规约分析功能;
步骤6)中生成配置IED描述文件,将自动导入IEC61850系统,从而方便系统建模;
步骤7)输出的比对结果是作为中间修改参照表存在,步骤8)中输出的标示为通过的结果报告将作为本次测试完成的报告,供日后佐证。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410232488.0A CN104052633B (zh) | 2014-05-29 | 2014-05-29 | 智能站61850与远动104规约集成测试方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410232488.0A CN104052633B (zh) | 2014-05-29 | 2014-05-29 | 智能站61850与远动104规约集成测试方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104052633A CN104052633A (zh) | 2014-09-17 |
CN104052633B true CN104052633B (zh) | 2017-12-01 |
Family
ID=51505017
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410232488.0A Expired - Fee Related CN104052633B (zh) | 2014-05-29 | 2014-05-29 | 智能站61850与远动104规约集成测试方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104052633B (zh) |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104363214B (zh) * | 2014-11-03 | 2017-08-04 | 许继电气股份有限公司 | 一种IEC61850规约和TCPModbus规约可配置的转换方法 |
CN106301833A (zh) * | 2015-05-22 | 2017-01-04 | 上海研电电力科技有限公司 | 一种变电站调度信息测试方法 |
CN105227402B (zh) * | 2015-09-29 | 2019-04-26 | 国网福建省电力有限公司 | 一种智能变电站多规约通信的集成一体化测试方法 |
CN105262230A (zh) * | 2015-11-26 | 2016-01-20 | 国网辽宁省电力有限公司大连供电公司 | 新建变电站调试用便携式调度主站系统的组建方法 |
CN106100932B (zh) * | 2016-07-01 | 2019-03-15 | 国网山东省电力公司博兴县供电公司 | 一种基于数据共享的变电站数据处理系统 |
CN106532958A (zh) * | 2016-12-22 | 2017-03-22 | 国网福建省电力有限公司 | 一种基于iec61850规约的变电站ied设备模拟方法 |
CN106708742B (zh) * | 2017-02-20 | 2020-06-23 | 许继集团有限公司 | 一种通讯规约模块测试架构的自动化测试方法及装置 |
CN107566370A (zh) * | 2017-09-05 | 2018-01-09 | 江苏电力信息技术有限公司 | 一种智能电网报文传输方法 |
CN110417688A (zh) * | 2018-04-26 | 2019-11-05 | 广东电网有限责任公司 | 一种调度自动化系统多通道报文分析处理系统及方法 |
CN108879949A (zh) * | 2018-06-26 | 2018-11-23 | 国网福建省电力有限公司 | 一种配电网cps主站与终端的测试方法 |
CN109713791B (zh) * | 2018-12-21 | 2023-02-28 | 国网四川省电力公司电力科学研究院 | 智能电网遥控命令异常的诊断方法 |
CN114401323B (zh) * | 2021-12-09 | 2024-02-13 | 国网江苏省电力有限公司苏州供电分公司 | 变电站通信规约全映射分析模拟转换装置 |
CN114221371A (zh) * | 2021-12-14 | 2022-03-22 | 广东电网有限责任公司 | 一种直流换流站与智能交流站跨站通讯系统及方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1976218A1 (en) * | 2007-03-30 | 2008-10-01 | ABB Technology AG | Method of configuring an intelligent electronic device |
CN102164058A (zh) * | 2011-05-13 | 2011-08-24 | 北京航空航天大学 | 基于iec61850标准变电站通信网络与系统测试方法 |
CN102570618A (zh) * | 2012-02-24 | 2012-07-11 | 安徽省电力公司芜湖供电公司 | 一种变电站双规约监控系统及其方法 |
CN102880792A (zh) * | 2012-08-31 | 2013-01-16 | 浙江省电力公司 | 一种基于iec标准的常规变电站的动态建模方法 |
CN103151840A (zh) * | 2013-03-12 | 2013-06-12 | 广东易事特电源股份有限公司 | 一种iec61850系统与非iec61850系统的通信方法和装置 |
CN103414251A (zh) * | 2013-08-26 | 2013-11-27 | 南京匹瑞电气科技有限公司 | 一种基于iec61850的变电站网络通信仿真系统 |
-
2014
