CN104036349A - System and method for preventing misoperation in electric power system by using two-dimension codes - Google Patents

System and method for preventing misoperation in electric power system by using two-dimension codes Download PDF

Info

Publication number
CN104036349A
CN104036349A CN201410237192.8A CN201410237192A CN104036349A CN 104036349 A CN104036349 A CN 104036349A CN 201410237192 A CN201410237192 A CN 201410237192A CN 104036349 A CN104036349 A CN 104036349A
Authority
CN
China
Prior art keywords
quick response
response code
prevent
maloperation
operation order
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410237192.8A
Other languages
Chinese (zh)
Inventor
邢涛
段君寨
张现清
范座堂
甄子替
耿道波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410237192.8A priority Critical patent/CN104036349A/en
Publication of CN104036349A publication Critical patent/CN104036349A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the field of a two-dimension code application system, in particular to a system and a method for preventing misoperation in an electric power system by using two-dimension codes. The method for preventing the misoperation in the electric power system by using the two-dimension codes sequentially comprises the following steps that: (1) a two-dimension code database is manufactured; (2) two-dimension code pictures are extracted and manufactured; (3) the two-dimension code pictures are pasted to corresponding positions of equipment; (4) a mobile operation order system is built; (5) an operation order is manufactured; (6) two-dimension code information of the equipment is implanted into relevant items of the operation order; (7) the operation order is pushed to a mobile terminal; and (8) mobile terminal equipment is used for scanning the two-dimension codes of the equipment. The system and the method provided by the invention have the advantages that the functionality is high; the operation by operators is convenient; great importance is realized on safety risk elimination, personal injury and equipment damage avoidance and safe operation guarantee; and the system and the method are suitable to be widely popularized and applied.

