CN103927626A - Method and system for project management - Google Patents
Method and system for project management Download PDFInfo
- Publication number
- CN103927626A CN103927626A CN201410162860.5A CN201410162860A CN103927626A CN 103927626 A CN103927626 A CN 103927626A CN 201410162860 A CN201410162860 A CN 201410162860A CN 103927626 A CN103927626 A CN 103927626A
- Authority
- CN
- China
- Prior art keywords
- project
- day
- unit
- unit project
- cost
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a method and system for project management and belongs to the technical field of information management. The method comprises the steps that the actual daily completed amount and the predicted daily work amount of each unit project are obtained and the resource ration of each unit project is determined from a resource ration bank stored in advance; the projects are analyzed daily and managed according to analysis results. According to the actual daily completed amount of each unit project, the predicted daily work amount of each unit project and the resource ration, determined from the resource ration bank stored in advance, of each unit project, the projects are analyzed and managed daily, and the projects are managed with a day serving as a unit, so that the auxiliary effect on overall control over the projects by project management personnel through the method for project management is enhanced; meanwhile, the resource ration of each unit project is determined from the resource ration bank stored and the condition that analysis and check computation are not accurate due to inaccurate manual input is avoided.
Description
Technical field
The present invention relates to information management technique field, particularly a kind of project management method and system.
Background technology
Along with social develop rapidly, civil construction project project is also more and more, and a civil construction project project comprises multiple single construction, and any single construction comprises again multiple unit projects.Civil construction project project is carried out to project management can assist the managerial personnel of civil construction project project to carry out entirety control to project under limited resources qualifications, for example: control cost, control project process, prediction profit, realizes or exceedes demand and the expectation of project settings.
At present, project management method is: according to resource quota, unit project resource and the actual quantities completing etc. of each unit project of the project budget, artificial input, expense to the actual generation of project, Cost Status are analyzed accounting, and monthly generate accounting form.Wherein, that resource quota is unification of the motherland regulation is artificial, the standard price of material, machinery, unit project resource be unit project actual occur manually, material, mechanical actual price.
Realizing in process of the present invention, inventor finds that prior art at least exists following problem:
Because the form of project management method output is all taking " moon " as measurement unit, and project manager be taking " my god " as unit carries out project management to civil construction project project, therefore, be unfavorable for that project manager carries out fine-grained management to project.In addition, in said method, the resource of each unit project quota is artificial input, because artificial input accuracy can not ensure, has therefore reduced and has analyzed the accuracy of adjusting, and reduced the efficiency of project management.
Summary of the invention
In order to solve the problem of prior art, the embodiment of the present invention provides a kind of method and system of project management.Described technical scheme is as follows:
On the one hand, provide a kind of method of project management, described method comprises:
The project of obtaining comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date, and the resource of determining each unit project from pre-stored resource quota storehouse by norm;
According to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes described project every day, according to analysis result, described project is managed.
Alternatively, the described resource according to each unit project quota, every day actual performance and estimate that quantities per diem analyzes described project every day, comprising:
Obtain unit project resource every day of each unit project;
According to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
According to projected cost every day of each unit project and every day real cost analyze profit every day of each unit project;
Obtain described project and come into effect day to total number of days of described calculation date, the plan of described project and complete the expectation engineering total of number of days and each unit project, and according to the resource quota of each unit project and estimate that engineering total determines total projected cost of each unit project;
Come into effect day the final profit that completes number of days and analyze described project to total number of days of described calculation date and the plan of described project according to real cost every day of each unit project, total projected cost, described project;
Describedly according to analysis result, described project is managed, comprising:
According to each unit project every day profit and described final profit described project is carried out to profit control.
Alternatively, the described resource according to each unit project quota, every day actual performance and estimate that quantities per diem analyzes described project every day, comprising:
According to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to the resource of each unit project by norm and estimate that quantities determines projected cost every day of each unit project every day;
According to projected cost every day of each unit project and complete every daily advance of each unit project of cost analysis every day;
Describedly according to analysis result, described project is managed, comprising:
According to every daily advance of described each unit project, described project is carried out to progress control.
Alternatively, the described resource according to each unit project quota, every day actual performance and estimate that quantities per diem analyzes described project every day, comprising:
Obtain unit project resource every day of each unit project;
According to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
According to the real cost and complete every day-rate cost of each unit project of cost analysis every day every day of each unit project;
Describedly according to analysis result, described project is managed, comprising:
According to every day-rate cost of each unit project, described project is carried out to cost management.
Alternatively, described in obtain project and come into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date, and the resource of determining each unit project from pre-stored resource quota storehouse by norm after, also comprise:
Actual performance every day, the every day that show each unit project and each unit project are estimated quantities and resource by norm, and after arbitrary unit project is selected, show that estimate quantities and resource by norm actual performance every day, the every day of described arbitrary unit project.
On the other hand, provide a kind of system of project management, described system comprises:
Acquisition module, comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date for obtaining project;
Determination module, for the resource quota of definite each unit project in resource quota storehouse from pre-stored;
Analysis module, for according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes described project every day;
Administration module, manages described project for the analysis result obtaining according to described analysis module.
Alternatively, described analysis module, comprising:
The first acquiring unit, for obtaining unit project resource every day of each unit project;
The first determining unit, for according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day;
The second determining unit, for according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
The first analytic unit, analyzes profit every day of each unit project for projected cost every day of each unit project determined according to described the first determining unit and definite real cost every day of described the second determining unit;
Second acquisition unit, comes into effect day to total number of days of described calculation date, the plan of described project and completes the expectation engineering total of number of days and each unit project for obtaining described project;
The 3rd determining unit, for according to the resource quota of each unit project and estimate that engineering total determines total projected cost of each unit project;
The second analytic unit, for coming into effect day the final profit that completes number of days and analyze described project to total number of days of described calculation date and the plan of described project according to real cost every day of each unit project, total projected cost, described project;
Described administration module, for according to each unit project every day profit and described final profit described project is carried out to profit control.
Alternatively, described analysis module, comprising:
The 4th determining unit, for according to the resource quota of each unit project and complete cost every day and determine completed projected cost every day of each unit project;
The 5th determining unit, for according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day;
The 3rd analytic unit, for according to projected cost every day of each unit project and complete every daily advance of each unit project of cost analysis every day;
Described administration module, carries out progress control for the every daily advance according to described each unit project to described project.
