CN103993730B - 钢煤斗对接安装施工操作台 - Google Patents
钢煤斗对接安装施工操作台 Download PDFInfo
- Publication number
- CN103993730B CN103993730B CN201410246160.4A CN201410246160A CN103993730B CN 103993730 B CN103993730 B CN 103993730B CN 201410246160 A CN201410246160 A CN 201410246160A CN 103993730 B CN103993730 B CN 103993730B
- Authority
- CN
- China
- Prior art keywords
- coal hopper
- steel
- operation platform
- rack group
- abutting joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及一种钢煤斗对接安装施工操作台,包括圆环形的用于操作工站立施工的圆环支架组以及焊接固定于圆环支架组上的若干吊耳,所述圆环支架组的外径比钢煤斗圆柱段的内径小1-1.5米。本钢煤斗对接安装施工操作台结构简单,因此制作容易。组装方便,相对于脚手架的搭建方式既提高效率又保证了高空作业的安全,缩短了施工工期,且可重复多次使用。
Description
技术领域
本发明涉及施工平台技术领域。
背景技术
电站燃煤机组设计有大型钢煤斗用于存储原煤,钢煤斗在现场一般分为底部圆锥段和上部圆柱端两端,分别吊装施工,需要在高空进行对口焊接作业。现阶段在施工过程中采用的是在底部圆锥段内部,搭设满堂脚手架用于高空对接作业。此种方法需要耗用大量的钢管、扣件、架板、铁条等脚手架搭设材料,且耗用人工较多,安装、拆除脚手架时危险性较大,且施工周期长。
发明内容
本发明为了克服以上技术的不足,提供了一种安全性高、施工效率高的钢煤斗对接安装施工操作台。
本发明克服其技术问题所采用的技术方案是:
本钢煤斗对接安装施工操作台,包括圆环形的用于操作工站立施工的圆环支架组以及焊接固定于圆环支架组上的若干吊耳,所述圆环支架组的外径比钢煤斗圆柱段的内径小1-1.5米。
上述圆环支架组包括由槽钢折弯制成的圆环形的外圈、由槽钢折弯制成的圆环形的内圈、连接于外圈与内圈之间的若干连杆,圆环形的花纹板焊接固定于外圈与内圈上面上,所述花纹板的外径与内径分别与外圈的外径以及内圈的内径相匹配。
为了方便施工人员排上操作台,上述圆环支架组上固定有软爬梯,所述软爬梯的下端与地面接触。
为了提高安全性,还包括沿圆周方向竖直固定于内圈上的若干套筒、分别插装于每个套筒上的立杆,所述套筒以及立杆底部分别设置有圆孔,螺栓依次穿过套筒以及立杆上的圆孔并通过螺母固定,所述立杆上端以及中间部位分别设置有穿线孔,钢丝安全绳Ⅰ以及钢丝安全绳Ⅱ依次穿过各个立杆上端以及中间部位的穿线孔,并围绕形成封闭的圈形。
为了降低成本并保证足够的操作空间,上述外圈与内圈的外圆半径之差为400-600mm。
本发明的有益效果是:本钢煤斗对接安装施工操作台结构简单,因此制作容易。组装方便,相对于脚手架的搭建方式既提高效率又保证了高空作业的安全,缩短了施工工期,且可重复多次使用。
附图说明
图1为本发明的主视结构示意图;
图2为本发明的俯视结构示意图;
图3为圆环支架组的结构示意图;
图4为图1中的A局部放大结构示意图;
图5为本发明的使用状态结构示意图;
图中,1.圆环支架组1.1外圈1.2内圈1.3花纹板1.4连杆2.吊耳3.套筒4.立杆5.钢丝安全绳Ⅰ6.钢丝安全绳Ⅱ7.螺栓8.螺母9.钢煤斗圆柱段10.钢煤斗圆锥段11.软爬梯。
具体实施方式
下面结合附图1至附图5对本发明做进一步说明。
如附图1和附图4所示,本钢煤斗对接安装施工操作台,包括圆环形的用于操作工站立施工的圆环支架组1以及焊接固定于圆环支架组1上的若干吊耳2,圆环支架组1的外径比钢煤斗圆柱段9的内径小1-1.5米。如附图5所示,使用时先利用大型吊车将圆筒锥段吊运至安装位置并固定,然后将制作组装完成的施工平台,利用大型吊车将本钢煤斗对接安装施工操作台通过吊耳2吊运至钢煤斗圆锥段10内部。由于钢煤斗圆锥段10为锥形结构,因此圆环支架组1会卡在钢煤斗圆锥段10内,实现固定。之后用大型吊车将钢煤斗圆柱段9吊运至钢煤斗圆锥段10上方,调整吊车吊钩位置,使钢煤斗圆柱段9下口与钢煤斗圆锥段10上口能吻合对接。施工人员在圆环支架组1上进行钢煤斗圆柱段9下口与钢煤斗圆锥段10上口的对口焊接作业。焊接完成后,利用大型吊车将本钢煤斗对接安装施工操作台吊运至下一个钢煤斗圆锥段10内部,以进行下一组安装工作。由于本钢煤斗对接安装施工操作台结构简单,因此制作容易。组装方便,相对于脚手架的搭建方式既提高效率又保证了高空作业的安全,缩短了施工工期,且可重复多次使用。
