CN103995162A - Power distribution network large user real-time electricity larceny prevention method based on advanced measuring system - Google Patents

Power distribution network large user real-time electricity larceny prevention method based on advanced measuring system Download PDF

Info

Publication number
CN103995162A
CN103995162A CN201410224870.7A CN201410224870A CN103995162A CN 103995162 A CN103995162 A CN 103995162A CN 201410224870 A CN201410224870 A CN 201410224870A CN 103995162 A CN103995162 A CN 103995162A
Authority
CN
China
Prior art keywords
power
stealing
feeder line
user
reactive power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410224870.7A
Other languages
Chinese (zh)
Other versions
CN103995162B (en
Inventor
苏海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Electric Power University
Original Assignee
North China Electric Power University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Electric Power University filed Critical North China Electric Power University
Priority to CN201410224870.7A priority Critical patent/CN103995162B/en
Publication of CN103995162A publication Critical patent/CN103995162A/en
Application granted granted Critical
Publication of CN103995162B publication Critical patent/CN103995162B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention belongs to the technical field of electricity larceny prevention of electric system distribution lines, and particularly relates to a power distribution network large user real-time electricity larceny prevention method based on an advanced measuring system. The method includes the steps that firstly, measured data of all intelligent electric meters are read, then, load flow calculation is conducted on user voltages and power at the current moment, the theoretical line loss active power and the theoretical line loss reactive power of a feeder line and the calculation voltages of all nodes are acquired, the electricity larceny power of a user is calculated, the electricity larceny behavior of the user is judged, if electricity larceny exists, monitoring points of voltage deviation are ranked from large to small, electricity larceny point positioning and electricity larceny amount calculation are conducted through a point-by-point electricity larceny power iterative optimization calculation method, and then electricity larceny alarming information is sent out. The method has the advantages of being high in data measurement and calculation accuracy, good in synchronism, high in speed and accurate in positioning, electricity larceny points can be found in real time and electricity larceny power can be calculated in real time, treatment is conducted immediately after the electricity larceny points are found, and losses of power supply enterprises are reduced to the maximum degree.