Description

A kind of system and method that uses Quick Response Code to prevent maloperation in electric system
Background technology
Electric system prevents that maloperation from being the problem of a lot of production safety management personnel hammer aways for many years, is a complicated comprehensive task.At present for the research that prevents maloperation related content be mainly confined to following some: (1) is based on operation order part; (2) based on hardware system; (3) carry out rules and regulations (4) and pay attention to personnel's quality.
At present a lot of units strengthen supervision from filling in the aspect such as review operations ticket, simulation preview, have strengthened to a certain extent the execution of operating process.But cannot fundamentally eliminate the maloperation possibility that human factor causes.
Prior art also cannot be from operating process the elimination maloperation hidden danger of essence, cannot realize " prevent from missing and divide, miss combination switch " at all, " prevent on-load drawing disconnecting link ", " prevent live connection of ground wire (closing grounding switch) ", " prevent that line with ground (grounding switch) from closing a floodgate ", the electric "five-proof" function of " preventing mistakenly entering charged chamber ".
Summary of the invention
For solve in prior art, exist cannot be from operating process the elimination maloperation hidden danger of essence, cannot realize " prevent from missing and divide, miss combination switch " at all, " prevent on-load drawing disconnecting link ", " prevent live connection of ground wire (closing grounding switch) ", " prevent that line with ground (grounding switch) from closing a floodgate ", the electric "five-proof" function of " preventing mistakenly entering charged chamber ".The invention provides a kind of system and method that uses Quick Response Code to prevent maloperation in electric system, in the operation order that can provide in prior art, increase the application of Quick Response Code, contact mobile terminal is convenient for carrying, advantage easy to use, realize error free in power system operation process, fundamentally realize and " prevent mistake point, mistake combination switch ", " prevent on-load drawing disconnecting link ", " prevent live connection of ground wire (closing grounding switch) ", " prevent that line with ground (grounding switch) from closing a floodgate ", the electric "five-proof" function that " prevents mistakenly entering charged chamber ".
The invention provides in a kind of electric system and use Quick Response Code to prevent the method for maloperation, it comprises the following steps successively:
(1) make Quick Response Code database;
(2) extract and make two-dimension code image;
(3) paste equipment corresponding site;
(4) set up move operation bill system;
(5) make operation order;
(6) implanting device 2 D code information in operation order relevant entry;
(7) operation order is pushed to mobile terminal;
(8) utilize mobile terminal device scanning device Quick Response Code;
(9) operation order information and Quick Response Code are carried out to verification.
Wherein preferably, in step (1), described making Quick Response Code database is to make Quick Response Code according to relevant device title, numbering, particular keywords, current operation clause.
In above-mentioned arbitrary scheme, preferably, in step (2), described making two-dimension code image can single making or batch making.
In above-mentioned arbitrary scheme, preferably, in step (2), described two-dimension code image comprises vector format and picture format.
In above-mentioned arbitrary scheme, preferably, described vector format comprises .wmf form.
In above-mentioned arbitrary scheme, preferably, described picture format comprises .png form.
In above-mentioned arbitrary scheme, preferably, in step (4), the described move operation bill system of setting up is taking existing operation ticket management system as exploitation basis.
In above-mentioned arbitrary scheme, preferably, in step (5), described operation order comprises facility information and clause information.
In above-mentioned arbitrary scheme, preferably, in step (5), described making operation order is to put to make by the key operation of clear and definite operating process.
In above-mentioned arbitrary scheme, preferably, the key operation point of described clear and definite operating process is according to electric "five-proof" requirement, for ensureing the committed step of safe operation.
In above-mentioned arbitrary scheme, preferably, in step (6), described implanting device 2 D code information comprises manual implantation and automatically implants.
In above-mentioned arbitrary scheme, preferably, described manual implantation Quick Response Code refers to the editor space by interface, in the place that need to implant Quick Response Code by implanting manually.
In above-mentioned arbitrary scheme preferably, described automatic implantation Quick Response Code comprises in actual applications, some names that need to implant the key operation of Quick Response Code have regularity, by decompose and mate these keywords in Quick Response Code operation steps, realize the intelligence of certain operation 2 D code information and implant, more meet respective rule.
In above-mentioned arbitrary scheme, preferably, in step (7), described push operation ticket is to connect by wireless network and described mobile terminal, then uploads, down operation ticket.
In above-mentioned arbitrary scheme, preferably, in step (7), described mobile terminal comprises IPAD.
In above-mentioned arbitrary scheme, preferably, in step (8), described scanning is to scan by the Quick Response Code scanner on described mobile terminal.
In above-mentioned arbitrary scheme, preferably, described scanning comprises that scanning sticks on the two-dimension code image on equipment on the spot in advance.
In above-mentioned arbitrary scheme preferably, in step (9), described verification comprises unique correspondence of utilizing Quick Response Code, carry out verification by described device name additional on the facility information on described operation order and described Quick Response Code, the information unlocking operation ticket that coincide, realize and prevent from going to the wrong way interval in logic, then by the clause information of described operation order and the current operation clause verification of described Quick Response Code, realize logic anti-misoperation locking, if information is coincide, this operation clause of release, if information misfits, prompting mistake, and lock operation ticket entry.
The present invention also provides in a kind of electric system and uses Quick Response Code to prevent the system of maloperation, comprise Quick Response Code, operation order, mobile terminal, equipment on the spot, it is characterized in that, in described electric system, use Quick Response Code to prevent that the system of maloperation from also comprising Quick Response Code database, move operation bill system, operation order.