如附图2和附图3所示,圆环支架组1可以为如下结构其包括由槽钢折弯制成的圆环形的外圈1.1、由槽钢折弯制成的圆环形的内圈1.2、连接于外圈1.1与内圈1.2之间的若干连杆1.4,圆环形的花纹板1.3焊接固定于外圈1.1与内圈1.2上面上,花纹板1.3的外径与内径分别与外圈1.1的外径以及内圈1.2的内径相匹配。由于外圈1.1与内圈1.2均由槽钢制成,因此其受力强度高,保证了可靠性,外圈1.1与内圈1.2之间通过若干连杆1.4连接,进一步提高了连接强度。因此圆环支架组1的结构简单、强度高、制造方便。外圈1.1与内圈1.2的外圆半径之差为400-600mm。如果外圈1.1与内圈1.2的外圆半径差过大,就会造成铺设的花纹板1.3的浪费,增加了制造成本以及操作台的重量,而差值过小就会导致施工人员站立施工时的空间过小,倒是施工工作不便。因此设置在400-600mm的差值是合理的范围。
如附图5所示,圆环支架组1上固定有软爬梯11,软爬梯11的下端与地面接触。施工人员可以通过软爬梯11方便攀爬至本钢煤斗对接安装施工操作台上,进一步提高了使用的便利性。
还可以包括沿圆周方向竖直固定于内圈1.2上的若干套筒3、分别插装于每个套筒3上的立杆4,套筒3以及立杆4底部分别设置有圆孔,螺栓7依次穿过套筒3以及立杆4上的圆孔并通过螺母8固定,立杆4上端以及中间部位分别设置有穿线孔,钢丝安全绳Ⅰ5以及钢丝安全绳Ⅱ6依次穿过各个立杆4上端以及中间部位的穿线孔,并围绕形成封闭的圈形。围绕成圈的钢丝安全绳Ⅰ5以及钢丝安全绳Ⅱ6可以防止施工人员从本钢煤斗对接安装施工操作台的内圈1.2的内孔处摔落,提高了安全性。
Claims (4)
1.一种钢煤斗对接安装施工操作台,包括圆环形的用于操作工站立施工的圆环支架组(1)以及焊接固定于圆环支架组(1)上的若干吊耳(2),其特征在于:所述圆环支架组(1)的外径比钢煤斗圆柱段(9)的内径小1-1.5米,所述圆环支架组(1)包括由槽钢折弯制成的圆环形的外圈(1.1)、由槽钢折弯制成的圆环形的内圈(1.2)、连接于外圈(1.1)与内圈(1.2)之间的若干连杆(1.4),圆环形的花纹板(1.3)焊接固定于外圈(1.1)与内圈(1.2)上面上,所述花纹板(1.3)的外径与内径分别与外圈(1.1)的外径以及内圈(1.2)的内径相匹配。
2.根据权利要求1所述的钢煤斗对接安装施工操作台,其特征在于:所述圆环支架组(1)上固定有软爬梯(11),所述软爬梯(11)的下端与地面接触。
3.根据权利要求1所述的钢煤斗对接安装施工操作台,其特征在于:还包括沿圆周方向竖直固定于内圈(1.2)上的若干套筒(3)、分别插装于每个套筒(3)上的立杆(4),所述套筒(3)以及立杆(4)底部分别设置有圆孔,螺栓(7)依次穿过套筒(3)以及立杆(4)上的圆孔并通过螺母(8)固定,所述立杆(4)上端以及中间部位分别设置有穿线孔,钢丝安全绳Ⅰ(5)以及钢丝安全绳Ⅱ(6)依次穿过各个立杆(4)上端以及中间部位的穿线孔,并围绕形成封闭的圈形。
4.根据权利要求1所述的钢煤斗对接安装施工操作台,其特征在于:所述外圈(1.1)与内圈(1.2)的外圆半径之差为400-600mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410246160.4A CN103993730B (zh) | 2014-06-05 | 2014-06-05 | 钢煤斗对接安装施工操作台 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410246160.4A CN103993730B (zh) | 2014-06-05 | 2014-06-05 | 钢煤斗对接安装施工操作台 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103993730A CN103993730A (zh) | 2014-08-20 |
CN103993730B true CN103993730B (zh) | 2016-04-20 |
Family
ID=51308045
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410246160.4A Active CN103993730B (zh) | 2014-06-05 | 2014-06-05 | 钢煤斗对接安装施工操作台 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103993730B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106320679B (zh) * | 2016-11-03 | 2018-06-29 | 中铁十局集团有限公司 | 超大型集束多边形煤仓群多功能隔离施工平台及施工方法 |
CN106320683B (zh) * | 2016-11-03 | 2018-06-29 | 中铁十局集团有限公司 | 超大型集束多边形煤仓群的圆锥体钢煤斗安装用平台 |
CN106760830B (zh) * | 2016-12-09 | 2019-03-26 | 中铁十局集团有限公司 | 超大型集束多边形煤仓群圆锥体钢煤斗拼装施工方法 |
CN110042180A (zh) * | 2019-05-21 | 2019-07-23 | 北京首钢建设集团有限公司 | 炉外环形平台在高炉建设中炉壳焊接环境的施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2314008Y (zh) * | 1997-10-24 | 1999-04-14 | 王玉群 | 锥形体建筑物表面高空作业装置 |