Description

The real-time electricity anti-theft method of power distribution network large user based on senior measurement system
Technical field
The invention belongs to the anti-theft electricity technology field of electric system distribution line, relate in particular to a kind of real-time electricity anti-theft method of power distribution network large user based on senior measurement system.
Background technology
For a long time, stealing electricity phenomenon is the problem that electric power enterprise is extremely paid close attention to always, and particularly large user's stealing is brought tremendous economic loss to country and electric power enterprise, but also brings a series of potential safety hazard and social concern.General in the electricity sales amount of various places power supply enterprise, 10kV dedicated transformer large user accounts for more than 70%.Therefore, do a good job of it 10kV dedicated transformer large user's anti-electricity-theft control, just can compared with great dynamics improve the economic benefit of power supply enterprise.Common stealing side is as follows: undercurrent stealing gimmick, under-voltage stealing gimmick, the poor stealing gimmick that expands, phase shift stealing gimmick, nothing table stealing gimmick, high-tech stealing gimmick etc.For above problem, power supply enterprise also actively develops the technical method of the aspect of opposing electricity-stealing, although obtained certain effect, these methods people can not control the generation of stealing electricity phenomenon completely, discovery user's that particularly can not be real-time electricity filching behavior.
The intelligent grid of the performances such as construction has flexibly, cleans, safety, economy, close friend is the developing direction of following electrical network.As most important technical support module in intelligent grid, senior measurement system (Advanced Metering Infrastructure, AMI) in intelligent grid, taking on very important role, in intelligent grid, a lot of intelligent functions are implemented by AMI and complete.It utilize intercommunication system and can recording user the intelligent electric meter of detailed information on load, can obtain user with time target at times or the multiple variable of (or quasi real time) in real time, as information such as power consumption, need for electricity, voltage, electric currents.Therefore, AMI is a basic functional module of intelligent grid, also referred to as intelligence, measures system.With traditional electric distribution network data collection and supervisory system (Supervisory Control And Data Acquisition, SCADA) compare, AMI metric data management system (Meter Data Management System, MDMS) can not only provide the metric data that data precision and sample frequency are higher, can also provide by load real-time measurement data, this is that distribution SCADA is not available.Senior measurement architectural schematic as shown in Figure 1.
The enforcement of AMI and application have improved the measurement redundance of distribution system greatly, for solid foundation has been established in the enforcement of the real-time electricity anti-theft method of power distribution network large user.AMI is the basic link of intelligent grid, and major function is the electric information (with markers) that gathers each monitoring point, and makes power consumer set up contact with load, supports operation of power networks.In the information gathering at AMI, continuous data occupies most important status.These continuous datas had both comprised active energy and the reactive energy that common electric energy meter can measure, and comprised again the electric network state data such as voltage, electric current, power factor, forward and reverse power.Continuous data be the prerequisite that AMI and even other functions of intelligent grid are achieved accurately and reliably.On the other hand, the continuous data that AMI gathers should not become the dead data that are kept in database, and should be used.By the abundant communication of AMI and calculating storage resources, data are carried out to deep processing and excavation, realize its value.The present invention is the real-time electricity anti-theft method based on AMI.
Summary of the invention
For current anti-theft electricity technology means, fall behind, and the measured data of AMI utilize the problem that degree is not high, propose a kind of real-time electricity anti-theft method of power distribution network large user based on senior measurement system, mainly comprise:
Step 1, read the metric data of each intelligent electric meter of MDMS current time, mainly comprise: the user node active-power P that each large user's distribution low-voltage side stoichiometric point or high-pressure side stoichiometric point, distribution feeder critical point stoichiometric point record i, user node reactive power Q i, user node voltage U i, feeder line outlet active-power P gz,, feeder line outlet reactive power Q gz,, feeder line Egress node voltage U g;
Step 2, the user node active-power P based on MDMS current time i, user node reactive power Q iwith feeder line outlet voltage U gcarry out trend calculating, obtain the theory wire loss active power Δ P of feeder line sc, theory wire loss reactive power Δ Q scwith each node calculating voltage U i_c;
Step 3, the user's stealing power calculation based on statistical line losses analytical approach;