In above-mentioned arbitrary scheme, preferably, described system comprises with lower module:
Module (a), for making Quick Response Code database;
Module (b), for extracting and make two-dimension code image;
Module (c), for pasting equipment corresponding site;
Module (d), for setting up move operation bill system;
Module (e), for making operation order;
Module (f), at operation order relevant entry implanting device 2 D code information;
Module (g), for being pushed to mobile terminal by operation order;
Module (h), for utilizing mobile terminal device scanning device Quick Response Code;
Module (i), for operation order information and Quick Response Code are carried out to verification.
In above-mentioned arbitrary scheme, preferably, in module (a), described making Quick Response Code database is to make Quick Response Code according to relevant device title, numbering, particular keywords, current operation clause.
In above-mentioned arbitrary scheme, preferably, in module (b), described making two-dimension code image can single making or batch making.
In above-mentioned arbitrary scheme, preferably, in module (b), described two-dimension code image comprises vector format and picture format.
In above-mentioned arbitrary scheme, preferably, described vector format comprises .wmf form.
In above-mentioned arbitrary scheme, preferably, described picture format comprises .png form.
In above-mentioned arbitrary scheme, preferably, in module (d), the described move operation bill system of setting up is taking existing operation ticket management system as exploitation basis.
In above-mentioned arbitrary scheme, preferably, in module (e), described operation order comprises facility information and clause information.
In above-mentioned arbitrary scheme, preferably, in module (e), described making operation order is to put to make by the key operation of clear and definite operating process.
In above-mentioned arbitrary scheme, preferably, the key operation point of described clear and definite operating process is according to electric "five-proof" requirement, for ensureing the committed step of safe operation.
In above-mentioned arbitrary scheme, preferably, in module (f), described implanting device 2 D code information comprises manual implantation and automatically implants.
In above-mentioned arbitrary scheme, preferably, described manual implantation Quick Response Code refers to the editor space by interface, in the place that need to implant Quick Response Code by implanting manually.
In above-mentioned arbitrary scheme preferably, described automatic implantation Quick Response Code comprises in actual applications, some names that need to implant the key operation of Quick Response Code have regularity, by decompose and mate these keywords in Quick Response Code operation steps, realize the intelligence of certain operation 2 D code information and implant, more meet respective rule.
In above-mentioned arbitrary scheme, preferably, in module (g), described push operation ticket is to connect by wireless network and described mobile terminal, then uploads, down operation ticket.
In above-mentioned arbitrary scheme, preferably, in module (g), described mobile terminal comprises IPAD.
In above-mentioned arbitrary scheme, preferably, in module (h), described scanning is to scan by the Quick Response Code scanner on described mobile terminal.
In above-mentioned arbitrary scheme, preferably, described scanning comprises that scanning sticks on the two-dimension code image on equipment on the spot in advance.
In above-mentioned arbitrary scheme preferably, module (i) in, described verification comprises unique correspondence of utilizing Quick Response Code, carry out verification by described device name additional on the facility information on described operation order and described Quick Response Code, the information unlocking operation ticket that coincide, realize and prevent from going to the wrong way interval in logic, then by the clause information of described operation order and the current operation clause verification of described Quick Response Code, realize logic anti-misoperation locking, if information is coincide, this operation clause of release, if information misfits, prompting mistake, and lock operation ticket entry.
The present invention, taking existing operation ticket management system as exploitation basis, sets up a move operation bill system; Implanting device 2 D code information in operation order relevant entry; Utilize the scan function of mobile terminal device (as ipad), in operating process, call Quick Response Code scanner and scan, confirm the data message of key point; Utilize unique correspondence of Quick Response Code, confirm correctness, realize and prevent maloperation function.The present invention can realize the pressure property checked of operating process, the supervision of operating process.From operating process, eliminate maloperation hidden danger, basic realization " prevent mistake point, mistake combination switch ", " prevent on-load drawing disconnecting link ", " prevent live connection of ground wire (closing grounding switch) ", " prevent that line with ground (grounding switch) from closing a floodgate ", the electric "five-proof" function of " preventing mistakenly entering charged chamber ".According to a kind of system and method that uses Quick Response Code to prevent maloperation in electric system of the present invention, functional strong, facilitate operations staff to operate, to eliminating security risk, avoid personal injury and device damage, ensure that safe operation is most important, be suitable for wide popularization and application.
Brief description of the drawings
Fig. 1 makes schematic diagram according to the Quick Response Code database of an a kind of specific embodiment that uses the system and method that Quick Response Code prevents maloperation in electric system of the present invention.
Fig. 2 is according to the Quick Response Code database manufacturing system schematic diagram of an a kind of specific embodiment that uses the system and method that Quick Response Code prevents maloperation in electric system of the present invention.
Fig. 3 makes process flow diagram according to the Quick Response Code database of an a kind of specific embodiment that uses the system and method that Quick Response Code prevents maloperation in electric system of the present invention.
Fig. 4 is according to the operation chart of an a kind of specific embodiment that uses the system and method that Quick Response Code prevents maloperation in electric system of the present invention.
Embodiment
In order to allow content of the present invention better be understood, below in conjunction with accompanying drawing, to being elaborated and explaining according to a kind of several specific embodiments that use the system and method that Quick Response Code prevents maloperation in electric system of the present invention.
Embodiment mono-