Alternatively, described analysis module, comprising:
The 3rd acquiring unit, for obtaining unit project resource every day of each unit project;
The 6th determining unit, for according to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project;
The 7th determining unit, for according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
The 4th analytic unit, for according to the real cost and complete every day-rate cost of each unit project of cost analysis every day every day of each unit project;
Described administration module, carries out cost management for the every day-rate cost according to each unit project to described project.
Alternatively, described system, also comprises:
Display module, estimate quantities and resource quota actual performance every day, the every day of each unit project and each unit project for showing, and after arbitrary unit project is selected, show that estimate quantities and resource by norm actual performance every day, the every day of described arbitrary unit project.
The beneficial effect that the technical scheme that the embodiment of the present invention provides is brought is:
By project per diem being analyzed and is managed according to the resource quota of each unit project of estimating the every day of each unit project actual performance, every day quantities and determine from pre-stored resource quota storehouse, realize taking " my god " as unit carries out project management to project, be beneficial to project carried out to fine-grained management.In addition, not only strengthen project has been carried out to the effect that entirety is controlled, from the resource quota storehouse of storage, determine the resource quota of each unit project simultaneously, avoid adjusting inaccurately because artificial input inaccurate causes analyzing, and then improved the efficiency of project management.
Brief description of the drawings
In order to be illustrated more clearly in the technical scheme in the embodiment of the present invention, below the accompanying drawing of required use during embodiment is described is briefly described, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skill in the art, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is the method flow diagram of the project management that provides of the embodiment of the present invention one;
Fig. 2 is the schematic diagram of the project management dendrogram that provides of the embodiment of the present invention two;
Fig. 3 is the method flow diagram of the project management that provides of the embodiment of the present invention two;
Fig. 4 is a kind of area schematic that unit project performance is managed that the embodiment of the present invention two provides;
Fig. 5 is a kind of area schematic that unit project performance is inputted that the embodiment of the present invention two provides;
Fig. 6 is a kind of resource schematic diagram of module by norm that the embodiment of the present invention two provides;
Fig. 7 is a kind of area schematic that unit project is managed that the embodiment of the present invention two provides;
Fig. 8 is a kind of area schematic that unit project resource is inputted that the embodiment of the present invention two provides;
Fig. 9 is the system architecture schematic diagram of a kind of project management of providing of the embodiment of the present invention three;
Figure 10 is the structural representation of the first analysis module of providing of the embodiment of the present invention three;
Figure 11 is the structural representation of the second analysis module of providing of the embodiment of the present invention three;
Figure 12 is the structural representation of the third analysis module of providing of the embodiment of the present invention three;
Figure 13 is the system architecture schematic diagram of the another kind of project management that provides of the embodiment of the present invention three.
Embodiment
For making the object, technical solutions and advantages of the present invention clearer, below in conjunction with accompanying drawing, embodiment of the present invention is described further in detail.
Because the form of project management is at present taking " moon " as measurement unit mostly, the form taking " moon " as measurement unit is unfavorable for that project manager carries out fine-grained management to project.Meanwhile, be artificial input for the resource quota of each unit project of project management, because artificial input accuracy can not ensure, therefore reduce and analyzed the accuracy of adjusting, and reduced the efficiency of project management.In order having strengthened, project to be carried out to the overall effect of controlling, to avoid because the inaccurate of artificial input causes analysis accounting inaccurate, the embodiment of the present invention provides a kind of method of project management.The method of this project management is applied to a kind of terminal, and in this terminal, operation has the system of project management, the system of the project management of the system of this project management as described in following embodiment tri-.The system of this project management can realize taking " my god " project is carried out to project management as unit, and can realize the resource quota of determining each unit project from the resource quota storehouse of storage.
Embodiment mono-
The present embodiment provides a kind of method of project management, and referring to Fig. 1, the method that the present embodiment provides comprises:
101: the project of obtaining comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date, and the resource of determining each unit project from pre-stored resource quota storehouse is by norm;
Alternatively, the project of obtaining comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date, and the resource of determining each unit project from pre-stored resource quota storehouse by norm after, also comprise:
Actual performance every day, the every day that show each unit project and each unit project are estimated quantities and resource quota, and after arbitrary unit project is selected, show that estimate quantities and resource by norm actual performance every day, the every day of arbitrary unit project.
102: according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes project every day, according to analysis result, project is managed.
Alternatively, according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes project every day, comprising:
Obtain unit project resource every day of each unit project;
According to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
According to projected cost every day of each unit project and every day real cost analyze profit every day of each unit project;
The project of obtaining comes into effect day to total number of days of calculation date, the plan of project and completes the expectation engineering total of number of days and each unit project, and according to the resource quota of each unit project and estimate that engineering total determines total projected cost of each unit project;
Come into effect according to real cost every day of each unit project, total projected cost, project day completes number of days analysis project final profit to total number of days of calculation date and the plan of project;
According to analysis result, project is managed, comprising:
According to each unit project every day profit and final profit project is carried out to profit control.
Alternatively, according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes project every day, comprising:
According to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to the resource of each unit project by norm and estimate that quantities determines projected cost every day of each unit project every day;
According to projected cost every day of each unit project and complete every daily advance of each unit project of cost analysis every day;
According to analysis result, project is managed, comprising:
According to every daily advance of each unit project, project is carried out to progress control.
Alternatively, according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes project every day, comprising:
Obtain unit project resource every day of each unit project;
According to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
According to the real cost and complete every day-rate cost of each unit project of cost analysis every day every day of each unit project;
According to analysis result, project is managed, comprising:
According to every day-rate cost of each unit project, project is carried out to cost management.
The method that the embodiment of the present invention provides, by project per diem being analyzed and is managed according to the resource quota of each unit project of estimating the every day of each unit project actual performance, every day quantities and determine from pre-stored resource quota storehouse, realize taking " my god " as unit carries out project management to project, be beneficial to project carried out to fine-grained management.In addition, not only strengthen project has been carried out to the effect that entirety is controlled, from the resource quota storehouse of storage, determine the resource quota of each unit project simultaneously, avoid adjusting inaccurately because artificial input inaccurate causes analyzing, and then improved the efficiency of project management.
