CN104022535B CN201410280571.5A CN201410280571A CN104022535B CN 104022535 B CN104022535 B CN 104022535B CN 201410280571 A CN201410280571 A CN 201410280571A CN 104022535 B CN104022535 B CN 104022535B
Authority
CN
China
Prior art keywords
wind
electricity generation
powered electricity
driven power
installed capacity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410280571.5A
Other languages
Chinese (zh)
Other versions
CN104022535A (en
Inventor
王魁
闫大威
宗志刚
梁群
李媛媛
罗涛
周进
崔广胜
刘丽霞
雷铮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410280571.5A priority Critical patent/CN104022535B/en
Publication of CN104022535A publication Critical patent/CN104022535A/en
Application granted granted Critical
Publication of CN104022535B publication Critical patent/CN104022535B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A kind of trans-regional installed capacity of wind-driven power coordinated planning method.It comprises acquisition related data, structure computation model, calculates wind-powered electricity generation combination efficient frontier curve and determine the steps such as program results.The inventive method, based on the installed capacity of wind-driven power unite planning of portfolio theory by zones of different, efficiently reduces the fluctuation of wind-powered electricity generation gross capability, reduces the peak demand that system is total.Using each region installed capacity of wind-driven power under wind-powered electricity generation combined article prime factor maximum case as final optimization pass result, wind-powered electricity generation volume metering and wind-powered electricity generation fluctuation problem are taken into account to the full extent.On the other hand, the present invention is provided with the installed capacity of wind-driven power bound of regional, has taken into full account the situations such as the electric network composition of regional, load level, government policy, has made program results more closing to reality.

