CN104047620A - 井下巷道大动水堵水方法 - Google Patents

井下巷道大动水堵水方法 Download PDF

Info

Publication number
CN104047620A
CN104047620A CN201410281845.2A CN201410281845A CN104047620A CN 104047620 A CN104047620 A CN 104047620A CN 201410281845 A CN201410281845 A CN 201410281845A CN 104047620 A CN104047620 A CN 104047620A
Authority
CN
China
Prior art keywords
iron chains
tunnel
permeable
boring
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410281845.2A
Other languages
English (en)
Inventor
王铁记
关永强
任明环
王君现
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIZHONG ENERGY FENGFENG GROUP Co Ltd
Original Assignee
JIZHONG ENERGY FENGFENG GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIZHONG ENERGY FENGFENG GROUP Co Ltd filed Critical JIZHONG ENERGY FENGFENG GROUP Co Ltd
Priority to CN201410281845.2A priority Critical patent/CN104047620A/zh
Publication of CN104047620A publication Critical patent/CN104047620A/zh
Pending legal-status Critical Current

Links

Abstract

本发明公开一种井下巷道大动水堵水方法,其工艺步骤为:⑴首先根据巷道设计图确定巷道位置、走向及规格形状;⑵在地面沿巷道走向,向透水巷道钻多个钻孔,孔与孔之间间隔一定距离,并在钻孔的上口设置有孔口管;⑶从任意一个钻孔中向透水巷道内试投骨料确定突水巷道动力条件,确定投放铁链的数量;⑷从最下游的钻孔向透水巷道内投放铁链,使铁链在透水巷道内堆积成山状;⑸从紧靠最下游的钻孔依次在上游钻孔中投放大、小骨料,使大、小骨料与铁链形成滤水骨架,直至形成堵水帷幕;⑹在堵水帷幕建成后从最上游钻孔向透水巷道内注浆即可将突水堵住;⑺待注浆凝固后即可将铁链提出。具有堵水快,节约材料的优点。