Embodiment bis-
The embodiment of the present invention provides a kind of method of project management, in conjunction with the content of above-described embodiment one, for convenience of explanation, the present embodiment is with the project management dendrogram of the project A shown in Fig. 2, and project A comprises 11 single construction 1 in Fig. 2, single construction 1 comprise that 1 unit project 11, calculation date are that the second day after project comes into effect, the construction content of each unit project are that earth excavation is example.The method of the project management that the present embodiment is provided describes.Referring to Fig. 3, the method flow that the present embodiment provides comprises:
301: the project of obtaining comes into effect day to actual performance every day of each unit project in calculation date;
Determine calculation date, and the project of obtaining comes into effect day to actual performance every day of each unit project in calculation date.
The present embodiment does not limit the concrete grammar of determining calculation date, includes but not limited to: the date of the method providing by the present embodiment being carried out to project management is defined as calculation date, or obtains the calculation date of user's input.
In addition, if the system of project management provides the first viewing area of each unit project actual performance every day, and user inputs actual performance every day of each unit project in the first viewing area, can obtain actual performance every day of each unit project that user inputs in the first viewing area.In addition, can also obtain project by alternate manner and come into effect day to actual performance every day of each unit project in calculation date, the present embodiment not to obtain project come into effect day to each unit project in calculation date every day actual performance concrete grammar limit.
For example, if the system of project management provides the region for unit project performance is managed shown in Fig. 4 (a), and user is selection unit's engineering 11 rear (as shown in Fig. 4 (b)) in the region shown in Fig. 4 (a), " * " that double-click unit project 11 correspondences in Fig. 4 (b) enters the region for unit project performance is inputted shown in Fig. 5, and the every day of inputting unit project 11 in the region shown in Fig. 5 actual performance, obtain actual performance every day of the unit project 11 that user inputs in the region shown in Fig. 5.
Certainly, the region shown in Fig. 4 or Fig. 5 can also be other form and content, and the present embodiment does not limit concrete form and the content in the region shown in Fig. 4 or Fig. 5.The mode that enters the region shown in Fig. 5 can also be alternate manner, and the present embodiment does not limit the concrete mode that enters the region shown in Fig. 5, and the present embodiment does not also limit the concrete mode that enters the region shown in Fig. 4 simultaneously.Region shown in Fig. 5 and the region shown in Fig. 4 can be two different regions in the same page, can be also two regions in the different pages, and the present embodiment does not limit the particular location in the region shown in the region shown in Fig. 5 and Fig. 4.Region shown in Fig. 4 or Fig. 5 can provide the input mode of selecting input data from option for user, also can be for user provides the input mode of inputting data from input equipment, the present embodiment does not limit for user provides the input mode of input data the region shown in Fig. 4 or Fig. 5.
In addition, for facilitate user to actual performance every day of each unit project of input check, revise, the subsequent operation such as deletion, come into effect in the project of getting day can show each unit project and each unit project the every day of each unit project to calculation date actual performance every day after actual performance, and after arbitrary unit project is selected, show actual performance every day of arbitrary unit project.The present embodiment not to show each unit project and each unit project every day actual performance concrete mode limit.
302: the project of obtaining comes into effect day estimates quantities to the every day of each unit project in calculation date;
Owing to can determining that in project bid process the expectation engineering total of each unit project and the plan of each unit project complete number of days, therefore, the expectation engineering total of each unit project is estimated to quantities with the business who has planned number of days as the every day of each unit project.In addition, can also obtain project by alternate manner and come into effect day and to estimate quantities to the every day of each unit project in calculation date, the present embodiment does not come into effect day to the every day of each unit project in calculation date and estimates that the concrete grammar of quantities limits obtaining project.
For example, determine that the expectation engineering total of unit project 11 is 100 hectosteres in project bid process, it is 5 days that the plan of unit project 11 completes number of days, therefore, estimates quantities using 100/5=20 hectostere/sky as the every day of unit project 11.
Certainly, the expectation engineering total of unit project 11 can also be other numerical value and unit, and the present embodiment not concrete numerical value and the concrete unit of the expectation engineering total to unit project 1 limits.The plan of unit project 11 completes number of days can also be for other numerical value and unit, and concrete numerical value and concrete unit that the present embodiment does not complete number of days to the plan of unit project 11 limit.
In addition, in order to facilitate user to subsequent operations such as the plan of each unit project complete that number of days is checked, come into effect after day to calculation date, the plan of each unit project completes number of days getting the project of obtaining
9 can show that the plan of each unit project and each unit project completes number of days, and after arbitrary unit project is selected, show that the plan of arbitrary unit project completes number of days.The present embodiment is not to showing that the concrete mode that the plan of each unit project and each unit project completes number of days limits.
303: storage resources quota storehouse;
While project being carried out to project management for the convenient method providing by the present embodiment, obtain the resource quota of each unit project, simultaneously, also because waiting some odjective causes, input error cause the resource of each unit project of obtaining inaccurate by norm for fear of resource when quota of obtaining each unit project, and that the method that causes providing by the present embodiment is carried out project management to project is inaccurate, the system of project management can pre-stored resource quota storehouse.The standard that comprises required artificial, the material of project that unification of the motherland specify, machinery in this resource quota storehouse is fixed a price.
The present embodiment does not limit the concrete grammar in pre-stored resource quota storehouse, for example: typing resource quota in the resource that provides in the project management system shown in Fig. 6 quota module, or get in the resource quota module providing in the project management system shown in Fig. 6 after the electronic version of resource quota and import resource quota.
In addition, carry out the present embodiment provide method time, without all perform step 303 storage resources quota storehouses at every turn, while applying for the first time the method that the present embodiment provides, perform step 303, in the time of the operation of subsequent project management, can directly utilize storage resources quota storehouse in step 303, thereby continue to carry out following step.But in the time that country issues new resource quota, again perform step 303 so that resource quota storehouse is upgraded.The present embodiment does not re-execute step 303 actual conditions to triggering limits.
In addition,, in order to facilitate user to check and wait subsequent operation resource quota storehouse, after the resource quota storehouse of storage, can show resource storehouse by norm.The present embodiment does not limit the concrete mode that shows resource quota storehouse.
304: the resource quota of determining each unit project from pre-stored resource quota storehouse;
The resource needing due to the content of constructing in each unit project comprises resource identification, in pre-stored resource quota storehouse, also comprise resource identification, therefore, can in pre-stored resource quota storehouse, select resource quota that resource identification the is corresponding resource quota as each unit project.In addition, can also from pre-stored resource quota storehouse, determine by alternate manner the resource quota of each unit project, the present embodiment is not to determining that from pre-stored resource quota storehouse the concrete grammar of the resource quota of each unit project limits.