Description

A kind of trans-regional installed capacity of wind-driven power coordinated planning method
Technical field
The invention belongs to Electric Power Network Planning technical field, particularly relate to a kind of trans-regional installed capacity of wind-driven power coordinated planning method.
Background technology
The dynamics reduced discharging along with national energy-saving continues to increase, and the renewable energy power generations such as wind-powered electricity generation obtain fast development.China's forehand brews alcoholic beverages eight ten million multikilowatt wind power base such as spring, Hami, Meng Dong, Meng Xi, Hebei, Jilin, Jiangsu, Shandong.In addition, relevant department is formulating the planning of Heilungkiang and Shanxi ten million multikilowatt wind power base, and China ten million multikilowatt wind power base is increased to 10 by from current 8.Current wind-powered electricity generation planing method, is generally the wind-powered electricity generation planning carrying out some areas according to local wind power resources situation, lacks unified planning guidance method, do not carry out trans-regional wind-powered electricity generation planning from the angle that the overall situation is overall, there is blindness randomness.Trans-regional wind power output has certain complementarity on a large scale, by reasonably planning the installed capacity of wind-driven power scale of zones of different, can reduce the fluctuation of wind-powered electricity generation gross capability, reducing the peak demand that system is total, be conducive to the safe and stable operation of electric power system.
Summary of the invention
In order to solve the problem, the object of the present invention is to provide a kind of trans-regional installed capacity of wind-driven power coordinated planning method.
In order to achieve the above object, trans-regional installed capacity of wind-driven power coordinated planning method provided by the invention comprises the following step performed in order:
Step 1) obtain S1 stage of related data: the installed capacity of wind-driven power bound obtaining planning areal, the wind-powered electricity generation capacity factor measure in planning region, the wind-powered electricity generation standard deviation in planning region, the wind-powered electricity generation installation total capacity of planning, each region, the wind-powered electricity generation coefficient correlation between each region;
Step 2) S2 stage of structure computation model: build with in given wind-powered electricity generation bank capability because subcase leeward electricity combination standard difference is minimum for target function, be constrained to the computation model of constraints with the constraint of installed capacity of wind-driven power ratio, the constraint of wind-powered electricity generation capacity factor measure and installed capacity of wind-driven power;
Step 3) calculate S3 stage of wind-powered electricity generation combination efficient frontier curve: the installed capacity of wind-driven power bound in the wind-powered electricity generation capacity factor measure in the planning areal obtained by the S1 stage, planning region, the planning wind-powered electricity generation standard deviation in region, the wind-powered electricity generation total installation of generating capacity of planning and each region is substituted into the computation model built in the S2 stage, and by the wind-powered electricity generation bank capability factor in given zone in continuous value, repeatedly calculate the computation model built in the S2 stage, obtain one group of wind-powered electricity generation combination standard difference and corresponding each region installed capacity of wind-driven power, make wind-powered electricity generation combination efficient frontier curve;
Step 4) determine the program results S4 stage: utilize wind-powered electricity generation to combine efficient frontier curve and calculate wind-powered electricity generation combined article prime factor, and therefrom choose wind-powered electricity generation combined article prime factor maximum time each region installed capacity of wind-driven power as final program results.
In the S2 stage, the method for described structure computation model comprises the following steps:
S21: build optimization aim: with given wind-powered electricity generation bank capability because of subcase leeward electricity combination standard difference minimum for target function;
S22: build constraints, comprising: the constraint of installed capacity of wind-driven power ratio, the constraint of wind-powered electricity generation capacity factor measure and installed capacity of wind-driven power constraint.
In the S3 stage, described to refer between the given zone of the wind-powered electricity generation bank capability factor in given zone continuously in value in this interval, utilize method of Lagrange multipliers repeatedly to calculate the computation model of structure, one group of wind-powered electricity generation combination standard difference and corresponding each region installed capacity of wind-driven power can be obtained.
In the S4 stage, described wind-powered electricity generation combined article prime factor is defined as the ratio of the wind-powered electricity generation bank capability factor and wind-powered electricity generation combination standard difference; Wind-powered electricity generation capacity factor measure refers to that wind energy turbine set annual is exerted oneself and the ratio of specified installed capacity.
In the S21 stage, described target function is: wherein, σ totalfor wind-powered electricity generation constitution's risk; N is planning areal; x ifor the installed capacity of wind-driven power ratio of region i; σ ifor the wind-powered electricity generation standard deviation of region i; ρ ijfor the wind-powered electricity generation coefficient correlation of wind power base i and j.
In the S22 stage, described constraints comprises:
1) installed capacity of wind-driven power ratio constraint: Σ i = 1 N x i = 1 x i ≥ 0 , i = 1,2 , · · · , N , The installed capacity of wind-driven power ratio sum of all areas to be planned must be 1;
2) wind-powered electricity generation capacity factor measure constraint: wherein, E ifor the wind-powered electricity generation capacity factor measure of region i; E totalfor the wind-powered electricity generation bank capability factor;
3) installed capacity of wind-driven power constraint: P i = x i P total P i min ≤ P i ≤ P i max , Wherein, P ifor the installed capacity of wind-driven power of the region i of planning; P totalfor the wind-powered electricity generation total installation of generating capacity of planning; P iminand P imaxbe respectively the installed capacity of wind-driven power bound of region i.