Description

井下巷道大动水堵水方法
技术领域
 本发明涉及一种煤矿井下透水后的抢险救灾方法,尤其是一种井下巷道大动水堵水方法。
背景技术
煤矿井下突水事故时有发生,给煤矿生产、安全和经营造成重大损失。以往堵水是根据地质资料从地面打钻找到出水巷道位置,通过钻孔往出水巷道注入骨料(大、小石子、大豆、海带、玻璃水、水泥等),依靠骨料沉淀、堆积、逐步将管道流建造成渗透流,建造骨料帷幕,然后注浆封堵截流。但当由于出水量过大(每分钟流量80~90m3)大量骨料注入后被水流冲走,浪费了大量骨料和时间,封堵效果差,也对封堵后巷道清淤工作造成困难。因此,研究一种能够快速将出现特大突水的煤矿井下巷道封堵的井下巷道大动水堵水方法,是目前需要解决的技术问题。
发明内容
本发明所要解决的技术问题是提供一种能够快速将出现特大突水的煤矿井下巷道封堵的井下巷道大动水堵水方法。
本发明解决其技术问题的技术方案是:
井下巷道大动水堵水方法,其特征在于,其工艺步骤为:
⑴首先根据巷道设计图确定巷道位置、走向及规格形状;
在地面沿巷道走向,向透水巷道钻多个钻孔,孔与孔之间间隔一定距离,并在钻孔的上口设置有孔口管;(其中最下游的钻孔为投放铁链孔,往上游紧靠投放铁链孔的为大骨料投放孔、再往上游依次为小骨料投放孔和注浆孔)。
⑶从任意一个钻孔中向透水巷道内试投骨料确定突水巷道动力条件,确定投放铁链的数量;
⑷从最下游的钻孔向透水巷道内投放铁链,使铁链在透水巷道内堆积成山状;
⑸从紧靠最下游的钻孔依次在上游钻孔中投放大、小骨料,使大、小骨料与铁链形成滤水骨架,直至形成堵水帷幕;所述的大、小骨料为大、小石子。
⑹在堵水帷幕建成后从最上游钻孔向透水巷道内注浆即可将突水堵住;
待注浆凝固后即可将铁链提出。
所述的铁链为在施工过程中由多段铁链焊接在一起的整根铁链。
所述的铁链投放步骤为:首先平整最下游的钻孔周围的场地,场地平整好后搭设三角架和安装绞车,然后在三角架上安装链轮,在绞车滚筒上固定牵引用钢丝绳,钢丝绳的长度与矿用铁链的长度匹配,在钢丝绳的端部安装挂钩,用挂钩勾住铁链的尾端,将铁链的首端放进孔口管内,启动绞车将铁链往透水巷道送,待整根铁链即将送完时,用垫叉棍将铁链担在孔口管上,摘掉挂钩,用电焊机将下一个铁链的首端与上一根铁链的尾端焊接,用挂钩挂住下一根铁链的尾端,启动绞车继续将铁链往透水巷道送,循环以上步骤,直至铁链在透水巷道内堆积成山状(铁链能投入多少就投入多少,巷道内铁链条是否堆满巷道以链条绷紧度作为初步判断,并以投链数量作校核);最后一根铁链系于孔口管,以便日后续投或提拉链条。
所述的绞车为11KW绞车,钢丝绳为 4#钢丝绳,钢丝绳的长度为40-100m。
本发明的原理:
利用废旧工业铁链比重大,易堆积,阻水力小,堆积后呈网状空隙,既阻水又不易被水冲走的特点,在出水巷道中形成一个网状透水体,该网状透水体既能减少一部分水的流量又能拦截由上游钻孔投放的石子骨料,投放的石子骨料由大(直径240mm  )到小(直径5mm  ),将出水巷道堵死,然后注浆加固,彻底将出水巷道封闭。
本发明一是利用透巷钻孔依层次投放工业铁链和石子构成滤层堵水塞的骨架,将管道流逐渐改变成渗透流以利注浆胶结骨架;二是工业铁链因其能滤水而又能减小高速水流动能冲击便于集中堆(盘)放,并且单根(每根40-100m)连接成整体便于在孔口自如牵放而改变骨架形状和长(高)度。
与现有技术相比,利用工业铁链在突水巷道快速建成堵水帷幕,达到了快速截流堵水的目的,从而改变了松散骨料(砂石甚至铁块铁球)在特大动水中长距离充填的堵水历史,避免了原来充填各粒级石子被动水大量冲走消耗大量堵水材料又起不到堵水作用的弊病,节约大量堵水材料,尤其是对于大动水高承压条件下使用该技术效果更明显。
附图说明
图1是本发明钻孔位置布局图;
图2是图1的A-A向剖面图;
图3是图1的B-B向剖面图。
具体实施方式
如图所示,井下巷道大动水堵水方法,其特征在于,其工艺步骤为:
⑴首先根据巷道设计图确定巷道位置、走向及规格形状;
在地面沿巷道走向,向透水巷道钻多个钻孔,孔与孔之间间隔一定距离,并在钻孔的上口设置有孔口管;
⑶从任意一个钻孔中向透水巷道内试投骨料确定突水巷道动力条件,确定投放铁链的数量;
⑷从最下游的钻孔向透水巷道内投放铁链,使铁链在透水巷道内堆积成山状;
⑸从紧靠最下游的钻孔依次在上游钻孔中投放大、小骨料,使大、小骨料与铁链形成滤水骨架,直至形成堵水帷幕;
⑹在堵水帷幕建成后从最上游钻孔向透水巷道内注浆即可将突水堵住;
待注浆凝固后即可将铁链提出。
所述的大、小骨料为大、小石子。
所述的铁链为在施工过程中由多段铁链焊接在一起的整根铁链。
所述的铁链投放步骤为:首先平整最下游的钻孔周围的场地,场地平整好后搭设三角架和安装绞车,然后在三角架上安装链轮,在绞车滚筒上固定牵引用钢丝绳,钢丝绳的长度与矿用铁链的长度匹配,在钢丝绳的端部安装挂钩,用挂钩勾住铁链的尾端,将铁链的首端放进孔口管内,启动绞车将铁链往透水巷道送,待整根铁链即将送完时,用垫叉棍将铁链担在孔口管上,摘掉挂钩,用电焊机将下一个铁链的首端与上一根铁链的尾端焊接,用挂钩挂住下一根铁链的尾端,启动绞车继续将铁链往透水巷道送,循环以上步骤,直至铁链在透水巷道内堆积成山状;最后一根铁链系于孔口管,以便日后续投或提拉链条。所述的绞车为11KW绞车,钢丝绳为 4#钢丝绳,钢丝绳的长度为40-100m。

Claims (5)