Step 4, carry out the judgement of user's electricity filching behavior, if feeder line management line loss active power Δ P smwith feeder line management line loss reactive power Δ Q smbeing greater than threshold value δ has stealing to occur, and goes to step 5 and carries out stealing point location, otherwise occur without stealing;
Step 5, node voltage variance analysis;
Step 6, stealing point location and power-steeling quantity calculate, and send stealing warning message.
The active-power P of feeder line outlet for described step 3 gzdeduct all user's active power of feeder line sum deduct again the feeder line theory wire loss active power Δ P that step 2 calculates sc, obtain this feeder line management line loss active power Δ P sm; Reactive power Q with feeder line outlet gz, deduct all user's reactive powers of feeder line sum deduct again the feeder line theory wire loss reactive power Δ Q that step 2 calculates sc, obtain this feeder line management line loss reactive power; User's stealing rating formula based on statistical line losses analytical approach is shown below:
ΔP sm = P gz - Σ i = 1 N P i - ΔP sc ΔQ sm = Q gz - Σ i = 1 N Q i - ΔQ sc
Wherein, Δ P smfor feeder line management line loss active power, Δ Q smfeeder line management line loss reactive power, P gzfor the active power of feeder line outlet, Q gzthe reactive power of feeder line outlet.
In described step 4, feeder line management transmission power is greater than actual stealing power and measuring error sum as the higher limit of stealing power, can obtain thus stealing active power codomain [0, Δ P sm] and the codomain of stealing reactive power [0, Δ Q sm].
In described step 5 by the calculating voltage U of each load bus calculating by trend i_cwith user node voltage U iit is poor to do, and obtains each node voltage deviation delta U i, be shown below:
ΔU i=U i_c-U i
Due to the generation of electricity filching behavior, the active power that stealing point is uploaded and reactive power are less than active power and the reactive power of stealing point actual consumption, the U that trend calculates i_cbe greater than each user node U i, and the voltage deviation Δ U of the neighbor node after stealing point and stealing point ilarger.
In described step 6, be by the Δ U in step 5 icarry out from big to small monitoring point sequence, adopt pointwise stealing power iteration optimization computing method to carry out stealing point location and power-steeling quantity calculating; Derivation algorithm adopts basic particle group algorithm, and stealing active power and reactive power are variable to be solved, and objective function is each node voltage absolute value of the bias sum of feeder line minimum, hour, power distribution network running status and trend computing mode are on all four, and constraint condition is that stealing active power is less than this feeder line management line loss active power Δ P sc, stealing reactive power is less than this feeder line management line loss reactive power Δ Q sm.
The invention has the beneficial effects as follows the data management system of the senior measurement system based on existing power distribution network, electricity consumption data to large user gather computational analysis, calculate feeder line theory wire loss power, node voltage, and judge whether to occur the calculating of stealing and stealing point location and power-steeling quantity, have that measurements and calculations data precision is high, synchronism good, speed is fast, the feature of accurate positioning, can find in real time stealing point and calculate stealing power, accomplish to find at any time to administer at any time, reduce to greatest extent the loss of power supply enterprise.
Accompanying drawing explanation
Fig. 1 is senior measurement architectural schematic;
Fig. 2 is the real-time electricity anti-theft method process flow diagram of the power distribution network large user based on senior measurement system;
Fig. 3 is the senior measurement system arrangement plan of power distribution network;
Fig. 4 is power distribution network topological structure and parameter distribution in embodiment.
Embodiment
Below in conjunction with drawings and Examples, method proposed by the invention is described further.
The invention discloses a kind of real-time electricity anti-theft method of power distribution network large user based on senior measurement system, particular content is as follows:
Target user node voltage U when the intelligent electric meter in the senior measurement system of intelligent distribution network can be the band of each monitoring point (large user's distribution low-voltage side stoichiometric point or high-pressure side stoichiometric point, distribution feeder critical point stoichiometric point) i, user node active-power P i, user node reactive power Q iupload to the MDMS of senior measurement system.
Due to senior measurement system have clock synchronous function (generally by software to time mode realize), target node voltage U during the band that obtains i, active-power P i, reactive power Q iunder the mode of power distribution network steady-state operation, can be used as the data of section at the same time, meet node voltage and Branch Power Flow equation, can carry out distribution power system load flow calculation.
Based on MDMS data constantly, utilize distribution feeder trend computing module to carry out trend calculating, obtain the theory wire loss active power Δ P of feeder line sc, theory wire loss reactive power Δ Q scwith each node calculating voltage U i_c.