Compared with prior art, the beneficial effect of trans-regional installed capacity of wind-driven power coordinated planning method provided by the invention is: the inventive method is based on the installed capacity of wind-driven power unite planning of portfolio theory by zones of different, efficiently reduce the fluctuation of wind-powered electricity generation gross capability, reduce the peak demand that system is total.Using each region installed capacity of wind-driven power under wind-powered electricity generation combined article prime factor maximum case as final optimization pass result, wind-powered electricity generation volume metering and wind-powered electricity generation fluctuation problem are taken into account to the full extent.On the other hand, the present invention is provided with the installed capacity of wind-driven power bound of regional, has taken into full account the situations such as the electric network composition of regional, load level, government policy, has made program results more closing to reality.
Accompanying drawing explanation
Fig. 1 is trans-regional installed capacity of wind-driven power coordinated planning method flow diagram provided by the invention.
Embodiment
In order to make object of the present invention, technical scheme and advantage clearly understand, below in conjunction with accompanying drawing, subordinate list and embodiment, the present invention is further elaborated.Should be appreciated that specific embodiment described herein only for explaining the present invention, being not intended to limit the present invention.
In an embodiment of the present invention, trans-regional installed capacity of wind-driven power coordinated planning method on a large scale, using the wind-powered electricity generation bank capability factor as income, using wind-powered electricity generation combination standard difference as risk, by optimizing the installed capacity of wind-driven power ratio in each region, make in certain wind-powered electricity generation bank capability because of under subcase, wind-powered electricity generation combination standard difference reaches minimum, efficiently reduce the fluctuation of wind-powered electricity generation gross capability, the peak demand that the system that reduces is total.
As shown in Figure 1, trans-regional installed capacity of wind-driven power coordinated planning method provided by the invention comprises the following step performed in order:
Step 1) obtain S1 stage of related data: the installed capacity of wind-driven power bound obtaining planning areal, the wind-powered electricity generation capacity factor measure in planning region, the wind-powered electricity generation standard deviation in planning region, the wind-powered electricity generation installation total capacity of planning, each region, the wind-powered electricity generation coefficient correlation between each region;
Step 2) S2 of structure computation model: build with in given wind-powered electricity generation bank capability because subcase leeward electricity combination standard difference is minimum for target function, be constrained to the computation model of constraints with the constraint of installed capacity of wind-driven power ratio, the constraint of wind-powered electricity generation capacity factor measure and installed capacity of wind-driven power;
Step 3) calculate S3 stage of wind-powered electricity generation combination efficient frontier curve: the installed capacity of wind-driven power bound in the wind-powered electricity generation capacity factor measure in the planning areal obtained by the S1 stage, planning region, the planning wind-powered electricity generation standard deviation in region, the wind-powered electricity generation total installation of generating capacity of planning and each region is substituted into the computation model built in the S2 stage, and by the wind-powered electricity generation bank capability factor in given zone in continuous value, repeatedly calculate the computation model built in the S2 stage, obtain one group of wind-powered electricity generation combination standard difference and corresponding each region installed capacity of wind-driven power, make wind-powered electricity generation combination efficient frontier curve;
Step 4) determine the program results S4 stage: utilize wind-powered electricity generation to combine efficient frontier curve, calculate wind-powered electricity generation combined article prime factor, and therefrom choose wind-powered electricity generation combined article prime factor maximum time each region installed capacity of wind-driven power as final program results.
In the S2 stage, the method for described structure computation model comprises the following steps:
S21: build optimization aim: with given wind-powered electricity generation bank capability because of subcase leeward electricity combination standard difference minimum for target function;
S22: build constraints, comprising: the constraint of installed capacity of wind-driven power ratio, the constraint of wind-powered electricity generation capacity factor measure and installed capacity of wind-driven power constraint.
In the S21 stage, described target function is: wherein, σ totalfor wind-powered electricity generation constitution's risk; N is planning areal; x ifor the installed capacity of wind-driven power ratio of region i; σ ifor the wind-powered electricity generation standard deviation of region i; ρ ijfor the wind-powered electricity generation coefficient correlation of wind power base i and j;
In the S22 stage, described constraints comprises:
1) installed capacity of wind-driven power ratio constraint: Σ i = 1 N x i = 1 x i ≥ 0 , i = 1,2 , · · · , N , The installed capacity of wind-driven power ratio sum of all areas to be planned must be 1;
2) wind-powered electricity generation capacity factor measure constraint: wherein, E ifor the wind-powered electricity generation capacity factor measure of region i; E totalfor the wind-powered electricity generation bank capability factor;
3) installed capacity of wind-driven power constraint: P i = x i P total P i min ≤ P i ≤ P i max , Wherein, P ifor the installed capacity of wind-driven power of the region i of planning; P totalfor the wind-powered electricity generation total installation of generating capacity of planning; P iminand P imaxbe respectively the installed capacity of wind-driven power bound of region i; If do not arrange P iminand P imax, then the region installed capacity of wind-driven power ratio had in result of calculation may be 0, in addition, in order to take into full account the actual conditions such as electric network composition, load level, government policy of regional, therefore need arrange P iminand P imax.
