CN103979073A - Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe - Google Patents

Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe Download PDF

Info

Publication number
CN103979073A
CN103979073A CN201410225992.8A CN201410225992A CN103979073A CN 103979073 A CN103979073 A CN 103979073A CN 201410225992 A CN201410225992 A CN 201410225992A CN 103979073 A CN103979073 A CN 103979073A
Authority
CN
China
Prior art keywords
anchor
segmentation
hawse pipe
hawse
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410225992.8A
Other languages
Chinese (zh)
Inventor
尹志双
王飞腾
孟鹏
张华�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiangnan Changxing Heavy Industry Co Ltd
Original Assignee
Shanghai Jiangnan Changxing Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiangnan Changxing Heavy Industry Co Ltd filed Critical Shanghai Jiangnan Changxing Heavy Industry Co Ltd
Priority to CN201410225992.8A priority Critical patent/CN103979073A/en
Publication of CN103979073A publication Critical patent/CN103979073A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention provides an installation method for segmented pre-installation of an anchor table, an anchor mouth and a hawse pipe. The installation method comprises a first step of performing segmented division on a bow ship body structure, enabling two subsections of the top to form a first subsection and a second subsection; a second step of breaking the hawse pipe along the normal to form an upper hawse pipe and a lower hawse pipe, and respectively dividing the upper hawse pipe and the lower hawse pipe to the first subsection and the second subsection; a third step of performing segmented installation of the anchor table, the anchor mouth and the hawse pipe in the second subsection; and a fourth step of enabling the lower hawse pipe to be in butt joint with the upper hawse pipe when the first subsection and the second subsection are assembled. According to the installation method, not only is integrity of the ship body structure improved, but also the dock construction working environment is greatly improved, working at heights is avoided, the damage to outside plate paint is also reduced, the dock cycle is reduced, and shipbuilding efficiency is improved.

Description

The installation method of anchor platform, anchor lip and hawse pipe segmentation prepackage
Technical field
The present invention relates to ship building technical field, especially relate to the installation method of a kind of anchor platform, anchor lip and hawse pipe segmentation prepackage.
Background technology
Hawse pipe is the duct of turnover and collection anchor, and its diameter is about 10 times of left and right of anchor chain diameter.Hawse pipe is comprised of chain hole, deck, side of a ship side chain hole and cylindrical shell three parts.The upper and lower opening of hawse pipe is generally equipped with that anchor lip is called anchor lip, the lip that casts anchor, and its effect is the abrasion that reduces anchor chain and upper and lower opening.In cylindrical shell, be provided with flushometer, for rinse anchor and anchor chain when weighing anchor.At chain hole, deck place, be provided with storm cover, to prevent that seawater from swarming deck from hawse pipe, can also guarantee staff's safety, some ships are provided with chain cable fairlead at place, chain hole, deck, to alleviate the friction in anchor chain and chain hole, deck.
The position of hawse pipe and size should be able to meet: while receiving anchor, make anchor fluke be close to shell, shank is stayed in hawse pipe together with change; While casting anchor, make shank be easy to hawse pipe.In addition, the end opening of hawse pipe should have certain distance from fully loaded water, and while navigating by water to reduce, Mintrop wave impacts anchor body; There is suitable distance the position of hawse pipe apart from boats and ships center line, and anchor fluke is stuck on stem when avoiding weighing anchor.
In order to increase building berth production efficiency, reduce time on building berth, the Installation Modes that hawse pipe is pre-installed in bow segmentation obtains applying more and more widely.But the difference due to hull structure, the position in side of a ship side chain hole can be different, cause boats and ships being carried out to when segmentation is divided side of a ship side chain hole can being broken as to two parts, the hull structure relating to can cannot be assembled in advance and weld, cause hawse pipe, anchor platform and anchor lip cannot install in advance equally, thereby it is elongated to have affected construction period, production efficiency reduces, the problems such as outside plate breakdown of coating.
Summary of the invention
Technical matters to be solved by this invention is exactly for above shortcomings in prior art, provides the installation method of a kind of anchor platform, anchor lip and hawse pipe segmentation prepackage, for solving the problems of the prior art.
For achieving the above object and other relevant objects, the invention provides the installation method of a kind of anchor platform, anchor lip and hawse pipe segmentation prepackage, comprise the following steps:
1) bow hull structure is carried out to segmentation division, two segmentations at top form the first segmentation and the second segmentation;
2) hawse pipe disconnects and forms upper hawse pipe and the chain barrel that casts anchor along normal, and is divided in respectively in described the first segmentation and the second segmentation;
3) anchor platform, anchor lip and the chain barrel that casts anchor were installed in the second segmentation stage;
4), when the first segmentation and the second block assembly, the chain barrel that casts anchor docks with upper hawse pipe.
Further, step 1), in, using the waterline at intersection point place of hawse pipe line of centers and outside plate as altitude datum line.
Further, step 3) in, anchor platform, anchor lip and the chain barrel that casts anchor are installed in the second anti-state of segmentation stage.
Further, step 4) in, the first segmentation and the second segmentation adopt total group of normal state.
By above technical scheme, the present invention has following technique effect compared to prior art: when the segmentation of bow platform, side of a ship side chain hole position of opening is divided in same segmentation, hawse pipe, anchor platform and anchor lip were installed in advance in the segmentation stage, not only the integraty of hull structure is improved, equally also greatly improve dock construction operation environment, avoided aloft work, also reduced the destruction of outside plate paint simultaneously, reduce the dock cycle, improved shipbuilding efficiency.
Accompanying drawing explanation
Fig. 1 is bow platform segmentation schematic diagram;
Fig. 2 is hawse pipe segmentation schematic diagram.
Element numbers explanation:
1 first segmentation
2 second segmentations
Hawse pipe on 3
4 chain barrels that cast anchor
The specific embodiment
By particular specific embodiment explanation embodiments of the present invention, person skilled in the art scholar can understand other advantages of the present invention and effect easily by the disclosed content of this specification sheets below.
Refer to Fig. 1 to Fig. 2.Notice, appended graphic the illustrated structure of this specification sheets, ratio, size etc., equal contents in order to coordinate specification sheets to disclose only, for person skilled in the art scholar, understand and read, not in order to limit the enforceable qualifications of the present invention, therefore the technical essential meaning of tool not, the adjustment of the modification of any structure, the change of proportionate relationship or size, not affecting under the effect that the present invention can produce and the object that can reach, all should still drop on disclosed technology contents and obtain in the scope that can contain.Simultaneously, in this specification sheets, quote as " on ", the term of D score, " left side ", " right side ", " centre " and " " etc., also only for ease of understanding of narrating, but not in order to limit the enforceable scope of the present invention, the change of its relativeness or adjustment, under without essence change technology contents, when being also considered as the enforceable category of the present invention.
Below in conjunction with 21000m 3division and the installation phase of LEG ship anchor platform, anchor lip and hawse pipe describe in detail to the present invention:
1) segmentation is divided:
As shown in Figure 1, segmentation is divided to adopt and is divided by each layer of platform of bow, and two segmentations at top form the first segmentation 1 and the second segmentation 2.
When deck secondary is rule, according to datum rib bit line and the line of hull line of centers, mark hawse pipe center rib bit line, the deck projection line of hawse pipe line of centers.The deck projection line of hawse pipe line of centers and the intersection point of rib bit line, the i.e. center-point of hawse pipe line of centers on deck plane.
2) hawse pipe is divided:
As shown in Figure 2, according to the structure of hawse pipe and dock reason easily, the direction by hawse pipe along normal disconnects, in formations hawse pipe 3 with cast anchor chain barrel 4.Upper hawse pipe 3 is divided in the first segmentation 1, and the chain barrel 4 that casts anchor is divided in the second segmentation 2.Anchor platform, anchor lip and the chain barrel 4 that casts anchor are installed in the second anti-state of 2 stage of segmentation;
3) precision control program:
Total group of the first segmentation 1 and the second segmentation 2 normal state: during the first segmentation 1 location, need be with reference to hull line of centers, datum rib bit line.Wherein, datum rib bit line is length direction, and hull line of centers is Width, usings the waterline at intersection point place of hawse pipe line of centers and outside plate as altitude datum line.Waterline guarantees the precision with the second segmentation port and starboard, bow stern direction, floor height.According to above by the first segmentation Primary Location, then
According to the first split fix situation, upper hawse pipe center position on fore castle deck plate is opened aperture, from the chain barrel end that the casts anchor hawse pipe aperture that makes progress, draw steel wire, check the straightness accuracy of the second segmentation, the first segmentation side of a ship side chain centerline hole, the chain barrel that casts anchor docks with upper hawse pipe, finally forms complete hawse pipe.During hawse pipe welding, note symmetrical welding, guarantee the straightness accuracy of hawse pipe postwelding.Two sections of hawse pipes are made completion, and simulation draws one to zygonema and strikes ocean and develop and print while closing up.
In sum, the present invention is divided in side of a ship side chain hole position of opening in same segmentation when the segmentation of bow platform, hawse pipe, anchor platform and anchor lip were installed in advance in the segmentation stage, not only the integraty of hull structure is improved, equally also greatly improve dock construction operation environment, avoided aloft work, also reduced the destruction of outside plate paint simultaneously, reduce the dock cycle, improved shipbuilding efficiency.So the present invention has effectively overcome various shortcoming of the prior art and tool high industrial utilization.
Above-described embodiment is illustrative principle of the present invention and effect thereof only, but not for limiting the present invention.Any person skilled in the art scholar all can, under spirit of the present invention and category, modify or change above-described embodiment.Therefore, such as in affiliated technical field, have and conventionally know that the knowledgeable, not departing from all equivalence modifications that complete under disclosed spirit and technological thought or changing, must be contained by claim of the present invention.