1. 井下巷道大动水堵水方法,其特征在于,其工艺步骤为:
⑴首先根据巷道设计图确定巷道位置、走向及规格形状;
在地面沿巷道走向,向透水巷道钻多个钻孔,孔与孔之间间隔一定距离,并在钻孔的上口设置有孔口管;
⑶从任意一个钻孔中向透水巷道内试投骨料确定突水巷道动力条件,确定投放铁链的数量;
⑷从最下游的钻孔向透水巷道内投放铁链,使铁链在透水巷道内堆积成山状;
⑸从紧靠最下游的钻孔依次在上游钻孔中投放大、小骨料,使大、小骨料与铁链形成滤水骨架,直至形成堵水帷幕;
⑹在堵水帷幕建成后从最上游钻孔向透水巷道内注浆即可将突水堵住;
待注浆凝固后即可将铁链提出。
2.根据权利要求1所述的井下巷道大动水堵水方法,其特征在于,所述的大、小骨料为大、小石子。
3. 根据权利要求1所述的井下巷道大动水堵水方法,其特征在于,所述的铁链为在施工过程中由多段铁链焊接在一起的整根铁链。
4. 根据权利要求1所述的井下巷道大动水堵水方法,其特征在于,所述的铁链投放步骤为:首先平整最下游的钻孔周围的场地,场地平整好后搭设三角架和安装绞车,然后在三角架上安装链轮,在绞车滚筒上固定牵引用钢丝绳,钢丝绳的长度与矿用铁链的长度匹配,在钢丝绳的端部安装挂钩,用挂钩勾住铁链的尾端,将铁链的首端放进孔口管内,启动绞车将铁链往透水巷道送,待整根铁链即将送完时,用垫叉棍将铁链担在孔口管上,摘掉挂钩,用电焊机将下一个铁链的首端与上一根铁链的尾端焊接,用挂钩挂住下一根铁链的尾端,启动绞车继续将铁链往透水巷道送,循环以上步骤,直至铁链在透水巷道内堆积成山状;最后一根铁链系于孔口管,以便日后续投或提拉链条。
5. 根据权利要求4所述的井下巷道大动水堵水方法,其特征在于,所述的
绞车为11KW绞车,钢丝绳为 4#钢丝绳,钢丝绳的长度为40-100m。
CN201410281845.2A 2014-06-23 2014-06-23 井下巷道大动水堵水方法 Pending CN104047620A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410281845.2A CN104047620A (zh) 2014-06-23 2014-06-23 井下巷道大动水堵水方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410281845.2A CN104047620A (zh) 2014-06-23 2014-06-23 井下巷道大动水堵水方法

Publications (1)

Publication Number Publication Date
CN104047620A true CN104047620A (zh) 2014-09-17

Family

ID=51500971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410281845.2A Pending CN104047620A (zh) 2014-06-23 2014-06-23 井下巷道大动水堵水方法

Country Status (1)

Country Link
CN (1) CN104047620A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105114029A (zh) * 2015-08-19 2015-12-02 中煤科工集团西安研究院有限公司 一种矿井巷道内封闭不良钻孔的堵水方法
CN107227744A (zh) * 2017-07-28 2017-10-03 中国水利水电第十工程局有限公司 一种突水断层带堵漏的施工方法
CN109442130A (zh) * 2018-12-24 2019-03-08 北京市市政工程研究院 排水管道口袋形堵水装置与施工安装结构及堵水拆堵方法
CN110847850A (zh) * 2019-10-22 2020-02-28 冀中能源峰峰集团有限公司 一种井下高承压大流量失控水文钻孔封堵系统及方法
CN111139853A (zh) * 2019-12-24 2020-05-12 同济大学 一种高流速岩溶管道挂网、钩石、注浆联合堵水方法
CN115141611A (zh) * 2021-03-31 2022-10-04 中国石油化工股份有限公司 钻井用堵剂及其制备方法和应用