In addition, in order to facilitate user the subsequent operation such as to check to the resource quota of each unit project, after the resource quota of determining each unit project from pre-stored resource quota storehouse, can show the resource quota of each unit project and each unit project, and after arbitrary unit project is selected, show the resource quota of arbitrary unit project.The present embodiment does not limit the concrete mode of the resource quota that shows each unit project and each unit project.
305: according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes project every day, according to analysis result, project is managed.
The present embodiment is not to according to the resource quota of each unit project, every day actual performance and estimate that the concrete analysis content that quantities is per diem analyzed project limits every day.Include but not limited to be analyzed as follows three aspects: content:
First aspect: according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem carries out profit analysis to project every day;
The present embodiment is not to according to the resource quota of each unit project, every day actual performance and estimate that the concrete grammar that quantities is per diem carried out profit analysis to project limits, and includes but not limited to every day: unit project resource every day of obtaining each unit project; According to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project; According to projected cost every day of each unit project and every day real cost analyze profit every day of each unit project.The project of obtaining comes into effect day to total number of days of calculation date, the plan of project and completes the expectation engineering total of number of days and each unit project, and according to the resource quota of each unit project and estimate that engineering total determines total projected cost of each unit project; Come into effect according to real cost every day of each unit project, total projected cost, project day completes number of days analysis project final profit to total number of days of calculation date and the plan of project.
For unit project resource step every day of obtaining each unit project, the present embodiment not to obtain each unit project every day unit project resource concrete grammar limit.Include but not limited to: if the system of project management provides the second viewing area of each unit project unit project every day resource, and user inputs unit project resource every day of each unit project in the second viewing area, can obtain unit project resource every day of each unit project that user inputs in the second viewing area.In addition, can also obtain by alternate manner unit project resource every day of each unit project, the present embodiment not to obtain each unit project every day unit project resource concrete grammar limit.
For example, if the system of project management provides the region for unit project is managed shown in Fig. 7 (a), and user is selection unit's engineering 11 rear (as shown in Fig. 7 (b)) in the region shown in Fig. 7 (a), " the branch's subitem " of clicking unit project 11 correspondences in Fig. 7 (b) enters the region for unit project resource is inputted shown in Fig. 8, and in the region shown in Fig. 8, input unit project resource every day of unit project 11, obtain unit project resource every day of the unit project 11 that user inputs in the region shown in Fig. 8.
Certainly, the region shown in Fig. 7 or Fig. 8 can also be other form and content, and the present embodiment does not limit concrete form and the content in the region shown in Fig. 7 or Fig. 8.The mode that enters the region shown in Fig. 8 can also be alternate manner, and the present embodiment does not limit the concrete mode that enters the region shown in Fig. 8, and the present embodiment does not also limit the concrete mode that enters the region shown in Fig. 7 simultaneously.Region shown in Fig. 8 and the region shown in Fig. 7 can be two different regions in the same page, can be also two regions in the different pages, and the present embodiment does not limit the particular location in the region shown in the region shown in Fig. 8 and Fig. 7.Region shown in Fig. 7 or Fig. 8 can provide the input mode of selecting input data from option for user, also can be for user provides the input mode of inputting data from input equipment, the present embodiment does not limit for user provides the input mode of input data the region shown in Fig. 7 or Fig. 8.
In addition, for facilitate user to unit project resource every day of each unit project of input check, revise, the subsequent operation such as deletion, getting unit project resource every day that can show each unit project and each unit project every day after unit project resource of each unit project, and after arbitrary unit project is selected, show unit project resource every day of arbitrary unit project.The present embodiment not to show each unit project and each unit project every day unit project resource concrete mode limit.
For according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day, and according to each unit project every day unit project resource and every day actual performance determine each unit project every day real cost step, can be by the resource quota of each unit project and long-pending projected cost every day that is defined as each unit project of estimating quantities every day, by each unit project every day unit project resource and every day actual performance long-pending real cost every day that is defined as each unit project.In addition, can also by be its computing method determine each unit project projected cost every day and every day real cost, the present embodiment is to according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day, and according to each unit project every day unit project resource and every day actual performance determine each unit project every day real cost concrete grammar limit.
For according to projected cost every day of each unit project and every day real cost analyze each unit project every day profit step, according to projected cost every day of each unit project and every day real cost profit every day of each unit project of difference analysis.In addition, can also be by being profit every day of its each unit project of analytical, the present embodiment not to according to projected cost every day of each unit project and every day real cost analyze each unit project every day profit concrete grammar limit.
Taking the resource quota of earth excavation as 3000 yuan/hectostere, the unit project 11 actual performance of the 1st day is 15 hectosteres, the unit project 11 actual performance of the 2nd day is that 25 hectosteres are example, obtaining the unit project 11 unit project resource of the 1st day is 3500 yuan/hectostere, and the unit project 11 unit project resource of the 2nd day is 2500 yuan/hectostere; 3000*20=60000 unit is defined as to unit project 11 the 1st day and projected cost on the 2nd, 3500*15=52500 unit is defined as to unit project 11 real cost on the 1st, 2500*25=62500 unit is defined as to unit project 11 real cost on the 2nd; Being 60000-52500=7500 unit according to unit project 11 projected cost on the 1st and unit project 11 real cost unit of analysis engineering 11 on the 1st profit on the 1st, is 60000-62500=-2500 unit according to unit project 11 projected cost on the 2nd and unit project 11 real cost unit of analysis engineering 11 on the 2nd profit on the 2nd.
Wherein, the 1st for project implementation day, and the 2nd is the second day of project after coming into effect, and for the convenient method that embodiment is provided describes, the present embodiment is all taking project implementation day as the 1st day, and the second day after project comes into effect is within 2nd, to be example.
Certainly, the resource quota of earth excavation can also be other numerical value and unit, and the present embodiment not concrete numerical value and the unit of the resource quota to earth excavation limits.The actual performance of unit project 11 can also be other numerical value and unit, and the present embodiment not concrete numerical value and the unit of the actual performance to unit project 11 limits.Unit project resource every day of unit project 11 can also be other numerical value and unit, the present embodiment not to unit project 11 every day unit project resource concrete numerical value and unit limit.
Come into effect day to the step of total number of days of calculation date for the project of obtaining, calculation date and project can be come into effect to the difference on date and be defined as total number of days.