Claims (4)

1. an installation method for anchor platform, anchor lip and hawse pipe segmentation prepackage, is characterized in that, comprises the following steps:
1) bow hull structure is carried out to segmentation division, two segmentations at top form the first segmentation and the second segmentation;
2) hawse pipe disconnects and forms upper hawse pipe and the chain barrel that casts anchor along normal, and is divided in respectively in described the first segmentation and the second segmentation;
3) anchor platform, anchor lip and the chain barrel that casts anchor were installed in the second segmentation stage;
4), when the first segmentation and the second block assembly, the chain barrel that casts anchor docks with upper hawse pipe.
2. the installation method of anchor platform according to claim 1, anchor lip and hawse pipe segmentation prepackage, is characterized in that step 1) in, using the waterline at intersection point place of hawse pipe line of centers and outside plate as altitude datum line.
3. the installation method of anchor platform according to claim 1, anchor lip and hawse pipe segmentation prepackage, is characterized in that step 3) in, anchor platform, anchor lip and the chain barrel that casts anchor are installed in the second anti-state of segmentation stage.
4. the installation method of anchor platform according to claim 1, anchor lip and hawse pipe segmentation prepackage, is characterized in that step 4) in, the first segmentation and the second segmentation adopt total group of normal state.
CN201410225992.8A 2014-05-26 2014-05-26 Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe Pending CN103979073A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410225992.8A CN103979073A (en) 2014-05-26 2014-05-26 Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410225992.8A CN103979073A (en) 2014-05-26 2014-05-26 Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe

Publications (1)

Publication Number Publication Date
CN103979073A true CN103979073A (en) 2014-08-13

Family

ID=51271308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410225992.8A Pending CN103979073A (en) 2014-05-26 2014-05-26 Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe

Country Status (1)