According to a kind of system and method that uses Quick Response Code to prevent maloperation in electric system of the present invention, the present embodiment provides in a kind of electric system and uses Quick Response Code to prevent the method for maloperation, comprise Quick Response Code, operation order, mobile terminal, equipment on the spot, it is characterized in that, in described electric system, use Quick Response Code to prevent that the method for maloperation from comprising the following steps successively:
(1) make Quick Response Code database;
(2) extract and make two-dimension code image;
(3) paste equipment corresponding site;
(4) set up move operation bill system;
(5) make operation order;
(6) implanting device 2 D code information in operation order relevant entry;
(7) operation order is pushed to mobile terminal;
(8) utilize mobile terminal device scanning device Quick Response Code;
(9) operation order information and Quick Response Code are carried out to verification.
In step (1), described making Quick Response Code database is to make Quick Response Code according to relevant device title, numbering, particular keywords, current operation clause.In step (2), described making two-dimension code image can single making or batch making.In step (2), described two-dimension code image comprises vector format and picture format.Described vector format comprises .wmf form.Described picture format comprises .png form.In step (4), the described move operation bill system of setting up is taking existing operation ticket management system as exploitation basis.In step (5), described operation order comprises facility information and clause information.In step (5), described making operation order is to put to make by the key operation of clear and definite operating process.The key operation point of described clear and definite operating process is according to electric "five-proof" requirement, for ensureing the committed step of safe operation.In step (6), described implanting device 2 D code information comprises manual implantation and automatically implants.Described manual implantation Quick Response Code refers to the editor space by interface, in the place that need to implant Quick Response Code by implanting manually.Described automatic implantation Quick Response Code comprises in actual applications, some names that need to implant the key operation of Quick Response Code have regularity, by decompose and mate these keywords in Quick Response Code operation steps, realize the intelligence of certain operation 2 D code information and implant, more meet respective rule.In step (7), described push operation ticket is to connect by wireless network and described mobile terminal, then uploads, down operation ticket.In step (7), described mobile terminal comprises IPAD.In step (8), described scanning is to scan by the Quick Response Code scanner on described mobile terminal.Described scanning comprises that scanning sticks on the two-dimension code image on equipment on the spot in advance.In step (9), described verification comprises unique correspondence of utilizing Quick Response Code, carry out verification by described device name additional on the facility information on described operation order and described Quick Response Code, the information unlocking operation ticket that coincide, realize and prevent from going to the wrong way interval in logic, then by the clause information of described operation order and the current operation clause verification of described Quick Response Code, realize logic anti-misoperation locking, if information is coincide, this operation clause of release, if information misfits, prompting mistake, and lock operation ticket entry.
Embodiment bis-
The present embodiment also provides in a kind of electric system and uses Quick Response Code to prevent the system of maloperation, comprise Quick Response Code, operation order, mobile terminal, equipment on the spot, it is characterized in that, in described electric system, use Quick Response Code to prevent that the system of maloperation from also comprising Quick Response Code database, move operation bill system, operation order.Described system comprises with lower module:
Module (a), for making Quick Response Code database;
Module (b), for extracting and make two-dimension code image;
Module (c), for pasting equipment corresponding site;
Module (d), for setting up move operation bill system;
Module (e), for making operation order;
Module (f), at operation order relevant entry implanting device 2 D code information;
Module (g), for being pushed to mobile terminal by operation order;
Module (h), for utilizing mobile terminal device scanning device Quick Response Code;
Module (i), for operation order information and Quick Response Code are carried out to verification.
In module (a), described making Quick Response Code database is to make Quick Response Code according to relevant device title, numbering, particular keywords, current operation clause.In module (b), described making two-dimension code image can single making or batch making.In module (b), described two-dimension code image comprises vector format and picture format.Described vector format comprises .wmf form.Described picture format comprises .png form.In module (d), the described move operation bill system of setting up is taking existing operation ticket management system as exploitation basis.In module (e), described operation order comprises facility information and clause information.In module (e), described making operation order is to put to make by the key operation of clear and definite operating process.The key operation point of described clear and definite operating process is according to electric "five-proof" requirement, for ensureing the committed step of safe operation.In module (f), described implanting device 2 D code information comprises manual implantation and automatically implants.Described manual implantation Quick Response Code refers to the editor space by interface, in the place that need to implant Quick Response Code by implanting manually.Described automatic implantation Quick Response Code comprises in actual applications, some names that need to implant the key operation of Quick Response Code have regularity, by decompose and mate these keywords in Quick Response Code operation steps, realize the intelligence of certain operation 2 D code information and implant, more meet respective rule.In module (g), described push operation ticket is to connect by wireless network and described mobile terminal, then uploads, down operation ticket.In module (g), described mobile terminal comprises IPAD.In module (h), described scanning is to scan by the Quick Response Code scanner on described mobile terminal.Described scanning comprises that scanning sticks on the two-dimension code image on equipment on the spot in advance.Module (i) in, described verification comprises unique correspondence of utilizing Quick Response Code, carry out verification by described device name additional on the facility information on described operation order and described Quick Response Code, the information unlocking operation ticket that coincide, realize and prevent from going to the wrong way interval in logic, then by the clause information of described operation order and the current operation clause verification of described Quick Response Code, realize logic anti-misoperation locking, if information is coincide, this operation clause of release, if information misfits, prompting mistake, and lock operation ticket entry.