- 2014-05-29 CN CN201410232488.0A patent/CN104052633B/zh not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1976218A1 (en) * | 2007-03-30 | 2008-10-01 | ABB Technology AG | Method of configuring an intelligent electronic device |
CN102164058A (zh) * | 2011-05-13 | 2011-08-24 | 北京航空航天大学 | 基于iec61850标准变电站通信网络与系统测试方法 |
CN102570618A (zh) * | 2012-02-24 | 2012-07-11 | 安徽省电力公司芜湖供电公司 | 一种变电站双规约监控系统及其方法 |
CN102880792A (zh) * | 2012-08-31 | 2013-01-16 | 浙江省电力公司 | 一种基于iec标准的常规变电站的动态建模方法 |
CN103151840A (zh) * | 2013-03-12 | 2013-06-12 | 广东易事特电源股份有限公司 | 一种iec61850系统与非iec61850系统的通信方法和装置 |
CN103414251A (zh) * | 2013-08-26 | 2013-11-27 | 南京匹瑞电气科技有限公司 | 一种基于iec61850的变电站网络通信仿真系统 |
Non-Patent Citations (6)
Title |
---|
IEC60870-5-104 规约在配电自动化系统的应用与测试;陈众等;《电气技术》;20120315(第2012年第3期);第58-61页 * |
IEC61850互操作测试分析;陈炯聪等;《电力系统保护与控制》;20090801;第37卷(第15期);第121-123页 * |
变电站通信网络和系统第10部分:一致性测试;中华人民共和国国家发展和改革委员会;《中华人民共和国电力行业标准》;20061217;全文 * |
数据集中器方式下 IEC 61850 新系统与常规系统的相互转换;徐鹤勇等;《电网技术》;20071231;第31卷(第增刊2期);第315-317页 * |
智能变电站中IEC60870-5-104到IEC61850的映射互通研究;宋妍等;《陕西电力》;20120820(第2012年第08期);第29-33页 * |
电力规约通用测试系统的研究与实现;于海;《中国优秀硕士学位论文全文数据库》;20140215(第2014年02期);C042-340 * |
Also Published As
Publication number | Publication date |
---|---|
CN104052633A (zh) | 2014-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104052633B (zh) | 智能站61850与远动104规约集成测试方法 | |
CN108400908B (zh) | 变电站监控信息自动验收方法 | |
US20170169144A1 (en) | Method and device for generating engineering topology of digital substation | |
CN102957204B (zh) | 一种配电网终端的智能仿真方法及系统 | |
CN104483842B (zh) | 一种调控一体自动化主站比对方法 | |
CN104391244B (zh) | 继电保护设备闭环检验方法和系统 | |
CN107783809A (zh) | 一种智能设备控制面板远程渲染方法 | |
CN108923953A (zh) | 一种电力远动机调试用的虚拟主站系统 | |
CN108767818B (zh) | 一种基于虚拟保信主站的继电保护调试系统及调试方法 | |
CN103905275A (zh) | 基于iec61850取代服务的电力远动装置测试方法 | |
CN109873497A (zh) | 一种基于智能验收装置的配电主站与终端自动联调验收方法 | |
CN204291050U (zh) | 一种调度监控信息核对系统 | |
CN104375038A (zh) | 一种可扩展的闭环同步配电自动化终端检测平台及方法 | |
CN107749811A (zh) | 一种基于配电主站的配电终端接入自适应调试分析方法 | |
CN109495290B (zh) | 一种运维系统主子站交互方法和系统 | |
CN110958327A (zh) | 一种智能变电站远程测试系统及方法 | |
CN113419920B (zh) | 物联管理平台仿真测试系统联调测试过程实时监控方法 | |
CN109752607A (zh) | 一种牵引变流器故障诊断的方法及系统 | |
CN105243116A (zh) | 智能变电站电子设备能力描述文件的自动生成方法 | |
CN112737115A (zh) | 一种针对变电站的主站和厂站的遥信联调解耦方法 | |
CN108595390B (zh) | 智能变电站scd与ied参数一致性的校验方法 | |
CN104698374A (zh) | 一种提高自动化继电保护测试仪测试效率和准确度的方法 | |
CN107204887A (zh) | 一种scd文件与保护装置cid文件一致性测试系统及方法 | |
CN112187582B (zh) | 智能变电站过程层交换机端口流量监测预告警系统及方法 | |
CN207601245U (zh) | 一种配电终端自动化检测的组网测试系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171201 Termination date: 20190529 |