CN103955197B - Linkage production line control method applied to intake manifold accessory installation - Google Patents

Linkage production line control method applied to intake manifold accessory installation Download PDF

Info

Publication number
CN103955197B
CN103955197B CN201410202235.9A CN201410202235A CN103955197B CN 103955197 B CN103955197 B CN 103955197B CN 201410202235 A CN201410202235 A CN 201410202235A CN 103955197 B CN103955197 B CN 103955197B
Authority
CN
China
Prior art keywords
equipment
product
airtight
qualified
production line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410202235.9A
Other languages
Chinese (zh)
Other versions
CN103955197A (en
Inventor
刘建华
潘国运
乐旭辉
张银辉
于春霞
李淑华
张恺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd
Original Assignee
QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd filed Critical QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd
Priority to CN201410202235.9A priority Critical patent/CN103955197B/en
Publication of CN103955197A publication Critical patent/CN103955197A/en
Application granted granted Critical
Publication of CN103955197B publication Critical patent/CN103955197B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

The invention provides a linkage production line control method applied to intake manifold accessory installation. A production line sequentially comprises an air tightness initial inspection device used for detecting whether welding is qualified or not, a cold insertion device used for pressing stop collars, a nut embedment device used for pressing copper nuts, a tool device used for installing accessories such as an intake manifold actuator and a solenoid valve, and an air tightness final inspection device used for detecting whether overall welding and accessory installation are qualified or not. According to the linkage production line control method applied to intake manifold accessory installation, before the devices operate, product number retrieval is carried out through a database system, whether missing installation or error installation exist or not is judged according to retrieval information, then, a whether a system meets operation conditions or not is judged, the working procedure error and the part missing installation error are avoided, the reject ratio of products is reduced, and production efficiency is improved; production and processing quality of each product can be tracked in the whole process through a two-dimension code technology, and therefore machining quality is improved; in addition, a client can carry out product quality tracing through two-dimension code scanning or database information retrieval.

Description

A kind of linkage production line control method being applied to the installation of inlet manifold adnexa
Technical field
The present invention relates to automobile manufacturing field, particularly to a kind of linkage production line being applied to the installation of inlet manifold adnexa Control method.
Background technology
In China, the development of automobile industry and plastic manufacturing process is advanced by leaps and bounds, and the engine fittings that metal makes are gradually Replaced by the engine fittings of the plastic production with inlet manifold as representative, as one of the part of electromotor most critical, air inlet Manifold achieves in automobile industry and is widely applied, and its Core Feature is to provide full and uniform mixing for each cylinder of electromotor Gas, is the key factor of impact engine forces and oil consumption.
The assembling of existing domestic inlet manifold adnexa is manual assembly mostly or single device produces, adnexa neglected loading, operation Misloading is all artificially to check, mistake proofing performance is not high.
Content of the invention
The present invention, for the problems such as under adnexa neglected loading, operation misloading, low production efficiency, discloses one kind and is applied to air inlet discrimination The linkage production line control method that pipe fittings is installed.
The technical scheme is that and be achieved in that:
A kind of linkage production line control method being applied to the installation of inlet manifold adnexa, described production line includes successively: uses In the whether qualified airtight initial survey equipment of detection welding, for press-fit stop collar cold plug standby, for press-fiting the spiral shell of copper nut Female heeling-in equipment, for installing the tooling device of the adnexaes such as inlet manifold executor, electromagnetic valve, and is used for detecting overall weldering Connect, whether qualified adnexa install airtight whole inspection equipment;Produce line control method to comprise the following steps:
Step (a), arranges Quick Response Code coder, in air inlet discrimination after airtight initial survey is qualified on described airtight initial survey equipment The production code member of unique Quick Response Code form is printed on pipe product, and by production code member and welds qualified information by opc interface Send airtight whole inspection equipment to;
Step (b), airtight whole inspection equipment sets up data base by industrial computer, the product coding in receiving step (a) Afterwards, set up and the one-to-one data storage cell of this product coding, qualified information is welded in storage, and pass through opc communication line Cold plug standby, nut heeling-in equipment, tooling device and be uniformly controlled to follow-up;
Step (c), in the described cold linking plugging standby, nut heeling-in equipment, tooling device and the airtight equipment of inspection eventually Cross part, be respectively provided with two-dimensional code scanning instrument, by two-dimensional code scanning instrument and opc communication line, production code member is sent to airtight Inspection equipment eventually, the airtight equipment of inspection eventually retrieves the product information in data space under this product coding in described data base, sentences Whether disconnected product information is qualified: if product information is qualified, airtight whole inspection equipment sends instruction and continues detection to this product, simultaneously The product information of current detection is stored in the data space under this production code member of data base;If product information does not conform to Lattice, airtight whole inspection equipment sends instruction makes the equipment that error product is located send alarm signal, and miscellaneous equipment continues to run with.
Alternatively, in described step (c), when product, operation mistake, production code member mistake or last process unqualified When, the industrial computer system of airtight eventually inspection equipment judges that product information is unqualified, send instruction make the equipment at error product place to Go out alarm signal, when miscellaneous equipment continues to run until that replacement of products meets working condition, warning device automatically engages operation.
The invention has the beneficial effects as follows:
(1) before equipment runs, carry out production code member retrieval by Database Systems, judge whether to leak according to retrieval information Dress, misloading, and then judge whether system meets service condition, it is to avoid operation mistake, neglected loading parts error, reduces product not Qualification rate, improves production efficiency;
(2) tracking control of full process is able to by the production and processing quality that planar bar code technology makes every product, improves processing matter Amount, simultaneously client product quality can be carried out by two-dimensional code scanning or database information retrieval and review.
Brief description
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing Have technology description in required use accompanying drawing be briefly described it should be apparent that, drawings in the following description be only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, acceptable Other accompanying drawings are obtained according to these accompanying drawings.
The process chart that Fig. 1 installs for inlet manifold adnexa;
Fig. 2 is the flow chart of the linkage production line control method being applied to the installation of inlet manifold adnexa of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation description is it is clear that described embodiment is only a part of embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of not making creative work Embodiment, broadly falls into the scope of protection of the invention.