In the S3 stage, described to refer between the given zone of the wind-powered electricity generation bank capability factor in given zone continuously in value in this interval, utilize method of Lagrange multipliers repeatedly to calculate the computation model of structure, one group of wind-powered electricity generation combination standard difference and corresponding each region installed capacity of wind-driven power can be obtained.
In the S4 stage, described wind-powered electricity generation combined article prime factor is defined as the ratio of the wind-powered electricity generation bank capability factor and wind-powered electricity generation combination standard difference; Wind-powered electricity generation capacity factor measure refers to that wind energy turbine set annual is exerted oneself and the ratio of specified installed capacity; This parameter reflects a regional wind energy resources condition, and capacity factor measure shows that more greatly this area's wind energy resources is abundanter; Standard deviation is the average that each data depart from the distance of average; Standard deviation reflects the dispersion degree of a data set, and a larger standard deviation represents between most of numerical value and its mean value and differs greatly; A less standard deviation represents these numerical value comparatively close to mean value; A regional wind-powered electricity generation standard deviation features the degree of fluctuation of this area's wind power, and the wind power standard deviation of a wind power base is less, and the impact brought electrical network is less; In order to overall merit and measurement wind power resources quality, definition wind-powered electricity generation quality factor equals the ratio of this area's wind-powered electricity generation capacity factor measure and standard deviation, quality factor had both considered wind power size (capacity factor measure), take into account again wind-powered electricity generation degree of fluctuation (standard deviation), quality factor is larger, and wind-powered electricity generation condition is more excellent.
In order to illustrate further the embodiment of the present invention, the eight large ten million multikilowatt wind power base of now building with China are for research object: Jiuquan, Hami, Meng Dong (Chifeng), cover west (Wulanchabu League), Hebei (Zhangjiakou), Jilin (Baicheng), Jiangsu (great Feng), Shandong (Laizhou), optimize the installed capacity of wind-driven power ratio of eight large wind power base.The wind-powered electricity generation characteristic index of the large wind power base of China eight is as shown in table 1.
Based on set up trans-regional installed capacity of wind-driven power coordinated planning model, effective frontal can be combined.For the optimum organization of several wind power base, the bank capability factor is the weighted average of these wind power base capacity factor measures, wherein weights are the installed capacity ratio of each wind power base, therefore the bank capability factor must exceed the maximum of these wind power base capacity factor measures.The standard deviation of Jiuquan region is 0.2368, and wind-powered electricity generation capacity factor measure is 0.1759, and quality factor is 0.7462; And combining wind-powered electricity generation under identical standard deviation, capacity factor measure and quality factor are all greater than the twice (being respectively 0.3640,1.5385) in Jiuquan.The standard deviation of Hami Prefecture is 0.2876, and wind-powered electricity generation capacity factor measure is 0.1899, and quality factor is 0.6602; And combining wind-powered electricity generation under identical standard deviation, capacity factor measure and quality factor are also greater than the twice (being respectively 0.3955,1.3751) in Hami.
For wind-powered electricity generation combination, combination effective frontal comprises numerous point, and the minimum sandards that can obtain under each point wherein all represents the heap(ed) capacity factor or the specified vol factor that can obtain under specific criteria difference is poor.Wherein combined article prime factor maximum is 1.8675, and now the bank capability factor is 0.275, and combination standard difference is 0.1473, and the installed capacity of wind-driven power ratio in each region is as shown in table 2.In China's eight large ten million kilowatts of wind power base, cover west quality factor maximum (1.1716), and combined article prime factor maximum be cover west be 1.6 times.Using each region installed capacity of wind-driven power under wind-powered electricity generation combined article prime factor maximum case as final optimization pass result, wind-powered electricity generation volume metering and wind-powered electricity generation fluctuation problem are taken into account to the full extent.By the installed capacity of wind-driven power unite planning of zones of different, efficiently reduce the fluctuation of wind-powered electricity generation gross capability, reduce the peak demand that system is total.
Those skilled in the art's easy understand; the foregoing is only preferred embodiment of the present invention; not in order to limit the present invention, all any amendments done within the spirit and principles in the present invention, equivalent replacement and improvement etc., all should be included within protection scope of the present invention.
The wind-powered electricity generation characteristic index that eight, table 1 China is regional
The installed capacity of wind-driven power ratio in each region of table 2
Region Jiuquan Hami Cover east Cover west Hebei Jilin Jiangsu Shandong
Ratio 21.52% 17.17% 9.35% 16.19% 0 13.55% 22.22% 0
Trans-regional installed capacity of wind-driven power coordinated planning method provided by the invention is by the installed capacity of wind-driven power unite planning of zones of different, based on portfolio theory, using the wind-powered electricity generation bank capability factor as income, using wind-powered electricity generation combination standard difference as risk, take into full account the electric network composition of regional, load level, the situations such as government policy, using each region installed capacity of wind-driven power under wind-powered electricity generation combined article prime factor maximum case as final optimization pass result, efficiently reduce the fluctuation of wind-powered electricity generation gross capability, the peak demand that reduction system is total, carry out installed capacity of wind-driven power planning for the angle overall from the overall situation and provide guidance.