For according to the resource quota of each unit project and estimate that engineering total determines the step of total projected cost of each unit project, can and estimate the long-pending total projected cost that is defined as each unit project of engineering total by the resource quota of each unit project.In addition, can also be by being total projected cost that its computing method is determined each unit project, the present embodiment is not to determining that according to the resource quota of each unit project and expectation engineering total the concrete grammar of total projected cost of each unit project limits.
For coming into effect according to real cost every day of each unit project, total projected cost, project day completes the final profit of number of days analysis project step to total number of days of calculation date and the plan of project, can be by the final profit of following formula analysis project.In addition, can also be by being the final profit of its analytical project, the present embodiment does not limit come into effect day the concrete grammar that completes the final profit of number of days analysis project to total number of days of calculation date and the plan of project according to real cost every day of each unit project, total projected cost, project.
the final profit that wherein η is project, a
ibe total projected cost of i unit project, b
i,jbe i unit project j day real cost, the quantity that t is unit project, m is for having planned number of days, and n is that described project comes into effect the total number of days of day to described calculation date.
Still taking the resource quota of earth excavation as 3000 yuan/hectostere, the unit project 11 actual performance of the 1st day is 15 hectosteres, the unit project 11 actual performance of the 2nd day is that 25 hectosteres are example, because calculation date is the second day after project comes into effect, the project of obtaining comes into effect day to total number of days of calculation date 2 days, the plan of project completes number of days 5 days and the expectation engineering total of each unit project is 100 hectosteres, 3000*100=300000 unit is defined as to total projected cost of unit project 11, and unit project 11 real cost on the 1st is 52500 yuan, unit project 11 real cost on the 2nd is 62500 yuan, the quantity of unit project is 1, the final profit of project is:
In addition,, for first aspect, according to analysis result, project is managed and is specially: according to each unit project every day profit and final profit project is carried out to profit control.
The present embodiment not to according to each unit project every day profit and final profit concrete organize content and mode of management that project is carried out to profit control limit.
For example, the analysis results such as the final profit 12500 of 7500 yuan of unit project 11 profits on the 1st and unit project 11 profit-2500 on the 2nd yuan, project are showed with the profit report form shown in table 1.
Table 1
? | Unit project 11 | Explanation |
Profit on the 1st | 7500 | Profit |
Profit on the 2nd | -2500 | Loss |
Day profit sum | 5000 | Profit |
Final profit | 12500 | Profit |
Certainly, can also form the profit form of other form, the present embodiment does not limit the concrete form of the profit form forming.Analysis result can also be showed with histogram or other form, the present embodiment does not limit the concrete manifestation form of final analysis result.
Second aspect: according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem carries out progress analysis to project every day;
The present embodiment is not to according to the resource quota of each unit project, every day actual performance and estimate that the concrete grammar that quantities is per diem carried out progress analysis to project limits every day, include but not limited to: according to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to the resource of each unit project by norm and estimate that quantities determines projected cost every day of each unit project every day; According to projected cost every day of each unit project and complete every daily advance of each unit project of cost analysis every day.
For according to the resource quota of each unit project and every day actual performance determine and complete the step of cost the every day of each unit project, can by the resource quota of each unit project with every day actual performance ly amass the every day that is defined as each unit project and complete cost.In addition, can also be by being that its computing method is determined and completed cost the every day of each unit project, the present embodiment not to according to the resource quota of each unit project and every day actual performance determine that the concrete grammar that completes cost the every day of each unit project limits.
For according to projected cost every day of each unit project and complete the step of every daily advance of each unit project of cost analysis every day, analyze every daily advance of each unit project according to projected cost every day of each unit project and the business that completes cost every day.In addition, can also be by being every daily advance of its each unit project of analytical, the present embodiment is not to limiting according to projected cost every day of each unit project and the concrete grammar that completes every daily advance of each unit project of cost analysis every day.
Taking the resource quota of earth excavation as 3000 yuan/hectostere, the unit project 11 actual performance of the 1st day is 15 hectosteres, the unit project 11 actual performance of the 2nd day is 25 hectosteres, it is example that the expectation quantities of unit project 11 the 1st day and the 2nd day is 20 hectosteres, 3000*15=45000 unit is defined as to unit project 11 and within 1st, completes cost, 3000*25=75000 unit is defined as to unit project 11 and within 2nd, completes cost, and 3000*20=60000 unit is defined as to the projected cost of unit project 11 the 1st day and the 2nd day; 45000/60000=0.75 is defined as to unit project 11 the 1st daily advance, 75000/60000=1.25 is defined as to unit project 11 the 2nd daily advance.
In addition, for second aspect, according to analysis result, project is managed and is specially: according to every daily advance of each unit project, project is carried out to progress control.
The present embodiment does not limit concrete organize content and the mode of management of project being carried out to progress control according to every daily advance of each unit project.
For example, the analysis results such as unit project 11 the 1st daily advance 0.75 and the 2nd daily advance 1.25 are showed with the progress report form shown in table 2.
Table 2
? | Unit project 11 | Explanation |
The 1st daily advance | 0.75 | Progress is incured loss through delay |
The 2nd daily advance | 1.25 | Progress is leading |
Certainly, can also form the progress report of other form, the present embodiment does not limit the concrete form of the progress report forming.Analysis result can also be showed with histogram or other form, the present embodiment does not limit the concrete manifestation form of final analysis result.
The third aspect: according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem carries out cost analysis to project every day.
The present embodiment is not to according to the resource quota of each unit project, every day actual performance and estimate that the concrete grammar that quantities is per diem carried out cost analysis to project limits, and includes but not limited to every day: unit project resource every day of obtaining each unit project; According to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project; According to the real cost and complete every day-rate cost of each unit project of cost analysis every day every day of each unit project.
For according to the real cost and complete the step of every day-rate cost of each unit project of cost analysis every day every day of each unit project, according to complete the every day of each unit project cost and every day real cost every day-rate cost of each unit project of difference analysis.In addition, can also be by being every day-rate cost of its each unit project of analytical, the present embodiment not to according to each unit project every day real cost and the concrete grammar that completes every day-rate cost of each unit project of cost analysis every day limit.