The active-power P that the critical point intelligent electric meter (as shown in Fig. 3 1.) providing with MDMS is measured gz, reactive power Q gzdeduct respectively each user's electric energy meter (as in Fig. 3 2. 3. 4. 5. 6. as shown in) active power sum reactive power sum obtain the statistical line losses active power Δ P of this feeder line stwith statistical line losses reactive power Δ Q st, as shown in formula (2).
ΔP st = P gz - Σ i = 1 N P i ΔQ st = Q gz - Σ i = 1 N Q i - - - ( 2 )
Statistical line losses active power Δ P with this feeder line stwith statistical line losses reactive power Δ Q stdeduct respectively the theory wire loss active power Δ P of this feeder line scwith theory wire loss reactive power Δ Q sc, obtain the management line loss active power Δ P of this feeder line smwith management line loss reactive power Δ Q sm, as shown in formula (3).
ΔP sm = ΔP st - ΔP sc ΔQ sm = ΔQ st - ΔQ sc - - - ( 3 )
Because the theory wire loss power of feeder line is to calculate according to the measurement performance number of intelligent electric meter, be less than the active loss power (practical line loss power is produced by measurement power and the acting in conjunction of stealing power of electric energy meter) of this feeder line.Therefore, the feeder line that obtained by formula (3) management transmission power is greater than actual stealing power and measuring error sum, can be similar to the higher limit as stealing power, can obtain thus stealing active power codomain [0, Δ P sm] and the codomain of stealing reactive power [0, Δ Q sm].
Management line loss equals the difference that statistical line losses deducts theory wire loss, and theory wire loss is inevitably, be that distribution line will consume really, and statistical line losses is the true loss of power supply enterprise.Management transmission power is mainly produced by measuring error and stealing.In intelligence measurement system, the power attenuation that measuring error causes is much smaller than stealing power, and in theory, if do not consider measuring error, while occurring without stealing, the management transmission power of feeder line is zero.Therefore,, if the management transmission power of feeder line is larger, explanation has stealing to occur.
In addition, when stealing electricity phenomenon occurs, (suppose that stealing point occurs in Fig. 3 4. point), 4. put P that intelligent electric meter measures, Q value than actual value (realtime power of user's actual consumption for 4. point measurement power and stealing power sum) less than normal.Due to 4. point measurement to active power and the reactive power active power and the reactive power that are less than user's actual consumption, so the calculating voltage value of each node of calculating of trend can be more higher than the measured value obtaining by electric energy meter.By the calculating voltage U of each load bus calculating by trend i_cwith user node U iit is poor to do, and obtains each node voltage deviation delta U i, as shown in formula (4).Generation due to electricity filching behavior, the active power that stealing point is uploaded and reactive power are less than active power and the reactive power of stealing point actual consumption, the magnitude of voltage that trend calculates is greater than each monitoring point actual voltage value, and the voltage deviation of the neighbor node after stealing point and stealing point is larger, the possibility of the node generation stealing that voltage deviation is larger is larger.
ΔU i=U i_c-U i (4)
Stealing point location with cut electric power and calculate.With stealing active power and reactive power, for variable to be solved, objective function is each node voltage deviation sum of feeder line minimum hour, power distribution network actual motion status data and the trend computational data based on measurement data are on all four), constraint condition is that stealing active power is less than this feeder line management loss active power Δ P sc, stealing reactive power is less than this feeder line management loss reactive power Δ Q sm.Derivation algorithm adopts basic particle group algorithm.
It is below the applied stealing analysis of the method enforcement calculated example of not considering that measuring error adopts the present invention to propose.
The equivalent power distribution network shown in Fig. 4 of take is example, carries out electricity filching behavior judgement and stealing point location, and the branch impedance parameter in figure, transformer impedance parameter are for conversion is on high-tension side parameter.
Reading the measurement data of current time in MDMS comprises: critical point intelligent electric meter measuring voltage amplitude 10.5kV, active power 2134.44kW, reactive power 1086.72kVar (in this simulation example active power 2134.44kW and reactive power 1086.72kVar carry out trend according to user's actual load calculate), the active power of each user's intelligent electric meter, reactive power and node voltage amplitude, as shown in fourth, fifth, six row in table 1.
Active power, the reactive power data that the voltage magnitude of measuring based on critical point intelligent electric meter and each user's intelligent electric meter are measured push back generation calculating before carrying out.Obtain computing node voltage and feeder line theory wire loss power based on measurement data, as shown in table 1 the 7th row and the 8th row.