Claims (3)

1. a trans-regional installed capacity of wind-driven power coordinated planning method, is characterized in that: described trans-regional installed capacity of wind-driven power coordinated planning method comprises the following step performed in order:
Step 1) obtain S1 stage of related data: the installed capacity of wind-driven power bound obtaining planning areal, the wind-powered electricity generation capacity factor measure in planning region, the wind-powered electricity generation standard deviation in planning region, the wind-powered electricity generation installation total capacity of planning, each region, the wind-powered electricity generation coefficient correlation between each region;
Step 2) S2 stage of structure computation model: build with in given wind-powered electricity generation bank capability because subcase leeward electricity combination standard difference is minimum for target function, be constrained to the computation model of constraints with the constraint of installed capacity of wind-driven power ratio, the constraint of wind-powered electricity generation capacity factor measure and installed capacity of wind-driven power;
Step 3) calculate S3 stage of wind-powered electricity generation combination efficient frontier curve: the installed capacity of wind-driven power bound in the wind-powered electricity generation capacity factor measure in the planning areal obtained by the S1 stage, planning region, the planning wind-powered electricity generation standard deviation in region, the wind-powered electricity generation total installation of generating capacity of planning and each region is substituted into the computation model built in the S2 stage, and by the wind-powered electricity generation bank capability factor in given zone in continuous value, repeatedly calculate the computation model built in the S2 stage, obtain one group of wind-powered electricity generation combination standard difference and corresponding each region installed capacity of wind-driven power, make wind-powered electricity generation combination efficient frontier curve; Refer between given zone wherein Ei represents the wind-powered electricity generation capacity factor measure of region i, utilizes method of Lagrange multipliers repeatedly to calculate the computation model of structure in this interval, can obtain one group of wind-powered electricity generation combination standard difference and corresponding each region installed capacity of wind-driven power; Wind-powered electricity generation standard deviation refers to the degree of fluctuation of a certain local wind electrical power;
Step 4) determine the program results S4 stage: utilize wind-powered electricity generation to combine efficient frontier curve and calculate wind-powered electricity generation combined article prime factor, and therefrom choose wind-powered electricity generation combined article prime factor maximum time each region installed capacity of wind-driven power as final program results; Wind-powered electricity generation combined article prime factor is defined as the ratio of the wind-powered electricity generation bank capability factor and wind-powered electricity generation combination standard difference; Wind-powered electricity generation capacity factor measure refers to that wind energy turbine set annual is exerted oneself and the ratio of specified installed capacity.
2. trans-regional installed capacity of wind-driven power coordinated planning method according to claim 1, it is characterized in that: in the S2 stage, described target function is: wherein, σ totalfor wind-powered electricity generation constitution's risk; N is planning areal; x ifor the installed capacity of wind-driven power ratio of region i; σ ifor the wind-powered electricity generation standard deviation of region i; ρ ijfor the wind-powered electricity generation coefficient correlation of wind power base i and j.
3. trans-regional installed capacity of wind-driven power coordinated planning method according to claim 1, it is characterized in that: in the S2 stage, described constraints comprises:
1) installed capacity of wind-driven power ratio constraint: Σ i = 1 N x i = 1 x i ≥ 0 j = 1 , 2 , ... , N , The installed capacity of wind-driven power ratio sum of all areas to be planned must be 1;
2) wind-powered electricity generation capacity factor measure constraint: wherein, E ifor the wind-powered electricity generation capacity factor measure of region i; E totalfor the wind-powered electricity generation bank capability factor;
3) installed capacity of wind-driven power constraint: P i = x i P t o t a l P i min ≤ P i ≤ P i max , Wherein, P ifor the installed capacity of wind-driven power of the region i of planning; P totalfor the wind-powered electricity generation total installation of generating capacity of planning; P iminand P imaxbe respectively the installed capacity of wind-driven power bound of region i.
CN201410280571.5A 2014-06-20 2014-06-20 A kind of trans-regional installed capacity of wind-driven power coordinated planning method Active CN104022535B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410280571.5A CN104022535B (en) 2014-06-20 2014-06-20 A kind of trans-regional installed capacity of wind-driven power coordinated planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410280571.5A CN104022535B (en) 2014-06-20 2014-06-20 A kind of trans-regional installed capacity of wind-driven power coordinated planning method

