CN103901875A - Load change actual increasing and decreasing rate calculating method for generator unit AGC test - Google Patents

Load change actual increasing and decreasing rate calculating method for generator unit AGC test Download PDF

Info

Publication number
CN103901875A
CN103901875A CN201410079878.9A CN201410079878A CN103901875A CN 103901875 A CN103901875 A CN 103901875A CN 201410079878 A CN201410079878 A CN 201410079878A CN 103901875 A CN103901875 A CN 103901875A
Authority
CN
China
Prior art keywords
load
point
unit
actual
change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410079878.9A
Other languages
Chinese (zh)
Inventor
赵毅
杨鑫
欧阳佳慧
张长志
张应田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410079878.9A priority Critical patent/CN103901875A/en
Publication of CN103901875A publication Critical patent/CN103901875A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a load change actual increasing and decreasing rate calculating method for a generator unit AGC test. The method comprises the steps that (1) a unit load Q1 obtained after the actual load value exceeds an instruction within +/-1 % Pe is selected as a start point load of a change, and the specific time T1 when the change occurs is recorded at the same time; (2) a unit load Q2 obtained after the actual load value reaches the instrument within +/-1% Pe is selected as a terminal point load of the change, and the specific time T2 when the change occurs is recorded at the same time; (3) the actual change rate V=(Q2-Q1)/(T2-T1) is calculated; (4) if the unit grinding start stage or the unit grinding stop stage of the load change process is passed, the time T3 when the unit is in the start/stop grinding load point within +/-1% Pe is recorded, the time T4 when the unit is not in the start/stop grinding load point within +/-1% Pe is recorded, and the change rate is changed into V=(Q2-Q1)/(T2-T1-T4+T3). According to the load change actual increasing and decreasing rate calculating method for the generator unit AGC test, by means of determination of the most reasonable start point and the terminal point of the load change, whether the AGC test is up to standard or not is accurately judged.