With active power 2134.44kW, the reactive power 1086.72kVar of critical point intelligent electric meter, deduct respectively feeder line theory wire loss active power 83.74kW, theory wire loss reactive power 128.82kVar, deduct again measurement active power 1830kW and the reactive power 830kVar of each load point, obtain management active loss power 220.70kW and the management reactive loss power 147.90kVar of this feeder line, as shown in table 1 the 9th row.Do not consider in theory measuring error, while occurring without stealing, the management transmission power of feeder line is zero.The management line loss active power that this example obtains is 220.70kW, and management line loss reactive power is 147.90kVar, can conclude and have stealing to occur.
In addition, by calculating each node calculating voltage and uploading the poor of magnitude of voltage, obtain each node voltage deviation, the node that voltage deviation is larger is doubtful stealing node.By last row of table 1, can be found out, 4. 5. 6. 2. 3. the doubtful degree of node stealing node generation stealing is from high to low successively, meets stealing point and the stealing point larger judgment criterion of neighbor node voltage deviation afterwards in step 5.
Table 1 power distribution network stealing data analysis
Stealing point location and stealing power calculation.Suppose that respectively node, 4. 5. 6. for suspicious stealing contact, adopts particle cluster algorithm, with stealing active power and reactive power, for variable to be solved, objective function is each node voltage deviation sum of feeder line minimum, constraint condition is that stealing active power codomain is [0,220.70] kW, stealing reactive power codomain is [0,147.90] kVar.In order to verify that 3. 2. the probability of stealing occur is minimum, to node be 2. 3. also assumed to be stealing point capable power-steeling quantity analysis.The analysis result of each node is as shown in table 2.
Each node voltage deviation sum when table 2 stealing occurs in different node
4. the load point of voltage deviation absolute value sum minimum is stealing point, while supposing 2. 3. for stealing node, Σ i = 1 N | ΔU i | Larger.
The error analysis of the inventive method:
The middle-and-high-ranking measurement system of practical application has measuring error, and the error of mark is electric energy metering error conventionally, and the precision of senior measurement system is all in 0.5 grade, and the precision that special gate energy meter has reaches 0.2 grade or 0.1 grade.The measuring accuracy of the power of senior measurement system, voltage, electric current will be far above electric energy metrical precision, conventionally in 0.2 grade.
Therefore the stealing analysis of considering measuring error is the key point of weighing the method practicality.
The measurement relative error of supposing power and voltage is below respectively ± 0.2% and ± 0.1% carry out simulation calculation, and result is respectively if table 3 is to as shown in table 6.
Simulation analysis result when table 3 measurement relative error is ± 0.2%
Each node voltage deviation sum when table 4 stealing occurs in different node
Simulation analysis result when table 5 measurement relative error is ± 0.1%
Each node voltage deviation sum when table 6 stealing occurs in different node
By table 4 and table 6, can be found out, the senior measurement system based on 0.2 grade and 0.1 grade, can accurately analyze stealing position and stealing power.
In addition, the method computational accuracy is also relevant with user's power-steeling quantity size, through simulation calculation, power-steeling quantity (applied power) is greater than 50kVA, and when measuring accuracy is 0.2 grade, system can accurately be judged stealing point and stealing power, when measuring accuracy is 0.1 grade, the stealing that is greater than 20kVA can accurately be judged.When not meeting above-mentioned requirements, stealing is analyzed accurate qualitative meeting and is declined to some extent.While being 0.2 grade such as the precision of the measuring system adopting in above-mentioned example, when power-steeling quantity power is less than 50kVA, the stealing point of judging may be sometimes node 5..
About the stability analysis of particle swarm optimization algorithm result of calculation.With particle cluster algorithm, carry out multivariate optimization problem and release, exist each result of calculation inconsistent, this is because the randomness of particle cluster algorithm produces, that is, differ and find surely optimum solution, and be normal phenomenon.When optimization problem is relatively simple, each result of calculation can be consistent,, can find optimum solution that is at every turn.Variable to be optimized of the present invention only has two, and value constraint within the specific limits.Actual analysis finds, population scale is 60, and when maximum iteration time is 30 times, result of calculation is unique, while finding the mean iterative number of time of optimum solution 10 times.
The above; be only the present invention's embodiment preferably, but protection scope of the present invention is not limited to this, is anyly familiar with in technical scope that those skilled in the art disclose in the present invention; the variation that can expect easily or replacement, within all should being encompassed in protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection domain of claim.

Claims (5)

1. the real-time electricity anti-theft method of power distribution network large user based on senior measurement system, is characterized in that, mainly comprises:
Step 1, read the metric data of each intelligent electric meter of MDMS current time, mainly comprise: the user node active-power P that each large user's distribution low-voltage side stoichiometric point or high-pressure side stoichiometric point, distribution feeder critical point stoichiometric point record i, user node reactive power Q i, user node voltage U i, feeder line outlet active-power P gz, feeder line outlet reactive power Q gz, feeder line Egress node voltage U g;
Step 2, the user node active-power P based on MDMS current time i, user node reactive power Q iwith feeder line Egress node voltage U gcarry out trend calculating, obtain the theory wire loss active power Δ P of feeder line sc, theory wire loss reactive power Δ Q scwith each node calculating voltage U i_c;
Step 3, the user's stealing power calculation based on statistical line losses analytical approach;
Step 4, carry out the judgement of user's electricity filching behavior, if feeder line management line loss active power Δ P smwith feeder line management line loss reactive power Δ Q smbeing greater than threshold value δ has stealing to occur, and goes to step 5 and carries out stealing point location, otherwise occur without stealing;
Step 5, node voltage variance analysis;
Step 6, stealing point location and power-steeling quantity calculate, and send stealing warning message.
2. method according to claim 1, is characterized in that, the active-power P of feeder line outlet for described step 3 gzdeduct all user's active power of feeder line sum deduct again the feeder line theory wire loss active power Δ P that step 2 calculates sc, obtain this feeder line management line loss active power Δ P sm; Reactive power Q with feeder line outlet gz, deduct all user's reactive powers of feeder line sum deduct again the feeder line theory wire loss reactive power Δ Q that step 2 calculates sc, obtain this feeder line management line loss reactive power; User's stealing rating formula based on statistical line losses analytical approach is shown below:
ΔP sm = P gz - Σ i = 1 N P i - ΔP sc ΔQ sm = Q gz - Σ i = 1 N Q i - ΔQ sc
Wherein, Δ P smfor feeder line management line loss active power, Δ Q smfeeder line management line loss reactive power, P gzfor the active power of feeder line outlet, Q gzthe reactive power of feeder line outlet.
3. method according to claim 1, is characterized in that, in described step 4, feeder line management transmission power is greater than actual stealing power and measuring error sum as the higher limit of stealing power, can obtain thus stealing active power codomain [0, Δ P sm] and the codomain of stealing reactive power [0, Δ Q sm], wherein, Δ P smfor feeder line management line loss active power, Δ Q smfeeder line management line loss reactive power.
4. method according to claim 1, is characterized in that, in described step 5 by the calculating voltage U of each load bus calculating by trend i_cwith user node voltage U iit is poor to do, and obtains each node voltage deviation delta U i, be shown below:
ΔU i=U i_c-U i
Due to the generation of electricity filching behavior, the active power that stealing point is uploaded and reactive power are less than active power and the reactive power of stealing point actual consumption, the U that trend calculates i_cbe greater than each user node voltage U i, and the voltage deviation Δ U of the neighbor node after stealing point and stealing point ilarger.
5. method according to claim 1, is characterized in that, is by each node voltage deviation delta U in step 5 in described step 6 icarry out from big to small monitoring point sequence, adopt pointwise stealing power iteration optimization computing method to carry out stealing point location and power-steeling quantity calculating; Derivation algorithm adopts basic particle group algorithm, and stealing active power and reactive power are variable to be solved, and objective function is each node voltage absolute value of the bias sum of feeder line minimum, hour, power distribution network running status and trend computing mode are on all four, and constraint condition is that stealing active power is less than this feeder line management line loss active power Δ P sc, stealing reactive power is less than this feeder line management line loss reactive power Δ Q sm.
CN201410224870.7A 2014-05-26 2014-05-26 The real-time electricity anti-theft method of power distribution network large user based on senior measurement system Expired - Fee Related CN103995162B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410224870.7A CN103995162B (en) 2014-05-26 2014-05-26 The real-time electricity anti-theft method of power distribution network large user based on senior measurement system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410224870.7A CN103995162B (en) 2014-05-26 2014-05-26 The real-time electricity anti-theft method of power distribution network large user based on senior measurement system

Publications (2)

Publication Number Publication Date
CN103995162A true CN103995162A (en) 2014-08-20
CN103995162B CN103995162B (en) 2016-10-05

Family

ID=51309382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410224870.7A Expired - Fee Related CN103995162B (en) 2014-05-26 2014-05-26 The real-time electricity anti-theft method of power distribution network large user based on senior measurement system

Country Status (1)

Country Link
CN (1) CN103995162B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107741530A (en) * 2017-10-10 2018-02-27 珠海许继电气有限公司 A kind of release unit that management through quantification is realized to line loss, system and implementation method
CN109142831A (en) * 2018-09-21 2019-01-04 国网安徽省电力公司电力科学研究院 A kind of resident's exception electricity consumption analysis method and device based on impedance analysis
CN109557362A (en) * 2018-11-24 2019-04-02 国网青海省电力公司西宁供电公司 A kind of anti-electricity-theft monitoring method of distribution line and system
CN110045194A (en) * 2018-01-15 2019-07-23 国网江苏省电力公司常州供电公司 High voltage supply route is opposed electricity-stealing method
CN110082577A (en) * 2019-04-18 2019-08-02 中国电力科学研究院有限公司 It is a kind of for judging the diagnostic method and system of electricity-saving appliance electricity stealing
CN110187239A (en) * 2019-06-17 2019-08-30 邓宏伟 A kind of low-voltage distribution net wire loss based on straight algorithm and the steathily calculation method of leakage point of electricity
CN110945368A (en) * 2017-06-14 2020-03-31 伊顿智能动力有限公司 System and method for detecting power theft using integrity check analysis
CN112649642A (en) * 2020-12-14 2021-04-13 广东电网有限责任公司广州供电局 Electricity stealing position judging method, device, equipment and storage medium
CN113742878A (en) * 2021-11-04 2021-12-03 国网北京市电力公司 Power grid loss electric quantity position positioning method, system, equipment and medium
WO2024037351A1 (en) * 2022-08-19 2024-02-22 西门子(中国)有限公司 Non-technical loss detection method for electric power distribution system, electronic device, and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003021649A (en) * 2001-07-10 2003-01-24 Fuji Electric Co Ltd Electricity stealing prevention device, electricity stealing prevention method and program for executing method by computer
CN101477163A (en) * 2009-01-04 2009-07-08 保定市三川电气有限责任公司 Method for monitoring electric consumption
CN101477162A (en) * 2009-01-04 2009-07-08 保定市三川电气有限责任公司 Energy consumption monitoring terminal
CN101799681A (en) * 2010-02-10 2010-08-11 刘文祥 Intelligent grid
CN102735966A (en) * 2012-06-12 2012-10-17 燕山大学 Power transmission line evaluation and diagnosis system and power transmission line evaluation and diagnosis method
CN203151227U (en) * 2013-03-29 2013-08-21 山东电力集团公司 Line loss professional comprehensive management system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003021649A (en) * 2001-07-10 2003-01-24 Fuji Electric Co Ltd Electricity stealing prevention device, electricity stealing prevention method and program for executing method by computer
CN101477163A (en) * 2009-01-04 2009-07-08 保定市三川电气有限责任公司 Method for monitoring electric consumption
CN101477162A (en) * 2009-01-04 2009-07-08 保定市三川电气有限责任公司 Energy consumption monitoring terminal
CN101799681A (en) * 2010-02-10 2010-08-11 刘文祥 Intelligent grid
CN102735966A (en) * 2012-06-12 2012-10-17 燕山大学 Power transmission line evaluation and diagnosis system and power transmission line evaluation and diagnosis method
CN203151227U (en) * 2013-03-29 2013-08-21 山东电力集团公司 Line loss professional comprehensive management system