Publications (2)

Publication Number Publication Date
CN104022535A CN104022535A (en) 2014-09-03
CN104022535B true CN104022535B (en) 2016-02-10

Family

ID=51439164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410280571.5A Active CN104022535B (en) 2014-06-20 2014-06-20 A kind of trans-regional installed capacity of wind-driven power coordinated planning method

Country Status (1)

Country Link
CN (1) CN104022535B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108053139B (en) * 2017-12-28 2022-03-25 北方大贤风电科技(北京)有限公司 Wind power plant combination method and system
CN110797906B (en) * 2018-08-02 2021-01-08 电力规划总院有限公司 Method and device for determining maximum installed capacity of wind power base and storage medium

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102510108A (en) * 2011-11-10 2012-06-20 山东电力调度中心 Method for calculating maximum wind power installed capacity of district power network
CN102545258A (en) * 2012-01-12 2012-07-04 西安交通大学 Power grid optimal planning method of large-scale grid-connected wind farm

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5494279B2 (en) * 2010-06-23 2014-05-14 東京電力株式会社 Thermal power generator operation planning system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102510108A (en) * 2011-11-10 2012-06-20 山东电力调度中心 Method for calculating maximum wind power installed capacity of district power network
CN102545258A (en) * 2012-01-12 2012-07-04 西安交通大学 Power grid optimal planning method of large-scale grid-connected wind farm

Also Published As

Publication number Publication date
CN104022535A (en) 2014-09-03

Similar Documents

Publication Publication Date Title
Shi et al. Comprehensive evaluation index system for wind power utilization levels in wind farms in China
CN104882905B (en) A kind of new energy for considering transient security constraint receives capability assessment method
CN103412526B (en) A kind of thermal power plant unit is in the dispatching method of specific electric load and system
CN104377726B (en) A kind of peak regulating method of extensive new energy grid-connected power
CN103530817A (en) Distributed photovoltaic grid-connected adaptability evaluation method
CN109214655A (en) Construction method of power grid construction level and economic structure and acceleration evaluation index system thereof
CN105071423B (en) Energy storage system capacity allocation method taking wind limiting characteristic and economy into consideration
CN103366030A (en) Operation simulation method with wind electricity and pumped storage power station united to bear system base loads
CN102769299B (en) Wind farm voltage control method based on voltage operating state
CN112241923B (en) Distribution network power balance method based on comprehensive energy system source load equivalent external characteristics
CN103049609A (en) Wind power multi-stage scene simulation method
Chen et al. Scheduling strategy of hybrid wind-photovoltaic-hydro power generation system
CN102769292B (en) Method for enhancing voltage safety margin of wind farm
CN104022535B (en) A kind of trans-regional installed capacity of wind-driven power coordinated planning method
CN103824231B (en) A kind of wind energy turbine set transformator selection method considering wind power distribution characteristics
Liu et al. Multi-objective optimal reactive power dispatch for distribution network considering pv generation uncertainty
CN103186818A (en) Optimal matching method for wind turbine generator systems and wind resource conditions
CN105207255A (en) Electric system peak regulation calculation method suitable for wind power output
CN105225070A (en) Energy-saving power generation dispatching method of planning and system
Li et al. Proportion optimization of wind and solar power capacity for regional power network
Chowdhury et al. Optimal allocation of wind based DG for enhancement of technical, economic and social benefits using jaya algorithm for radial distribution networks
CN102790402B (en) Fan selecting method for grid connection point voltage of wind power farm
Hadjsaid et al. Considering local photovoltaic production in planning studies for low voltage distribution grids
CN104063812A (en) Method for evaluating low voltage ride-through performance of wind-solar complementary power generation system
CN105391085A (en) Nuclear power-wind power joint running analysis method taking nuclear power unit maintenance optimization into consideration

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant