CN103901503A - 矿山地下巷道掘进时对前方不良地质体的一种综合探测方法 - Google Patents

矿山地下巷道掘进时对前方不良地质体的一种综合探测方法 Download PDF

Info

Publication number
CN103901503A
CN103901503A CN201410113061.9A CN201410113061A CN103901503A CN 103901503 A CN103901503 A CN 103901503A CN 201410113061 A CN201410113061 A CN 201410113061A CN 103901503 A CN103901503 A CN 103901503A
Authority
CN
China
Prior art keywords
plastid
poorly
tunnel
survey
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410113061.9A
Other languages
English (en)
Inventor
李国祥
杜坤乾
赵建海
展国伟
李志朋
李庆功
张红旗
王静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Original Assignee
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC filed Critical Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority to CN201410113061.9A priority Critical patent/CN103901503A/zh
Publication of CN103901503A publication Critical patent/CN103901503A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Geophysics And Detection Of Objects (AREA)

Abstract

本发明矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,巷道没有开挖前在地表进行“工程地质测绘+氡气测量+CSAMT”的综合探测;在巷道掘进施工时进行“工程地质素描+TSP+GPR”的综合探测;在探测布局上形成立体空间交叉探测体系,可以精准的探测到不良地质体的存在空间形态及其规模。其优点是:避免了单一物探或化探方法的局限性,或单一进行地表或单一进行地下测探的不合理性,可以通过从地表到地下,从短距离到长距离所形成的立体空间探测体系,较为准确的测得巷道前方的不良地质体的分布位置及空间形态特征,为巷道的掘进、支护提供可靠的技术情报与服务支撑。

Description

矿山地下巷道掘进时对前方不良地质体的一种综合探测方法
技术领域
本发明涉及地球物理勘探和化探领域,具体地说是矿山地下巷道掘进时对前方不良地质体的一种综合探测方法。
背景技术
矿山地下巷道在掘进时,需对巷道前方的不良地质体,如:断层破碎带、软弱夹层、溶(空)洞、突水、突泥、涌沙、塌方、岩爆、大型含水体等进行预判,为开挖、支护及疏排水等工作做好准备,避免地质灾害的发生。现阶段对地下不良地质体的探测方法有以下几种基本方法:
一是主要在地表进行地球物理勘探,其方法主要有电法勘探、电磁法勘探及地震勘探等,其中电法勘探包括电阻率法、充电法、自然电场法和激发极化法;电磁法勘探包括频率电磁测深法、瞬变电磁法(TEM)、可控源音频大地电磁测深法(CSAMT)、探地雷达(GPR);地震勘探包括透射波法、反射波法、折射波法、瑞雷波法;可根据地下巷道的底板埋深及预估不良地质体的主要类型综合确定选用,此种类型方法也可结合地质方法,如工程地质调查与测绘等或结合化探方法。
另一种方法是在地下进行地球物理勘探,即在巷道每次开挖前,做巷道地质超前预报,地质超前预报的主要方法有地质方法和地球物理方法,地质方法包括地质素描、超前钻、超前导坑等,现在很少用。地球物理方法包括地震法、电磁法、波反射法、声波透射法及CT层析成像法等,目前以地震法为主。地震法中包括负视速度、HSP、TSP、TGP、TRT、TST等各种方法。
由于一种地球物理方法或几种地球物理方法的组合选择不当,致使对地下巷道前方不良地质体的探测效果较差或不显著,基于上述原因,发明一种能够准确探测地下巷道掘进前方不良地质体的综合方法,具有广泛的应用价值。
发明内容
本发明提供矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,能够较为准确的测得巷道掘进前方不良地质体的具体位置及形态特征。
本发明矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,包括有步骤S1和步骤S2,共两个步骤;
所述的步骤S1为在巷道的设计位置确定后,没有进行施工开挖前在地表进行探测;
所述的步骤S2为在巷道开始掘进时,在巷道内进行探测。
所述的步骤S1又包含步骤101至步骤103,共三个步骤:
   步骤101:在工程区进行工程地质调查与测绘,了解区域地质构造、地层岩性及厚度,岩石结构面特征、大的断裂构造及节理裂隙的发育程度等;
   步骤102:垂直巷道的走向布设氡气测量线,进行浅部土壤的氡气测量,目的是探测地下巷道深度内是否存在断层,及其活动性如何;
步骤103:垂直巷道的走向布设CSAMT测线,测线位置与氡气测量线的位置重合(这样化探和物探结果可以相互验证),进行地下不良地质体的探测,探测深度在2km左右。
所述的步骤S2又包括步骤201至步骤203,共三个步骤:
步骤201:在巷道掘进掌子面进行地质素描,掌握巷道围岩是否存在不良地质体,以及不良地质体的基本特征;
步骤202:在巷道掌子面进行长距离(探测有效距离100 m左右)TSP地质超前预报,初步掌握巷道前方不良地质体的存在位置及形态特征;
步骤203:在巷道掌子面每掘进20m左右,即进行短距离(探测有效距离20 m左右)GPR地质超前预报,可以精确掌握巷道前方不良地质体的存在及形态特征。
所述的TSP地质超前预报和GPR地质超前预报可以相互印证。
本发明矿山地下巷道掘进时对前方不良地质体的一种综合探测方法的原理如下:
基本内容之一是在地表由浅部到深部,由地表到地下的垂直综合探测,其结合了地质方法、地球物理勘探和化探,具体为“工程地质测绘+氡气测量+CSAMT”。
基本内容之二是在地下巷道内由短距离到长距离的水平综合探测,其结合了地质方法、地震法和电磁法,具体为“工程地质素描+TSP+GPR”。
形成地表与地下相结合,长距离与短距离相结合,地质方法与地球物理勘探方法、化学勘探方法相结合,电磁法与地震法相结合的立体交叉空间探测体系,可以精准的探测到不良地质体的存在空间形态及其规模。
本发明的有益效果如下:该种综合探测方法可以通过从地表到地下,从短距离到长距离所形成的立体空间探测体系,较为准确的测得巷道前方的不良地质体的分布位置及空间形态特征,为巷道的掘进、支护提供可靠的技术情报与服务支撑。
具体实施方式
本发明矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,包括有步骤S1和步骤S2,共两个步骤;
所述的步骤S1为在巷道的设计位置确定后,没有进行施工开挖前在地表进行探测;
所述的步骤S2为在巷道开始掘进时,在巷道内进行探测。
所述的步骤S1又包含步骤101至步骤103,共三个步骤:
   步骤101:在工程区进行工程地质调查与测绘,了解区域地质构造、地层岩性及厚度,岩石结构面特征、大的断裂构造及节理裂隙的发育程度等;
   步骤102:垂直巷道的走向布设氡气测量线,进行浅部土壤的氡气测量,目的是探测地下巷道深度内是否存在断层,及其活动性如何;
步骤103:垂直巷道的走向布设CSAMT测线,测线位置与氡气测量线的位置重合(这样化探和物探结果可以相互验证),进行地下不良地质体的探测,探测深度在2km左右。
所述的步骤S2又包括步骤201至步骤203,共三个步骤:
步骤201:在巷道掘进掌子面进行地质素描,掌握巷道围岩是否存在不良地质体,以及不良地质体的基本特征;
步骤202:在巷道掌子面进行长距离(探测有效距离100 m左右)TSP地质超前预报,初步掌握巷道前方不良地质体的存在位置及形态特征;
步骤203:在巷道掌子面每掘进20m左右,即进行短距离(探测有效距离20 m左右)GPR地质超前预报,可以精确掌握巷道前方不良地质体的存在及形态特征。
所述的TSP地质超前预报和GPR地质超前预报可以相互印证。
本发明矿山地下巷道掘进时对前方不良地质体的一种综合探测方法的原理如下:
基本内容之一是在地表由浅部到深部,由地表到地下的垂直综合探测,其结合了地质方法、地球物理勘探和化探,具体为“工程地质测绘+氡气测量+CSAMT”。
基本内容之二是在地下巷道内由短距离到长距离的水平综合探测,其结合了地质方法、地震法和电磁法,具体为“工程地质素描+TSP+GPR”。
形成地表与地下相结合,长距离与短距离相结合,地质方法与地球物理勘探方法、化学勘探方法相结合,电磁法与地震法相结合的立体交叉空间探测体系,可以精准的探测到不良地质体的存在空间形态及其规模。

Claims (4)