Taking the resource quota of earth excavation as 3000 yuan/hectostere, the unit project 11 actual performance of the 1st day is 15 hectosteres, the unit project 11 actual performance of the 2nd day is 25 hectosteres, it is example that the expectation quantities of unit project 11 the 1st day and the 2nd day is 20 hectosteres, obtaining the unit project 11 unit project resource of the 1st day is 3500 yuan/hectostere, and the unit project 11 unit project resource of the 2nd day is 2500 yuan/hectostere; 3000*15=45000 unit is defined as to unit project 11 and within 1st, completes cost, 3000*25=75000 unit is defined as to unit project 11 and within 2nd, completes cost, and 3500*15=52500 unit is defined as to unit project 11 real cost on the 1st, 2500*25=62500 unit is defined as to unit project 11 real cost on the 2nd; 45000-52500=-7500 unit is defined as to unit project 11 the 1st day-rate cost, 75000-62500=12500 unit is defined as to unit project 11 the 2nd day-rate cost.
In addition, for the third aspect, according to analysis result, project is managed and is specially: according to every day-rate cost of each unit project, project is carried out to cost management.
The present embodiment does not limit concrete organize content and the mode of management of project being carried out to cost management according to every day-rate cost of each unit project.
For example, the analysis results such as unit project 11 the 1st day-rate cost-7500 and the 2nd day-rate cost 12500 are showed with the statement of cost form shown in table 3.
Table 3
? | Unit project 11 | Explanation |
The 1st day-rate cost | -7500 | Cost overrun |
The 2nd day-rate cost | 12500 | Cost surplus |
Certainly, can also form the statement of cost of other form, the present embodiment does not limit the concrete form of the statement of cost forming.Analysis result can also be showed with histogram or other form, the present embodiment does not limit the concrete manifestation form of final analysis result.
It should be noted that, due to estimate actual performance every day, the every day of each unit project quantities and every day unit project resource can As time goes on not change, therefore, if before the method providing by the present embodiment at this is carried out project management, the method providing by the present embodiment was equally carried out project management to this project, and while this project being carried out to project management before, come into effect day to the part date in this calculation date by project or all the date was carried out analysis (for convenience of description to this project, project is come into effect day to the date of carrying out analyzing in this calculation date and was designated as for the first date, the date of not carrying out analyzing was designated as for the second date), perform step 305 quotas of the resource according to each unit project, first every day on date actual performance and estimate that quantities per diem analyzes project the first every day on date, and store this project the first Dates Study result.In such cases, for fear of replicate analysis, accelerate analysis speed, when this method providing by the present embodiment is carried out this project management, can only per diem analyze the analysis result that the first Dates Study result of storage is per diem analyzed this first date of project as this to this second date of project.
Taking this calculation date after project A comes into effect the 3rd day, comes into effect project A day to be designated as the 1st, and the second day after project A comes into effect is designated as the 2nd, and calculating and day being designated as the 3rd is example.This should carry out analyzing for 1st to project A according to the resource quota of each unit project, actual performance on the 1st and expectation quantities on the 1st; According to the resource quota of each unit project, actual performance on the 2nd and expectation quantities on the 2nd, project A is carried out analyzing for 2nd again; Finally according to the resource quota of each unit project, actual performance on the 3rd and expectation quantities on the 3rd, project A is carried out analyzing for 3rd.
If the method once providing by the present embodiment carries out analyzing for 1st to project A according to the resource quota of each unit project, actual performance on the 1st and expectation quantities on the 1st before, and store the analysis result on the 1st of project A, only the resource quota according to each unit project, actual performance on the 2nd and within 2nd, estimate that quantities carries out analyzing for 2nd to project A when this is analyzed; According to the resource quota of each unit project, actual performance on the 3rd and expectation quantities on the 3rd, project A is carried out analyzing for 3rd; Obtain again the analysis result on the 1st of the project A of storage, using the analysis result on the 1st of the project A of storage as this to the analysis result of analyzing for the 1st of project A.
The method that the present embodiment provides, by project per diem being analyzed and is managed according to the resource quota of each unit project of estimating the every day of each unit project actual performance, every day quantities and determine from pre-stored resource quota storehouse, realize taking " my god " as unit carries out project management to project, be beneficial to project carried out to fine-grained management.In addition, not only strengthen project has been carried out to the effect that entirety is controlled, from the resource quota storehouse of storage, determine the resource quota of each unit project simultaneously, avoid adjusting inaccurately because artificial input inaccurate causes analyzing, and then improved the efficiency of project management.
Embodiment tri-
The embodiment of the present invention provides a kind of system of project management, and this system is for the method for the project management carrying out above-described embodiment one or embodiment bis-and provide, and referring to Fig. 9, this system comprises:
Acquisition module 901, comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date for obtaining project;
Determination module 902, for the resource quota of definite each unit project in resource quota storehouse from pre-stored;
Analysis module 903, for according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes project every day;
Administration module 904, manages project for the analysis result obtaining according to analysis module.
Referring to Figure 10, analysis module 903, comprising:
The first acquiring unit 9031, for obtaining unit project resource every day of each unit project;
The first determining unit 9032, for according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day;
The second determining unit 9033, for according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
The first analytic unit 9034, analyzes profit every day of each unit project for projected cost every day of each unit project of determining according to the first determining unit 9032 and definite real cost every day of the second determining unit 9033;
Second acquisition unit 9035, comes into effect day to total number of days of calculation date, the plan of project and completes the expectation engineering total of number of days and each unit project for obtaining project;
The 3rd determining unit 9036, for according to the resource quota of each unit project and estimate that engineering total determines total projected cost of each unit project;
The second analytic unit 9037, for coming into effect according to real cost every day of each unit project, total projected cost, project day completes number of days analysis project final profit to total number of days of calculation date and the plan of project;
Wherein, administration module 904, for according to each unit project every day profit and final profit project is carried out to profit control.
Referring to Figure 11, analysis module 903, comprising:
The 4th determining unit 9038, for according to the resource quota of each unit project and complete cost every day and determine completed projected cost every day of each unit project;
The 5th determining unit 9039, for according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day;
The 3rd analytic unit 90310, for according to projected cost every day of each unit project and complete every daily advance of each unit project of cost analysis every day;
Wherein, administration module 904, carries out progress control for the every daily advance according to each unit project to project.
Referring to Figure 12, analysis module 903, comprising:
The 3rd acquiring unit 90311, for obtaining unit project resource every day of each unit project;
The 6th determining unit 90312, for according to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project;
The 7th determining unit 90313, for according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
The 4th analytic unit 90314, for according to the real cost and complete every day-rate cost of each unit project of cost analysis every day every day of each unit project;
Wherein, administration module 904, carries out cost management for the every day-rate cost according to each unit project to project.
