CN103911473B - A kind of method for improving furnace stokehole equipment mud gun nozzle service life - Google Patents

A kind of method for improving furnace stokehole equipment mud gun nozzle service life Download PDF

Info

Publication number
CN103911473B
CN103911473B CN201410170786.1A CN201410170786A CN103911473B CN 103911473 B CN103911473 B CN 103911473B CN 201410170786 A CN201410170786 A CN 201410170786A CN 103911473 B CN103911473 B CN 103911473B
Authority
CN
China
Prior art keywords
mud
big gun
gun mouth
vent
service life
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410170786.1A
Other languages
Chinese (zh)
Other versions
CN103911473A (en
Inventor
陈旭荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TANGSHAN CAOFEIDIAN DISTRICT SHOUYAN MACHINERY CO., LTD.
Original Assignee
TANGHAI SHOUYAN MACHINERY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TANGHAI SHOUYAN MACHINERY Co Ltd filed Critical TANGHAI SHOUYAN MACHINERY Co Ltd
Priority to CN201410170786.1A priority Critical patent/CN103911473B/en
Publication of CN103911473A publication Critical patent/CN103911473A/en
Application granted granted Critical
Publication of CN103911473B publication Critical patent/CN103911473B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Blast Furnaces (AREA)

Abstract

The present invention relates to a kind of method for improving furnace stokehole equipment mud gun nozzle service life, including mud set preparation method is improved and big gun mouth structure improves, it is characterised in that:Mud set preparation method is improved as follows:The use of mud mold is the mud mold that surface is provided with air-vent, is piled up by refractory material or ramming mass by pug, tamp shaping, the step of baking and curing three completes;Big gun mouth structure after improvement is:The outer rim rear portion of cylindric big gun mouth body is provided with seam step, there is a section on the cylindric big gun mouth body of seam step outer rim, and section is provided with pin-and-hole.The beneficial effect that can reach is to effectively improve the cylindricity and surface smoothness of mud set, ensure that mud set inner chamber is brought into close contact with big gun mouth working face, avoid Lou mud and ooze iron generation, greatly reduce big gun mouth end face scaling loss probability, and the increase of seam step, big gun mouth can not only be effectively improved, and integrally sturdy area to avoid Lou mud, and improves when blocking up resistance to compression impact resistance to reduce the rupture of big gun mouth.