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101526003A (zh) * 2009-03-23 2009-09-09 中国水电顾问集团华东勘测设计研究院 高压大流量稳定地下涌水封堵处理方法
CN102561720A (zh) * 2012-02-17 2012-07-11 葛洲坝集团试验检测有限公司 一种动水条件下的封堵止漏方法
CN102705005A (zh) * 2012-04-01 2012-10-03 中国矿业大学(北京) 定向导流注浆封堵矿井突水技术
CN103437790A (zh) * 2013-08-23 2013-12-11 西安建筑科技大学 一种地下水封堵方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101526003A (zh) * 2009-03-23 2009-09-09 中国水电顾问集团华东勘测设计研究院 高压大流量稳定地下涌水封堵处理方法
CN102561720A (zh) * 2012-02-17 2012-07-11 葛洲坝集团试验检测有限公司 一种动水条件下的封堵止漏方法
CN102705005A (zh) * 2012-04-01 2012-10-03 中国矿业大学(北京) 定向导流注浆封堵矿井突水技术
CN103437790A (zh) * 2013-08-23 2013-12-11 西安建筑科技大学 一种地下水封堵方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
岳卫振等: "牛儿庄矿奥灰溃水治理中投注骨料工艺技术", 《煤炭科学技术》 *
王铁记等: "短距离小断面大流量动水巷道快速截流技术", 《安全高效煤矿地质保障技术及应用》 *
王铁记等: "短距离小断面大流量动水巷道快速截流技术", 《安全高效煤矿地质保障技术及应用》, 1 August 2007 (2007-08-01), pages 236 - 238 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105114029A (zh) * 2015-08-19 2015-12-02 中煤科工集团西安研究院有限公司 一种矿井巷道内封闭不良钻孔的堵水方法
CN105114029B (zh) * 2015-08-19 2017-06-13 中煤科工集团西安研究院有限公司 一种矿井巷道内封闭不良钻孔的堵水方法
CN107227744A (zh) * 2017-07-28 2017-10-03 中国水利水电第十工程局有限公司 一种突水断层带堵漏的施工方法
CN109442130A (zh) * 2018-12-24 2019-03-08 北京市市政工程研究院 排水管道口袋形堵水装置与施工安装结构及堵水拆堵方法
CN110847850A (zh) * 2019-10-22 2020-02-28 冀中能源峰峰集团有限公司 一种井下高承压大流量失控水文钻孔封堵系统及方法
CN110847850B (zh) * 2019-10-22 2022-03-25 冀中能源峰峰集团有限公司 一种井下高承压大流量失控水文钻孔封堵系统及方法
CN111139853A (zh) * 2019-12-24 2020-05-12 同济大学 一种高流速岩溶管道挂网、钩石、注浆联合堵水方法
CN111139853B (zh) * 2019-12-24 2021-03-30 同济大学 一种高流速岩溶管道挂网、钩石、注浆联合堵水方法
CN115141611A (zh) * 2021-03-31 2022-10-04 中国石油化工股份有限公司 钻井用堵剂及其制备方法和应用

Similar Documents

Publication Publication Date Title
CN104047620A (zh) 井下巷道大动水堵水方法
CN101701526B (zh) 一种采空区袋式充填方法
CN104405436B (zh) 一种提高矿体充填接顶率的方法
CN102979535B (zh) 一种隧道衬砌用泄水式管片
CN102777182B (zh) 大采高工作面快速末采方法
CN112855223A (zh) 一种煤巷穿越采空区壁后-超前帷幕空间一体化注浆方法
CN103510957A (zh) 一种组合式石门揭煤方法
CN208294566U (zh) 一种高浓度尾砂胶结充填金属网结构挡墙
CN105804754B (zh) 一种煤层为主含水层矿井井筒揭煤方法
CN102518436A (zh) 煤矿巷道掘进时构造型冲击地压防治方法
CN105089693B (zh) 一种提高沿空留巷墙体接顶方法
CN102561950A (zh) 一种对地层空洞内填充的骨料进行注浆固结的工艺及喷射钻头
CN110630321A (zh) 一种采空区井上充填设备及其方法
CN106050300A (zh) 一种用于上向进路超高欠采的充填接顶方法
CN104863588A (zh) 超前预设墩柱沿空留巷方法
CN106381405A (zh) 一种稀土矿山集液系统及方法
CN106223978A (zh) 整体下行式金属模板施工煤仓施工工艺
CN204002912U (zh) 一种高溜井防堵塞装置
CN104234716B (zh) 袋装围堰充填采矿法
CN103498478B (zh) 岩石坝基帷幕灌浆施工方法
CN103061767B (zh) 下向水平分层干式充填采矿法
CN105937400B (zh) 一种一次掘进留设双巷采掘作业生产线
CN106337687A (zh) 矿山斜溜井便捷式分段支护方法
CN106677806A (zh) 一种用于井下巷道、隧道的管式棚架支护结构
CN103244121A (zh) 一种有轨与无轨耦合的底部出矿系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140917