Referring to Figure 13, this system, also comprises:
Display module 905, estimate quantities and resource quota actual performance every day, the every day of each unit project and each unit project for showing, and after arbitrary unit project is selected, show that estimate quantities and resource by norm actual performance every day, the every day of arbitrary unit project.
In sum, described in the embodiment of the present invention, install, by project per diem being analyzed and is managed according to the resource quota of each unit project of estimating the every day of each unit project actual performance, every day quantities and determine from pre-stored resource quota storehouse, realize taking " my god " as unit carries out project management to project, be beneficial to project carried out to fine-grained management.In addition, not only strengthen project has been carried out to the effect that entirety is controlled, from the resource quota storehouse of storage, determine the resource quota of each unit project simultaneously, avoid adjusting inaccurately because artificial input inaccurate causes analyzing, and then improved the efficiency of project management.
It should be noted that: when the system of the project management that above-described embodiment provides realizes project management, only be illustrated with the division of above-mentioned each functional module, in practical application, can above-mentioned functions be distributed and completed by different functional modules as required, be divided into different functional modules by the inner structure of system, to complete all or part of function described above.In addition, the system of the project management that above-described embodiment provides and the embodiment of the method for project management belong to same design, and its specific implementation process refers to embodiment of the method, repeats no more here.
The invention described above embodiment sequence number, just to describing, does not represent the quality of embodiment.
One of ordinary skill in the art will appreciate that all or part of step that realizes above-described embodiment can complete by hardware, also can carry out the hardware that instruction is relevant by program completes, described program can be stored in a kind of computer-readable recording medium, the above-mentioned storage medium of mentioning can be ROM (read-only memory), disk or CD etc.
The foregoing is only preferred embodiment of the present invention, in order to limit the present invention, within the spirit and principles in the present invention not all, any amendment of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.
Claims (10)
1. a method for project management, is characterized in that, described method comprises:
The project of obtaining comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date, and the resource of determining each unit project from pre-stored resource quota storehouse by norm;
According to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes described project every day, according to analysis result, described project is managed.
2. method according to claim 1, is characterized in that, the described resource according to each unit project quota, every day actual performance and estimate that quantities per diem analyzes described project every day, comprising:
Obtain unit project resource every day of each unit project;
According to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
According to projected cost every day of each unit project and every day real cost analyze profit every day of each unit project;
Obtain described project and come into effect day to total number of days of described calculation date, the plan of described project and complete the expectation engineering total of number of days and each unit project, and according to the resource quota of each unit project and estimate that engineering total determines total projected cost of each unit project;
Come into effect day the final profit that completes number of days and analyze described project to total number of days of described calculation date and the plan of described project according to real cost every day of each unit project, total projected cost, described project;
Describedly according to analysis result, described project is managed, comprising:
According to each unit project every day profit and described final profit described project is carried out to profit control.
3. method according to claim 1, is characterized in that, the described resource according to each unit project quota, every day actual performance and estimate that quantities per diem analyzes described project every day, comprising:
According to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to the resource of each unit project by norm and estimate that quantities determines projected cost every day of each unit project every day;
According to projected cost every day of each unit project and complete every daily advance of each unit project of cost analysis every day;
Describedly according to analysis result, described project is managed, comprising:
According to every daily advance of described each unit project, described project is carried out to progress control.
4. method according to claim 1, is characterized in that, the described resource according to each unit project quota, every day actual performance and estimate that quantities per diem analyzes described project every day, comprising:
Obtain unit project resource every day of each unit project;
According to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project, and according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
According to the real cost and complete every day-rate cost of each unit project of cost analysis every day every day of each unit project;
Describedly according to analysis result, described project is managed, comprising:
According to every day-rate cost of each unit project, described project is carried out to cost management.
5. method according to claim 1, it is characterized in that, the described project of obtaining comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date, and determine the resource quota of each unit project from pre-stored resource quota storehouse after, also comprise:
Actual performance every day, the every day that show each unit project and each unit project are estimated quantities and resource by norm, and after arbitrary unit project is selected, show that estimate quantities and resource by norm actual performance every day, the every day of described arbitrary unit project.
6. a system for project management, is characterized in that, described system comprises:
Acquisition module, comes into effect day the actual performance and estimate quantities every day every day to each unit project in calculation date for obtaining project;
Determination module, for the resource quota of definite each unit project in resource quota storehouse from pre-stored;
Analysis module, for according to the resource quota of each unit project, every day actual performance and estimate that quantities per diem analyzes described project every day;
Administration module, manages described project for the analysis result obtaining according to described analysis module.
7. system according to claim 6, is characterized in that, described analysis module, comprising:
The first acquiring unit, for obtaining unit project resource every day of each unit project;
The first determining unit, for according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day;
The second determining unit, for according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
The first analytic unit, analyzes profit every day of each unit project for projected cost every day of each unit project determined according to described the first determining unit and definite real cost every day of described the second determining unit;
Second acquisition unit, comes into effect day to total number of days of described calculation date, the plan of described project and completes the expectation engineering total of number of days and each unit project for obtaining described project;
The 3rd determining unit, for according to the resource quota of each unit project and estimate that engineering total determines total projected cost of each unit project;
The second analytic unit, for coming into effect day the final profit that completes number of days and analyze described project to total number of days of described calculation date and the plan of described project according to real cost every day of each unit project, total projected cost, described project;
Described administration module, for according to each unit project every day profit and described final profit described project is carried out to profit control.
8. system according to claim 6, is characterized in that, described analysis module, comprising:
The 4th determining unit, for according to the resource quota of each unit project and complete cost every day and determine completed projected cost every day of each unit project;
The 5th determining unit, for according to the resource quota of each unit project and estimate that quantities determines projected cost every day of each unit project every day;
The 3rd analytic unit, for according to projected cost every day of each unit project and complete every daily advance of each unit project of cost analysis every day;
Described administration module, carries out progress control for the every daily advance according to described each unit project to described project.
9. system according to claim 6, is characterized in that, described analysis module, comprising:
The 3rd acquiring unit, for obtaining unit project resource every day of each unit project;
The 6th determining unit, for according to the resource quota of each unit project and every day actual performance determine and complete cost the every day of each unit project;
The 7th determining unit, for according to each unit project every day unit project resource and every day actual performance determine real cost every day of each unit project;
The 4th analytic unit, for according to the real cost and complete every day-rate cost of each unit project of cost analysis every day every day of each unit project;
Described administration module, carries out cost management for the every day-rate cost according to each unit project to described project.