Description

A kind of method for improving furnace stokehole equipment mud gun nozzle service life
Technical field
The present invention relates to a kind of steel-refining blast furnace mud gun mouth, belong to metallurgical technology field, be specially a kind of raising blast furnace The method of casthouse equipment mud gun nozzle service life.
Background technology
Furnace stokehole equipment mud gun nozzle is to smelt iron the quick-wear part that consumption is larger in casthouse equipment, is made in casthouse equipment Occupy certain weight/power ratio in being adjusted with, maintenance cost.When clay gun blocks up blast furnace iron notch, big gun mouth directly connects with red-hot molten iron Touch, because of washing away for molten iron, it is easy to it is ablated, typically go out an iron and burn a big gun mouth, therefore, mud gun nozzle in blast furnace plant Belong to consumable accessory, its consumption and plant maintenance workload are sizable.
And the principal element for burning big gun mouth is because stemming leaks outside, it is primarily due to produce gap between big gun mouth and mud set, beats Stemming dynamics is excessive, causes stemming outwards to be gushed out along gap, because stemming temperature is very high, may result in big gun mouth and is burned.Therefore subtract Gap and preventing and treating stemming between small mud set and big gun mouth are leaked as preventing from burning the key factor of big gun mouth.
Tapping hole mud is covered typically by refractory casting(Or ramming)Material is piled up through pug, tamps shaping, the step of baking and curing three Complete.Through field observation, during the compacting of mud sleeve forming, original solid compacting mould due to the exhaust of wet mud it is not smooth and Wet mud splash is produced in the impact moment of compacting, causing mud to cover, local circularity is not accurate enough and pass inner surface plucking, this Big gun mouth and tapping hole sturdy tightness when clay gun is blocked up are have impact on, is caused because of leakage mud runout(Molten iron seepage)And by big gun mouth periphery (Majority is lower end)Scaling loss, therefore, the service life of big gun mouth are not only relevant with big gun mouth structure, material-structure, also with tapping hole The production quality of mud set is closely related.
Simultaneously as big gun mouth structure is unreasonable, it will also result in and cover cooperation imprecision with mud, cause molten iron seepage, and then will Big gun mouth is burnt out, and the service life of big gun mouth is had a greatly reduced quality.
The content of the invention
It is an object of the invention to provide a kind of cooperation tight ness rating by improving between mud set and big gun mouth, anti-leak-stopping mud oozes iron The generation of phenomenon.The method for improving the service life of blast furnace mud gun mouth.
The purpose of the present invention can be achieved in that:Mud set preparation method is improved and big gun mouth structure improves, it is characterised in that:
Mud set preparation method is improved as follows:The use of mud mold is the mud mold that surface is provided with air-vent, by fire proofed wood Expect or ramming mass is piled up by pug, tamps shaping, the step of baking and curing three completes;
Big gun mouth structure after improvement is:The outer rim rear portion of cylindric big gun mouth body is provided with seam step, seam step outer rim There is a section on cylindric big gun mouth body, section is provided with pin-and-hole.
The purpose of the present invention can also be achieved in that:The mud mold that described surface is provided with air-vent is hollow cylinder Body, the surface of hollow cylinder are provided with equally distributed air-vent, and air-vent is penetrated in hollow cylinder connection hollow cylinder body Cavity;
Described air-vent is arranged for 2-3;
Described air-vent is that every row is 4-6, and the hole of adjacent two row is in staggered distribution.
The beneficial effect that can reach is:Ensure that mud covers what is be extruded during wet mud is tamped using the mould with air-vent Air can exclude in time from dies cavity, eliminate plucking phenomenon of the wet mud splash to hole wall, effectively improve the cylindricity of mud set And surface smoothness, it is ensured that mud set inner chamber is brought into close contact with big gun mouth working face, avoid Lou mud with to ooze iron long-living, greatly reduce big gun mouth End face scaling loss probability;And the increase of big gun mouth seam step, can not only effectively improve big gun mouth integrally sturdy area to avoid Lou mud, And improve resistance to compression impact resistance when blocking up and ruptured with reducing big gun mouth;Mud mold after improvement and new big gun mouth are matched somebody with somebody After conjunction use, through stokehold production, observation and effect tracking evaluation, the maintenance period of mud set extend 3 times repeatedly, and big gun mouth is put down Equal service life improves nearly 10 times, therefore greatly reduces the labor intensity of tapping hole maintenance and making for operation of blast furnace spare part Use cost.
Brief description of the drawings
Fig. 1 is the axial sectional view of blast furnace mud stemming mold of the present invention;
Fig. 2 is the A-A sectional views of blast furnace mud stemming mold of the present invention;
Fig. 3 is the axial sectional view of blast furnace mud gun mouth of the present invention;
Fig. 4 is the blast furnace mud gun mouth side view of the present invention.
Embodiment
Parts title in accompanying drawing represented by each label is as follows:
Mud mold:Mud set 1, air-vent 2, hollow cylinder 3;Big gun mouth:Cylindric big gun mouth body 4, seam step 5, pin-and-hole 6th, section 7.
With reference to embodiment, the invention will be further described:
The present invention changes for a kind of method of raising furnace stokehole equipment mud gun nozzle service life, including mud set preparation method Enter and improved with big gun mouth structure, it is characterised in that:
Mud set preparation method is improved as follows:The use of mud mold is the mud mold that surface is provided with air-vent, by fire proofed wood Expect or ramming mass is piled up by pug, tamps shaping, the step of baking and curing three completes;
Big gun mouth structure after improvement is:The outer rim rear portion of cylindric big gun mouth body 4 is provided with seam step 5, the outer rim of seam step 5 Cylindric big gun mouth body 4 on have a section 7, section 7 is provided with pin-and-hole 6.
According to Fig. 1, Fig. 2:The blast furnace mud stemming mold of the present invention is provided with the mud mold of air-vent, bag for surface Hollow cylinder 3 is included, the surface of hollow cylinder 3 is provided with equally distributed air-vent 2, and air-vent 2 penetrates hollow cylinder 3 and connected Cavity in logical hollow cylinder 3, it is ensured that the air being extruded during the wet mud compacting of mud set 1 can be timely from dies cavity Exclude, eliminate plucking phenomenon of the wet mud splash to hole wall, effectively improve the cylindricity and surface smoothness of mud set 1, mud can be made to cover 1 Inner chamber is brought into close contact with big gun mouth working face, is avoided Lou mud and is oozed iron generation, greatly reduces big gun mouth end face scaling loss probability.
Described air-vent 2 is arranged for 2-3, and often row is 4-6, and the hole of adjacent two row is in staggered distribution, and can so make whole mould The moisture on tool periphery can all be discharged by inner chamber, and it is minimum that the influence of inner surface finish is covered on mud.
According to Fig. 3, Fig. 4:For the blast furnace mud gun mouth of the present invention, the setting of seam step 5, this can not only be effective Improving big gun mouth, integrally sturdy area to avoid Lou mud, and improves resistance to compression impact resistance when blocking up and ruptured with reducing big gun mouth; And section 7 protrudes from big gun mouth outer rim, which adds the thickness at big gun mouth pin-and-hole, the Burning corrosion resistance of increase big gun mouth.
Mud set makes:
Old mud set mud in iron oralia is destroyed, cleaned out, appropriate mud set mud is put on iron mouth pore passage, then incite somebody to action this The mud mold of invention is inserted in iron mouth, and in being piled up to mud set mud, tamping forming process, mud covers mud can produce because meeting high temperature Raw a large amount of moistures, moisture can be discharged by the air-vent on mud mold to its inner chamber, and then are discharged to exterior space, eliminated Wet mud splash effectively improves cylindricity and surface smoothness that mud covers, it is ensured that mud covers inner chamber and big gun mouth to the plucking phenomenon of hole wall Working face is brought into close contact, and is avoided Lou mud and is oozed iron generation.
Use operation:
After mud set is solid, the mud gun nozzle of the present invention is directed at tapping hole mud set, big gun mouth is stretched into inside tapping hole, seam Step is stuck in mud set outer end, then carries out stemming and blocks work, because the effect of the seam step of big gun mouth of the present invention, big gun mouth and mud Set closely snaps together, and internal stemming can not flow out, it may also reduce ooze the generation of iron phenomenon, big gun mouth body is tried one's best Reduce ablation loss.

Claims (4)

1. a kind of method for improving furnace stokehole equipment mud gun nozzle service life, including mud set preparation method is improved and big gun mouth knot Structure improves, it is characterised in that:
Mud set preparation method is improved as follows:The use of mud mold is the mud mold that surface is provided with air-vent, is passed through by refractory material Cross that pug is piled up, tamps shaping, the step of baking and curing three completes;
Big gun mouth structure after improvement is:Cylindric big gun mouth body(4)Outer rim rear portion be provided with seam step(5), seam step(5)Outside The cylindric big gun mouth body of edge(4)On have a section(7), section(7)It is provided with pin-and-hole(6).
A kind of 2. method for improving furnace stokehole equipment mud gun nozzle service life according to claim 1:Its feature exists In:The mud mold that described surface is provided with air-vent is hollow cylinder(3), hollow cylinder(3)Surface be provided with uniformly The air-vent of distribution(2), air-vent(2)Penetrate hollow cylinder(3)Connect hollow cylinder(3)Interior cavity.
3. a kind of method for improving furnace stokehole equipment mud gun nozzle service life according to claim 2, its feature exist In:Described air-vent(2)Arranged for 2-3.
4. a kind of method for improving furnace stokehole equipment mud gun nozzle service life according to claim 2, its feature exist In:Described air-vent(2)It it is 4-6 for every row, the hole of adjacent two row is in staggered distribution.
CN201410170786.1A 2013-12-20 2014-04-27 A kind of method for improving furnace stokehole equipment mud gun nozzle service life Active CN103911473B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410170786.1A CN103911473B (en) 2013-12-20 2014-04-27 A kind of method for improving furnace stokehole equipment mud gun nozzle service life

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN2013107078337 2013-12-20
CN201310707833 2013-12-20
CN201310707833.7 2013-12-20
CN201410170786.1A CN103911473B (en) 2013-12-20 2014-04-27 A kind of method for improving furnace stokehole equipment mud gun nozzle service life

Publications (2)

Publication Number Publication Date
CN103911473A CN103911473A (en) 2014-07-09
CN103911473B true CN103911473B (en) 2017-11-10

Family

ID=51037473

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410170786.1A Active CN103911473B (en) 2013-12-20 2014-04-27 A kind of method for improving furnace stokehole equipment mud gun nozzle service life

Country Status (1)

Country Link
CN (1) CN103911473B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3938547B1 (en) * 2019-03-13 2023-02-15 Tmt - Tapping Measuring Technology Sàrl Taphole plugging gun

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2854925B2 (en) * 1990-05-16 1999-02-10 川崎製鉄株式会社 Injection cooling method of remaining charge in furnace during air blow off operation of blast furnace
JPH08311513A (en) * 1995-05-15 1996-11-26 Shinagawa Refract Co Ltd Seal material for mud gun in blast furnace and method for preventing leakage of mud material
CN200946153Y (en) * 2006-08-31 2007-09-12 黄述生 Blast furnace taphole gun muzzle head
CN200999251Y (en) * 2007-01-19 2008-01-02 宝山钢铁股份有限公司 Flexible gun head for blast furnace front hole blocking
CN201261788Y (en) * 2008-09-30 2009-06-24 戴光荣 Novel mud gun nozzle
CN201395604Y (en) * 2009-04-16 2010-02-03 宝山钢铁股份有限公司 Gun head of blast furnace tapping-hole clay gun
CN202595170U (en) * 2012-03-27 2012-12-12 上海梅山钢铁股份有限公司 Blast-furnace gun nozzle capable of preventing mud from leaking

Also Published As

Publication number Publication date
CN103911473A (en) 2014-07-09

Similar Documents

Publication Publication Date Title
CN103911473B (en) A kind of method for improving furnace stokehole equipment mud gun nozzle service life
CN111843101A (en) Method for repairing and welding copper mold bottom plate made of nodular cast iron
CN205188326U (en) Can prevent iron notch of blast furnace structure of gas leakage
CN105087872A (en) Repairing method of RH refining furnace vacuum chamber tank bottom and circulation pipe
CN209877630U (en) Novel pot-type calcining furnace
CN108342533B (en) blast furnace residual iron safe discharging opening control method
CN111893231A (en) Blast furnace hearth and casting long-life lifting method thereof
CN203621479U (en) Continuous casting machine tundish dry material heating mold
CN102851040B (en) Method for repairing fusion holes in wall of carbonization chamber without cooling
CN202157079U (en) Iron runner residual iron hole for discharging blocked residual iron
CN110819750B (en) Blast furnace and plugging device for blast furnace shell and cooling wall
CN207376080U (en) Mineral hot furnace tapping device
CN108977603B (en) Repairing method for iron notch frame burn-through of iron-making blast furnace
CN102134621A (en) Blast furnace iron notch patching method
CN218627754U (en) Brick masonry structure for discharge area of rotary refining furnace
CN2550091Y (en) Boiling type resin sand thermal regenerating furnace
CN110408735B (en) Method for repairing gooseneck part under blast furnace air supply system hot blast bustle pipe
CN110607410B (en) Manufacturing method of blast furnace taphole mud sleeve and manufactured mud sleeve
CN105400920B (en) A kind of forced method for repairing and mending of air heating furnace roof heat-resisting liner
CN209872997U (en) Reduce embedded protective sheath of dismantling of big gun mouth scaling loss
CN110003922A (en) A kind of method for repairing and mending of peephole brick cup down tube brick
CN111438350B (en) Repairing method of ladle working lining brick
CN102816888A (en) Method for preventing sintering of steel outlet during fettling
CN218910239U (en) Mount-high bamboo calcining equipment
KR100428077B1 (en) Auxiliary tip of mud gun

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 063200 Hebei province Tangshan City Caofeidian District Tang Hai Town West Economic Zone

Patentee after: TANGSHAN CAOFEIDIAN DISTRICT SHOUYAN MACHINERY CO., LTD.

Address before: 063200 West Tanghai Economic Zone, Tanghai, Tangshan City, Hebei

Patentee before: TANGHAI SHOUYAN MACHINERY CO., LTD.