1.矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,其特征在于:包括有步骤S1和步骤S2,共两个步骤:
所述的步骤S1为在巷道的设计位置确定后,没有进行施工开挖前在地表进行探测;
所述的步骤S2为在巷道开始掘进时,在巷道内进行探测。
2.根据权利要求1所述的矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,其特征在于:所述的步骤S1又包含步骤101至步骤103,共三个步骤:
   步骤101:在工程区进行工程地质调查与测绘,了解区域地质构造、地层岩性及厚度,岩石结构面特征、大的断裂构造及节理裂隙的发育程度等;
   步骤102:垂直巷道的走向布设氡气测量线,进行浅部土壤的氡气测量,目的是探测地下巷道深度内是否存在断层,及其活动性如何;
步骤103:垂直巷道的走向布设CSAMT测线,测线位置与氡气测量线的位置重合,这样化探和物探结果可以相互验证,进行地下不良地质体的探测,探测深度在2km左右。
3.根据权利要求1所述的矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,其特征在于:所述的步骤S2又包括步骤201至步骤203,共三个步骤:
步骤201:在巷道掘进掌子面进行地质素描,掌握巷道围岩是否存在不良地质体,以及不良地质体的基本特征;
步骤202:在巷道掌子面进行长距离,探测有效距离100 m,TSP地质超前预报,初步掌握巷道前方不良地质体的存在位置及形态特征;
步骤203:在巷道掌子面每掘进20m左右,即进行短距离,探测有效距离20 m,GPR地质超前预报,可以精确掌握巷道前方不良地质体的存在及形态特征。
4.根据权利要求1所述的矿山地下巷道掘进时对前方不良地质体的一种综合探测方法,其特征在于:所述的TSP地质超前预报和GPR地质超前预报可以相互印证。
CN201410113061.9A 2014-03-25 2014-03-25 矿山地下巷道掘进时对前方不良地质体的一种综合探测方法 Pending CN103901503A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410113061.9A CN103901503A (zh) 2014-03-25 2014-03-25 矿山地下巷道掘进时对前方不良地质体的一种综合探测方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410113061.9A CN103901503A (zh) 2014-03-25 2014-03-25 矿山地下巷道掘进时对前方不良地质体的一种综合探测方法

Publications (1)

Publication Number Publication Date
CN103901503A true CN103901503A (zh) 2014-07-02

Family

ID=50992945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410113061.9A Pending CN103901503A (zh) 2014-03-25 2014-03-25 矿山地下巷道掘进时对前方不良地质体的一种综合探测方法

Country Status (1)

Country Link
CN (1) CN103901503A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104502985A (zh) * 2014-11-21 2015-04-08 大同煤矿集团有限责任公司 瞬变电磁分次探测法
CN108226998A (zh) * 2017-12-19 2018-06-29 山东大学 基于tsp系统和岩体随机不连续面三维网络的地质超前预测方法
CN111502677A (zh) * 2020-05-25 2020-08-07 中铁第六勘察设计院集团有限公司 一种地下工程深浅组合地质勘察布置方法
CN112485823A (zh) * 2020-10-15 2021-03-12 中铁四局集团第五工程有限公司 高效综合超前地质预报方法
WO2021147638A1 (zh) * 2020-01-21 2021-07-29 山东大学 Tbm搭载式放射性氡进行超前地质预报的系统及方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020099504A1 (en) * 1999-01-29 2002-07-25 Cross Timothy A. Method of predicting three-dimensional stratigraphy using inverse optimization techniques
CN101526629A (zh) * 2009-04-02 2009-09-09 中铁二局股份有限公司 一种过煤系地层隧道施工地质预报系统
WO2012052770A2 (en) * 2010-10-20 2012-04-26 Emon (Uk) Limited Methods and apparatus for geophysical prospecting to detect bodies of fluids in underground formations
CN102495434A (zh) * 2011-11-25 2012-06-13 成都畅达通地下工程科技发展有限公司 地下工程超前地质预报的方法
CN102681004A (zh) * 2012-05-14 2012-09-19 中国矿业大学(北京) 以掘进机为震源的巷道随掘地震超前探测装置及方法
CN103174418A (zh) * 2013-02-05 2013-06-26 中国矿业大学 掘进灾害超前探测系统及方法
CN103472499A (zh) * 2013-09-18 2013-12-25 中国华冶科工集团有限公司 矿山井下导水构造带的探测定位方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020099504A1 (en) * 1999-01-29 2002-07-25 Cross Timothy A. Method of predicting three-dimensional stratigraphy using inverse optimization techniques
CN101526629A (zh) * 2009-04-02 2009-09-09 中铁二局股份有限公司 一种过煤系地层隧道施工地质预报系统
WO2012052770A2 (en) * 2010-10-20 2012-04-26 Emon (Uk) Limited Methods and apparatus for geophysical prospecting to detect bodies of fluids in underground formations
CN102495434A (zh) * 2011-11-25 2012-06-13 成都畅达通地下工程科技发展有限公司 地下工程超前地质预报的方法
CN102681004A (zh) * 2012-05-14 2012-09-19 中国矿业大学(北京) 以掘进机为震源的巷道随掘地震超前探测装置及方法
CN103174418A (zh) * 2013-02-05 2013-06-26 中国矿业大学 掘进灾害超前探测系统及方法
CN103472499A (zh) * 2013-09-18 2013-12-25 中国华冶科工集团有限公司 矿山井下导水构造带的探测定位方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
D.R.GLASER,ET AL: "Temporal GPR imaging of an ethanol release within a laboratory-scaled sand tank", 《JOURNAL OF APPLIED GEOPHYSICS》, vol. 86, 31 December 2012 (2012-12-31), pages 133 - 145 *
刘菁华等: "煤矿采空区及塌陷区的地球物理探查", 《煤炭学报》, vol. 30, no. 6, 31 December 2005 (2005-12-31), pages 715 - 719 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104502985A (zh) * 2014-11-21 2015-04-08 大同煤矿集团有限责任公司 瞬变电磁分次探测法
CN108226998A (zh) * 2017-12-19 2018-06-29 山东大学 基于tsp系统和岩体随机不连续面三维网络的地质超前预测方法
CN108226998B (zh) * 2017-12-19 2019-12-24 山东大学 基于tsp系统和岩体随机不连续面三维网络的地质超前预测方法
WO2021147638A1 (zh) * 2020-01-21 2021-07-29 山东大学 Tbm搭载式放射性氡进行超前地质预报的系统及方法
CN111502677A (zh) * 2020-05-25 2020-08-07 中铁第六勘察设计院集团有限公司 一种地下工程深浅组合地质勘察布置方法
CN112485823A (zh) * 2020-10-15 2021-03-12 中铁四局集团第五工程有限公司 高效综合超前地质预报方法
CN112485823B (zh) * 2020-10-15 2022-07-01 中铁四局集团第五工程有限公司 高效综合超前地质预报方法