Country Link
CN (1) CN103979073A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104787246A (en) * 2015-03-24 2015-07-22 上海外高桥造船有限公司 Anchor mouth
CN105253251A (en) * 2015-10-23 2016-01-20 上海船舶研究设计院 Method for measuring minimum distance between anchor and hull plate
CN105292377A (en) * 2015-09-24 2016-02-03 中船黄埔文冲船舶有限公司 Testing method for wood mold anchor mouth
CN107226170A (en) * 2017-06-09 2017-10-03 中船黄埔文冲船舶有限公司 A kind of making of combined type wooden model anchor station part and installation method
CN107235117A (en) * 2017-06-09 2017-10-10 中船黄埔文冲船舶有限公司 A kind of fabrication and installation method of anchor recess
CN107458540A (en) * 2017-07-31 2017-12-12 上海江南长兴重工有限责任公司 A kind of ship anchor chain barrel installation and locating method
CN109204687A (en) * 2018-08-15 2019-01-15 招商局重工(江苏)有限公司 A kind of installation method of chain pipe anchor station anchor lip
CN109501960A (en) * 2018-12-29 2019-03-22 芜湖造船厂有限公司 A kind of pre-assembled structure of anchor station and its assembly method
CN109703694A (en) * 2018-12-30 2019-05-03 山海关船舶重工有限责任公司 A kind of whole single segmentation prepackage method of anchor station
CN110877682A (en) * 2019-11-13 2020-03-13 沪东中华造船(集团)有限公司 Ship unbalanced anchor lip preassembling process
CN112319722A (en) * 2020-09-25 2021-02-05 中船澄西船舶修造有限公司 Ship anchor platform structure design method adopting steel plates for splicing
CN112407189A (en) * 2020-11-26 2021-02-26 江南造船(集团)有限责任公司 Precision construction process for bow hawse pipe and anchor block of ultra-large ship
CN113148063A (en) * 2021-06-03 2021-07-23 江南造船(集团)有限责任公司 Construction method of ship anchor cave
CN115230906A (en) * 2022-08-10 2022-10-25 沪东中华造船(集团)有限公司 Method for mounting first anchor hawse pipe

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000062683A (en) * 1998-08-20 2000-02-29 Tokuyama Corp Anchoring part structure
GB2357487A (en) * 1998-09-03 2001-06-27 Norske Stats Oljeselskap An apparatus for guiding and stopping an anchor chain on a floating structure
CN102336251A (en) * 2011-08-16 2012-02-01 广东中远船务工程有限公司 Method for designing and manufacturing circular anchor mouths and right circular conical anchor beds
CN103010402A (en) * 2012-12-13 2013-04-03 沪东中华造船(集团)有限公司 Pre-installation method of bulker hawse pipe on section

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000062683A (en) * 1998-08-20 2000-02-29 Tokuyama Corp Anchoring part structure
GB2357487A (en) * 1998-09-03 2001-06-27 Norske Stats Oljeselskap An apparatus for guiding and stopping an anchor chain on a floating structure
CN102336251A (en) * 2011-08-16 2012-02-01 广东中远船务工程有限公司 Method for designing and manufacturing circular anchor mouths and right circular conical anchor beds
CN103010402A (en) * 2012-12-13 2013-04-03 沪东中华造船(集团)有限公司 Pre-installation method of bulker hawse pipe on section