10. system according to claim 6, is characterized in that, described system, also comprises:
Display module, estimate quantities and resource quota actual performance every day, the every day of each unit project and each unit project for showing, and after arbitrary unit project is selected, show that estimate quantities and resource by norm actual performance every day, the every day of described arbitrary unit project.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410162860.5A CN103927626A (en) | 2014-04-22 | 2014-04-22 | Method and system for project management |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410162860.5A CN103927626A (en) | 2014-04-22 | 2014-04-22 | Method and system for project management |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103927626A true CN103927626A (en) | 2014-07-16 |
Family
ID=51145841
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410162860.5A Pending CN103927626A (en) | 2014-04-22 | 2014-04-22 | Method and system for project management |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103927626A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104899702A (en) * | 2015-06-26 | 2015-09-09 | 江苏易合大成网络科技有限公司 | Big data-based decoration budget quota management system and method |
CN106022587A (en) * | 2016-05-12 | 2016-10-12 | 广州络维建筑信息技术咨询有限公司 | BIM project progress and cost management system based on earned value theory |
CN109087150A (en) * | 2018-08-18 | 2018-12-25 | 深圳市江益达科技股份有限公司 | Cost intelligent analysis method and device |
CN111415133A (en) * | 2020-03-18 | 2020-07-14 | 成都智造天下科技有限公司 | Shield project cost and benefit monitoring system |
CN111832999A (en) * | 2019-04-16 | 2020-10-27 | 杭州麦扑文化创意有限公司 | Project enterprise management system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1350253A (en) * | 2000-10-23 | 2002-05-22 | Pc网络大厦株式会社 | Project progress state management method |
US20060004618A1 (en) * | 2004-06-30 | 2006-01-05 | Microsoft Corporation | Explaining task scheduling for a project |
JP2012098849A (en) * | 2010-11-01 | 2012-05-24 | Katsuzo Honma | Credibility evaluation method for construction progress level |
CN102592195A (en) * | 2011-12-28 | 2012-07-18 | Tcl集团股份有限公司 | Project control system and method based on development of products |
CN102955982A (en) * | 2011-08-18 | 2013-03-06 | 大连博特软件科技有限公司 | System for managing construction project contracting |
CN103699953A (en) * | 2013-11-06 | 2014-04-02 | 北京驭时德隆科技有限公司 | Project management system, and data processing method and device thereof |
-
2014
- 2014-04-22 CN CN201410162860.5A patent/CN103927626A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1350253A (en) * | 2000-10-23 | 2002-05-22 | Pc网络大厦株式会社 | Project progress state management method |
US20060004618A1 (en) * | 2004-06-30 | 2006-01-05 | Microsoft Corporation | Explaining task scheduling for a project |
JP2012098849A (en) * | 2010-11-01 | 2012-05-24 | Katsuzo Honma | Credibility evaluation method for construction progress level |
CN102955982A (en) * | 2011-08-18 | 2013-03-06 | 大连博特软件科技有限公司 | System for managing construction project contracting |
CN102592195A (en) * | 2011-12-28 | 2012-07-18 | Tcl集团股份有限公司 | Project control system and method based on development of products |
CN103699953A (en) * | 2013-11-06 | 2014-04-02 | 北京驭时德隆科技有限公司 | Project management system, and data processing method and device thereof |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104899702A (en) * | 2015-06-26 | 2015-09-09 | 江苏易合大成网络科技有限公司 | Big data-based decoration budget quota management system and method |
CN104899702B (en) * | 2015-06-26 | 2018-08-24 | 江苏易合大成网络科技有限公司 | Decoration norm for detailed estimates management system based on big data and management method |
CN106022587A (en) * | 2016-05-12 | 2016-10-12 | 广州络维建筑信息技术咨询有限公司 | BIM project progress and cost management system based on earned value theory |
CN109087150A (en) * | 2018-08-18 | 2018-12-25 | 深圳市江益达科技股份有限公司 | Cost intelligent analysis method and device |
CN111832999A (en) * | 2019-04-16 | 2020-10-27 | 杭州麦扑文化创意有限公司 | Project enterprise management system |
CN111415133A (en) * | 2020-03-18 | 2020-07-14 | 成都智造天下科技有限公司 | Shield project cost and benefit monitoring system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5918219A (en) | System and method for estimating construction project costs and schedules based on historical data | |
Lu et al. | A financial decision making framework for construction projects based on 5D Building Information Modeling (BIM) | |
US20080034347A1 (en) | System and method for software lifecycle management | |
CN103927626A (en) | Method and system for project management | |
US11334824B2 (en) | Physical resource optimization system and associated method of use | |
US20210342761A1 (en) | System for mapping model, cost, and schedule of large-scale capital project | |
US8099715B2 (en) | Service-based software designing assistance method and apparatus thereof | |
US20180174243A1 (en) | Systems, methods and apparatus for enhanced navigation in preparation of an electronic tax return | |
Lee et al. | Stochastic project financing analysis system for construction | |
US20190026000A1 (en) | Management of ordered lists of data objects | |
Połoński | Application of the work breakdown structure in determining cost buffers in construction schedules | |
Tsai et al. | A three-stage framework for introducing a 4D tool in large consulting firms | |
CN106779439A (en) | A kind of task distribution method and device | |
US20080249839A1 (en) | Method and system for forecasting workforce demand using advance request and lead time | |
Häckel et al. | AI-based industrial full-service offerings: A model for payment structure selection considering predictive power | |
Chin et al. | The potential cost implications and benefits from building information modeling (BIM) in Malaysian construction industry | |
US10282407B1 (en) | Method for filtering data to generate a balance sheet | |
US20150356518A1 (en) | Aggregate task system | |
US20200410560A1 (en) | Prefilled Owner Invoices | |
Khalaf et al. | Parametric construction cash flow modeling combined with Building Information Modeling and simulation | |
Mundhra et al. | Managing Business in the Civil Construction Sector Through Information Communication Technologies | |
US20140114719A1 (en) | Allocating Service Consumers into Compatible Resource Pools | |
Tallgren et al. | A BIM-supported framework for enhancing joint planning in construction | |
CN104424590A (en) | House-leasing contract cost calculation method based on multi-Agent collaborative technology | |
Samant | Computer Support for Successful Project Management: Using MS Project 2016 with Information Technology Projects |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140716 |