The present invention, taking existing operation ticket management system as exploitation basis, sets up a move operation bill system; Implanting device 2 D code information in operation order relevant entry; Utilize the scan function of mobile terminal device (as ipad), in operating process, call Quick Response Code scanner and scan, confirm the data message of key point; Utilize unique correspondence of Quick Response Code, confirm correctness, realize and prevent maloperation function.The present invention can realize the pressure property checked of operating process, the supervision of operating process.From operating process, eliminate maloperation hidden danger, basic realization " prevent mistake point, mistake combination switch ", " prevent on-load drawing disconnecting link ", " prevent live connection of ground wire (closing grounding switch) ", " prevent that line with ground (grounding switch) from closing a floodgate ", the electric "five-proof" function of " preventing mistakenly entering charged chamber ".Method is specifically used, functional strong, facilitates operations staff to operate, and to eliminating security risk, avoids personal injury and device damage, ensures that safe operation is most important.Be suitable for wide popularization and application.
Embodiment tri-
What 1, Quick Response Code was additional is relevant device title, numbering, state and particular keywords.
For example: check #6 stove A coal pulverizer 66106 switch title numberings correct, 2 D code information comprises " #6 stove A coal pulverizer 66106 switches ".Pull open #6 stove A coal pulverizer 66106 switch grounding switch 66106-D, 2 D code information comprises " (pulling open) #6 stove A coal pulverizer 66106 switch grounding switch 66106-D ".
2, utilize Quick Response Code printer to print Quick Response Code, paste equipment assigned address on the spot.
3, make in operation order process, according to the principle of making an appointment, automatically implant Quick Response Code in respective entries, or manually implant.
4, when operation order is carried out the entry of implanting Quick Response Code, scanner is called in prompting scanning simultaneously.
5, scanning device two-dimension code image and the verification of Quick Response Code database, utilize unique correspondence of Quick Response Code, by operation order additional information and equipment additional information verification on the spot, the information unlocking operation ticket that coincide, realize and prevent from going to the wrong way interval in logic, by operation order clause optional equipment information and the verification of current operation clause, confirm correctness, this operation clause of release, realizes logic anti-misoperation locking.
Embodiment tetra-
1), according to correlation principle, according to facility information storehouse making Quick Response Code database;
2), print two-dimension code image and paste equipment assigned address on the spot;
3), set up real-time network communication platform (multistage network framework, data processing of information sends, synchronous etc.), media Digital Services platform (operation note and audio and video information processing), speech communication processing platform and mobile device management platform;
4) taking existing operation ticket management system as exploitation basis, set up a move operation bill system;
5), according to operation task, make operation order.Specify the key operation point of operating process.As " pulling open ... disconnecting link ", " closing ... switch " etc.;
6) implanting device 2 D code information in operation order relevant entry; Ensure that key operation point must have position information confirming.Positional information customization comprises two kinds of modes:
Manually implant Quick Response Code: interface provides editor space, has manually implant in the place that need to implant Quick Response Code;
Automatically implant Quick Response Code: in generating plant application, some names that need to implant the key operation of Quick Response Code have regularity, as " pulling open ... disconnecting link ", " closing ... switch " etc., by decompose and mate these keywords in Quick Response Code operation steps, realizing certain operation 2 D code information intelligence implants, greatly alleviate staff's failure rate, also more meet respective rule;
Find by practice, the Intelligent Matching of Quick Response Code is implanted can be by several mode, along with the expansion continuous renewal of service application scope,
7) obtain interface by operation order, from original two bill systems, obtain operation order (or in native system self manufacture operation order), connect with mobile terminal, operation order is pushed to mobile terminal;
8) utilize the scan function of ipad, in operating process, call Quick Response Code scanner, scan information checking in equipment is pasted in advance on the spot 2 D code information and operation order, confirm the data message of key point;
9) utilize unique correspondence of Quick Response Code, by operation order additional location information and equipment additional information verification on the spot, the information unlocking operation ticket that coincide, realize and prevent from going to the wrong way interval in logic, by operation order clause optional equipment information and the verification of current operation clause, confirm correctness, this operation clause of release, realizes logic anti-misoperation locking.If information misfits, prompting mistake, and lock operation ticket entry.
Embodiment five
On the basis of embodiment tetra-
8) utilize the scan function of mobile phone, in operating process, call Quick Response Code scanner, scan information checking in equipment is pasted in advance on the spot 2 D code information and operation order, confirm the data message of key point.
It should be noted that; comprise any one and the combination in any thereof in above-described embodiment according to a kind of system and method that uses Quick Response Code to prevent maloperation of the present invention in electric system; but embodiment recited above is described the preferred embodiment of the present invention; not the scope of the invention is limited; design under spiritual prerequisite not departing from the present invention; various distortion and improvement that the common engineering technical personnel in this area make technical scheme of the present invention, all should fall in the definite protection domain of claims of the present invention.

Claims (10)

1. in electric system, use Quick Response Code to prevent a method for maloperation, it is characterized in that, comprise the following steps successively:
Make Quick Response Code database;
Extract and make two-dimension code image;
Paste equipment corresponding site;
Set up move operation bill system;
Make operation order;
Implanting device 2 D code information in operation order relevant entry;
Operation order is pushed to mobile terminal;
Utilize mobile terminal device scanning device Quick Response Code;
Operation order information and Quick Response Code are carried out to verification.
2. in electric system according to claim 1, use Quick Response Code to prevent the method for maloperation, it is characterized in that, in step (1), described making Quick Response Code database is to make Quick Response Code according to relevant device title, numbering, particular keywords, current operation clause.
3. in electric system according to claim 1, use Quick Response Code to prevent the method for maloperation, it is characterized in that, in step (2), described making two-dimension code image can single making or batch making.
4. in electric system according to claim 1, use Quick Response Code to prevent the method for maloperation, it is characterized in that, in step (2), described two-dimension code image comprises vector format and picture format.
5. in electric system according to claim 4, use Quick Response Code to prevent the method for maloperation, it is characterized in that, described vector format comprises .wmf form.
6. in electric system according to claim 4, use Quick Response Code to prevent the method for maloperation, it is characterized in that, described picture format comprises .png form.
7. in electric system according to claim 1, use Quick Response Code to prevent the method for maloperation, it is characterized in that, in step (4), the described move operation bill system of setting up is taking existing operation ticket management system as exploitation basis.
8. in electric system according to claim 1, use Quick Response Code to prevent the method for maloperation, it is characterized in that, in step (5), described operation order comprises facility information and clause information.
9. in electric system according to claim 1, use Quick Response Code to prevent the method for maloperation, it is characterized in that, in step (5), described making operation order is to put to make by the key operation of clear and definite operating process.
10. in electric system according to claim 9, use Quick Response Code to prevent the method for maloperation, it is characterized in that, the key operation point of described clear and definite operating process is according to electric "five-proof" requirement, for ensureing the committed step of safe operation.
CN201410237192.8A 2014-05-30 2014-05-30 System and method for preventing misoperation in electric power system by using two-dimension codes Pending CN104036349A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410237192.8A CN104036349A (en) 2014-05-30 2014-05-30 System and method for preventing misoperation in electric power system by using two-dimension codes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410237192.8A CN104036349A (en) 2014-05-30 2014-05-30 System and method for preventing misoperation in electric power system by using two-dimension codes