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110945368A (en) * 2017-06-14 2020-03-31 伊顿智能动力有限公司 System and method for detecting power theft using integrity check analysis
CN107741530A (en) * 2017-10-10 2018-02-27 珠海许继电气有限公司 A kind of release unit that management through quantification is realized to line loss, system and implementation method
CN110045194A (en) * 2018-01-15 2019-07-23 国网江苏省电力公司常州供电公司 High voltage supply route is opposed electricity-stealing method
CN110045194B (en) * 2018-01-15 2021-01-01 国网江苏省电力公司常州供电公司 Anti-electricity-stealing method for high-voltage power supply line
CN109142831A (en) * 2018-09-21 2019-01-04 国网安徽省电力公司电力科学研究院 A kind of resident's exception electricity consumption analysis method and device based on impedance analysis
CN109557362A (en) * 2018-11-24 2019-04-02 国网青海省电力公司西宁供电公司 A kind of anti-electricity-theft monitoring method of distribution line and system
CN110082577A (en) * 2019-04-18 2019-08-02 中国电力科学研究院有限公司 It is a kind of for judging the diagnostic method and system of electricity-saving appliance electricity stealing
CN110187239A (en) * 2019-06-17 2019-08-30 邓宏伟 A kind of low-voltage distribution net wire loss based on straight algorithm and the steathily calculation method of leakage point of electricity
CN110187239B (en) * 2019-06-17 2021-07-20 邓宏伟 Low-voltage distribution network line loss and electricity stealing and leakage point calculation method based on straight algorithm
CN112649642A (en) * 2020-12-14 2021-04-13 广东电网有限责任公司广州供电局 Electricity stealing position judging method, device, equipment and storage medium
CN113742878A (en) * 2021-11-04 2021-12-03 国网北京市电力公司 Power grid loss electric quantity position positioning method, system, equipment and medium
CN113742878B (en) * 2021-11-04 2022-02-11 国网北京市电力公司 Power grid loss electric quantity position positioning method, system, equipment and medium
WO2024037351A1 (en) * 2022-08-19 2024-02-22 西门子(中国)有限公司 Non-technical loss detection method for electric power distribution system, electronic device, and storage medium

Also Published As

Publication number Publication date
CN103995162B (en) 2016-10-05

Similar Documents

Publication Publication Date Title
CN103995162B (en) The real-time electricity anti-theft method of power distribution network large user based on senior measurement system
CN108448568B (en) Power distribution network hybrid state estimation method based on multiple time period measurement data
US10958101B2 (en) Methods and apparatus incorporating topology error estimation for management of an electric power system
CN100554976C (en) Area voltage stability monitoring method based on synchronous phasor measurement
US11824354B2 (en) Online state estimation and topology identification using advanced metering infrastructure (AMI) measurements
CN108074198B (en) Power system PMU bad data identification method
CN102651049A (en) Method for calculating loss reducing rate of newly built transformer station of electric power system
CN113156247B (en) Early warning method and device for low-frequency oscillation of power system
Junaidi et al. Big data applications in electric energy systems
CA2602980A1 (en) Method and system for real time identification of voltage stability via identification of weakest lines and buses contributing to power system collapse
Khare et al. Optimal PMU placement using matrix modification based integer linear programming
Gomathi et al. Optimal location of PMUs for complete observability of power system network
US20230327438A1 (en) Scalable state estimation for power distribution grid
CN110048428A (en) Probabilistic Load calculation method based on conservation of probability principle
Domínguez et al. Analysis of electric power consumption using Self-Organizing Maps.
Song et al. A new method for processing and application of wide area measurement big data in a power system
US20220284156A1 (en) Real-time update of power system models for dynamic security assessment
Sarkar et al. A comprehensive assessment of the need and availability of smart grid technologies in an electricity distribution grid network
CN104135077A (en) Power-distribution-network state simulation and evaluation system based on tree topology structure
Zhang et al. Robust integrated optimization of active distribution network based on system risk index
Kerin et al. Dynamic security indication in power systems with large amount of renewables
Feng et al. A Data-driven Modeling Method for Power Quality Disturbance sources in Distribution Networks
Liang et al. Intelligent early warning system for power theft in distribution network based on IOT technology
TÁCZI et al. CHAPTER ELEVEN STATE ESTIMATION ON A LOW VOLTAGE GRID CONSIDERING THE EFFECT OF HOUSEHOLD
Zhou et al. A Theoretical Line Loss Calculation Method Based on Data Partition

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161005

Termination date: 20170526