As shown in figure 1, the inlet manifold technological process of the present invention includes: baking material, injection, umbrella valve assembling, vis system dress Join, vibrate friction welding (FW), spin friction weldering, airtight initial survey, cold slotting stop collar, heat insert copper nut, executor, electromagnetic valve, vacuum are soft Pipe assembling, egr pipe, the assembling of panel beating support, sealing ring assembling, airtight inspection eventually, packaging.
Airtight initial survey after spin friction weldering for the equipment linkage production line installed by inlet manifold adnexa according to the present invention Start.Wherein, executor, electromagnetic valve, vacuum hose, egr pipe, the assembling unification of panel beating support, sealing ring are an equipment Multiple frocks are realized.
As shown in Fig. 2 the linkage production line that the inlet manifold adnexa of the present invention is installed by airtight initial survey equipment, cold plug Standby, nut heeling-in equipment, the independent plc control system of 4 sets of tooling device of executor, electromagnetic valve etc. is installed and airtight examines eventually Equipment plc system and industrial computer control system are constituted.
Database information storage and retrieval is the basis setting up linkage production line, therefore will be with plc and industrial computer for controlling The airtight equipment of inspection eventually of system, as main equipment, sets up Database Systems, miscellaneous equipment is from equipment, by setting on industrial computer Opc communication line between standby, to carry out information transmission, realizes online control.
The control process of linkage production line comprises the following steps:
Step (a), arranges Quick Response Code coder on described airtight initial survey equipment, and airtight initial survey equipment detects Product jointing The production code member of unique Quick Response Code form, product, after qualified, are printed by quick response code printer on inlet manifold product Numbering and the qualified information of welding send airtight whole inspection equipment to by opc communication line;
Step (b), airtight whole inspection equipment sets up data base by industrial computer, the product coding in receiving step (a) Afterwards, set up and the one-to-one data storage cell of this product coding, qualified information is welded in storage, and pass through opc communication line Cold plug standby, nut heeling-in equipment, tooling device and be uniformly controlled to follow-up;
Step (c), in the described cold linking plugging standby, nut heeling-in equipment, tooling device and the airtight equipment of inspection eventually Cross part, be respectively provided with two-dimensional code scanning instrument, by two-dimensional code scanning instrument and opc communication line, production code member is sent to airtight Inspection equipment eventually, the airtight equipment of inspection eventually retrieves the product information in data space under this product coding in described data base, sentences Whether disconnected product information is qualified: if product information is qualified, airtight whole inspection equipment sends instruction and continues detection to this product, simultaneously The product information of current detection is stored in the data space under this production code member of data base;If product information does not conform to Lattice, airtight whole inspection equipment sends instruction makes the equipment that error product is located send alarm signal, and miscellaneous equipment continues to run with.
Step (c) specifically, entering that next process is cold to be inserted when product completes airtight initial survey, cold plug received shipment row it Before, airtight whole inspection equipment to is sent production code member by two-dimensional code scanning instrument and opc communication line, is compiled by retrieving product Number, run after obtaining the qualified information of airtight initial survey, run, after finishing, information is stored in data base;Product enters lower one work Sequence nut heeling-in, nut heeling-in equipment retrieves production code member before running, and obtains airtight initial survey and cold slotting stop collar is qualified Run after information, run, after finishing, information is stored in data base;Product enters next process executor, electromagnetic valve peace Dress, retrieves production code member before the tooling device operation installing the adnexaes such as executor, electromagnetic valve, obtains airtight initial survey, cold slotting limit Position covers and runs after press-fiting the qualified information of copper nut, runs, after finishing, information is stored in data base;Product enters lower one work Sequence is airtight to be examined eventually, the airtight equipment retrieval production code member of inspection eventually, runs, run after the qualified information of all process steps before acquisition After finishing, information is stored in data base, whole linkage production line completes to produce.
The linkage production line control method being applied to the installation of inlet manifold adnexa of the present invention, before equipment runs, passes through Database Systems carry out production code member retrieval, judge whether neglected loading, misloading according to retrieval information, and then judge whether system meets Service condition, it is to avoid operation mistake, neglected loading parts error, reduces product disqualification rate, improves production efficiency;By two The production and processing quality of dimension code every product of technology is able to tracking control of full process, improves crudy, client can pass through simultaneously Two-dimensional code scanning or database information retrieval carry out product quality and review.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention Within god and principle, any modification, equivalent substitution and improvement made etc., should be included within the scope of the present invention.