Publications (1)

Publication Number Publication Date
CN104036349A true CN104036349A (en) 2014-09-10

Family

ID=51467113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410237192.8A Pending CN104036349A (en) 2014-05-30 2014-05-30 System and method for preventing misoperation in electric power system by using two-dimension codes

Country Status (1)

Country Link
CN (1) CN104036349A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104820416A (en) * 2015-05-06 2015-08-05 华电国际电力股份有限公司邹县发电厂 Intelligent electric anti-misoperation management and control system based on two-dimension code
CN104952127A (en) * 2015-05-14 2015-09-30 中国神华能源股份有限公司 System and method for preventing error locking and misoperation
CN108268910A (en) * 2017-11-29 2018-07-10 国网河南省电力公司焦作供电公司 Utilize the method for Quick Response Code operation order supervise and examine error proof locking system of microcomputer Normalization rule
CN108388158A (en) * 2018-04-10 2018-08-10 济南纵向软件有限公司 Internet of Things wind turbine hatch door safe related function control method based on two ticket management of electric power
CN109460882A (en) * 2018-01-29 2019-03-12 国网浙江省电力公司湖州供电公司 A kind of transregional interactive information Transmission system of electric system and method
CN109819105A (en) * 2018-12-27 2019-05-28 维沃移动通信有限公司 The processing method and mobile terminal of operational order
CN110676933A (en) * 2019-09-27 2020-01-10 国网河北省电力有限公司沧州供电分公司 Prevent mistake power transmission system
CN110690070A (en) * 2019-09-27 2020-01-14 国网河北省电力有限公司沧州供电分公司 Knife switch for preventing mistaken power transmission
CN110690759A (en) * 2019-09-27 2020-01-14 国网河北省电力有限公司沧州供电分公司 Power dispatching management system
CN110707812A (en) * 2019-09-27 2020-01-17 国网河北省电力有限公司沧州供电分公司 Brake pull rod for preventing mistaken power transmission
CN110705829A (en) * 2019-09-06 2020-01-17 国网上海市电力公司 Ground wire management method and system based on two-dimensional code and intelligent lock technology
CN110896208A (en) * 2019-11-29 2020-03-20 广东欧文特电气有限公司 Intelligent load-limiting universal circuit breaker
CN111861778A (en) * 2020-06-30 2020-10-30 无锡诚源环境科技有限公司 Electric cabinet manufacturing management system
CN112990872A (en) * 2021-03-16 2021-06-18 国家电网有限公司 Interactive ground wire control method
CN114069868A (en) * 2021-11-25 2022-02-18 国网山东省电力公司威海市文登区供电公司 Power failure and transmission two-dimensional code scanning anti-misoperation device

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030090330A (en) * 2002-05-23 2003-11-28 (주)한국방재엔지니어링 Establishments checkup apparatus and method use bar code
CN102867227A (en) * 2012-07-17 2013-01-09 浙江新能量科技有限公司 Operation management system and management method for electric power equipment based on barcode technology
CN103729729A (en) * 2013-12-07 2014-04-16 国家电网公司 Grounding wire anti-misoperation method and system based on GPS positioning

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030090330A (en) * 2002-05-23 2003-11-28 (주)한국방재엔지니어링 Establishments checkup apparatus and method use bar code
CN102867227A (en) * 2012-07-17 2013-01-09 浙江新能量科技有限公司 Operation management system and management method for electric power equipment based on barcode technology
CN103729729A (en) * 2013-12-07 2014-04-16 国家电网公司 Grounding wire anti-misoperation method and system based on GPS positioning