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
何琴琴 等: "锚台、锚链筒及锚唇安装精度控制工艺", 《广东造船》 *
吴伦楷 等: "预舾装工艺的实践", 《造船技术》 *
艾记平: "80300DWT散货船锚链筒及凸台的放样及各开口的定位", 《机电技术》 *
陈鹤云 等: "浅析87000T散货轮锚链筒_锚唇在分段预装的精度控制方法", 《科技云》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104787246A (en) * 2015-03-24 2015-07-22 上海外高桥造船有限公司 Anchor mouth
CN105292377A (en) * 2015-09-24 2016-02-03 中船黄埔文冲船舶有限公司 Testing method for wood mold anchor mouth
CN105253251A (en) * 2015-10-23 2016-01-20 上海船舶研究设计院 Method for measuring minimum distance between anchor and hull plate
CN107226170A (en) * 2017-06-09 2017-10-03 中船黄埔文冲船舶有限公司 A kind of making of combined type wooden model anchor station part and installation method
CN107235117A (en) * 2017-06-09 2017-10-10 中船黄埔文冲船舶有限公司 A kind of fabrication and installation method of anchor recess
CN107458540A (en) * 2017-07-31 2017-12-12 上海江南长兴重工有限责任公司 A kind of ship anchor chain barrel installation and locating method
CN107458540B (en) * 2017-07-31 2019-02-22 江南造船(集团)有限责任公司 A kind of ship anchor chain barrel installation and locating method
CN109204687B (en) * 2018-08-15 2023-12-19 招商局重工(江苏)有限公司 Method for installing anchor lips of anchor chain pipe anchor table
CN109204687A (en) * 2018-08-15 2019-01-15 招商局重工(江苏)有限公司 A kind of installation method of chain pipe anchor station anchor lip
CN109501960A (en) * 2018-12-29 2019-03-22 芜湖造船厂有限公司 A kind of pre-assembled structure of anchor station and its assembly method
CN109501960B (en) * 2018-12-29 2020-05-19 芜湖造船厂有限公司 Anchor chock pre-assembly structure and assembling method thereof
CN109703694B (en) * 2018-12-30 2021-08-06 山海关船舶重工有限责任公司 Single-segment preassembling method for whole anchor platform
CN109703694A (en) * 2018-12-30 2019-05-03 山海关船舶重工有限责任公司 A kind of whole single segmentation prepackage method of anchor station
CN110877682A (en) * 2019-11-13 2020-03-13 沪东中华造船(集团)有限公司 Ship unbalanced anchor lip preassembling process
CN112319722A (en) * 2020-09-25 2021-02-05 中船澄西船舶修造有限公司 Ship anchor platform structure design method adopting steel plates for splicing
CN112407189A (en) * 2020-11-26 2021-02-26 江南造船(集团)有限责任公司 Precision construction process for bow hawse pipe and anchor block of ultra-large ship
CN113148063A (en) * 2021-06-03 2021-07-23 江南造船(集团)有限责任公司 Construction method of ship anchor cave
CN115230906A (en) * 2022-08-10 2022-10-25 沪东中华造船(集团)有限公司 Method for mounting first anchor hawse pipe
CN115230906B (en) * 2022-08-10 2024-06-11 沪东中华造船(集团)有限公司 Method for installing anchor hawse pipe

Similar Documents

Publication Publication Date Title
CN103979073A (en) Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe
CN101643109B (en) Method for centering centerline of subsection hull constructed in two-island mode
CN100366505C (en) Lengthening reform technology of ship
JP2009506930A (en) Moonpool flow control device
CN114492086B (en) Intelligent detection method for single-mooring anchor position of ship
CN105464049A (en) Real-time testing-controlling acceptance system for deepwater dumping ship and construction method
CN104354831A (en) Installation process for tail roller of three-purpose working ship
CN108776480B (en) Flight path planning method for supporting platform berthing drilling platform
CN110788822B (en) Method for surveying central line of hull deck
CN107187554A (en) The binary partly latent barge defeated for the dry haul of semisubmersible drilling platform and operational method
CN202953142U (en) Steel cylinder transportation equipment
CN205475100U (en) Deep water throwing is filled out ship and is observed and controled examination system in real time
Srše et al. Solutions to minimize sediment resuspension in ports
KR20110092564A (en) Optimized shape of skeg
Feikens et al. ‘Wet Handshake’: Workability Study of an Offshore Thruster Exchange Operation
Zu et al. DP Conversion for a Successful Float-over Installation
CN204548441U (en) A kind of dock
Parra Numerical Study on Offshore Lifting Operations of a Subsea Spool
Li Deep-Ocean Assessment and Reporting of Tsunamis (DART) BUOY
Song Doppler Velocity Log for Navigation System in Underwater Vehicle
Duan et al. Design of Pipelines and Risers
Ran et al. The Study on Control Methods to Semi-submersible Vessel Loading 300,000-ton FPSO
Du et al. Stability and Strength Analysis on Structure Ring Floating of FPSO
Formela et al. The Concept of Modernization Works Related to the Capability of Handling E Class Container Vessels in the Port Gdynia
Hu Drag Anchors

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140813

RJ01 Rejection of invention patent application after publication