Claims (2)

1. a kind of be applied to inlet manifold adnexa installation linkage production line control method it is characterised in that described production line according to Secondary inclusion: for the whether qualified airtight initial survey equipment of detection welding, for press-fit stop collar cold plug standby, be used for press-fiting copper The nut heeling-in equipment of nut, for installing the tooling device of inlet manifold executor, electromagnetic valve, and is used for detecting overall weldering Connect, whether qualified adnexa install airtight whole inspection equipment;Produce line control method to comprise the following steps:
Step (a), arranges Quick Response Code coder on described airtight initial survey equipment, produces in inlet manifold after airtight initial survey is qualified The product coding of unique Quick Response Code form is printed on product, and product coding and the qualified information of welding are transmitted by opc interface To airtight inspection equipment eventually;
Step (b), airtight whole inspection equipment sets up data base by industrial computer, after the product coding in receiving step (a), builds Stand and the one-to-one data storage cell of this product coding, qualified information is welded in storage, and by opc communication line to follow-up Cold plug standby, nut heeling-in equipment, tooling device and be uniformly controlled;
Step (c), in the described cold linking transition part plugging standby, nut heeling-in equipment, tooling device and the airtight equipment of inspection eventually Point, it is respectively provided with two-dimensional code scanning instrument, airtight inspection eventually to is sent production code member by two-dimensional code scanning instrument and opc communication line Equipment, the airtight equipment of inspection eventually retrieves the product information in data space under this product coding in described data base, judges to produce Whether product information is qualified: if product information is qualified, airtight whole inspection equipment sends instruction and continues detection to this product, ought simultaneously The product information of front detection is stored in the data space under this production code member of data base;If product information is unqualified, gas Close whole inspection equipment sends instruction makes the equipment that error product is located send alarm signal, and miscellaneous equipment continues to run with.
2. be applied to as claimed in claim 1 inlet manifold adnexa installation linkage production line control method it is characterised in that In described step (c), when product occur operation mistake, production code member mistake or last process unqualified when, airtight eventually inspection equipment Industrial computer system judge that product information is unqualified, sending instruction makes the equipment that error product is located provide alarm signal, other When equipment continues to run until that replacement of products meets working condition, warning device automatically engages operation.
CN201410202235.9A 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation Active CN103955197B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410202235.9A CN103955197B (en) 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410202235.9A CN103955197B (en) 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation

Publications (2)

Publication Number Publication Date
CN103955197A CN103955197A (en) 2014-07-30
CN103955197B true CN103955197B (en) 2017-01-25

Family

ID=51332482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410202235.9A Active CN103955197B (en) 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation

Country Status (1)

Country Link
CN (1) CN103955197B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104237967B (en) * 2014-08-29 2018-09-18 辽宁丰迪发动机进气系统有限公司 A kind of plastic air intake manifold metal embedding piece detection device
CN106078199B (en) * 2016-08-01 2018-11-30 上海超路自动化设备有限公司 A kind of automation integrated equipment handling inlet manifold
CN106226008B (en) * 2016-08-26 2018-09-28 青岛华涛汽车模具有限公司 A kind of airtight cold plug in all-in-one machine
CN106945296B (en) * 2017-04-24 2023-08-22 苏州科技大学 Intake manifold assembly test production system
CN107862237A (en) * 2017-11-29 2018-03-30 德盛镁汽车部件(芜湖)有限公司 A kind of parts two-dimensional code scanning fail-safe system
CN108145411B (en) * 2017-12-29 2024-04-05 博格华纳排放系统(宁波)有限公司 EGR valve assembly production line and assembly method thereof
CN108458834B (en) * 2018-03-27 2024-04-26 苏州科技大学 Engine manifold assembly test line and test method
JP7142463B2 (en) * 2018-05-15 2022-09-27 Juki株式会社 Production system, mounting equipment, production method
CN109117908A (en) * 2018-07-05 2019-01-01 安徽胜利精密制造科技有限公司 Material frame two dimensional code trace-back technique
CN109884998A (en) * 2019-02-19 2019-06-14 保定智通自动化技术有限公司 Traceable quality control system
CN112222690B (en) * 2020-09-30 2022-08-30 中石化第四建设有限公司 Method for establishing pipeline weld joint management information

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090055255A (en) * 2007-11-28 2009-06-02 기아자동차주식회사 Judging method for erreor of a intake manifold turning valve
CN102147607A (en) * 2010-02-09 2011-08-10 科博达技术有限公司 Flexible general production line and production method of electronic product
CN102166821A (en) * 2011-01-24 2011-08-31 青岛华涛汽车模具有限公司 Nut-embedding machine
CN202008429U (en) * 2011-03-07 2011-10-12 青岛华涛汽车模具有限公司 Air tightness detector
CN102354210A (en) * 2011-09-07 2012-02-15 华中科技大学 Quality early warning system and method for automobile assembling workshop
CN102749881A (en) * 2012-06-29 2012-10-24 大连交通大学 Error-proofing monitoring system and method for automobile engine valve assembling process
CN103279063A (en) * 2013-06-18 2013-09-04 华高王氏科技(深圳)有限公司 Detecting mistake-proof system applicable to electronic part production line and method thereof
CN103761550A (en) * 2014-01-18 2014-04-30 苏州亿铂信息科技有限公司 Method and system used for correlating product bar codes and production data