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
邓荣辉: "变电站在线式五防系统的研究与应用", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104820416A (en) * 2015-05-06 2015-08-05 华电国际电力股份有限公司邹县发电厂 Intelligent electric anti-misoperation management and control system based on two-dimension code
CN104952127A (en) * 2015-05-14 2015-09-30 中国神华能源股份有限公司 System and method for preventing error locking and misoperation
CN104952127B (en) * 2015-05-14 2018-09-14 中国神华能源股份有限公司 A kind of anti-misoperation locking and fool proof system and method
CN108268910A (en) * 2017-11-29 2018-07-10 国网河南省电力公司焦作供电公司 Utilize the method for Quick Response Code operation order supervise and examine error proof locking system of microcomputer Normalization rule
CN109460882A (en) * 2018-01-29 2019-03-12 国网浙江省电力公司湖州供电公司 A kind of transregional interactive information Transmission system of electric system and method
CN108388158A (en) * 2018-04-10 2018-08-10 济南纵向软件有限公司 Internet of Things wind turbine hatch door safe related function control method based on two ticket management of electric power
CN109819105A (en) * 2018-12-27 2019-05-28 维沃移动通信有限公司 The processing method and mobile terminal of operational order
CN109819105B (en) * 2018-12-27 2021-03-23 维沃移动通信有限公司 Processing method of operation instruction and mobile terminal
CN110705829A (en) * 2019-09-06 2020-01-17 国网上海市电力公司 Ground wire management method and system based on two-dimensional code and intelligent lock technology
CN110690070A (en) * 2019-09-27 2020-01-14 国网河北省电力有限公司沧州供电分公司 Knife switch for preventing mistaken power transmission
CN110707812A (en) * 2019-09-27 2020-01-17 国网河北省电力有限公司沧州供电分公司 Brake pull rod for preventing mistaken power transmission
CN110690759A (en) * 2019-09-27 2020-01-14 国网河北省电力有限公司沧州供电分公司 Power dispatching management system
CN110676933A (en) * 2019-09-27 2020-01-10 国网河北省电力有限公司沧州供电分公司 Prevent mistake power transmission system
CN110896208A (en) * 2019-11-29 2020-03-20 广东欧文特电气有限公司 Intelligent load-limiting universal circuit breaker
CN111861778A (en) * 2020-06-30 2020-10-30 无锡诚源环境科技有限公司 Electric cabinet manufacturing management system
CN112990872A (en) * 2021-03-16 2021-06-18 国家电网有限公司 Interactive ground wire control method
CN114069868A (en) * 2021-11-25 2022-02-18 国网山东省电力公司威海市文登区供电公司 Power failure and transmission two-dimensional code scanning anti-misoperation device

Similar Documents

Publication Publication Date Title
CN104036349A (en) System and method for preventing misoperation in electric power system by using two-dimension codes
CN102867227B (en) Based on power equipment operation management system and the management method of bar codes technique
CN105449867B (en) A kind of visualized operation process monitoring anti-error system and control method
CN104144420B (en) A kind of radio switch-in method and relevant device, system
CN104035404A (en) Development method for operation order real-time state monitoring
CN102325309B (en) Visualization switching operation management method
CN103839193A (en) Transformer substation anti-misoperation method and system based on two-dimension code identification technology
CN103870826A (en) Electronic archive scanning, recognizing and filing method and system
CN104464045A (en) Two-dimension code-based access control method and two-dimension code-based access control system
CN101897204A (en) System and method for facilitating the growth of a mobile community
CN102984689A (en) System and method for verifying mobile terminal
CN105205640A (en) System and method for achieving delivery of multiple express items through one cell of storage cabinet
CN102882851B (en) The generation method of address list and server
CN105930170A (en) SCD file semantic version management method based on comparison analysis results
CN108648318A (en) It is online to authorize Interlocking Methods and system
CN104318415A (en) Centralization express delivery and collection system and method in area
CN101847274A (en) Security inspection door used for court
CN104284153A (en) Distribution room safety and synchronous operation monitoring intercom system and operation method thereof
CN104112183A (en) Plug-and-play intelligent scheduling model management system and management method of intelligent substation
CN103944759A (en) Fault warning system of communication transmission network management part of power communication network
CN103295299A (en) Remote intelligent unlocking key management box
CN105429951A (en) Electronic cipher lock control method and control system
CN102882854B (en) Electric network data cut-in method
CN109508493A (en) A kind of application method based on BIM+ planar bar code technology in distribution debugging and maintenance
CN202285411U (en) Portable visual switching operation management system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140910

RJ01 Rejection of invention patent application after publication