JP2006124965A (ja) * | 2004-10-27 | 2006-05-18 | Murayama Doken:Kk | 鉄塔組立工法及び組立用足場 |
CN201224993Y (zh) * | 2007-11-27 | 2009-04-22 | 吴杰 | 烟囱、井道内壁施工用升降架体 |
CN202055501U (zh) * | 2011-03-28 | 2011-11-30 | 三一重工股份有限公司 | 粉料罐中节筒仓与锥节筒仓连接用施工平台 |
CN203905426U (zh) * | 2014-06-05 | 2014-10-29 | 山东电力建设第一工程公司 | 钢煤斗对接安装施工操作台 |
-
2014
- 2014-06-05 CN CN201410246160.4A patent/CN103993730B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2314008Y (zh) * | 1997-10-24 | 1999-04-14 | 王玉群 | 锥形体建筑物表面高空作业装置 |
JP2006124965A (ja) * | 2004-10-27 | 2006-05-18 | Murayama Doken:Kk | 鉄塔組立工法及び組立用足場 |
CN201224993Y (zh) * | 2007-11-27 | 2009-04-22 | 吴杰 | 烟囱、井道内壁施工用升降架体 |
CN202055501U (zh) * | 2011-03-28 | 2011-11-30 | 三一重工股份有限公司 | 粉料罐中节筒仓与锥节筒仓连接用施工平台 |
CN203905426U (zh) * | 2014-06-05 | 2014-10-29 | 山东电力建设第一工程公司 | 钢煤斗对接安装施工操作台 |
Also Published As
Publication number | Publication date |
---|---|
CN103993730A (zh) | 2014-08-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103993730B (zh) | 钢煤斗对接安装施工操作台 | |
CN201990404U (zh) | 房顶便携式起吊机 | |
CN204224191U (zh) | 用于烟气脱硫工程的钢内筒烟囱提升安装装置 | |
CN202073325U (zh) | 组合式定型外墙安全平网 | |
CN103043543B (zh) | 沿海区域塔吊加固装置 | |
CN103342296A (zh) | 风电设备吊装附着自升式塔吊 | |
CN202544468U (zh) | 拉杆型电力钢管杆 | |
CN203820287U (zh) | 钢结构厂房屋面瓦吊装组合钢扁担 | |
CN203320927U (zh) | 可扩展式烟囱防腐改造专用提升平台 | |
CN203905426U (zh) | 钢煤斗对接安装施工操作台 | |
CN205132955U (zh) | 一种电力行业低空吊装作业用吊装架 | |
CN202400754U (zh) | 桅杆式起重机 | |
CN203461720U (zh) | 简易悬臂吊装机械 | |
CN201722974U (zh) | 伸缩旗杆 | |
CN103362315B (zh) | 一种管道整体吊装用的吊架及其施工方法 | |
CN205132926U (zh) | 水轮发电机组尾水肘管的专用井字吊具 | |
CN204281116U (zh) | 风力发电塔跨越自爬式平移吊机 | |
CN204588457U (zh) | 自卸式箱型钢柱吊装夹具装置 | |
CN104110155B (zh) | 一种薄壁钢管杆塔及其加工与施工方法 | |
CN202467221U (zh) | 发电厂主厂房钢屋架吊装起重装置 | |
CN204002535U (zh) | 一种用于通信塔可拆卸式的爬梯 | |
CN204001927U (zh) | 输电钢管塔横担跨步拉手 | |
CN203654698U (zh) | 双导轨附着式升降脚手架结构 | |
CN201980890U (zh) | 高空特殊环境下吊装用人字起重桅杆 | |
CN204265249U (zh) | 一种门式起重机及其龙门架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: No.6 building, zone 2, Hanyu financial and business center, hi tech Zone, Jinan City, Shandong Province Patentee after: SEPCO1 ELECTRIC POWER CONSTRUCTION CORPORATION Co.,Ltd. Address before: 250131 No. 244 Industrial North Road, Jinan City, Shandong Province Patentee before: SEPCO1 ELECTRIC POWER CONSTRUCTION Corp. |