Description

The method of the actual elevation rate of load variations in genset AGC test
Technical field
The invention belongs to Automatic Generation Control technical field technical field, the method for the actual elevation rate of load variations in especially a kind of genset AGC test.
Background technology
At present according to grid-connected administrative provisions and safety evaluatio file, ensure electricity net safety stable reliability service, carry out the control of interconnection power and frequency control, need to carry out genset AGC(Automatic Generation Control according to the time between overhauls(TBO) of each power plant) performance test, pilot project is mainly as follows: Load Regulation speed, degree of regulation and response time.Three variablees calculate independent but interact.
The definition of index, regulations speed refers to the speed that in a period of time, unit active power changes, load instruction changes, just carry out regulations speed calculating, each speed of calculated load instruction changes phase, if instruction does not change, do not calculate, if opening mill point, reject and open the time that mill point consumes.
Open mill point and refer to, start the time period of coal pulverizer, can be compared to automobile lifting shelves the same, during to certain generation load, will change the number of units of moving coal pulverizer, generally need about 10 minutes.
At present, in various files specify, as " region, North China generate electricity by way of merging two or more grid systems factory's assistant service management implementation detailed rules and regulations " adopts said method regulation to regulations speed, but in actual computation, whether specifically note load variations starting point and destination node, so each computing method will draw different conclusions, especially in the time judging raising speed rate whether qualified, the difference of account form, access time, the difference of point will produce near the small deviation of qualified criterion, it is qualified causing underproof rate calculations, and qualified being calculated as is defective.By retrieval, do not retrieve pertinent literature and the patent content of the method solving the problems of the technologies described above in this technical field at present.
Summary of the invention
The object of the invention is for the deficiencies in the prior art, and propose the method for the actual elevation rate of load variations in a kind of genset AGC test.
The present invention solves its technical matters and takes following technical scheme to realize:
A method for the actual elevation rate of load variations in genset AGC test, comprises that step is as follows:
(1) choose the starting point of load variations, i.e., after unit load instruction changes, actual load value exceeds after instruction ± 1%Pe, and the unit load Q1 in this moment is the point load that rises changing, and records the concrete moment T1 that changes simultaneously;
(2) choose the terminal of load variations, i.e., after unit load instruction stops changing, after actual load entry instruction ± 1%Pe, the unit load Q2 in this moment is the terminal load changing, and records the concrete moment T2 that changes simultaneously;
(3) calculate actual rate: V=(Q2-Q1)/(T2-T1);
(4) if having passed through unit, load alternation process opens the mill stage, or stop the mill stage, record unit and enter and open/stop the time T 3 of grinding load point ± 1%Pe, record leaves the T4 of start and stop mill load point ± 1%Pe, and rate of change is changed to: V=(Q2-Q1)/(T2-T1-T4+T3).
Advantage of the present invention and good effect are:
1, can be according to this method, find the most rational starting point of each load variations and terminal;
2, utilize starting point and terminal, accurately calculate each speed during AGC tests central load variations;
3, according to each speed, no matter calculate mean speed or minimum-rate, can judge whether AGC test is qualified as raw data.
Brief description of the drawings
Fig. 1 is the starting point of load variations and the schematic diagram of evaluation of end point in the inventive method;
Fig. 2 is that in the inventive method, unit opens the mill stage, and stops the timing schematic diagram in the stage of grinding;
Fig. 3 is the starting point of load variations and the schematic diagram of evaluation of end point in example of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the invention process is further described, following examples are descriptive, are not determinate, can not limit protection scope of the present invention with this.
A method for the actual elevation rate of load variations in genset AGC test, as shown in Figure 1, method step is as follows:
(1) choose the starting point of load variations, i.e., after unit load instruction changes, actual load value exceeds after instruction ± 1%Pe, and this moment is the starting point Q1 that unit load changes, and records the concrete moment T1 that changes simultaneously; Wherein, choose load variations starting point Q1 according to being:
First we establish A, B 2 points, A point refers to, the moment that load instruction changes, B point refers to, after load instruction changes, actual load in load instruction change direction for the first time by the moment of former load instruction, if actual load and former load instruction do not have intersection point in load instruction change direction, get the intersection point place of last actual load and former load instruction.
As shown in Figure 1, if choose A point or B point as zequin, will conflict mutually with another index " response time ", after response time refers to that system is sent instruction, unit load former go out on the basis in force, step out reliably the adjusting dead band used time consistent with regulating direction.Regulate dead band to get 1%Pe, the rated power of the unit that Pe refers to, general response time starting point is chosen A point, and end point is T1 place.Reason one: the starting point of rate of load change is chosen to A point or B point because A point or B point also former go out within the dead band in force, do not step out dead band, thus think that this adjustment does not also have substantial progress, so should not select A point or B point.Two: three indexs of reason, response time, regulations speed, degree of regulation are interactional three amounts, choosing the response time should not affect the calculating of regulations speed, between their two variablees, it should be the mutual linking of time point, so it is very rational starting point being chosen to T1 from this aspect, and chose A point or B point is irrational in the past;
(2) choose the terminal of load variations, i.e., after unit load instruction stops changing, after actual load entry instruction ± 1%Pe, this moment is the terminal Q2 that unit load changes, and records the concrete moment T2 that changes simultaneously; Wherein, choose load variations terminal Q2 according to being:
First we establish C, D 2 points, C point refers to, actual load produces intersection point for the first time according to load instruction change direction moment with new load instruction, D point refers to, after load instruction changes, actual load reaches the moment of first peak value after load instruction change direction is for the first time by new load instruction.
If choose C point or D point as rate calculations terminal, will conflict mutually with the calculating of static deviation, static deviation refers to unit operation unit actual load and load deviation between instruction in the time of steady-state process.Steady-state process starting point refers to after unit instruction variation, changes to new instruction by former instruction, and unit actual load enters into the dead zone range of the new instruction of unit.And the terminal of steady-state process refers to the moment that unit instruction changes next time.If the relation between steady-state process and response time, regulations speed calculation stages, it should be an organic process overlapping, reason one: if choose C point or the D point terminal as rate calculations, because C point, D point have entered steady-state process, should there is no direct relation with lift adjustment process, but unit is in around the new instruction stable operation of unit.Reason two: if choose C point, D point as terminal, conflict mutually with the calculation stages of steady-state deviation.So the end point of calculating AGC speed is chosen should be at T2;
(3) calculate actual rate: V=(Q2-Q1)/(T2-T1);
(4) as shown in Figure 2, if this process has been passed through unit and opened the mill stage, or stop the mill stage, record unit and enter and open/stop the time T 3 of grinding load point ± 1%Pe, record leaves the T4 of start and stop mill load point ± 1%Pe, and rate of change is changed to: V=(Q2-Q1)/(T2-T1-T4+T3).
Example 1
Certain power plant's AGC process of the test is described below:
Unit rated capacity 330MW, testing standard: it is 6.6MW/min that regulations speed is not less than 2%Pe.
On 06 11st, 2012, three coal pulverizer operations, referring to Fig. 3, 11:25:46 is at A point, load instruction is made as 220MW by 165MW, main vapour pressure 14.54MPa, load changing rate is set as 7MW/min, 11:26:01 actual load arrives B point, leave 1% dead band T1 point to 11:26:06 actual load, 11:34:26 arrives T2 point, 11:34:30 actual load arrives C point, and to the time of peaking D be 11:35:02, if choose A point or B point according to starting point, terminal is chosen T2, the result of computation rate is 6.35MW/min, 6.53MW/min, be starting point and choose T1, and C point, D point is terminal, speed is respectively 6.55MW/min, 6.15MW/min, standard 6.6MW/min according to the rules, if access time, point was not right, speed does not reach requirement, thereby can not obtain AGC and drop into license.
According to the AGC test period standard that is month, if this defective next stand the test, at least the loss of the electricity price of this month is calculated according to following formula: taking 330MW unit as example, monthly the unit generation time was according to 500 hours, 0.001 yuan/kilowatt hour of the electric price difference of every degree, result is 0.001 yuan/kilowatt hour=165000 yuan of 500 hours * 330*1000 kilowatt hour *.Bring approximately more than 160,000 yuan of direct economic loss.

Claims (1)

1. a method for the actual elevation rate of load variations in genset AGC test, is characterized in that comprising that step is as follows:
(1) choose the starting point of load variations, i.e., after unit load instruction changes, actual load value exceeds after instruction ± 1%Pe, and the unit load Q1 in this moment is the point load that rises changing, and records the concrete moment T1 that changes simultaneously;
(2) choose the terminal of load variations, i.e., after unit load instruction stops changing, after actual load entry instruction ± 1%Pe, the unit load Q2 in this moment is the terminal load changing, and records the concrete moment T2 that changes simultaneously;
(3) calculate actual rate: V=(Q2-Q1)/(T2-T1);
(4) if having passed through unit, load alternation process opens the mill stage, or stop the mill stage, record unit and enter and open/stop the time T 3 of grinding load point ± 1%Pe, record leaves the T4 of start and stop mill load point ± 1%Pe, and rate of change is changed to: V=(Q2-Q1)/(T2-T1-T4+T3).
CN201410079878.9A 2014-03-06 2014-03-06 Load change actual increasing and decreasing rate calculating method for generator unit AGC test Pending CN103901875A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410079878.9A CN103901875A (en) 2014-03-06 2014-03-06 Load change actual increasing and decreasing rate calculating method for generator unit AGC test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410079878.9A CN103901875A (en) 2014-03-06 2014-03-06 Load change actual increasing and decreasing rate calculating method for generator unit AGC test

Publications (1)

Publication Number Publication Date
CN103901875A true CN103901875A (en) 2014-07-02

Family

ID=50993263

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410079878.9A Pending CN103901875A (en) 2014-03-06 2014-03-06 Load change actual increasing and decreasing rate calculating method for generator unit AGC test

Country Status (1)

Country Link
CN (1) CN103901875A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106529161A (en) * 2016-10-28 2017-03-22 东南大学 Method for determining ascending and descending load speed on basis of thermal power unit operation data
CN109339872A (en) * 2018-10-18 2019-02-15 中广核工程有限公司 Nuclear power station steam turbine control system
CN109802449A (en) * 2019-03-13 2019-05-24 国网山东省电力公司电力科学研究院 AGC unit dynamic adaptation method and device based on active power notch
CN111638409A (en) * 2020-05-22 2020-09-08 国网天津市电力公司电力科学研究院 Automatic power generation control step load disturbance test method for thermal generator set
CN111650512A (en) * 2020-05-22 2020-09-11 国网天津市电力公司电力科学研究院 Follow-up load disturbance test method for automatic power generation control of thermal generator set
CN113231188A (en) * 2021-06-07 2021-08-10 国投云顶湄洲湾电力有限公司 Method for improving response load rate of generator set of pulverizing system of medium-speed coal mill

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070038335A1 (en) * 2005-07-22 2007-02-15 Mcintyre Timothy J Real Power Regulation for the Utility Power Grid Via Responsive Loads
CN102175972A (en) * 2011-01-25 2011-09-07 北京四方继保自动化股份有限公司 Method for analyzing AGC (automatic generation control) power adjustment linear property of power generator based on PMU (phasor measurement unit) data
CN102255311A (en) * 2011-08-05 2011-11-23 辽宁省电力有限公司 Method for controlling automatic gain control (AGC) set
CN103345205A (en) * 2013-05-21 2013-10-09 国家电网公司 Data verification-based AGC load optimizing controlling method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070038335A1 (en) * 2005-07-22 2007-02-15 Mcintyre Timothy J Real Power Regulation for the Utility Power Grid Via Responsive Loads
CN102175972A (en) * 2011-01-25 2011-09-07 北京四方继保自动化股份有限公司 Method for analyzing AGC (automatic generation control) power adjustment linear property of power generator based on PMU (phasor measurement unit) data
CN102255311A (en) * 2011-08-05 2011-11-23 辽宁省电力有限公司 Method for controlling automatic gain control (AGC) set
CN103345205A (en) * 2013-05-21 2013-10-09 国家电网公司 Data verification-based AGC load optimizing controlling method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘芳,田亮,申克峰: "火电机组AGC 速率的在线计算方法研究", 《电力科学与工程》, vol. 29, no. 5, 30 May 2013 (2013-05-30) *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106529161A (en) * 2016-10-28 2017-03-22 东南大学 Method for determining ascending and descending load speed on basis of thermal power unit operation data
CN109339872A (en) * 2018-10-18 2019-02-15 中广核工程有限公司 Nuclear power station steam turbine control system
CN109802449A (en) * 2019-03-13 2019-05-24 国网山东省电力公司电力科学研究院 AGC unit dynamic adaptation method and device based on active power notch
CN111638409A (en) * 2020-05-22 2020-09-08 国网天津市电力公司电力科学研究院 Automatic power generation control step load disturbance test method for thermal generator set
CN111650512A (en) * 2020-05-22 2020-09-11 国网天津市电力公司电力科学研究院 Follow-up load disturbance test method for automatic power generation control of thermal generator set
CN113231188A (en) * 2021-06-07 2021-08-10 国投云顶湄洲湾电力有限公司 Method for improving response load rate of generator set of pulverizing system of medium-speed coal mill
CN113231188B (en) * 2021-06-07 2022-05-24 国投云顶湄洲湾电力有限公司 Method for improving response load rate of generator set of pulverizing system of medium-speed coal mill

Similar Documents

Publication Publication Date Title
CN103901875A (en) Load change actual increasing and decreasing rate calculating method for generator unit AGC test
CN101793228B (en) Method and device for monitoring a wind farm
CN104201670B (en) Cooperative control method and system of battery energy storage power source participating in secondary frequency modulation of power grid
CN102347637B (en) Supervisory control method and equipment for smart grids
CN105703382B (en) A kind of wind power plant sub-synchronous oscillation suppression method and system
CN103823183B (en) A kind of measuring method of synchronous generator stator open circuit transient time-constant
US9513650B2 (en) Method in an electric power system, controller, computer programs, computer program products and electric power system
RU2015156049A (en) METHOD FOR SUPPLYING ELECTRIC POWER TO THE POWER SUPPLY NETWORK
CN106611965B (en) Wind power plant coordination control method and system for preventing large-scale wind power from frequently crossing
CN104810851B (en) Load regulation speed dynamic regulating method and device under AGC mode of thermal power generating unit
CN103760768A (en) Generator set multivariable system identification method based on normal operating data
CN103366064A (en) Test method for parameters of wind farm dynamic model
CN104600708B (en) Wind energy turbine set automatism voltage control distribution method containing SVG
CN105067905A (en) Frequency converter power electronics controllable loading method based on grid connected inverter
Gabash et al. Analysis of influence factors on rejected active power from active distribution networks
CN103683325A (en) Island control method based on FCB set
CN204086850U (en) The step setting value of coordinated control system forms loop
CN102607007B (en) Control method and control device for primary fan system of coal-fired unit
CN104333326B (en) A kind of test method of photovoltaic DC-to-AC converter controller external characteristics test
Constantin et al. Open loop Q (U) stability investigation in case of PV power plants
CN104242298B (en) A kind of control method for frequency of the isolated island exchange micro-capacitance sensor of all distributed structure
CN105334846A (en) Water power station diversion system dynamic characteristic parameter prototype test method
CN105759159A (en) Wind power plant static var generator (SVG) response time test system of with voltage dividing regulating device
CN103806959A (en) Method and device for preventing turbine control system of nuclear power station from generating disturbance
CN204741287U (en) Device of load regulation speed dynamic adjustment under coal -fired power unit AGC mode

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 300010 Tianjin city Hebei District Wujing Road No. 39

Applicant after: State Grid Corporation of China

Applicant after: State Grid Tianjin Electric Power Company

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant before: State Grid Corporation of China

Applicant before: State Grid Tianjin Electric Power Company

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140702