Similar Documents

Publication Publication Date Title
Bin et al. Comprehensive surface geophysical investigation of karst caves ahead of the tunnel face: a case study in the Xiaoheyan section of the water supply project from Songhua River, Jilin, China
Song et al. Identification, remediation, and analysis of karst sinkholes in the longest railroad tunnel in South Korea
Demanet et al. The use of geophysical prospecting for imaging active faults in the Roer Graben, Belgium
CN103995296B (zh) 瞬变电磁法地孔探测方法与装置
Li et al. Predicting geological hazards during tunnel construction
Bu et al. Application of the comprehensive forecast system for water-bearing structures in a karst tunnel: a case study
CN102645674B (zh) 工作面煤层采前立体探测方法
Sloan et al. Using near-surface seismic refraction tomography and multichannel analysis of surface waves to detect shallow tunnels: A feasibility study
CN104166164A (zh) 煤巷掘进地质构造三分量多波反射三维地震超前探测方法
Wu et al. Mapping coalmine goaf using transient electromagnetic method and high density resistivity method in Ordos City, China
CN104597511A (zh) 一种多层采空区地面-巷道瞬变电磁探测方法
Gan et al. Multi-geophysical approaches to detect karst channels underground—A case study in Mengzi of Yunnan Province, China
CN103901503A (zh) 矿山地下巷道掘进时对前方不良地质体的一种综合探测方法
CN105807336A (zh) 适用于多地球物理探测方法的综合孤石探测模型试验装置及试验方法
Chen et al. Tunnel prospecting based on integrated interpretation of geophysical data: Xiangyun Tunnel, Yunnan Province, China
Gao et al. Water detection within the working face of an underground coal mine using 3D electric resistivity tomography (ERT)
Su et al. Progressive fine integrated geophysical method for karst detection during subway construction
Li et al. The detection of the boulders in metro tunneling in granite strata using a shield tunneling method and a new method of coping with boulders
Ba et al. Near-surface site investigation and imaging of karst cave using comprehensive geophysical and laser scanning: a case study in Shandong, China
CN105137487A (zh) 基于人工放水干扰场的地下水流场描述方法
Jianliang et al. Integrated Geophysical Survey in Defining Subsidence Features of Glauber's Salt Mine, Gansu Province in China
Kovačević et al. Application of geophysical investigations in underground engineering
Nie et al. Comprehensive ahead prospecting of tunnels in severely weathered rock mass environments with high water inrush risk: a case study in Shaanxi Province
Nwokebuihe et al. A description of an effective sinkhole investigation approach: a case study of a site in Greene County, Missouri
CN103901482A (zh) 一种快速获取地下介质电性连续变化信息的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140702

RJ01 Rejection of invention patent application after publication