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007046470A (en) * 2005-08-05 2007-02-22 Denso Corp Air intake system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090055255A (en) * 2007-11-28 2009-06-02 기아자동차주식회사 Judging method for erreor of a intake manifold turning valve
CN102147607A (en) * 2010-02-09 2011-08-10 科博达技术有限公司 Flexible general production line and production method of electronic product
CN102166821A (en) * 2011-01-24 2011-08-31 青岛华涛汽车模具有限公司 Nut-embedding machine
CN202008429U (en) * 2011-03-07 2011-10-12 青岛华涛汽车模具有限公司 Air tightness detector
CN102354210A (en) * 2011-09-07 2012-02-15 华中科技大学 Quality early warning system and method for automobile assembling workshop
CN102749881A (en) * 2012-06-29 2012-10-24 大连交通大学 Error-proofing monitoring system and method for automobile engine valve assembling process
CN103279063A (en) * 2013-06-18 2013-09-04 华高王氏科技(深圳)有限公司 Detecting mistake-proof system applicable to electronic part production line and method thereof
CN103761550A (en) * 2014-01-18 2014-04-30 苏州亿铂信息科技有限公司 Method and system used for correlating product bar codes and production data

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
基于可装配性分析的塑料进气歧管设计研究;靳红蕾;《中国优秀硕士学位论文全文数据库工程科技II辑》;20111215(第S2期);全文 *
柴油发动机塑料进气歧管设计研究;王龙;《中国优秀硕士学位论文全文数据库 工程科技II辑》;20111215(第S2期);全文 *

Also Published As

Publication number Publication date
CN103955197A (en) 2014-07-30

Similar Documents

Publication Publication Date Title
CN103955197B (en) Linkage production line control method applied to intake manifold accessory installation
CN105458686A (en) Mistake prevention device and mistake prevention method thereof
CN112324745B (en) Portable hydraulic system leakage signal acquisition device and acquisition method thereof
CN105865775B (en) Full-automatic pilot valve combination property test desk
CN104571037A (en) Key torque assembling system
CN105090755A (en) Method and system for locating suspicious gas leakage and leakage points based on pressure monitoring
CN104568308B (en) detection device, method and system of pressure sensor
CN106482349A (en) Secondary pressure intelligent adjusting method and system for gas water heater
CN103488562A (en) Automated testing method and device
Ardi et al. Design of pokayoke systems to increase the efficiency of function check oxygen sensor machine using programmable logic controller in manufacturing industry
CN115525636A (en) Multi-wheel alignment method and device for internal detection data of magnetic leakage of long-distance gas pipeline
CN103455000A (en) SCADA system device modeling method for forming control logic automatically
CN106644301B (en) Vehicle air conditioner leakage detection method with high detection efficiency
CN110417195A (en) Driving motor automated assembly line
CN210533628U (en) Automatic device for air leakage monitoring and wire harness insertion of electric steering gear
CN116186951A (en) Method and device for checking connection relation of three-dimensional pipeline model
CN105675217A (en) Air-conditioning heat exchanger leakage point detection method and detection platform
CN213985674U (en) Valve steam medium test device
CN202614594U (en) Double-station air pressure testing table
CN104198203A (en) Method and device for detecting operation of air-conditioners
CN104833459B (en) A kind of automobile pipe fitting impermeability leakage detection apparatus and leak hunting method thereof
CN202471370U (en) Production test stand for clutch thruster air passage control system assembly
CN202571574U (en) Silencer welding protective gas pressure measurement alarm device
CN114323491B (en) Automatic airtight detection method for low-voltage system
CN205298145U (en) Hydrovalve dynamic test platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant